REGIONAL INFRASTRUCTURE DEVELOPMENT FUND PROJECT DEVELOPMENT FACILITY (RIDF-PDF) GRANT No. TF0A3871 Procurement Plan Version No.: 3 Date: July 10, 2018 I. General Information 1. Project information: a. Country: Indonesia b. Recipient: Republic of Indonesia c. Project Name: Regional Infrastructure Development Fund - Project Development Facility (RIDF-PDF) d. Project Implementing Agency (PIA): (i) PT Sarana Multi Infrastruktur (Persero) (PT SMI) 2. Bank’s No Objection Date of the Procurement Plan: a. Original : December 30, 2016 b. Version 2 : December, 21, 2017 c. Version 3 : July, 24, 2018 3. Date of General Procurement Notice: January 17, 2017 4. Period covered by this procurement plan: Effectiveness – Closing Date (estimated mid 2019) II. Types of Contract, Bank’s Review Requirements and Applied Methods A. Works, Goods and Non-Consulting Services 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review No. Procurement Method Threshold Threshold 1. ICB (Goods) > US$ 2 million All contract 2. NCB (Goods) US$ 100,000 - US$ 2 million ≥ US$ 1.5 million 3. Shopping for Goods < US$ 100,000 N/A 4. ICB (Non-Consultant ≥ US$ 10 million All contract Service) 5. NCB (Non-Consultant US$ 100,000 - US$ 10 ≥ US$ 1.5 million Service) million 6. Shopping for Non- < US$ 100,000 N/A Consulting Service 1. Pre-qualification: N/A. 2. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: As specified in the Project Operations Manual (POM). 3. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual of RIDF. 4. Any Other Special Procurement Arrangements: N/A. 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement): N/A. B. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to prior review by Bank as stated in Appendix 1 to the Guidelines for Selection and Employment of Consultants: Ref. Bank’s Prior Review Selection Method Selection Method Threshold Requirement No. 1. Competitive ≥ US$ 300,000 ≥ US$ 500,000 Methods (Firms) QCBS, QBS, LCS, FBS 2. Competitive < US$ 300,000 ≥ US$ 500,000 Methods (Firms) CQS 3. Individual Competitive Selection by ≥ US$ 200,000 and specific Consultants comparing at least 3 CVs position as indicated in this procurement plan 2. Short list comprising entirely of national consultants: Short list of consultants for services (firms), estimated to cost less than $ 400,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: N/A 4. Summary of Consultancy Assignments with Selection Methods and Time Schedule after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 5 6 7 Ref. Description Type of Estimated Packages/ Review Comments No. of Assignments Cost Positions by Bank Assignments (US$ (Prior / million) Post) 1. Summary of (Lump-Sum) 374,597 1 Post number of contracts that will be let under QCBS 2. Summary of (Lump-Sum) 2,388,602 25 Post number of contracts that will be let under CQS 3. Summary of (Time-Based 180,362 7 Post number of /Lump-Sum) individual consultant contracts that 34,286 1 Prior will be let under competitive selection PROCUREMENT Indonesia : Regional Infrastructure Development Fund PLAN General Information Country: Indonesia Bank’s Approval Date of the Original Procurement Plan: 2018-09-07 2019-11-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154947 GPN Date: Project Name: Regional Infrastructure Development Fund Loan / Credit No: TF / A3871, COFN / C1480 Executing Agency(ies): PT SARANA MULTI INFRASTRUKTUR (PERSERO) WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RIDF-PDF-1 / Detailed Consultant Component 2: RIDF Project Engineering Design of Eye TF / A3871 Post Qualification Open - National 124,866.00 0.00 Under Review 2018-09-03 2018-09-24 2018-11-07 2018-12-07 2019-01-11 2019-07-10 Development Facility Hospital (North Sulawesi) Selection RIDF-PDF-2 / Consultant Environmental Impact Component 2: RIDF Project TF / A3871 Post Qualification Open - National 38,677.00 0.00 Under Review 2018-09-03 2018-09-24 2018-11-07 2018-12-07 