18 Months Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: January 19, 2016 2. Date of General Procurement Notice: August 5, 2016 3. Period covered by this procurement plan: June 2016 to December 2017 4. Implementing Agencies: • Component 1: Ministry of Agriculture, Forestry and Fisheries (MAFF): Fisheries Administration (FiA) • Component 2: Cambodian National Mekong Committee (CNMC) II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement. Procurement Method Prior Review Threshold Comments US$ 1. Each package estimated Goods to cost more than 2,000,000 2. Each package estimated Works to cost more than 10,000,000 3. (Non-Consultant Services) Each package estimated to cost more than 2,000,000 2. Prequalification. Not applicable. 3. Any Other Special Procurement Arrangements: Not Applicable 4. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) Component 1: Fisheries and Aquatic Resources Management in Northern Cambodia 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) nce (yes/no) Office equipment, office furniture, Shopping boats, and NCB Laboratory methods FiA- Aquatic life will be G001- and water 343,000 8 No Post followed to 008 quality procure monitoring these equipment , goods. Mapping Equipment, motorbikes, vehicles, Construction of Office for FiA Stung Shopping Treng and FiA- and NCB Kratie, CW00 660,000 3 No Post methods Hatchery 1-003 will be construction, followed and FiA office renovation Component 2: Support for WRM in the Northern Cambodia and trans-boundary dialogue 1 2 3 4 5 6 7 Ref. No. Description Estimated Packages Domestic Review Comments Cost Preference by Bank US$ (yes/no) (Prior / Post) Office furniture, office equipment, Hydro- metrological equipment, Water and Shopping and hydrological NCB methods will G01-10 measurement 1,000,500 10 No Post be followed to (goods) equipment, procure these vehicles, goods. motorbikes, Supply and Installation of Meteorology measurement equipment, ect. Construction of W01a PDOWRAM 390,000 1 No Post NCB (Works) office building in Kratie, Steung Treng , Rattanakiri, and Mondulkiri Province ( 4 buildings) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comment 1. Each package estimated Selection of Consulting firms to cost more than 1,000,000 2. Each package estimated Selection of Individual Consultant to cost more than 300,000 2. Any Other Special Selection Arrangements: Not Applicable 3. Consultancy Assignments with Selection Methods Component 1: Fisheries and Aquatic Resources Management in Northern Cambodia 1 2 3 4 5 6 Ref. No. Description of Estimated Packag Review Comments Assignment Cost es by Bank US$ (Prior / million Post) FiA-CS FM consultants, 001- 026 Procurement Consultants, International Fishery Resource Management Specialist, International 26 individual Community Fishery national and Specialist, National 1,873,000 26 Post international Lead Fishery consultants will be Resource Specialist, engaged. National Lead Community Fishery Specialist, National Environmental and Social (safeguards) specialist, National Gender Specialist, Regional Aquaculture Specialist, National Infrastructure Engineer, etc. Component 2: Support for WRM in the Northern Cambodia and trans-boundary dialogue 1 2 3 4 5 6 Ref. No. Description of Estimated Packag Review Comments Assignment Cost es by Bank US$ (Prior / million Post) 2 FM consultants, 2 5 individual national Procurement and international CS 01-05 Consultants, Project 302,000 5 Post consultants will be accountant engaged. consultant. Bundled auditor selected by MEF. CS07 SSS method will be External audit firm 50,000 1 Post followed to engage the auditor for this project Technical Water QCBS method will CS08 Resource 2,500,000 1 Prior be followed. Management Firm NIS upgrading CS09 CQS method will be support consultant ( 50,000 1 Post followed. Firm) PROCUREMENT Cambodia : Mekong Integrated Water Resources Management Project- Phase III PLAN General Information Country: Cambodia Bank’s Approval Date of the Original Procurement Plan: 2017-03-21 