Procurement Plan I. General 1. Project Information Country: Tanzania Project Name: Second Water Sector Support Project (WSSP II) Project ID: P150361 2. Project Implementation Agency: Ministry of Water and Irrigation Dar es Salaam Water Supply and Sewerage Authority Dar es Salaam Water Supply ans Sewerage Corporation 3. Date of the Procurement Plan: April 2017 4. Period Covered by this Procurement Plan: First 18 Months II. Thresholds for Prior Review, Procurement Approaches and Methods A. Goods, Works and Non-Consulting Services Procurement Approaches and Methods (US$ millions) Prior Review Category (US$ millions) Open International Open Request for National Quotation (RfQ) Works ≥ 10 ≥ 15.0 < 15 ≤ 0.2 Goods, IT, and non- ≥2 ≥5 <5 ≤ 0.1 consulting services B. Consulting Services Category Prior Review Short List of National Consultants (US$ million) (US$ millions) Consulting Services Engineering and Construction Supervision Consultants (Firms) ≥1 ≤ 0.3 ≤ 0.3 Individual Consultants ≥ 0.3 NA. NA. [Overall Project Procurement Risk is SUBSTANTIAL] Notes: Terms of Reference: Terms of Reference for all contracts shall be cleared by the Bank, regardless of whether the assignment is for prior or post review. Advertisement: Consultancy Service for Contracts estimated to cost US$ 300,000 equivalent and above per contract shall be advertised in UNDB online in addition to advertising in National News Paper(s) of wide circulation and/or Regional News Paper(s). 1 PROCUREMENT Tanzania : Second Tanzania Water Sector Support Project PLAN General Information Country: Tanzania Bank’s Approval Date of the Original Procurement Plan: 2017-04-13 2020-01-14 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150361 GPN Date: Project Name: Second Tanzania Water Sector Support Project Loan / Credit No: IDA / 59490, IDA / V0310 Executing Agency(ies): Ministry of Water and Irrigation WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-12669-CW-RFB / Drilling Works for Ground Component 1: Integrated Pending Single Stage - One Water Monitoring Network IDA / 59490 Water Resources Post Request for Bids Open - National 1,000,000.00 0.00 Implementati 2017-09-01 2017-09-06 2017-10-18 2017-11-17 2017-12-22 2018-06-20 Envelope in Wami-Ruvu and Internal Management (IWRM) on Drainage Basins TZ-MOW-12671-CW-RFB / Civil Works Construction Component 1: Integrated Pending and Installation of Water Single Stage - One IDA / 59490 Water Resources Post Request for Bids Open - National 2,750,000.00 0.00 Implementati 2018-07-02 2018-07-07 2018-08-18 2018-09-17 2018-10-22 2019-04-20 Resources Monitoring Gauges Envelope Management (IWRM) on in all the nine Basins in Tanzania TZ-MOW-12673-CW-RFB / Construction of Office Block Component 1: Integrated Pending for the Proposed Water Single Stage - One IDA / 59490 Water Resources Post Request for Bids Open - National 800,000.00 0.00 Implementati 2019-03-04 2019-03-09 2019-04-20 2019-05-20 2019-06-24 2019-12-21 Resources Centre of Envelope Management (IWRM) on Excellency (COE) in Dar es Salaam TZ-MOW-12670-CW-RFB / Construction of office and water laboratory buildings for Wami-Ruvu Basin Water Board (BWB) Headquarter at Component 1: Integrated Single Stage - One Morogoro and Water Users IDA / 59490 Water Resources Post Request for Bids Open - National 1,000,000.00 0.00 Canceled 2018-06-04 2018-06-09 2018-07-21 2018-08-20 2018-09-24 2019-03-23 Envelope Association (WUA) Offices at Management (IWRM) Msowero and rehabilitation and extension of office building for Wami-Ruvu BWB in Dodoma. GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-11480-GO-RFB / Supply of eighteen four- Component 1: Integrated Pending Single Stage - One Wheel Drive Vehicles for the IDA / 59490 Water Resources Post Request for Bids Open - National 