2019-01-11 2019-07-10 Assessment of Eye Hospital Development Facility Selection (North Sulawesi) RIDF-PDF-10 / Feasibility Consultant Study of 2 Roads and Component 2: RIDF Project TF / A3871 Post Qualification Open - National 106,904.00 0.00 Canceled 2018-09-03 2018-09-24 2018-11-07 2018-12-07 2019-01-11 2019-07-10 Bridges Projects in Sulawesi Development Facility Selection and Sumatera RIDF-PDF-11 / Feasibility Consultant Component 2: RIDF Project Study of Hospital Project in TF / A3871 Post Qualification Open - National 53,452.00 0.00 Canceled 2018-09-03 2018-09-24 2018-11-07 2018-12-07 2019-01-11 2019-07-10 Development Facility Kalimantan Selection RIDF-PDF-12 / Feasibility Consultant Component 2: RIDF Project Study of a Water Supply TF / A3871 Post Qualification Open - National 53,452.00 0.00 Canceled 2018-09-03 2018-09-24 2018-11-07 2018-12-07 2019-01-11 2019-07-10 Development Facility Project in Sumatera Selection Page 1 RIDF-PDF-13 / Feasibility Consultant Study of a Traditional Component 2: RIDF Project TF / A3871 Post Qualification Open - National 53,452.00 0.00 Canceled 2018-09-10 2018-10-01 2018-11-14 2018-12-14 2019-01-18 2019-07-17 Market Project in Nusa Development Facility Selection Tenggara RIDF-PDF-14 / Feasibility Consultant Study of a Solid Waste Component 2: RIDF Project TF / A3871 Post Qualification Open - National 53,452.00 0.00 Canceled 2018-09-10 2018-10-01 2018-11-14 2018-12-14 2019-01-18 2019-07-17 Management Project in Nusa Development Facility Selection Tenggara RIDF-PDF-15 / Feasibility Consultant Study of a Waste Water Component 2: RIDF Project TF / A3871 Post Qualification Open - National 53,452.00 0.00 Canceled 2018-09-10 2018-10-01 2018-11-14 2018-12-14 2019-01-18 2019-07-17 Treatment Project in Nusa Development Facility Selection Tenggara RIDF-PDF-16 / Feasibility Consultant Study Review of 2 Hospital Component 2: RIDF Project TF / A3871 Post Qualification Open - National 19,376.00 0.00 Canceled 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 Projects in Sumatera and Development Facility Selection Kalimantan RIDF-PDF-17 / Detailed Consultant Component 2: RIDF Project Under Engineering Design of a TF / A3871 Post Qualification Open - National 124,866.00 0.00 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 Development Facility Implementation Road Project in Sumatera Selection RIDF-PDF-18 / Detailed Engineering Design of 3 Component 2: RIDF Project Quality And Cost- TF / A3871 Post Open - National 374,597.00 0.00 Canceled 2018-11-12 2018-12-03 2019-01-16 2019-02-13 2019-03-15 2019-04-19 2019-05-24 2020-05-23 Hospital Projects in Development Facility Based Selection Sumatera and Kalimantan RIDF-PDF-19 / Detailed Consultant Engineering Design of a Component 2: RIDF Project TF / A3871 Post Qualification Open - National 124,866.00 0.00 Canceled 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 Water Supply Project in Development Facility Selection Sumatera RIDF-PDF-20 / Detailed Engineering Design of 2 Consultant Component 2: RIDF Project Under Traditional Market Projects TF / A3871 Post Qualification Open - National 249,731.00 0.00 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 Development Facility Implementation in Nusa Tenggara and Selection Kalimantan RIDF-PDF-21 / Detailed Consultant Engineering Design of a Component 2: RIDF Project TF / A3871 Post Qualification Open - National 124,866.00 0.00 Canceled 2018-11-19 2018-12-10 2019-01-23 2019-02-22 2019-03-29 2019-09-25 Solid Waste Management Development Facility Selection Project in Nusa Tenggara RIDF-PDF-22 / Detailed Consultant Engineering Design of a Component 2: RIDF Project TF / A3871 Post Qualification Open - National 124,866.00 0.00 Canceled 2018-11-19 2018-12-10 2019-01-23 2019-02-22 2019-03-29 2019-09-25 Waste Water Treatment Development Facility Selection Project in Nusa Tenggara RIDF-PDF-23 / Consultant Environmental Impact Component 2: RIDF