2019-11-05 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P148647 GPN Date: Project Name: Mekong Integrated Water Resources Management Project- Phase III Loan / Credit No: IDA / 57770 Executing Agency(ies): Fisheries Administration WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual 1. Fisheries and Aquatic FIA-CW-003 / Office Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 20,000.00 19,995.83 Signed 2017-07-26 2017-10-08 2017-12-07 Renovation for FiA Quotations Envelope Northern Cambodia FIA-CW-001 / Construction of New Office Buildings for 1. Fisheries and Aquatic PFiA Stung Treng and Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 140,000.00 208,362.81 Signed 2019-03-04 2019-04-23 2019-10-20 Kratie (Including renovation Quotations Envelope Northern Cambodia of existing office of PFiA Kratie) FIA-CW-074 / Natural Laterite Road Reconstruction (Length 690m Width 4m 1. Fisheries and Aquatic Community Earth Work Heigh t0.3m IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Signed 2019-02-08 2019-02-13 2019-03-04 2019-06-02 Natural Gravel Height 0.1m) Northern Cambodia Development in Preaek Prasab Commune, Preaek Prasab District, Kratie Province FIA-CW-075 / Natural Laterite Road Reconstruction (Length 630m Width 5m 1. Fisheries and Aquatic Community Earth Work Height 0.3m IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Signed 2019-02-08 2019-02-13 2019-03-04 2019-06-02 Natural Gravel Height Northern Cambodia Development 0.15m) in Bos Leav Commune, Chetr Borei District, Kratie Province FIA-CW-076 / Laterite Road Reconstruction (Length 1278m Width 6m, Earth 1. Fisheries and Aquatic Community Work Height 0.2m, Laterite IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Signed 2019-02-08 2019-02-13 2019-03-04 2019-06-02 Height 0.15m) in Preah Northern Cambodia Development Rumkel Commune, Thalaborivat District, Stung Treng Province FIA-CW-077 / Pipe Culverts Construction (4 Pipe Culverts Diameter of Pipe 1. Fisheries and Aquatic Community 1m, Length 6m) in Koh IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Signed 2019-02-08 2019-02-13 2019-03-04 2019-05-03 Sampeay Commune, Siem Northern Cambodia Development Bouk District, Stung Treng Province Page 1 FIA-CW-078 / Pipe Culverts Construction and Earth Road 125m (Pipe Culverts and 1. Fisheries and Aquatic Community Double Pipe Culvert, IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Signed 2019-02-08 2019-02-13 2019-03-04 2019-06-02 Diameter of Pipe 1m, Northern Cambodia Development Length 6m) in Sdao Commune, Se San District, Stung Treng Province FIA-CW-079 / Natural Gravel Road Reconstruction (Length 690m, Width 4m, 1. Fisheries and Aquatic Community Earth Work Height 0.3m, IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Signed 2019-03-18 2019-03-23 2019-04-11 2019-07-10 Natural Gravel Height Northern Cambodia Development 0.15m) in Ruseykeo Commune, Sambour District, Kratie Province FIA-CW-081 / Natural Gravel Road Reconstruction and Culvert (Length 1300m, Width 3m, Earth Work 1. Fisheries and Aquatic Community Height 0.2m, Natural Gravel IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Signed 2019-03-18 2019-03-23 2019-04-11 2019-07-10 Height 0.15m, and Single Northern Cambodia Development Culvert Length 5m, Diameter 0.6m) in Sambour Commune, Sambour District, Kratie Province FIA-CW-082 / Natural Gravel Road Reconstruction (Length 800m, Width 4m, 1. Fisheries and Aquatic Community Natural Gravel Height 0.2m) IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Signed 2019-03-18 2019-03-23 2019-04-11 2019-07-10 in Kampong Cham Northern Cambodia Development Commune, Sambour District, Kratie Province FIA-CW-083 / Laterite Road Reconstruction (Length 930m, Width 5m, Earth 1. Fisheries and Aquatic Community Work Height 0.2m, Laterite IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Signed 2019-05-06 2019-05-11 2019-05-30 2019-08-28 Height 0.15m) in Koh Pras Northern Cambodia Development Commune, Siem Bouk District, Stung Treng Province FIA-CW-084 / 2 