1,080,000.00 0.00 Implementati 2017-07-03 2017-07-08 2017-08-07 2017-08-28 2017-10-02 2017-12-31 Envelope Basin Water Boards and Management (IWRM) on MoWI's Division of WR. TZ-MOW-12602-GO-RFB / Component 1: Integrated Supply of Motorbikes and Single Stage - One IDA / 59490 Water Resources Post Request for Bids Open - National 350,000.00 19,504.05 Signed 2017-07-03 2017-07-08 2017-08-07 2017-08-21 2017-09-25 2017-11-24 Bicycles (100 of each) to Envelope Management (IWRM) support 100 WUAs Page 1 TZ-MOW-12667-GO-RFB / Supply of office data Component 1: Integrated Single Stage - One management tools and IDA / 59490 Water Resources Post Request for Bids Open - National 1,250,000.00 818,766.58 Signed 2018-03-01 2018-03-06 2018-04-05 2018-05-05 2018-06-09 2018-09-07 Envelope equipment including ICT Management (IWRM) equipment TZ-MOW-12610-GO-RFP / Component 1: Integrated Pending Supply of water quality Single Stage - One IDA / 59490 Water Resources Post Request for Bids Open - National 300,000.00 0.00 Implementati 2017-07-01 2017-07-06 2017-08-05 2017-09-04 2017-10-09 2018-04-07 monitoring equipment and Envelope Management (IWRM) on tools TZ-MOW-12605-GO-RFB / Supply of surface and groundwater monitoring Component 1: Integrated Pending Single Stage - One network gauges monitoring IDA / 59490 Water Resources Prior Request for Bids Open - National 3,200,000.00 0.00 Implementati 2017-07-03 2017-07-08 2017-08-07 2017-09-06 2017-10-11 2018-04-09 Envelope instruments for large dams Management (IWRM) on and sediment monitoring equipment TZ-MOW-10924-GO-RFB / Component 1: Integrated Supply of Water Users Single Stage - One IDA / 59490 Water Resources Post Request for Bids Open - National 150,000.00 252,960.06 Signed 2017-05-30 2017-06-04 2017-06-25 2017-07-25 2017-08-29 2017-11-27 Associations Survival Envelope Management (IWRM) Working Kits TZ-MOW-63646-GO-RFQ / Purchase of office equipments (Laptop Desktop, Ups, Network Component 4: Project Pending Request for Single Stage - One Printer, Scanner, IDA / 59490 management and Post Open - National 40,010.20 0.00 Implementati 2018-08-06 2018-10-01 2019-03-30 Quotations Envelope Photocopier, Projector, WiFi Implementation Support on Router, Printer LaserJet pro M402dne, Garmin GPS NAVA F 78) TZ-MOW-70318-GO-UN / Supply of eighteen four- Component 1: Integrated UN Agencies Wheel Drive Vehicles for the IDA / 59490 Water Resources Prior Direct 1,080,000.00 847,979.00 Signed 2018-08-22 2018-08-27 2018-10-01 2019-03-30 (Direct) Basin Water Boards and Management (IWRM) MoWI's Division of WR. TZ-MOW-12668-GO-RFB / Component 1: Integrated Single Stage - One Supply of Communication IDA / 59490 Water Resources Post Request for Bids Open - National 200,000.00 0.00 Canceled 2018-09-27 2018-10-02 2018-11-01 2018-12-01 2019-01-05 2019-04-05 Envelope Strategy Materials Management (IWRM) TZ-MOW-109251-GO-RFB / Component 1: Integrated Pending Supply and Installation of Single Stage - One IDA / 59490 Water Resources Post Request for Bids Open - National 240,000.00 0.00 Implementati 2019-04-12 2019-04-17 2019-05-29 2019-06-28 2019-08-02 2020-01-29 Dam safety Monitoring Envelope Management (IWRM) on Instruments TZ-MOW-63647-GO-RFQ / Component 4: Project Pending Purchase of office equipment Request for Single Stage - One IDA / 59490 management and Post Open - National 17,418.50 0.00 Implementati 2018-08-20 2018-10-15 2019-04-13 to support three consultant Quotations Envelope Implementation Support on of WSSP II project TZ-MOW-113290-GO-RFB / Component 4: Project Pending Purchase of office furniture's Single Stage - One IDA / 59490 management and Post Request for Bids Open - National 175,000.00 0.00 Implementati 2019-05-08 2019-05-13 2019-06-23 2019-07-23 2019-08-27 2020-02-23 for MoW through support of