Procurement Plan for Beijing Rooftop Solar Pho Contract Amount/Cost Contract Amount/Cost Contract Title Contract Description (USD) (USD) Procurement/ Selection Bank Review Estimated Ref. No. Method (Prior/Post) Opening Equipment Procurement Estimated Actual Supply and installation of rooftop solar photovoltaic (PV) system construction for SS(RE)- the 2011 Beijing Supply and installation of rooftop solar PV system US$4,092,954 US$2,416,631 NCB Prior 4/5/2012 G2011-01 Sunshine Schools construction in the first batch of 35 schools. Golden Sun Project (the first batch of 5MW) Supply and installation of rooftop solar photovoltaic (PV) system construction for SS(RE)- the 2011 Beijing Supply and installation of rooftop solar PV system US$3,898,051 US$2,630,137 NCB Prior 4/20/2012 G2011-02 Sunshine Schools construction in the second batch of 24 schools. Golden Sun Project(the second batch of 5MW) Supply and installation of rooftop solar photovoltaic (PV) Selection of schools, supply and installation of rooftop solar SS-G2013-01 system construction US$2,698,651 US$2,468,966 NCB Prior 11/6/2013 PV system construction in Beijing Schools (the first batch of 95MW-1 ) Supply and installation of rooftop solar photovoltaic (PV) Selection of schools, supply and installation of rooftop SS-G2013-02 system construction US$2,698,651 US$2,078,851 NCB Prior 11/6/2013 solar PV system construction in Beijing Schools (the second batch of 95MW-2) Supply and installation of rooftop solar photovoltaic (PV) Selection of schools, supply and installation of PV system SS-G2013-03 system construction US$2,698,651 US$2,449,037 NCB Prior 11/6/2013 construction in Beijing Schools (the first batch of 95MW -3) Supply and installation of rooftop solar photovoltaic (PV) Selection of schools, supply and installation of PV system SS-G2013-04 system construction US$2,698,651 none NCB Prior 11/6/2013 construction in Beijing Schools (the first batch of 95MW -4) Supply and installation of rooftop solar photovoltaic (PV) Selection of schools, supply and installation of PV system SS-G2013-05 system construction US$2,698,651 US$2,078,851 NCB Prior 11/6/2013 construction in Beijing Schools (the first batch of 95MW -5) Supply and installation of rooftop solar photovoltaic (PV) Selection of schools, supply and installation of PV system SS-G2014-01 system construction US$2,698,651 US$2,446,777 NCB Post 4/11/2014 construction in Beijing Schools (the second batch of 95MW -1) Supply and installation of rooftop solar photovoltaic (PV) Selection of schools, supply and installation of PV system SS-G2014-02 system construction US$2,698,651 US$2,401,511 NCB Post 4/11/2014 construction in Beijing Schools (the second batch of 95MW -2) Supply and installation of rooftop solar photovoltaic (PV) Selection of schools, supply and installation of PV system SS-G2014-03 system construction US$2,698,651 US$2,222,060 NCB Post 4/11/2014 construction in Beijing Schools (the second batch of 95MW -3) Supply and installation of rooftop solar photovoltaic (PV) Selection of schools, supply and installation of PV system SS-G2014-04 system construction US$2,698,651 US$2,375,431 NCB Post 4/11/2014 construction in Beijing Schools (the second batch of 95MW -4) Supply and installation of rooftop solar photovoltaic (PV) Selection of schools, supply and installation of PV system SS-G2014-05 system construction US$2,698,651 US$2,244,843 NCB Post 4/11/2014 construction in Beijing Schools (the second batch of 95MW -5) Supply and installation of rooftop solar photovoltaic (PV) Selection of schools, supply and installation of PV system SS-G2014-06 system construction US$2,698,651 US$2,046,654 NCB Post 4/11/2014 construction in Beijing Schools (the third batch of 95MW -6) Supply and installation of rooftop solar photovoltaic (PV) Selection of schools, supply and installation of PV system SS-G2014-07 system construction US$7,196,402 US$5,598,181 NCB Post 11/18/2014 construction in Beijing Schools (the fourth batch of 95MW -1) Supply and installation of rooftop solar photovoltaic (PV) Choosing of schools,Design,supply,installation and runtime SS-G2014-08 system construction