Culverts Construction and Fill Earth Works (Length 60m, Width 1. Fisheries and Aquatic Community 6m and Height 3m) in Ou IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Signed 2019-05-06 2019-05-11 2019-05-30 2019-08-28 Mreah Commune, Ou Mreah Northern Cambodia Development District, Stung Treng Province FIA-CW-085 / Laterite Road Reconstruction (Length 1,043m, Width 5m, Earth 1. Fisheries and Aquatic Community Work Height 0.5m, Laterite IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Signed 2019-05-06 2019-05-11 2019-05-30 2019-08-28 Height 0.15m) in Kang Northern Cambodia Development Cham Commune, Thalaborivat District, Stung Treng Province FIA-CW-080 / Natural Gravel Road Reconstruction and Culvert (Length 730m, Width 4m, Earth Work Height 0.2m, Natural Gravel 1. Fisheries and Aquatic Community Height 0.15m, and Single IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Signed 2019-03-18 2019-03-23 2019-04-11 2019-07-10 Culvert Length 5m, Northern Cambodia Development Diameter 1.00m) in Voathonak Commune, Sambour District, Kratie Province Page 2 FIA-CW-086 / 4 Pipe 1. Fisheries and Aquatic Community Culverts Construction in Ou IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Signed 2019-07-17 2019-07-22 2019-08-10 2019-11-08 Krieng Commune, Sambour Northern Cambodia Development District, Kratie Province FIA-CW-087 / 2 Pipe Culverts Construction in 1. Fisheries and Aquatic Community Boeng Char Commune, IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Signed 2019-07-17 2019-07-22 2019-08-10 2019-11-08 Sambour District, Kratie Northern Cambodia Development Province FIA-CW-088 / Earth Work Road Construction (Length 500m, Width 4m, Height 1. Fisheries and Aquatic Community 0.5m) in Kaoh Sneng IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Signed 2019-09-30 2019-10-05 2019-10-24 2020-01-22 Commune, Thalaborivat Northern Cambodia Development District, Stung Treng Province FIA-CW-089 / Earth Work Road Construction (Length 1. Fisheries and Aquatic Community Under 610mm, Width 3m, Height IDA / 57770 Resources Management in Post Driven Direct 10,000.00 10,000.00 Implementati 2019-09-30 2019-10-05 2019-10-24 2020-01-22 0.6m) in Ou Svay Commune, Northern Cambodia Development on Thalaborivat District, Stung Treng Province GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FIA-G-001 / Supply, 1. Fisheries and Aquatic Request for Single Stage - One Delivery and Installation of IDA / 57770 Resources Management in Post Open - National 35,000.00 32,723.90 Signed 2017-04-12 2017-06-28 2017-08-09 Quotations Envelope Office Equipment Northern Cambodia FIA-G-007 / Supply and 1. Fisheries and Aquatic Single Stage - One Delivery of 5 Pick Up IDA / 57770 Resources Management in Post Request for Bids Open - National 150,000.00 136,500.00 Signed 2017-04-20 2017-04-25 2017-06-06 2017-07-06 2017-08-10 2017-10-05 Envelope Trucks Northern Cambodia 1. Fisheries and Aquatic FIA-G-009 / Office Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 8,000.00 0.00 Canceled 2017-04-24 2017-07-10 2017-09-04 Furniture for FiA Quotations Envelope Northern Cambodia FIA-G-004 / Supply and 1. Fisheries and Aquatic Delivery of 12 Motorcycles Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 24,000.00 0.00 Canceled 2017-04-25 2017-07-04 2017-08-29 for FiA/IFReDI and PFiA Quotations Envelope Northern Cambodia Kratie/Stung Treng FIA-G-010 / Supply and 1. Fisheries and Aquatic Installation of 6 Licensed Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 9,000.00 0.00 Canceled 2017-05-24 2017-08-09 2017-10-08 Accounting Software with 6 Quotations Envelope Northern Cambodia Desktop Computers FIA-G-004RE / Supply and 1. Fisheries and Aquatic Delivery of 12 Motorcycles Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 24,000.00 16,560.00 Signed 2017-06-17 2017-08-26 2017-09-23 for FiA/IFReDI and PFiA Quotations Envelope Northern Cambodia Kratie/Stung Treng FIA-G-009RE / Supply and 1. Fisheries and Aquatic Request for Single Stage - One Delivery of Office Furniture IDA / 