Envelope Implementation Support on WSSP II Project TZ-MOW-109947-GO-RFB / Purchase of three motor Component 4: Project Single Stage - One vehicles for PDCU to IDA / 59490 management and Post Request for Bids Open - National 136,363.64 0.00 Canceled 2019-04-23 2019-04-28 2019-06-09 2019-07-09 2019-08-13 2020-02-09 Envelope support WSSP II Implementation Support implementation Page 2 TZ-MOW-118055-GO-UN / Purchase of three motor Component 4: Project UN Agencies vehicles for PDCU to IDA / 59490 management and Post Direct 136,363.64 108,343.00 Signed 2019-06-13 2019-06-18 2019-07-23 2020-01-19 (Direct) support WSSP II Implementation Support implementation TZ-MOW-121119-GO-UN / Supply of Five (5) Four Component 1: Integrated Under UN Agencies Wheel Drive Vehicles for IDA / 59490 Water Resources Post Direct 350,000.00 0.00 Implementati 2019-07-05 2019-07-10 2019-08-14 2020-02-10 (Direct) Water Resources Center of Management (IWRM) on Excellence (WRCoE) TZ-MOW-136409-GO-RFB / Component 1: Integrated Under Supply of Dam Safety Single Stage - One IDA / 59490 Water Resources Post Request for Bids Open - National 410,586.00 0.00 Implementati 2019-10-07 2019-10-12 2019-11-23 2019-12-23 2020-01-27 2020-07-25 Working Tools Equipment Envelope Management (IWRM) on and Software TZ-MOW-148402-GO-UN / Component 1: Integrated Pending Supply of Four (4) Four UN Agencies IDA / 59490 Water Resources Post Direct 180,000.00 0.00 Implementati 2020-01-08 2020-01-13 2020-02-17 2020-08-15 Wheel Motor Vehicles for (Direct) Management (IWRM) on the Basin Water Boards TZ-MOW-153185-GO-RFQ / Component 1: Integrated Pending Request for Single Stage - One Supply of Communication IDA / 59490 Water Resources Post Limited 51,222.00 0.00 Implementati 2020-01-29 2020-03-25 2020-09-21 Quotations Envelope Strategy Materials Management (IWRM) on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-153183-NC-DIR / Component 1: Integrated Pending Printing of Communication IDA / 59490 Water Resources Post Direct Selection Direct 148,778.00 0.00 Implementati 2020-01-24 2020-01-29 2020-03-04 2020-08-31 Strategy Materials Management (IWRM) on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-11548-CS-CQS / Consultancy Services for Component 1: Integrated Consultant Technical Assistance on Pending IDA / 59490 Water Resources Post Qualification Open - National 100,000.00 0.00 2017-08-30 2017-09-20 2017-11-03 2017-12-03 2018-01-07 2018-07-06 Preparation of Water Implementation Management (IWRM) Selection Resources Use Charges Regulations TZ-MOW-11553-CS-CQS / Consultancy for Development Component 1: Integrated Consultant Under and Implementation of IDA / 59490 Water Resources Post Qualification Open - National 150,000.00 0.00 2017-09-20 2017-10-11 2017-11-24 2017-12-24 2018-01-28 2018-07-27 Implementation Laboratory Information Management (IWRM) Selection Management System TZ-MOW-11854-CS-QCBS / Component 1: Integrated Consultancy services for Quality And Cost- Open - Under IDA / 59490 Water Resources Prior 1,750,000.00 0.00 2017-08-18 2017-09-08 2017-10-22 2017-11-19 2017-12-19 2018-01-23 2018-02-27 2019-02-27 National Hydrological Based Selection International Implementation Management (IWRM) Aquifer Mapping Page 3 TZ-MOW-11857-CS-QCBS / Consultancy Services for Component 1: Integrated Operational Decision Support Quality And Cost- Open - Under IDA / 59490 Water Resources Prior 2,500,000.00 0.00 2017-10-05 2017-11-04 2017-12-18 2018-01-15 2018-02-14 2018-03-21 2018-04-25 2019-04-25 System Through Enhanced Based Selection International Implementation Management (IWRM) Hydro- Meteorological Services TZ-MOW-11878-CS-CQS / Component 1: Integrated Consultant Design and Supervision for Under IDA / 59490 Water Resources Post Qualification Open - National 250,000.00 0.00 