services for rooftopsolar photovoltaic (PV) system in US$7,196,402 US$5,913,043 NCB Post 11/18/2014 (the third batch of Beijing Schools 95MW -2) Supply and installation of rooftop solar photovoltaic (PV) Choosing of schools,Design,supply,installation and runtime SS-G2014-09 system construction services for rooftopsolar photovoltaic (PV) system in US$7,196,402 US$6,104,948 NCB Post 11/18/2014 (the third batch of Beijing Schools 95MW -3) Supply and installation of rooftop solar photovoltaic (PV) Selection of schools, supply and installation of PV system SS-G2015-01 system construction US$7,196,402 US$5,982,302 NCB Post 3/4/2015 construction in Beijing Schools (the fourth batch of 95MW -1) Supply and installation of rooftop solar photovoltaic (PV) Selection of schools, supply and installation of PV system SS-G2015-02 system construction US$7,196,402 US$5,523,088 NCB Post 3/4/2015 construction in Beijing Schools (the fourth batch of 95MW -2) Supply and installation of rooftop solar photovoltaic (PV) Selection of schools, supply and installation of PV system SS-G2015-03 system construction US$7,196,402 US$5,691,297 NCB Post 3/4/2015 construction in Beijing Schools (the fourth batch of 95MW -3) Supply and installation of rooftop solar photovoltaic (PV) Supply and installation of rooftop solar PV system SS-G2016-01 system construction construction (excluding PV modules) in Beijing schools US$2,248,876 NCB Post 10/25/2016 (excluding PV and other educational institutions. modules) (the fifth batch of 95MW -1) Procurement of 15MW PV modules for rooftop Procurement of 15MW PV modules for rooftop solar PV SS-G2016-02 solar PV system system construction in Beijing schools and other US$7,871,064 NCB Post 10/25/2016 construction . (the fifth educational institutions. batch of 95MW -2) PROCUREMENT China : CN: Beijing Rooftop Solar Photovoltaic Scale-Up (Sunshine Schools) Project PLAN General Information Country: China Bank’s Approval Date of the Original Procurement Plan: 2017-08-11 2019-08-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P125022 GPN Date: Project Name: CN: Beijing Rooftop Solar Photovoltaic Scale-Up (Sunshine Schools) Project Loan / Credit No: IBRD / 82350 Executing Agency(ies): Beijing Rooftop Solar WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CN-BEIJING SOLAR-44461- CW-RFB / Supply and installation of rooftop solar PV system construction in Under 1. Sunshine Schools Single Stage - One three subsidiaries of Beijing IBRD / 82350 Post Request for Bids Open - National 3,692,308.00 3,236,474.27 Implementati 2018-02-01 2018-02-07 2018-03-26 2018-04-25 2018-06-08 2018-12-05 Program Support Envelope Energy Investment Holding on Co., Ltd, the tender's installed capacity is expected to be 3MW. CN-BEIJING SOLAR-67064- CW-RFB / Supply and installation of rooftop solar PV system construction in 1. Sunshine Schools Single Stage - One IBRD / 82350 Post Request for Bids Open - National 10,937,500.00 0.00 Canceled 2018-08-10 2018-08-17 2018-09-28 2018-10-28 2018-12-21 2019-06-19 different districts of Beijing , Program Support Envelope the tender's installed capacity is expected to be 10MW. CN-BEIJING SOLAR-72282- CW-RFB / Supply and installation of rooftop solar Under PV system construction in 1. Sunshine Schools Single Stage - One IBRD / 82350 Post Request for Bids Open - National 5,147,059.00 3,746,424.76 Implementati 2018-08-20 2018-08-27 2018-10-08 2018-11-07 2019-01-04 2019-07-03 different districts of Beijing , Program Support Envelope on the tender's installed capacity is expected to be 5MW. CN-BEIJING SOLAR-88283- CW-RFB / Supply and installation of rooftop solar Pending 1. Sunshine Schools Single Stage - One PV system construction in IBRD / 82350 Post Request for Bids Open - National 3,962,536.00 0.00 Implementati 2018-12-07 2018-12-17 2019-01-30 2019-03-01 2019-04-12 2019-10-09 Program Support Envelope Northern Vehicle , the on tender's installed capacity is expected to be 5MW CN-BEIJING SOLAR-88284- CW-RFB / Supply and installation of rooftop solar Pending 1. Sunshine Schools Single Stage - One PV system construction in IBRD / 82350 Post Request for Bids Open - National 