57770 Resources Management in Post Open - National 8,000.00 7,949.70 Signed 2017-06-17 2017-08-26 2017-10-07 Quotations Envelope for FiA Northern Cambodia FIA-G-010RE / Supply and 1. Fisheries and Aquatic Request for Single Stage - One Installation of Licensed IDA / 57770 Resources Management in Post Open - National 9,000.00 4,600.00 Signed 2017-06-17 2017-08-26 2017-10-07 Quotations Envelope Accounting Software Northern Cambodia Page 3 FIA-G-002 / Office 1. Fisheries and Aquatic Request for Single Stage - One Furniture for PFiA, IDA / 57770 Resources Management in Post Open - National 10,000.00 9,820.00 Signed 2018-01-20 2018-03-17 2018-04-30 Quotations Envelope Kratie/Stung Treng Northern Cambodia FIA-G-011 / Printing and 1. Fisheries and Aquatic Delivery of Training Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 10,500.00 11,322.30 Signed 2018-09-19 2018-11-14 2018-12-28 Documents of Cfi Co- Quotations Envelope Northern Cambodia Management 1. Fisheries and Aquatic FIA-G-015 / Supply and UN Agencies IDA / 57770 Resources Management in Post Direct 30,000.00 39,670.50 Signed 2019-03-01 2019-03-08 2019-04-12 2019-08-10 Delivery of One (1) Vehicle (Direct) Northern Cambodia FIA-G-008 / Supply, 1. Fisheries and Aquatic Request for Single Stage - One Delivery and Installation of IDA / 57770 Resources Management in Post Open - National 8,000.00 7,549.30 Signed 2019-04-03 2019-05-17 2019-06-14 Quotations Envelope Mapping Equipment Northern Cambodia FIA-G-014 / Supply and 1. Fisheries and Aquatic Delivery of 6 Motorcycles for Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 10,500.00 10,662.00 Signed 2019-04-03 2019-05-17 2019-06-14 FiA/IFReDI and PFiA Quotations Envelope Northern Cambodia Kratie/Stung Treng FIA-G-018 / Supply, 1. Fisheries and Aquatic Delivery and Installation of Single Stage - One IDA / 57770 Resources Management in Post Request for Bids Open - National 175,000.00 132,200.00 Signed 2019-04-12 2019-04-19 2019-05-29 2019-06-19 2019-07-10 2019-10-02 Boats with Engines for 50 Envelope Northern Cambodia Community Fisheries FIA-G-013 / Supply, 1. Fisheries and Aquatic Delivery and Installation of Request for Single Stage - One IDA / 57770 Resources Management in Post Open - National 10,000.00 9,827.40 Signed 2019-04-17 2019-06-07 2019-07-05 Laptops and Quotations Envelope Northern Cambodia Color Laser Printers FIA-G-012 / Supply and 1. Fisheries and Aquatic Request for Single Stage - One Delivery of Fisheries IDA / 57770 Resources Management in Post Open - National 15,000.00 14,557.76 Signed 2019-07-06 2019-08-26 2019-10-07 Quotations Envelope Monitoring Equipment Northern Cambodia FIA-G-017 / Supply and 1. Fisheries and Aquatic Request for Single Stage - One Delivery of Equipment for IDA / 57770 Resources Management in Post Open - National 9,500.00 7,889.20 Signed 2019-06-04 2019-07-16 2019-09-10 Quotations Envelope Engineering Works Northern Cambodia NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FIA-CS-024 / Engineering Design and Construction 1. Fisheries and Aquatic Consultant Supervision for a fish IDA / 57770 Resources Management in Post Qualification Open - National 75,000.00 82,128.00 Signed 2018-04-02 2018-04-19 2018-06-18 2018-07-18 2018-08-18 2019-02-18 hatchery in Stung Treng Northern Cambodia Selection Province, Cambodia INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Page 4 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FIA-CS-008 / International 1. Fisheries and Aquatic Individual Fishery Resource IDA / 57770 Resources Management in Post Consultant Open 200,000.00 224,327.44 Signed 2016-11-01 2017-02-09 2017-03-02 2017-04-06 2021-04-05 Management Specialist Northern Cambodia Selection FIA-CS-009 / International 1. Fisheries and Aquatic Individual Community Fishery IDA / 57770 Resources Management in Post Consultant Open 200,000.00 198,746.05 Signed 2016-11-01 2017-02-09 2017-03-02 2017-04-06 2021-04-05 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-010 / National IDA / 57770 Resources Management