Project TF / A3871 Post Qualification Open - National 38,677.00 0.00 Canceled 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 Assessment of a Road Development Facility Selection Project Sumatera RIDF-PDF-24 / Consultant Environmental Impact Component 2: RIDF Project TF / A3871 Post Qualification Open - National 112,950.00 0.00 Canceled 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 Assessment of a Hospital Development Facility Selection Project in Kalimantan RIDF-PDF-25 / Consultant Environmental Impact Component 2: RIDF Project TF / A3871 Post Qualification Open - National 112,950.00 0.00 Canceled 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 Assessment of a Water Development Facility Selection Supply Project in Sumatera Page 2 RIDF-PDF-26 / Environmental Impact Consultant Assessment of 2 Traditional Component 2: RIDF Project Under TF / A3871 Post Qualification Open - National 225,901.00 0.00 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 Market Projects in Development Facility Implementation Selection Kalimantan and Nusa Tenggara RIDF-PDF-27 / Environmental Impact Consultant Component 2: RIDF Project Assessment of a Solid Waste TF / A3871 Post Qualification Open - National 112,950.00 0.00 Canceled 2018-11-19 2018-12-10 2019-01-23 2019-02-22 2019-03-29 2019-09-25 Development Facility Management Project in Nusa Selection Tenggara RIDF-PDF-28 / Environmental Impact Consultant Component 2: RIDF Project Assessment of a Waste TF / A3871 Post Qualification Open - National 112,950.00 0.00 Canceled 2018-11-19 2018-12-10 2019-01-23 2019-02-22 2019-03-29 2019-09-25 Development Facility Water Treatment Project in Selection Nusa Tenggara RIDF-PDF-29 / Master Plan Consultant Component 2: RIDF Project of 3 Hospital Projects in TF / A3871 Post Qualification Open - National 116,030.00 0.00 Canceled 2018-11-12 2018-12-03 2019-01-16 2019-02-15 2019-03-22 2019-09-18 Development Facility Kalimantan and Sumatera Selection RIDF-PDF-30 / Feasibility Consultant Component 2: RIDF Project Study of Road Project TF / A3871 Post Qualification Open - National 31,476.00 0.00 Under Review 2017-08-09 2017-08-30 2017-10-13 2017-11-12 2017-12-17 2018-06-15 Development Facility (Central Lampung) Selection RIDF-PDF-31 / Consultant Environmental Impact Component 2: RIDF Project TF / A3871 Post Qualification Open - National 36,698.00 0.00 Canceled 2018-01-09 2018-01-30 2018-03-15 2018-04-14 2018-05-19 2018-11-15 Assessment of a Road and Development Facility Selection Bridge Project in Lampung RIDF-PDF-35 / Feasibility Consultant Component 2: RIDF Project Study of a Street Lighting TF / A3871 Post Qualification Open - National 33,074.00 0.00 Under Review 2019-02-09 2019-03-02 2019-04-15 2019-05-15 2019-06-19 2019-12-16 Development Facility Project (Bengkulu) Selection RIDF-PDF-40 / Feasibility Consultant Component 2: RIDF Project Under Study of 3 Road Project in TF / A3871 Post Qualification Open - National 154,827.00 0.00 2019-09-30 2019-10-21 2019-12-04 2020-01-03 2020-02-07 2020-08-05 Development Facility Implementation Sumatera dan Jawa Selection RIDF-PDF-41 / Feasibility Consultant Component 2: RIDF Project Study of a Traditional TF / A3871 Post Qualification Open - National 51,609.00 0.00 Under Review 2019-09-30 2019-10-21 2019-12-04 2020-01-03 2020-02-07 2020-08-05 Development Facility Market Project in Sulawesi Selection RIDF-PDF-42 / Feasibility Consultant Component 2: RIDF Project Study of 2 Hospital Project TF / A3871 Post Qualification Open - National 103,218.00 0.00 Under Review 2019-11-29 2019-12-20 2020-02-02 2020-03-03 2020-04-07 2020-10-04 Development Facility in Sumatera and Kalimantan Selection RIDF-PDF-43 / Detailed Engineering Design of 6 Component 2: RIDF Project Quality And Cost- TF / A3871 Post Open - National 615,901.00 0.00 Under Review 2019-11-29 2019-12-20 2020-02-02 2020-03-01 2020-03-31 2020-05-05 2020-06-09 2021-06-09 Road Project in