The World Bank Implementation Status & Results Report National Hydrology Project (P152698) National Hydrology Project (P152698) SOUTH ASIA | India | Water Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 6 | ARCHIVED on 04-Dec-2019 | ISR39562 | Implementing Agencies: Ministry of Finance, Department of Economic Affairs, Ministry of Water Resources, River Development & Ganga Rejuvenation Key Dates Key Project Dates Bank Approval Date: 15-Mar-2017 Effectiveness Date: 05-May-2017 Planned Mid Term Review Date: 10-Dec-2019 Actual Mid-Term Review Date: Original Closing Date: 31-Mar-2025 Revised Closing Date: 31-Mar-2025 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The proposed Project Development Objective (PDO) is to improve the extent, quality, and accessibility of water resources information and to strengthen the capacity of targeted water resources management institutions in India. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Water Resources Monitoring System:(Cost $150.00 M) Water Resources Information Systems:(Cost $50.00 M) Water Resources Operations and Planning System:(Cost $66.00 M) Institutional Capacity Enhancement:(Cost $83.56 M) Front End Fee:(Cost $0.44 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO ►Moderately Satisfactory ►Moderately Satisfactory Overall Implementation Progress (IP) ►Moderately Unsatisfactory ►Moderately Unsatisfactory Overall Risk Rating ►Substantial ►Substantial Implementation Status and Key Decisions 12/4/2019 Page 1 of 6 The World Bank Implementation Status & Results Report National Hydrology Project (P152698) The project Mid-Term Review (MTR) is drawing to a close. The project is making progress in implementing all components and efforts have been introduced to ensure a common level of performance by the various implementing agencies. To date, good progress is seen in strengthening of core services by central including standardized online database management system for integrated water management. The online database management system, e-SWIS (only for surface water) has successfully been upgraded to the Water Information Management system (WIMS) that will now allow data collation for surface water, groundwater and water quality. This data will feed into the recently operationalized Water Resources Information System (WRIS). More significantly, 24 states have joined the national database platform and 17 States have begun sharing key historical data which will pave the way for holistic and integrated decision making beyond administrative boundaries. This is being operated and maintained by the National Water Informatics Center (NWIC) which is now functional and is hosting IndiaWRIS at http://indiawris.gov.in/wris/. This platform will host a vast amount of historical and real time spatio-temporal information. Now the states would be able to use and update their river basin information systems in a dynamic fashion. Ministry of Jal Shakti has instituted a policy to share data online for classified basins (Ganga and Brahmaputra) with the key basin states. Eventually the major products from the project shall include: Flood forecasting and reservoir operation systems; mapping water availability and accounting from watershed to basin scales; drought management plans for selected rivers basins. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance ►Low ►Low ►Low Macroeconomic ►Low ►Low ►Low Sector Strategies and Policies ►Substantial ►Substantial ►Substantial Technical Design of Project or Program ►Substantial ►Substantial ►Substantial Institutional Capacity for Implementation and Sustainability ►Substantial ►Substantial ►Substantial Fiduciary ►Substantial ►Substantial ►Substantial Environment and Social ►Low ►Low ►Moderate Stakeholders ►Low ►Low ►Low Other ►High ►High ►High Overall ►Substantial ►Substantial ►Substantial Results PDO Indicators by Objectives / Outcomes Project Development Objective Indicators IN00773892 12/4/2019 Page 2 of 6 The World Bank Implementation Status & Results Report National Hydrology Project (P152698) ►Water resources monitoring stations operated by implementing agencies providing validated data online (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 4,370.00 4,650.00 4,650.00 12,000.00 Date 16-Mar-2017 20-Feb-2019 20-Feb-2019 31-Mar-2025 IN00773893 ►Surface water stations (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 909.00 950.00 950.00 2,500.00 Date 16-Mar-2017 20-Feb-2019 20-Feb-2019 31-Mar-2025 IN00773894 ►Groundwater stations (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 2,310.00 2,500.00 2,500.00 7,000.00 Date 16-Mar-2017 20-Feb-2019 20-Feb-2019 31-Mar-2025 IN00773895 ►Meteorology stations (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 1,140.00 1,200.00 1,200.00 2,500.00 Date 16-Mar-2017 20-Feb-2019 20-Feb-2019 31-Mar-2025 IN00773916 ►Information products produced under the project made available to the relevant stakeholders (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 5.00 5.00 5.00 50.00 Date 16-Mar-2017 20-Feb-2019 20-Feb-2019 31-Mar-2025 IN00773917 ►Water Resources Institutions achieving benchmark performance levels (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 10.00 10.00 10.00 25.00 Date 16-Mar-2017 20-Feb-2019 20-Feb-2019 31-Mar-2025 IN00773918 ►Institutions upgraded to next performance level (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 25.00 12/4/2019 Page 3 of 6 The World Bank Implementation Status & Results Report National Hydrology Project (P152698) Date 16-Mar-2017 20-Feb-2019 20-Feb-2019 31-Mar-2025 Intermediate Results Indicators by Components Intermediate Results Indicators IN00773919 ►WRIS users satisfied with the services (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 16-Mar-2017 20-Feb-2019 20-Feb-2019 31-Mar-2025 IN00773920 ►Water data centers functioning satisfactorily (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 10.00 10.00 10.00 30.00 Date 16-Mar-2017 20-Feb-2019 20-Feb-2019 31-Mar-2025 IN00773921 ►Page views to access the information at WRIS (Number (Thousand), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 400.00 420.00 420.00 900.00 Date 16-Mar-2017 20-Feb-2019 20-Feb-2019 31-Mar-2025 IN00773922 ►Water availability report for river sub-basins published regularly (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 3.00 3.00 3.00 30.00 Date 16-Mar-2017 20-Feb-2019 20-Feb-2019 31-Mar-2025 IN00773923 ►Streamflow forecasting stations with improved lead time (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 200.00 200.00 200.00 325.00 Date 16-Mar-2017 20-Feb-2019 20-Feb-2019 31-Mar-2025 IN00773924 ►Targeted professionals trained (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 12/4/2019 Page 4 of 6 The World Bank Implementation Status & Results Report National Hydrology Project (P152698) Value 0.00 110.00 110.00 2,000.00 Date 16-Mar-2017 20-Feb-2019 20-Feb-2019 31-Mar-2025 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P152698 IBRD-87250 Effective USD 175.00 175.00 0.00 17.39 157.61 9.9% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P152698 IBRD-87250 Effective 15-Mar-2017 18-Apr-2017 05-May-2017 31-Mar-2025 31-Mar-2025 Cumulative Disbursements 12/4/2019 Page 5 of 6 The World Bank Implementation Status & Results Report National Hydrology Project (P152698) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 12/4/2019 Page 6 of 6