in Post Consultant Open 108,000.00 127,468.24 Signed 2016-11-01 2017-02-09 2017-03-02 2017-04-06 2021-04-05 Component Coordinator Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-014 / National IDA / 57770 Resources Management in Post Consultant Open 30,000.00 53,992.94 Signed 2016-11-01 2017-02-09 2017-03-02 2017-04-06 2021-04-05 Gender Specialist Northern Cambodia Selection FIA-CS-013 / National Lead 1. Fisheries and Aquatic Individual Community Fishery IDA / 57770 Resources Management in Post Consultant Open 90,000.00 107,985.88 Terminated 2016-11-01 2017-02-09 2017-03-02 2017-04-06 2021-04-05 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-001 / National IDA / 57770 Resources Management in Post Consultant Open 90,000.00 141,176.00 Terminated 2016-07-01 2016-11-08 2016-11-29 2017-01-03 2021-01-02 Procurement Consultant Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-002 / National IDA / 57770 Resources Management in Post Consultant Open 90,000.00 110,552.94 Signed 2016-07-01 2016-11-08 2016-11-29 2017-01-03 2021-01-02 Financial Consultant Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-003 / National IDA / 57770 Resources Management in Post Consultant Open 60,000.00 65,094.12 Terminated 2016-07-01 2016-11-08 2016-11-29 2017-01-03 2021-01-02 Project Accountant Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-025 / Regional IDA / 57770 Resources Management in Post Consultant Open 50,000.00 0.00 Canceled 2016-11-01 2017-02-09 2017-03-02 2017-04-06 2021-04-05 Aquaculture Specialist (RAS) Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-012 / National Lead IDA / 57770 Resources Management in Post Consultant Open 90,000.00 0.00 Canceled 2016-11-01 2017-02-09 2017-03-02 2017-04-06 2021-04-05 Fishery Resource Specialist Northern Cambodia Selection FIA-CS-015 / National 1. Fisheries and Aquatic Individual Environmental Safeguards IDA / 57770 Resources Management in Post Consultant Open 15,000.00 19,687.00 Signed 2017-06-01 2017-08-17 2017-08-31 2017-09-28 2021-09-27 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-027 / National IDA / 57770 Resources Management in Post Consultant Open 15,000.00 23,169.00 Terminated 2017-06-01 2017-08-17 2017-08-31 2017-09-28 2021-09-27 Social Safeguards Specialist Northern Cambodia Selection FIA-CS-006 / National 1. Fisheries and Aquatic Individual Finance Consultant at PFiA IDA / 57770 Resources Management in Post Consultant Open 60,000.00 60,223.52 Terminated 2017-06-09 2017-08-25 2017-09-08 2017-10-06 2021-10-05 Kratie Northern Cambodia Selection FIA-CS-007 / National 1. Fisheries and Aquatic Individual Finance Consultant at PFiA IDA / 57770 Resources Management in Post Consultant Open 60,000.00 60,223.52 Signed 2017-06-09 2017-08-25 2017-09-08 2017-10-06 2021-10-05 Stung Treng Northern Cambodia Selection FIA-CS-017 / Kratie 1. Fisheries and Aquatic Individual National Community Fishery IDA / 57770 Resources Management in Post Consultant Open 60,000.00 0.00 Canceled 2017-08-01 2017-10-17 2017-11-07 2017-12-05 2021-12-04 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-018 / Kratie IDA / 57770 Resources Management in Post Consultant Open 60,000.00 81,871.00 Signed 2017-08-01 2017-10-17 2017-11-07 2017-12-05 2021-12-04 National Livelihood Specialist Northern Cambodia Selection Page 5 FIA-CS-019 / Kratie 1. Fisheries and Aquatic Individual National Community IDA / 57770 Resources Management in Post Consultant Open 60,000.00 68,341.00 Signed 2017-08-01 2017-10-17 2017-11-07 2017-12-05 2021-12-04 Facilitator Northern Cambodia Selection FIA-CS-021 / Stung Treng 1. Fisheries and Aquatic Individual National Community Fishery IDA / 57770 Resources Management in Post Consultant Open 60,000.00 58,871.00 Signed 2017-08-01 2017-10-17 2017-11-07 2017-12-05 2021-12-04 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-022 / Stung Treng IDA / 57770 Resources Management in Post Consultant Open 60,000.00 72,738.00 Signed 2017-08-01 2017-10-17 2017-11-07 2017-12-05 2021-12-04 National Livelihood Specialist