2,773,775.00 0.00 Implementati 2018-12-28 2019-01-09 2019-02-28 2019-03-30 2019-05-11 2019-11-07 Program Support Envelope Yizhuang of State Grid , the on tender's installed capacity is expected to be 3.5MW CN-BEIJING SOLAR-88285- CW-RFB / Supply and installation of rooftop solar Pending PV system construction in 1. Sunshine Schools Single Stage - One IBRD / 82350 Post Request for Bids Open - National 4,755,043.00 0.00 Implementati 2018-12-28 2019-01-09 2019-02-28 2019-03-30 2019-05-11 2019-11-07 different districts of Beijing , Program Support Envelope on the tender's installed capacity is expected to be 6MW Page 1 CN-BEIJING SOLAR-91385- CW-RFB / Supply and installation of rooftop solar 1. Sunshine Schools Single Stage - One PV system construction in IBRD / 82350 Post Request for Bids Open - National 7,959,479.00 0.00 Canceled 2018-12-28 2019-01-11 2019-03-05 2019-04-04 2019-05-17 2019-11-13 Program Support Envelope BAIC Motor Shenbao, the tender's installed capacity is expected to be 9MW. CN-BEIJING SOLAR-95968- CW-RFB / Supply and instal Pending lation of rooftop solar photov 1. Sunshine Schools Single Stage - One IBRD / 82350 Post Request for Bids Open - National 1,533,923.00 0.00 Implementati 2019-01-25 2019-02-12 2019-03-26 2019-04-25 2019-06-19 2019-12-16 oltaic (PV) system constructi Program Support Envelope on on (the first batch in 2019) . CN-BEIJING SOLAR- 104927-CW-RFB / Supply and installation of rooftop Pending 1. Sunshine Schools Single Stage - One solar PV system construction IBRD / 82350 Post Request for Bids Open - National 4,626,866.00 0.00 Implementati 2019-03-08 2019-03-15 2019-04-26 2019-05-26 2019-07-07 2019-12-24 Program Support Envelope in Jingliang JCL, the on tender's installed capacity is expected to be 5.5MW. CN-BEIJING SOLAR- 106338-CW-RFB / Supply and installation of rooftop Pending solar PV system construction 1. Sunshine Schools Single Stage - One IBRD / 82350 Post Request for Bids Open - National 626,866.00 0.00 Implementati 2019-03-19 2019-03-26 2019-05-07 2019-06-06 2019-07-18 2019-12-15 in Jingfeng Thermal Power, Program Support Envelope on the tender's installed capacity is expected to be 0.6MW. CN-BEIJING SOLAR- 107671-CW-RFB / Supply and installation of rooftop Pending 1. Sunshine Schools Single Stage - One solar PV system construction IBRD / 82350 Post Request for Bids Open - National 7,014,925.00 0.00 Implementati 2019-03-26 2019-04-02 2019-05-14 2019-06-13 2019-08-07 2019-12-25 Program Support Envelope in CRRCGC 27 Plant, the on tender's installed capacity is expected to be 10MW. CN-BEIJING SOLAR- 110930-CW-RFB / Supply and installation of rooftop Pending 1. Sunshine Schools Single Stage - One solar PV system construction IBRD / 82350 Post Request for Bids Open - National 8,059,701.00 0.00 Implementati 2019-04-17 2019-04-24 2019-06-05 2019-07-05 2019-08-16 2019-12-31 Program Support Envelope in Mercedes-Benz plant, the on tender's installed capacity is expected to be 9MW. CN-BEIJING SOLAR- 111566-CW-RFB / Supply and installation of rooftop Pending solar PV system construction 1. Sunshine Schools Single Stage - One IBRD / 82350 Post Request for Bids Open - National 3,176,119.00 0.00 Implementati 2019-04-24 2019-04-29 2019-06-10 2019-07-10 2019-08-21 2019-12-29 in Pingxifu Vehicle Repair Program Support Envelope on Factory, the tender's installed capacity is expected to be 4.092MW CN-BEIJING SOLAR- 120179-CW-RFB / Supply and installation of rooftop Pending 1. Sunshine Schools Single Stage - One solar PV system construction IBRD / 82350 Post Request for Bids Open - National 3,117,647.00 0.00 Implementati 2019-06-24 2019-07-01 2019-08-12 2019-09-11 2019-10-23 2019-12-22 Program Support Envelope in LIANDONG U Valley, the on tender's installed capacity is expected to be 4MW CN-BEIJING SOLAR- 120868-CW-RFB / Supply and installation of rooftop solar PV system construction Pending 1. Sunshine Schools Single Stage - One in National Automobile IBRD / 82350 Post Request for Bids Open - National 3,117,647.00 0.00 Implementati 2019-06-26 2019-07-03 2019-08-14 2019-09-13 2019-10-25 2019-12-24 Program Support Envelope Quality Supervision and on Inspection