2017-05-25 2017-06-15 2017-07-29 2017-08-28 2017-10-02 2018-03-31 Centre of Excellence Implementation Management (IWRM) Selection Building TZ-MOW-10918-CS-QCBS / Component 1: Integrated Consultancy Services for Quality And Cost- Open - Under IDA / 59490 Water Resources Post 750,000.00 0.00 2017-03-30 2017-04-28 2017-06-02 2017-06-30 2017-07-30 2017-08-29 2017-10-03 2018-10-03 Catchment Conservation in Based Selection International Implementation Management (IWRM) Wami-Ruvu Basin TZ-MOW-44490-CS-CQS / Consultancy services for Consolidation of Data, Component 1: Integrated Consultant Information and Models from IDA / 59490 Water Resources Post Qualification Open - National 300,000.00 277,090.70 Signed 2018-01-18 2018-02-08 2018-03-24 2018-04-23 2018-05-28 2018-11-24 the IWRMD Plans and Management (IWRM) Selection Preparation of Requirements Specification for WRIS & Web Portal TZ-MOW-54418-CS-QCBS / Consultancy Services on Component 1: Integrated Quality And Cost- Open - Water Resources IDA / 59490 Water Resources Prior 414,000.00 385,210.34 Signed 2015-02-03 2015-02-13 2015-09-23 2015-11-13 2016-02-10 2016-07-01 2018-12-15 2019-06-13 Based Selection International Management Financing Management (IWRM) Options TZ-MOW-54421-CS-QCBS / Consultancy Services for Component 1: Integrated Preparation of Integrated Quality And Cost- Open - Under IDA / 59490 Water Resources Prior 533,000.00 0.00 2015-02-03 2015-02-13 2015-09-07 2015-11-12 2016-04-04 2016-12-21 2017-06-01 2017-11-28 Water Management and Based Selection International Implementation Management (IWRM) Development Plan for Wami/Ruvu Basin TZ-MOW-64973-CS-QCBS / Consultancy Service for Component 4: Project Quality And Cost- Open - Under Project Management Firm to IDA / 59490 management and Prior 1,200,000.00 0.00 2018-06-20 2018-07-11 2018-08-15 2018-09-12 2018-10-12 2018-11-16 2018-12-21 2019-12-21 Based Selection International Implementation Support Implementation of Implementation Support WSSP II TZ-MOW-11389-CS-QCBS / Consultancy Services for design review and supervision of construction of office and laboratory Component 1: Integrated buildings for Wami-Ruvu Quality And Cost- Open - IDA / 59490 Water Resources Post 600,000.00 0.00 Canceled 2017-09-05 2017-09-26 2017-10-24 2017-11-21 2017-12-21 2018-01-25 2018-03-01 2019-03-01 Basin Water Boards Based Selection International Management (IWRM) Headquarter Morogoro and Water Users Associations Offices at Msowero and rehabilitation and extension at Dodoma TZ-MOW-12527-CS-QCBS / Component 1: Integrated Institutional development Quality And Cost- Open - IDA / 59490 Water Resources Prior 1,000,000.00 0.00 Canceled 2017-10-20 2017-11-10 2017-12-24 2018-01-21 2018-02-20 2018-03-27 2018-05-01 2019-05-01 support technical assistance Based Selection International Management (IWRM) COE TZ-MOW-10915-CS-QCBS / Consultancy Services for Component 1: Integrated Quality And Cost- Open - Modernizing Hydrological IDA / 59490 Water Resources Prior 1,750,000.00 0.00 Canceled 2017-03-30 2017-04-28 2017-06-02 2017-06-30 2017-07-30 2017-08-29 2017-10-03 2019-11-30 Based Selection International and Meteorological Management (IWRM) Monitoring Systems Page 4 TZ-MOW-10921-CS-QCBS / Consultancy Services for Component 1: Integrated Quality And Cost- Open - Operational Decision Support IDA / 59490 Water Resources Prior 2,500,000.00 0.00 Canceled 2017-04-11 2017-05-12 2017-06-16 2017-07-14 2017-08-13 2017-09-12 2017-10-17 2018-10-17 Based Selection International System through Enhanced Management (IWRM) Hydro-Meteorological Services TZ-MOW-11875-CS-CQS / Consultancy Services for the Component 1: Integrated Consultant study of institutional set up IDA / 59490 Water Resources Post Qualification Open - National 50,000.00 0.00 Canceled 2017-05-25 2017-06-15 