Public Disclosure Copy The World Bank Implementation Status & Results Report SOUTH KARAKALPAKSTAN WATER RESOURCES MGMT IMPROVEMENT (P127764) SOUTH KARAKALPAKSTAN WATER RESOURCES MGMT IMPROVEMENT (P127764) EUROPE AND CENTRAL ASIA | Uzbekistan | Water Global Practice | IBRD/IDA | Investment Project Financing | FY 2014 | Seq No: 6 | ARCHIVED on 01-Nov-2017 | ISR30149 | Implementing Agencies: Project Implementation Unit, Ministry of Finance Key Dates Key Project Dates Bank Approval Date:12-Jun-2014 Effectiveness Date:07-Apr-2015 Planned Mid Term Review Date:01-Jun-2018 Actual Mid-Term Review Date:-- Original Closing Date:30-Sep-2021 Revised Closing Date:30-Sep-2021 Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective (PDO) of South Karakalpakstan Water Resources Management Improvement Project (SKWRMIP) is to restore irrigation and improve water management in the project area in a sustainable and financially efficient manner. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Modernization of the Irrigation Network:(Cost $273.85 M) Modernization of Agriculture:(Cost $55.43 M) Project Management, Monitoring and Evaluation:(Cost $8.10 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Unsatisfactory  Unsatisfactory Overall Implementation Progress (IP)  Unsatisfactory  Unsatisfactory Overall Risk Rating  Substantial  Substantial Implementation Status and Key Decisions 11/1/2017 Page 1 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report SOUTH KARAKALPAKSTAN WATER RESOURCES MGMT IMPROVEMENT (P127764) This is an interim ISR only. Full details will be provided following the upcoming mission November 13-24, 2017. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  --  Substantial  Substantial Macroeconomic  --  Moderate  Moderate Sector Strategies and Policies  --  Substantial  Substantial Technical Design of Project or Program  --  Substantial  Substantial Institutional Capacity for Implementation and Sustainability  --  Low  Low Fiduciary  --  Moderate  Moderate Environment and Social  --  High  Substantial Stakeholders  --  Substantial  Substantial Other  --  --  -- Overall  --  Substantial  Substantial Results Project Development Objective Indicators PHINDPDOTBL  Improved irrigation water delivery service (MASSCOTE M&E system) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1.60 1.60 1.60 2.50 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 PHINDPDOTBL  Water users provided with new/improved irrigation and drainage services (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 41,000.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 11/1/2017 Page 2 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report SOUTH KARAKALPAKSTAN WATER RESOURCES MGMT IMPROVEMENT (P127764) PHINDPDOTBL  Water users provided with irrigation and drainage services - female (number) (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 27,000.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 PHINDPDOTBL  Reduction in annual public and WCA expenditures for pumping (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 PHINDPDOTBL  Increased collection rate by WCAs to cover O&M costs (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 40.00 40.00 40.00 50.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 Overall Comments Intermediate Results Indicators 11/1/2017 Page 3 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report SOUTH KARAKALPAKSTAN WATER RESOURCES MGMT IMPROVEMENT (P127764) PHINDIRITBL  Area provided with new/improved irrigation or drainage services (Hectare(Ha), Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 75,000.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 PHINDIRITBL  Area provided with new irrigation or drainage services (Hectare(Ha), Corporate Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 75,000.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 PHINDIRITBL  Reduction of energy consumption (Megawatt, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 60,000.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 PHINDIRITBL  Irrigation water distribution schedule prepared (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 11/1/2017 Page 4 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report SOUTH KARAKALPAKSTAN WATER RESOURCES MGMT IMPROVEMENT (P127764) PHINDIRITBL  Dam safety plan for Tuyamuyun dam prepared and submitted to the government (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 PHINDIRITBL  Operational water user associations created and/or strengthened (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 25.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 PHINDIRITBL  Number of BVO, PAN-ISA, and LABAIS staffs trained (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 PHINDIRITBL  Percentage of BVO, LABAIS and PAN-ISA staff satisfied with training (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 80.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 11/1/2017 Page 5 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report SOUTH KARAKALPAKSTAN WATER RESOURCES MGMT IMPROVEMENT (P127764) PHINDIRITBL  Area producing non-cotton/non-wheat crop (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 6,500.00 6,500.00 6,500.00 10,000.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 PHINDIRITBL  Client days of training provided (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 600.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 PHINDIRITBL  Client days of training provided - Female (number) (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 120.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 PHINDIRITBL  Percentage of cotton area harvested mechanically (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 5.00 5.00 70.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 11/1/2017 Page 6 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report SOUTH KARAKALPAKSTAN WATER RESOURCES MGMT IMPROVEMENT (P127764) PHINDIRITBL  Number of demonstrations established (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 245.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 PHINDIRITBL  Number of project monitoring reports submitted on time annually (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 2.00 Date 01-Aug-2013 08-Dec-2016 08-Dec-2016 30-Sep-2020 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P127764 IBRD-83890 Effective USD 18.29 0.05 18.24 0.05 0.00 100% P127764 IDA-54900 Effective USD 242.50 214.21 28.29 15.27 174.02 7% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P127764 IBRD-83890 Effective 12-Jun-2014 29-Oct-2014 07-Apr-2015 30-Sep-2021 30-Sep-2021 P127764 IDA-54900 Effective 12-Jun-2014 29-Oct-2014 07-Apr-2015 30-Sep-2021 30-Sep-2021 Cumulative Disbursements 11/1/2017 Page 7 of 8 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report SOUTH KARAKALPAKSTAN WATER RESOURCES MGMT IMPROVEMENT (P127764) Restructuring History Level 2 Approved on 07-Apr-2015 Related Project(s) There are no related projects. 11/1/2017 Page 8 of 8 Public Disclosure Copy