Northern Cambodia Selection FIA-CS-023 / Stung Treng 1. Fisheries and Aquatic Individual National Community IDA / 57770 Resources Management in Post Consultant Open 60,000.00 74,125.00 Terminated 2017-08-01 2017-10-17 2017-11-07 2017-12-05 2021-12-04 Facilitator Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-028 / National IDA / 57770 Resources Management in Post Consultant Open 90,000.00 131,662.00 Signed 2017-08-01 2017-10-17 2017-11-07 2017-12-05 2021-12-04 M&E Specialist Northern Cambodia Selection FIA-CS-025RE / 1. Fisheries and Aquatic Individual International Aquaculture IDA / 57770 Resources Management in Post Consultant Open 152,000.00 147,819.00 Signed 2017-08-01 2017-10-17 2017-11-07 2017-12-05 2021-12-04 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-001RE / National IDA / 57770 Resources Management in Post Consultant Open 36,000.00 40,949.81 Terminated 2017-08-10 2017-10-26 2017-11-09 2017-12-07 2019-12-07 Procurement Consultant Northern Cambodia Selection FIA-CS-012RE / National 1. Fisheries and Aquatic Individual Lead Fisheries Resources IDA / 57770 Resources Management in Post Consultant Open 90,000.00 0.00 Canceled 2017-05-19 2017-08-04 2017-08-18 2017-09-15 2021-09-14 Specialist Northern Cambodia Selection FIA-CS-016 / Kratie 1. Fisheries and Aquatic Individual National Fishery Resource IDA / 57770 Resources Management in Post Consultant Open 60,000.00 0.00 Canceled 2017-08-01 2017-10-17 2017-11-07 2017-12-05 2021-12-04 Specialist Northern Cambodia Selection FIA-CS-020 / Stung Treng 1. Fisheries and Aquatic Individual National Fishery Resource IDA / 57770 Resources Management in Post Consultant Open 60,000.00 0.00 Canceled 2017-08-01 2017-10-17 2017-11-07 2017-12-05 2021-12-04 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-030 / Sampling IDA / 57770 Resources Management in Post Consultant Open 2,800.00 0.00 Canceled 2017-08-01 2017-10-17 2017-11-07 2017-12-05 2017-12-13 Framework Design Specialist Northern Cambodia Selection FIA-CS-026 / National 1. Fisheries and Aquatic Individual Infrastructure Engineer IDA / 57770 Resources Management in Post Consultant Open 20,000.00 76,980.00 Signed 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-30 Consultant Northern Cambodia Selection FIA-CS-032 / National 1. Fisheries and Aquatic Individual Community Development IDA / 57770 Resources Management in Post Consultant Open 8,000.00 14,706.00 Signed 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2018-08-31 Training Specialist Northern Cambodia Selection FIA-CS-033 / National 1. Fisheries and Aquatic Individual Specialist on Geographic IDA / 57770 Resources Management in Post Consultant Open 76,000.00 195,664.00 Signed 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-30 Information System and Northern Cambodia Selection Database Management FIA-CS-012RE2 / National 1. Fisheries and Aquatic Individual Lead Fishery Resource IDA / 57770 Resources Management in Post Consultant Open 90,000.00 234,040.00 Signed 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-30 Specialist Northern Cambodia Selection FIA-CS-016RE / Kratie 1. Fisheries and Aquatic Individual National Fishery Resource IDA / 57770 Resources Management in Post Consultant Open 60,000.00 0.00 Canceled 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-30 Specialist Northern Cambodia Selection Page 6 FIA-CS-020RE / Stung 1. Fisheries and Aquatic Individual Streng National Fishery IDA / 57770 Resources Management in Post Consultant Open 60,000.00 0.00 Canceled 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-30 Resource Specialist Northern Cambodia Selection FIA-CS-029 / Provincial 1. Fisheries and Aquatic Individual Project Engineer Consultant IDA / 57770 Resources Management in Post Consultant Open 54,000.00 55,488.00 Terminated 2018-01-26 2018-03-16 2018-04-06 2018-05-11 2021-05-11 for Kratie Northern Cambodia Selection FIA-CS-035 / Provincial 1. Fisheries and Aquatic Individual Project Engineer Consultant IDA / 57770 Resources Management in Post