2017-07-29 2017-08-28 2017-10-02 2018-03-31 for water Resources Centre Management (IWRM) Selection of Excellence TZ-MOW-12529-CS-CQS / Component 1: Integrated Consultant Consultancy Services for Open - IDA / 59490 Water Resources Prior Qualification 300,000.00 0.00 Canceled 2017-07-03 2017-07-24 2017-08-21 2017-09-04 2017-10-09 2018-04-07 preparation of future International Management (IWRM) Selection investments TZ-MOW-11533-CS-CQS / Technical Assistance for Component 1: Integrated Consultant Pending strengthening Ground water IDA / 59490 Water Resources Post Qualification Open - National 100,000.00 0.00 2017-08-10 2017-08-31 2017-10-14 2017-11-13 2017-12-18 2018-06-16 Implementation Resources Development and Management (IWRM) Selection Management in Tanzania TZ-MOW-79016-CS-QCBS / Consultancy Services for Preparation of Strategic Environmental and Social Component 1: Integrated Appraisal (SESA) for Quality And Cost- Open - IDA / 59490 Water Resources Prior 600,000.00 0.00 Under Review 2018-11-14 2018-12-05 2019-01-18 2019-02-15 2019-03-17 2019-04-21 2019-05-26 2020-05-25 Integrated Water Resources Based Selection International Management (IWRM) Management and Development (IWRMD) Plans for Five Basins in Tanzania. TZ-MOW-64970-CS-CQS / Component 4: Project Consultant Consultancy Services for IDA / 59490 management and Post Qualification Open - National 150,000.00 0.00 Canceled 2018-10-16 2018-11-06 2018-12-11 2019-01-05 2019-02-09 2019-08-08 Project Manager Consultancy Implementation Support Selection for Support of WSSP II TZ-MOW-11545-CS-CQS / Technical Assistance on Component 1: Integrated Consultant Supporting Implementation IDA / 59490 Water Resources Post Qualification Open - National 100,000.00 0.00 Canceled 2017-08-30 2017-09-20 2017-11-03 2017-12-03 2018-01-07 2018-07-06 of IWRMD at National and Management (IWRM) Selection Basin Levels TZ-MOW-11558-CS-CQS / Technical Assistance for Conceptualisation, Strategic Component 1: Integrated Consultant Planning and IDA / 59490 Water Resources Post Qualification Open - National 200,000.00 0.00 Canceled 2017-11-30 2017-12-21 2018-02-03 2018-03-05 2018-04-09 2018-10-06 Opertionslisation of the Management (IWRM) Selection Water Resources Centre of Excellence (WRCoE) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual TZ-MOW-12593-CS-INDV / Consultancy Service for Component 4: Project Individual updating, upgrading, refining IDA / V0310 management and Post Consultant Open 30,000.00 0.00 Canceled 2017-04-20 2017-04-27 2017-05-01 2017-05-03 2017-05-17 and improvement of the Implementation Support Selection PIM, workshops Page 5 TZ-MOW-11864-CS-IND / Component 1: Integrated Individual Consultancy Services for Under IDA / 59490 Water Resources Prior Consultant Open 300,000.00 0.00 2018-09-10 2018-10-29 2018-11-19 2018-12-24 2019-06-22 Modernizing Hydrological Implementation Management (IWRM) Selection and Monitoring Systems TZ-MOW-63683-CS-INDV / Consultancy Service for Component 4: Project Individual Under Technical Advisor for IDA / 59490 management and Post Consultant Open 80,000.00 0.00 2018-10-16 2018-11-25 2018-12-17 2019-01-21 2019-07-20 Implementation Financial Management Implementation Support Selection Support to WSSP II TZ-MOW-63691-CS-INDV / Consultancy Service for Component 4: Project Individual Technical Advisor for IDA / 59490 management and Post Consultant Open 80,000.00 0.00 Canceled 2018-10-16 2018-11-19 2018-11-30 2019-01-04 2019-07-03 Procurement and Contract Implementation Support Selection Management Support to WSSP II TZ-MOW-87731-CS-INDV / Component 4: Project Individual Consultancy Service for Pending IDA / 59490 management and Post Consultant Open 150,000.00 0.00 2018-11-22 2018-12-25 2019-01-08 2019-02-12 2019-08-11 Project manager consultancy