Sumatera, Development Facility Based Selection Sulawesi and Nusa Tenggara RIDF-PDF-44 / Detailed Consultant Engineering Design of a Component 2: RIDF Project Pending TF / A3871 Post Qualification Open - National 101,386.00 0.00 2019-11-29 2019-12-20 2020-02-02 2020-03-03 2020-04-07 2020-10-04 Traditional Market in Development Facility Implementation Selection Sulawesi RIDF-PDF-45 / Detailed Consultant Engineering Design of 2 Component 2: RIDF Project Pending TF / A3871 Post Qualification Open - National 206,565.00 0.00 2019-11-29 2019-12-20 2020-02-02 2020-03-03 2020-04-07 2020-10-04 Hospital Projects in Development Facility Implementation Selection Sumatera RIDF-PDF-46 / Detailed Consultant Engineering Design Review Component 2: RIDF Project TF / A3871 Post Qualification Open - National 101,386.00 0.00 Under Review 2019-09-30 2019-10-21 2019-12-04 2020-01-03 2020-02-07 2020-08-05 of a Tourism Project in Development Facility Selection Sulawesi Page 3 RIDF-PDF-47 / Environmental Impact Component 2: RIDF Project Quality And Cost- Assessment of 5 Road TF / A3871 Post Open - National 512,634.00 0.00 Under Review 2019-11-29 2019-12-20 2020-02-02 2020-03-01 2020-03-31 2020-05-05 2020-06-09 2021-06-09 Development Facility Based Selection Project in Sumatera, Sulawesi dan Jawa RIDF-PDF-48 / Consultant Environmental Impact Component 2: RIDF Project Pending TF / A3871 Post Qualification Open - National 102,812.00 0.00 2019-11-29 2019-12-20 2020-02-02 2020-03-03 2020-04-07 2020-10-04 Assessment of a Hospital Development Facility Implementation Selection Project in Sumatera RIDF-PDF-49 / Masterplan Consultant Component 2: RIDF Project of 2 General Hospital in TF / A3871 Post Qualification Open - National 103,218.00 0.00 Under Review 2019-11-29 2019-12-20 2020-02-02 2020-03-03 2020-04-07 2020-10-04 Development Facility Sumatera and Kalimantan Selection RIDF-PDF-50 / Consultant Consultant Component 2: RIDF Project Team for Capacity Building TF / A3871 Post Qualification Open - National 63,448.00 0.00 Under Review 2019-11-29 2019-12-20 2020-02-02 2020-03-03 2020-04-07 2020-10-04 Development Facility Activities (outreach activity) Selection RIDF-PDF-56 / FS of Study Consultant Component 1: Capital Pending of a Hospital in Musi COFN / C1480 Post Qualification Open - National 25,095.00 0.00 2019-11-06 2019-11-27 2020-01-10 2020-02-09 2020-03-15 2020-09-11 Support for RIDF Implementation Banyuasin Selection RIDF-PDF-57 / AMDAL Consultant Component 1: Capital Pending General Hospital in North COFN / C1480 Post Qualification Open - National 112,950.00 0.00 2019-11-06 2019-11-27 2020-01-10 2020-02-09 2020-03-15 2020-09-11 Support for RIDF Implementation Sulawesi Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RIDF-PDF-3 / Individual Individual Component 2: RIDF Project Under Consultant for TF / A3871 Post Consultant Open 34,286.00 0.00 2018-09-03 2018-10-22 2018-11-12 2018-12-17 2019-06-15 Development Facility Implementation Environmental Specialist Selection RIDF-PDF-4 / Individual Individual Component 2: RIDF Project Under Consultant for Social TF / A3871 Post Consultant Open 34,286.00 0.00 2018-09-03 2018-10-22 2018-11-12 2018-12-17 2019-06-15 Development Facility Implementation Specialist Selection RIDF-PDF-5 / Individual Individual Component 2: RIDF Project Consultant for Procurement TF / A3871 Prior Consultant Open 34,286.00 33,578.90 Signed 2018-09-03 2018-10-22 2018-11-12 2018-12-17 2019-06-15 Development Facility Specialist Selection RIDF-PDF-6 / Individual Individual Consultant for Feasibility Component 2: RIDF Project TF / A3871 Post Consultant Open 9,688.00 0.00 Canceled 2018-11-12 2018-12-31 2019-01-21 2019-02-25 2019-08-24 Study Review of a Road Development Facility Selection Project in Papua RIDF-PDF-7 / Individual Individual Consultant to Review Component 2: RIDF Project TF / A3871 Post Consultant Open 9,688.00 0.00 Canceled 2018-11-12 2018-12-31 2019-01-21 2019-02-25 