The World Bank Implementation Status & Results Report Modernizing Production of Statistics in Vietnam (P166158) Modernizing Production of Statistics in Vietnam (P166158) EAST ASIA AND PACIFIC | Vietnam | Poverty and Equity Global Practice | Recipient Executed Activities | Investment Project Financing | FY 2018 | Seq No: 1 | ARCHIVED on 25-Oct-2019 | ISR36468 | Implementing Agencies: General Statistics Office, Government of Vietnam Key Dates Key Project Dates Bank Approval Date: 21-May-2018 Effectiveness Date: 07-Dec-2018 Original Closing Date: 30-Jun-2020 Revised Closing Date: 30-Jun-2020 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The overall development objective of this project is to enhance the capacity of the General Statistics Office to adopt advanced methods of data collection and processing. This development objective will be achieved through adopting a revised Vietnam Statistics Development Strategy incorporating use of non-survey data to generate statistics, establishing and piloting methodologies for using non-survey data to generate statistics and piloting use of CAPI in major surveys. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO -- Unsatisfactory Overall Implementation Progress (IP) -- Moderately Unsatisfactory Implementation Status and Key Decisions Implementation of the project activities is behind schedule. None of the procurement activities have been completed and no disbursement has been made as a result. Acceleration of procurement activities is crucial for the completion of activities by the project close date of 30 June 2020. The close date cannot be extended as the Trust Fund financing this project shall also be closing. Therefore a decision was made to expedite the ongoing selection processes and award of contracts and fast track implementation of the VSDS component by concurrently implementing activities where possible. Risks Overall Risk Rating Risk Category Rating at Approval Previous Rating Current Rating Overall Moderate -- Moderate 10/25/2019 Page 1 of 4 The World Bank Implementation Status & Results Report Modernizing Production of Statistics in Vietnam (P166158) 5. Results Project Development Objective Indicators IN00685579 ►Sets of pilot statistics produced using administative data (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 2.00 Date 06-Mar-2018 -- 27-Sep-2019 30-Jun-2020 IN00685588 Set of economic statistics indicators from tax and customs data (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 05-Mar-2018 -- 27-Sep-2019 30-Jun-2020 IN00685589 Set of education statistics produced using administarive data (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 05-Mar-2018 -- 27-Sep-2019 30-Jun-2020 IN00685578 ►Pilot household survey succesfully completed using CAPI (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1.00 Date 05-Mar-2018 -- 27-Sep-2019 31-Mar-2020 IN00685587 ►Updated Vietnam Strategy for Development of Statistics (VSDS) reflecting use of administrative data (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Current VSDS does not VSDS updated to incorporate use of non- incorporate use on non- Value -- VSDS not yet updated survey data for survey data to generate generating statistics statistics Date 05-Mar-2018 -- 27-Sep-2019 20-Jun-2020 Overall Comments PDO Results and outcomes for the project have not yet been achieved due to delayed in implementation. However, the end target results remain unchanged. 10/25/2019 Page 2 of 4 The World Bank Implementation Status & Results Report Modernizing Production of Statistics in Vietnam (P166158) Intermediate Results Indicators IN00685580 ►Developed operation manuals for producing selected official national statistics using administrative data (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 2.00 Date 05-Mar-2018 -- 27-Sep-2019 30-Jun-2020 IN00685586 ►CAPI platforms evaluated and institutional guidelines developed for using CAPI in main GSO surveys (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Several platforms being Policy for CAPI platforms to explored, with no clear Value -- No CAPI review yet be used in its surveys by guidelines on preferred GSO is defined. platforms Date 05-Mar-2018 -- 27-Sep-2019 30-Jun-2020 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P166158 TF-A7413 Effective USD 0.35 0.35 0.00 0.00 0.35 0%% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P166158 TF-A7413 Effective 21-May-2018 07-Dec-2018 07-Dec-2018 30-Jun-2020 30-Jun-2020 Cumulative Disbursements 10/25/2019 Page 3 of 4 The World Bank Implementation Status & Results Report Modernizing Production of Statistics in Vietnam (P166158) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 10/25/2019 Page 4 of 4