Public Disclosure Copy The World Bank Implementation Status & Results Report Mexico Municipal Energy Efficiency Project (P149872) Mexico Municipal Energy Efficiency Project (P149872) LATIN AMERICA AND CARIBBEAN | Mexico | Energy & Extractives Global Practice | IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 4 | ARCHIVED on 21-Dec-2017 | ISR30471 | Implementing Agencies: United Mexican States, Secretaría de Energía (SENER) Key Dates Key Project Dates Bank Approval Date:08-Mar-2016 Effectiveness Date:23-Sep-2016 Planned Mid Term Review Date:31-Jan-2019 Actual Mid-Term Review Date:-- Original Closing Date:31-Oct-2021 Revised Closing Date:31-Oct-2021 Project Development Objectives Project Development Objective (from Project Appraisal Document)

The objective of the project is to promote the efficient use of energy in the Borrower's municipalities by carrying out energy efficiency investments in selected municipal sectors and contribute to strengthening the enabling environment.

Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Policy development and institutional strengthening:(Cost $7.00 M) Municipal energy efficiency investments:(Cost $148.75 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Satisfactory Overall Implementation Progress (IP)  Moderately Satisfactory  Moderately Satisfactory Overall Risk Rating  Substantial  Substantial Implementation Status and Key Decisions 12/21/2017 Page 1 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Mexico Municipal Energy Efficiency Project (P149872) The operation was approved by the World Bank’s Executive Board on March 8, 2016 and became effective on September 23, 2016. The project is being implemented by SENER over a five-year period. The operation’s closing date is October 31, 2021. Most project ratings are currently rated as “Satisfactory” (including “Progress towards achievement of PDO”, “Overall Safeguards” and “Overall Risk”), while “Overall Implementation Progress” is rated as “Moderately Satisfactory”. The Project is progressing well; although disbursements have been slower than originally planned, they will be accelerating, as a robust pipeline of subprojects has been developed and the lessons learned from first pilots have been integrated into the PRESEM procedures. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  Moderate  Moderate  Moderate Macroeconomic  Low  Moderate  Moderate Sector Strategies and Policies  Low  Low  Low Technical Design of Project or Program  Substantial  Substantial  Substantial Institutional Capacity for Implementation and Sustainability  Moderate  Moderate  Moderate Fiduciary  Substantial  Substantial  Substantial Environment and Social  Low  Low  Low Stakeholders  Low  Low  Low Other  Moderate  Low  Low Overall  Substantial  Substantial  Substantial Results Project Development Objective Indicators PHINDPDOTBL  Projected lifetime energy savings (Megawatt hour(MWh), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1,020,714.00 Date 01-Feb-2016 04-May-2017 18-Dec-2017 31-Oct-2021 PHINDPDOTBL  Number of ESAs signed (Number) (Number, Custom) 12/21/2017 Page 2 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Mexico Municipal Energy Efficiency Project (P149872) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 2.00 23.00 Date 01-Feb-2016 04-May-2017 18-Dec-2017 31-Oct-2021 PHINDPDOTBL  Framework to scale up municipal energy efficiency in the country (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Framework Value No framework No framework No framework accepted by the SENER Date 01-Feb-2016 04-May-2017 18-Dec-2017 31-Oct-2021 Overall Comments Intermediate Results Indicators PHINDIRITBL  Projected lifetime GHG emission reductions (tCO2eq) (Tons/year) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 463,405.00 Date 01-Feb-2016 04-May-2017 18-Dec-2017 31-Oct-2021 PHINDIRITBL  Default rate of municipalities (%, average rate of non-payment over total outstanding loan balance) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 10.00 Date 01-Feb-2016 04-May-2017 18-Dec-2017 31-Oct-2021 12/21/2017 Page 3 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Mexico Municipal Energy Efficiency Project (P149872) PHINDIRITBL  Sub-projects designed (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 3.00 4.00 28.00 Date 01-Feb-2016 04-May-2017 18-Dec-2017 31-Oct-2021 PHINDIRITBL  Street light interventions (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 1.00 9.00 Date 01-Feb-2016 04-May-2017 18-Dec-2017 31-Oct-2021 PHINDIRITBL  Water and wastewater interventions (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 8.00 Date 01-Feb-2016 04-May-2017 18-Dec-2017 31-Oct-2021 PHINDIRITBL  Municipal building interventions (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 6.00 Date 01-Feb-2016 04-May-2017 18-Dec-2017 31-Oct-2021 12/21/2017 Page 4 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Mexico Municipal Energy Efficiency Project (P149872) PHINDIRITBL  Capacity-building, and outreach activities implemented (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 4.00 4.00 25.00 Date 01-Feb-2016 04-May-2017 18-Dec-2017 31-Oct-2021 PHINDIRITBL  Design of energy management systems (EnMS) for street lighting, water and wastewater, and municipal buildings (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 3.00 Date 01-Feb-2016 04-May-2017 18-Dec-2017 31-Oct-2021 PHINDIRITBL  Participants in consultation activities during project implementation (number) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 65.00 1,000.00 Date 01-Feb-2016 04-May-2017 18-Dec-2017 31-Oct-2021 PHINDIRITBL  Participants in consultation activities during project implementation - female (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 250.00 0.00 10.00 400.00 Date 01-Feb-2016 04-May-2017 18-Dec-2017 31-Oct-2021 Overall Comments 12/21/2017 Page 5 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Mexico Municipal Energy Efficiency Project (P149872) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P149872 IBRD-85940 Effective USD 100.00 100.00 0.00 0.48 99.52 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P149872 IBRD-85940 Effective 08-Mar-2016 29-Jul-2016 23-Sep-2016 31-Oct-2021 31-Oct-2021 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) 12/21/2017 Page 6 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report Mexico Municipal Energy Efficiency Project (P149872) P165585-PRESEM Additional Finance for Energy Efficiency in Public Buildings 12/21/2017 Page 7 of 7 Public Disclosure Copy