2019-08-24 Detailed Engineering Design Development Facility Selection of a Road Project in Papua RIDF-PDF-8 / Individual Consultant to Review Individual Environmental Impact Component 2: RIDF Project TF / A3871 Post Consultant Open 19,376.00 0.00 Canceled 2018-11-12 2018-12-31 2019-01-21 2019-02-25 2019-08-24 Assessment of 2 Roads Development Facility Selection Projects in Sumatera and Kalimantan Page 4 RIDF-PDF-9 / Individual Consultant to Review Individual Environmental Impact Component 2: RIDF Project TF / A3871 Post Consultant Open 19,376.00 0.00 Canceled 2018-11-12 2018-12-31 2019-01-21 2019-02-25 2019-08-24 Assessment of 2 Hospital Development Facility Selection Projects in Sumatera and Kalimantan RIDF-PDF-32 / Detailed Individual Component 2: RIDF Project Engineering Design of Road TF / A3871 Post Consultant Open 70,922.00 0.00 Canceled 2018-01-09 2018-02-27 2018-03-20 2018-04-24 2018-10-21 Development Facility Project (Central Lampung) Selection RIDF-PDF-33 / Detailed Individual Component 2: RIDF Project Engineering Design General TF / A3871 Post Consultant Open 124,866.00 0.00 Under Review 2018-05-09 2018-06-27 2018-07-18 2018-08-22 2019-02-18 Development Facility Hospital (North Sulawesi) Selection RIDF-PDF-34 / Individual Environmental Impact Component 2: RIDF Project TF / A3871 Prior Consultant Open 112,950.00 0.00 Canceled 2018-05-09 2018-06-27 2018-07-18 2018-08-22 2019-02-18 Assessment of General Development Facility Selection Hospital (North Sulawesi) RIDF-PDF-36 / Individual Consultant financial and Individual Component 2: RIDF Project Under economic for Feasibility TF / A3871 Post Consultant Open 10,109.00 0.00 2019-04-11 2019-05-30 2019-06-20 2019-07-25 2020-01-21 Development Facility Implementation Study Review of a Tourism Selection Project in Sulawesi RIDF-PDF-37 / Individual Consultant engineering for Individual Component 2: RIDF Project Feasibility Study Review of TF / A3871 Post Consultant Open 10,109.00 0.00 Under Review 2019-04-12 2019-05-31 2019-06-21 2019-07-26 2020-01-22 Development Facility a Tourism Project in Selection Sulawesi RIDF-PDF-38 / Individual Consultant planning for Individual Component 2: RIDF Project Feasibility Study Review of TF / A3871 Post Consultant Open 10,109.00 0.00 Under Review 2019-04-13 2019-06-01 2019-06-22 2019-07-27 2020-01-23 Development Facility a Tourism Project in Selection Sulawesi RIDF-PDF-39 / Individual Consultant for Individual Component 2: RIDF Project Pending Environmental Impact TF / A3871 Post Consultant Open 25,679.00 0.00 2019-04-14 2019-06-02 2019-06-23 2019-07-28 2020-01-24 Development Facility Implementation Assessment Review of a Selection Tourism Project in Sulawesi RIDF-PDF-51 / Individual Individual Component 2: RIDF Project Pending Consultant for Enviromental TF / A3871 Post Consultant Open 22,759.00 0.00 2019-08-02 2019-09-20 2019-10-11 2019-11-15 2020-05-13 Development Facility Implementation Specialist Contract 2 Selection RIDF-PDF-52 / Individual Component 2: RIDF Project Pending Consultant for Social TF / A3871 Post Direct Selection Direct 22,579.00 0.00 2019-08-02 2019-08-12 2019-10-16 2020-04-13 Development Facility Implementation Specialist contract 2 RIDF-PDF-53 / Individual Component 2: RIDF Project Pending Consultant for Procurement TF / A3871 Prior Direct Selection Direct 22,759.00 0.00 2019-08-02 2019-08-12 2019-10-16 2020-04-13 Development Facility Implementation Specialist 3 RIDF-PDF-54 / Individual Individual Component 1: Capital Pending Consultant for Health COFN / C1480 Post Consultant Open 24,000.00 0.00 2019-09-06 2019-10-25 2019-11-15 2019-12-20 2020-06-17 Support for RIDF Implementation Specialist Selection RIDF-PDF-55 / RIDF-PDF Individual Component 1: Capital Pending Procurement Specialist COFN / C1480 Prior Consultant Open 5,559.00 0.00 2019-11-06 2019-12-25 2020-01-15 2020-02-19 2020-08-17 Support for RIDF Implementation Contract 2 Selection Page 5