The World Bank Implementation Status & Results Report Chad Statistical Development (P159434) Chad Statistical Development (P159434) AFRICA | Chad | Poverty and Equity Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 5 | ARCHIVED on 24-Jun-2019 | ISR37451 | Implementing Agencies: INSEED, Republic of Chad Key Dates Key Project Dates Bank Approval Date: 03-Apr-2017 Effectiveness Date: 25-Aug-2017 Planned Mid Term Review Date: 12-Dec-2019 Actual Mid-Term Review Date: -- Original Closing Date: 31-Mar-2022 Revised Closing Date: 31-Mar-2022 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To strengthen the capacity of the national statistics institute to collect, process, and disseminate data with improved quality, frequency, and timeliness. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Strengthening Institutional Capacity and Developing Human Resources:(Cost $4.10 M) Data Collection, Processing, Analysis, and Dissemination:(Cost $6.70 M) Project Management and Improving of IT infrastructure:(Cost $1.20 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions Component 1: Strengthening Institutional Capacity and Developing Human Resources 1 . Statistic Law: The Economic and Planning commission of the National Assembly approved the draft “Statistics Law” on May 27th, 2019 with recommendation to incorporate the comments provided by the World Bank regarding Article 18 and 51. The law incorporating the changes has been promulgated by the President on June 11th, 2019. 2 . Human Resources (HR review) : The firm (Agora consulting) in charge of conducting the HR review was in Ndjamena on April 24, 2019 to submit the diagnostic report for validation by INSEED. The documents are being reviewed by all Directors within INSEED. 3 . Scholarship: The call for application was launched on November 13th, 2018 and closed on January 25th, 2019. The first selection test took place on February 03, 2019. for both ISE and ITS degrees, 113 candidates passed the initial test (08 girls and 105 boys). 6/24/2019 Page 1 of 5 The World Bank Implementation Status & Results Report Chad Statistical Development (P159434) Component 2: Data Collection, Processing, Analysis, and Dissemination 1 . Implementation of National survey ECOSIT4: The two waves of data collection was completed in April 2019 and the cleaning work is ongoing. INSEED is planning to participate in the two technical workshops planned by the WAEMU in July and September 2019. by October 2019 the preliminary poverty rates will be available. 2 . Macroeconomic Data: to update GDP numbers, a contract with AFRISTAT was signed in October 2018. a) AFRISTAT's second mission was in May in Ndjamena to process all the data; (b) the training for the enumerators for the remaining field work is completed; c) work on the business register is being triangulated to clean the data; (d) the report on the fishing survey is in the process of being completed; e) the price bulletin for the month of March is available; Component 3: Project Management and Improving of IT infrastructure 1 . Recruitment for PIU: In November 2018, the financial management specialist of the project decided to leave to join another WB project. A new recruitment process was initiated in December 2018. A new financial management specialist came on board in March 2019. 4 . IT: diagnostics of INSEED IT network conducted by three firms; technical propositions already shared with INSEED are being evaluated. A firm has been selected to revamp the internet connection within INSEED. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial Substantial Substantial Macroeconomic Substantial Substantial Substantial Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Sustainability Substantial Substantial Substantial Fiduciary High Substantial Substantial Environment and Social Low Low Moderate Stakeholders Moderate Moderate Moderate Other Low Low Low Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes Project Development Objective Indicators IN00711953 ►NSDS is drafted and adopted (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 30-Sep-2016 31-Dec-2018 15-Jun-2019 31-Mar-2022 6/24/2019 Page 2 of 5 The World Bank Implementation Status & Results Report Chad Statistical Development (P159434) NSDS is drafted but not adopted. Comments: IN00711954 ►Number of scholarships awarded for advanced degrees in statistics (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 23.00 23.00 30.00 Date 30-Sep-2016 31-Dec-2018 15-Jun-2019 31-Mar-2022 IN00711955 ►Number of household surveys completed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.50 1.00 2.00 Date 30-Sep-2016 31-Dec-2018 15-Jun-2019 31-Mar-2022 IN00711986 ►The number of household surveys implemented with improved data collection methods and computerized data checking to improve data quality. (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.50 1.00 2.00 Date 30-Sep-2016 31-Dec-2018 15-Jun-2019 31-Mar-2022 IN00711987 ►Dissemination of statistical abstracts, key findings and updated poverty statistics to take place within 12 months of data cleaning for each round of the HHS. (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 30-Sep-2016 31-Dec-2018 15-Jun-2019 31-Mar-2022 IN00711988 ►The number of datasets from household surveys implemented under the project that are publicly released within 12 months of data cleaning (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2.00 Date 30-Sep-2016 31-Dec-2018 15-Jun-2019 31-Mar-2022 Intermediate Results Indicators by Components Strengthening Institutional Capacity and Developing Human Resources IN00711989 ►Regulatory reform is drafted and ready for adoption (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes 6/24/2019 Page 3 of 5 The World Bank Implementation Status & Results Report Chad Statistical Development (P159434) Date 30-Sep-2016 31-Dec-2018 15-Jun-2019 31-Mar-2022 IN00711992 ►Number of INSEED staff trained (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 12.00 12.00 50.00 Date 30-Sep-2016 31-Dec-2018 15-Jun-2019 31-Mar-2022 IN00711994 ►Number of students to complete the statistics entrance exam preparation program (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 40.00 211.00 250.00 Date 30-Sep-2016 31-Dec-2018 15-Jun-2019 31-Mar-2022 Data Collection, Processing, Analysis, and Dissemination IN00711990 ►Rebasing of CPI measure using expanded geographic coverage of price data collection (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No Yes Yes Date 30-Sep-2016 31-Dec-2018 15-Jun-2019 31-Mar-2022 IN00711993 ►Web based data portal available to the public (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 30-Sep-2016 31-Dec-2018 15-Jun-2019 31-Mar-2022 Project Management and Improving of IT infrastructure IN00711991 ►Annual production of a data user feedback report for project steering committee. (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 30-Sep-2016 31-Dec-2018 15-Jun-2019 31-Mar-2022 Data on Financial Performance Disbursements (by loan) 6/24/2019 Page 4 of 5 The World Bank Implementation Status & Results Report Chad Statistical Development (P159434) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P159434 IDA-D1760 Effective USD 12.00 12.00 0.00 5.04 7.32 41% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P159434 IDA-D1760 Effective 03-Apr-2017 21-Apr-2017 25-Aug-2017 31-Mar-2022 31-Mar-2022 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/24/2019 Page 5 of 5