Implementation Implementation Support Selection for support of WSSP II TZ-MOW-89190-CS-INDV / Technical Assistance for Component 1: Integrated Individual supporting implementation of IDA / 59490 Water Resources Post Consultant Open 150,000.00 150,000.00 Signed 2018-12-10 2019-01-28 2019-02-18 2019-03-25 2019-09-21 IWRMD at National and Management (IWRM) Selection Basin Levels TZ-MOW-94046-CS-INDV / Technical Assistance for Conceptualisation, Strategic Component 1: Integrated Individual Planning and IDA / 59490 Water Resources Post Consultant Open 200,000.00 115,600.00 Signed 2019-01-09 2019-02-27 2019-03-20 2019-04-24 2019-10-21 Operationslisation of the Management (IWRM) Selection Water Resources Centre of Excellence (WRCoE) TZ-MOW-70351-CS-INDV / Component 1: Integrated Individual Individual consultant to Under IDA / 59490 Water Resources Post Consultant Open 200,000.00 0.00 2018-09-19 2018-11-07 2018-11-28 2019-01-02 2019-07-01 support the COE as the Gis Implementation Management (IWRM) Selection and Remote Sensing Expert TZ-MOW-70349-CS-INDV / Individual consultant to Component 1: Integrated Individual Under support the COE core team IDA / 59490 Water Resources Post Consultant Open 200,000.00 0.00 2018-09-05 2018-10-24 2018-11-14 2018-12-19 2019-06-17 Implementation as Water Resources Expert Management (IWRM) Selection and Modeller TZ-MOW-70350-CS-INDV / Individual consultant to Component 1: Integrated Individual Under support the COE core team IDA / 59490 Water Resources Post Consultant Open 200,000.00 0.00 2018-09-12 2018-10-31 2018-11-21 2018-12-26 2019-06-24 Implementation as Groundwater Expert and Management (IWRM) Selection Modeller TZ-MOW-130152-CS-INDV / Component 4: Project Individual Consultancy Services for Under IDA / 59490 management and Post Consultant Open 80,000.00 0.00 2019-09-05 2019-10-08 2019-11-05 2019-11-15 2020-11-14 Procurement Specialist under Implementation Implementation Support Selection WSSP II TZ-MOW-109248-CS-INDV / Individual Consultant to Conduct Surveillance Survey, Component 1: Integrated Individual Design, Tender Preparation IDA / 59490 Water Resources Post Consultant Open 178,600.00 0.00 Canceled 2019-04-08 2019-05-11 2019-06-01 2019-07-06 2020-01-02 and Supervision of Management (IWRM) Selection Installation of Dam Safety Monitoring Instrumentation Page 6 TZ-MOW-12520-CS-INDV / Individual consultant to Component 1: Integrated Individual support the COE core team IDA / 59490 Water Resources Post Consultant Open 200,000.00 0.00 Canceled 2017-10-01 2017-11-12 2017-11-19 2017-12-31 2018-06-29 in providing multi-sectoral Management (IWRM) Selection analysis and policy support to different Stakeholders TZ-MOW-136426-CS-INDV / Individual consultant to Component 1: Integrated Individual support the COE core team IDA / 59490 Water Resources Prior Consultant Open 300,000.00 0.00 Canceled 2019-10-07 2019-11-25 2019-12-16 2020-01-20 2020-07-18 in providing multi-sectoral Management (IWRM) Selection analysis and policy support to different Stakeholders TZ-MOW-136407-CS-INDV / Individual Consultant to Conduct Surveillance Survey, Component 1: Integrated Individual Under Design, Tender Preparation IDA / 59490 Water Resources Prior Consultant Open 400,000.00 0.00 2019-10-07 2019-11-25 2019-12-16 2020-01-20 2020-07-18 Implementation and Supervision of Management (IWRM) Selection Installation of Dam Safety Monitoring Instrumentation TZ-MOW-145207-CS-INDV / Individual consultant to Component 1: Integrated Individual support the COE core team Under IDA / 59490 Water Resources Post Consultant Open 200,000.00 0.00 2019-11-17 2020-01-05 2020-01-26 2020-03-01 2020-08-28 in providing multi-sectoral Implementation Management (IWRM) Selection analysis and policy support to different Stakeholders Page 7