Center, the tender's installed capacity is expected to be 4MW. Page 2 CN-BEIJING SOLAR- 120872-CW-RFB / Supply and installation of rooftop Pending 1. Sunshine Schools Single Stage - One solar PV system construction IBRD / 82350 Post Request for Bids Open - National 2,573,529.00 0.00 Implementati 2019-06-26 2019-07-03 2019-08-14 2019-09-13 2019-10-25 2019-12-25 Program Support Envelope in Beijiantongcheng the on tender's installed capacity is expected to be 3.5MW. CN-BEIJING SOLAR- 120883-CW-RFB / Supply and installation of rooftop Pending 1. Sunshine Schools Single Stage - One solar PV system construction IBRD / 82350 Post Request for Bids Open - National 7,352,941.00 0.00 Implementati 2019-06-26 2019-07-03 2019-08-14 2019-09-13 2019-10-25 2019-12-24 Program Support Envelope in Shunyi Airport Area the on tender's installed capacity is expected to be 10MW SS-G2019-12 / Supply and installation of rooftop solar Pending PV system construction in 1. Sunshine Schools Single Stage - One IBRD / 82350 Post Request for Bids Open - National 9,529,412.00 0.00 Implementati 2019-06-26 2019-07-03 2019-08-14 2019-09-13 2019-10-25 2019-12-25 SHUNYI DISTRICT, the Program Support Envelope on tender's installed capacity is expected to be 12MW SS-G2019-09 / Supply and installation of rooftop solar Pending PV system construction in 1. Sunshine Schools Single Stage - One IBRD / 82350 Post Request for Bids Open - National 1,345,588.00 0.00 Implementati 2019-06-28 2019-07-05 2019-08-16 2019-09-15 2019-10-27 2019-12-26 Jimei Furniture the tender's Program Support Envelope on installed capacity is expected to be 1.5MW SS-G2019-13 / Supply and installation of rooftop solar Pending PV system construction in 1. Sunshine Schools Single Stage - One IBRD / 82350 Post Request for Bids Open - National 3,529,412.00 0.00 Implementati 2019-06-28 2019-07-05 2019-08-16 2019-09-15 2019-10-27 2019-12-26 three subsidiaries of Beijing Program Support Envelope on Energy Investment Holding Co., Ltd CN-BEIJING SOLAR- 128677-CW-RFB / Supply and installation of rooftop Pending 1. Sunshine Schools Single Stage - One solar PV system construction IBRD / 82350 Post Request for Bids Open - National 3,200,000.00 0.00 Implementati 2019-08-23 2019-08-26 2019-09-30 2019-10-10 2019-10-20 2019-12-19 Program Support Envelope in SHUNYI SMC, the on tender's installed capacity is expected to be 4MW. CN-BEIJING SOLAR- 128691-CW-RFB / Supply and installation of rooftop Pending 1. Sunshine Schools Single Stage - One solar PV system construction IBRD / 82350 Post Request for Bids Open - National 700,000.00 0.00 Implementati 2019-08-23 2019-08-26 2019-09-30 2019-10-09 2019-10-19 2019-12-19 Program Support Envelope in Zhuo Chen Livestock, the on tender's installed capacity is expected to be 1MW CN-BEIJING SOLAR- 128694-CW-RFB / Supply and installation of rooftop Pending 1. Sunshine Schools Single Stage - One solar PV system construction IBRD / 82350 Post Request for Bids Open - National 1,050,000.00 0.00 Implementati 2019-08-23 2019-08-26 2019-09-30 2019-10-10 2019-10-20 2019-12-19 Program Support Envelope in YI Garden, the tender's on installed capacity is expected to be 1.5MW CN-BEIJING SOLAR- 128695-CW-RFB / Supply and installation of rooftop Pending 1. Sunshine Schools Single Stage - One solar PV system construction IBRD / 82350 Post Request for Bids Open - National 1,714,286.00 0.00 Implementati 2019-08-23 2019-08-26 2019-09-30 2019-10-10 2019-10-20 2019-12-19 Program Support Envelope in HUIYUAN Juice, the on tender's installed capacity is expected to be 2.4MW GOODS Page 3 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SS-G2017-02 / According to the EPC contract of Beijing Sunshine Schools Golden Su n Project (5MW and the firs Under 1. Sunshine Schools Single Stage - One t batch of 95MW-1)and Ene IBRD / 82350 Post Request for Bids Open - National 591,716.00 345,495.54 Implementati 2017-08-16 2017-08-22 2017-10-10 2017-11-09 2017-12-23 2018-06-21 Program Support Envelope rgy saving and environmenta on l protection center,offering pr ocurement services of commu nication data collector. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4