Consultant Open 54,000.00 59,336.00 Terminated 2018-01-26 2018-03-16 2018-04-06 2018-05-11 2021-05-11 for Stung Treng Northern Cambodia Selection FIA-CS-017RE / Kratie 1. Fisheries and Aquatic Individual National Community IDA / 57770 Resources Management in Post Consultant Open 60,000.00 74,480.00 Terminated 2018-02-12 2018-04-02 2018-04-23 2018-05-28 2021-06-01 Fisheries Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-034 / National IDA / 57770 Resources Management in Post Consultant Open 30,000.00 27,191.00 Signed 2018-04-02 2018-05-21 2018-06-11 2018-07-16 2021-06-01 Internal Audit Consultant Northern Cambodia Selection FIA-CS-020RE2 / Stung 1. Fisheries and Aquatic Individual Streng National Fishery IDA / 57770 Resources Management in Post Consultant Open 60,000.00 64,005.00 Signed 2018-04-30 2018-06-18 2018-07-09 2018-08-13 2021-06-01 Resource Specialist Northern Cambodia Selection FIA-CS-016RE2 / Kratie 1. Fisheries and Aquatic Individual National Fishery Resource IDA / 57770 Resources Management in Post Consultant Open 60,000.00 53,550.00 Signed 2018-04-30 2018-06-18 2018-07-09 2018-08-13 2021-06-01 Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-027RE / National IDA / 57770 Resources Management in Post Consultant Open 15,000.00 24,628.24 Signed 2018-07-03 2018-08-21 2018-09-11 2018-10-16 2019-04-14 Social Safeguards Specialist Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-001RE1 / National IDA / 57770 Resources Management in Post Consultant Open 36,000.00 62,929.40 Signed 2018-07-03 2018-08-21 2018-09-11 2018-10-16 2019-04-14 Procurement Consultant Northern Cambodia Selection FIA-CS-013RE / National 1. Fisheries and Aquatic Individual Lead Community Fisheries IDA / 57770 Resources Management in Post Consultant Open 62,000.00 58,427.50 Signed 2018-08-01 2018-09-19 2018-10-10 2018-11-14 2021-05-13 Specialist Northern Cambodia Selection FIA-CS-023RE / Stung 1. Fisheries and Aquatic Individual Treng National Community IDA / 57770 Resources Management in Post Consultant Open 45,000.00 56,367.64 Signed 2018-10-01 2018-11-17 2018-11-24 2018-12-03 2021-05-13 Facilitator Northern Cambodia Selection FIA-CS-006RE / National 1. Fisheries and Aquatic Individual Finance Consultant at PFiA IDA / 57770 Resources Management in Post Consultant Open 29,000.00 35,180.00 Signed 2018-12-10 2019-01-28 2019-02-04 2019-02-11 2021-06-30 Kratie Northern Cambodia Selection FIA-CS-035RE / Provincial 1. Fisheries and Aquatic Individual Project Engineer Consultant IDA / 57770 Resources Management in Post Consultant Open 40,000.00 52,462.35 Signed 2019-01-12 2019-03-02 2019-03-09 2019-03-16 2021-07-03 for Stung Treng Northern Cambodia Selection 1. Fisheries and Aquatic Individual FIA-CS-003RE / Project IDA / 57770 Resources Management in Post Consultant Open 32,500.00 39,603.53 Signed 2019-01-28 2019-03-18 2019-03-25 2019-04-01 2021-05-20 Accountant Consultant (PAC) Northern Cambodia Selection FIA-CS029RE / Provincial 1. Fisheries and Aquatic Individual Project Engineer Consultant IDA / 57770 Resources Management in Post Consultant Open 30,000.00 32,941.18 Signed 2019-07-01 2019-08-12 2019-08-17 2019-08-24 2021-05-15 for Kratie Northern Cambodia Selection FIA-CS017RE1 / Kratie 1. Fisheries and Aquatic Individual Under National Community IDA / 57770 Resources Management in Post Consultant Open 35,000.00 0.00 2019-08-01 2019-09-19 2019-10-10 2019-11-14 2020-05-12 Implementation Fisheries Specialist Northern Cambodia Selection Page 7 1. Fisheries and Aquatic Individual FIA-CS-003RE1 / Project Pending IDA / 57770 Resources Management in Post Consultant Open 22,100.00 0.00 2019-10-23 2019-12-13 2019-12-20 2020-01-01 2021-05-25 Accountant Consultant Implementation Northern Cambodia Selection FIA-CS-006RE1 / National 1. Fisheries and Aquatic Individual Pending Finance Consultant at PFiA- IDA / 57770 Resources Management in Post Consultant Open 20,400.00 0.00 2019-10-23 2019-12-13 2019-12-20 2020-01-01 2021-05-25 Implementation Kratie Northern Cambodia Selection Page 8