PROCUREMENT PLAN(Textual Part) Project information: INDIA, Assam Agribusiness and Rural Transformation Project (APART) Project Implementation agency: Assam Rural Infrastructure and Agricultural Services Society (ARIASS)is the main agency. Date of the Procurement Plan:October 01, 2019 Period covered by this Procurement Plan:Until publication of next version of the Procurement Plan. Preamble In accordance with paragraph5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016, Revised November 2017 and August 2018) (“Procurement Regulations”)the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plansand conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEPconstitute the Procurement Plan for the Project.The following conditionsapply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. Procurement for the project will be carried out in accordance with the World Bank’s Procurement Regulations for IPF Borrowers, July 2016, Revised November 2017 and August 2018 and applicable to Investment Project Financing (IPF). The project will be subject to the World Bank’s Anticorruption Guidelines, dated October 15, 2006, as revised in January 2011 and July 2016. The table below describes various procurement methods to be used for activities financed by the loan. The thresholds (Table 1) indicated will govern the procurement approach and methods; Table 1: Procurement Thresholds Procurement Approaches and Methods Thresholds (US$ equivalent) Open international (works – including turnkey, Any value activity supply and installation of plant and equipment and PPP) Open national (works – including turnkey, supply Below 40 million and installation of plant and equipment and PPP) Open international (goods, IT system, and non- Any value activity consulting services) Open national (goods, IT system, and non- Below 10 million consulting services) National request for quotation (goods and works) Up to 100,000 Direct selection No threshold; For works, goods, non-consulting services and IT system procurement: According to paragraphs 6.8–6.10 of the Regulations; For consultants: According to paragraphs 7.13–7.15 of the Regulations Shortlist of national consultants Up to 800,000 Procurement prior-review thresholds. The World Bank will prior review the following contracts: 1. Works (including turnkey, supply and installation of plant and equipment and PPP): All contracts more than US$ 15 million equivalent 2. Goods, IT system and Non-consulting services: All contracts more than US$4 million equivalent 3. Consultants: All contracts >US$2 million equivalent for firms and >US$400,000 equivalent for individuals 4. There is no automatic requirement to undertake prior review for direct selection for value less than these thresholds 5. Additional provisions as mentioned at paragraph 2.2, 2.3, 2.4 & 2.5 of Annex I (Mandatory Procurement Prior Review Thresholds) under Bank Procedure (Effective August 01, 2018), “Procurement in IPF and Other Operational Procurement Matters” will also apply. National Procurement Arrangements:National competition for the procurement of works, goods, IT system procurement and non-consulting services according to the established thresholds will be conducted in accordance with paragraphs 5.3–5.5 of Section V of the Regulations and the following provisions: 1. Only the model bidding documents for National Competitive Procurement (NCP) agreed with the GOI Task Force (and as amended for time to time), shall be used for bidding. 2. Invitations to bid shall be advertised on a widely used website or electronic portal with free open access at least 30 days prior to the deadline for the submission of bids, unless otherwise agreed in the approved procurement plan. 3. No special preference will be accorded to any bidder either for price or for other terms and conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State. 4. Except with the prior concurrence of the Bank, there shall be no negotiation of price with the bidders, even with the lowest evaluated bidder. 5. Government e-Marketplace (GeM) set-up by Ministry of Commerce, Government of India will be acceptable for procurement under Request for Quotations (RFQ) method. 6. At the Borrower’s request, the Bank may agree to the Borrower’s use, in whole or in part, of its electronic procurement system, provided that the Bank is satisfied with the adequacy of such system. 7. Procurement will be open to eligible firms from any country. This eligibility shall be as defined under Section III of the Procurement Regulations. Accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. 8. The request for bids/request for proposals document shall require that Bidders/Proposers submitting Bids/Proposals include a signed acceptance in the bid, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 9. The Borrower shall use an effective complaints mechanism for handling procurement related complaints in a timely manner. 10. Procurement Documents will include provisions, as agreed with the Bank, intended to adequately mitigate against environmental, social (including sexual exploitation and abuse and gender-based violence), health and safety (“ESHS”) risks and impacts. Domestic preference-The provision of domestic preference will be applied in the evaluation of bids in accordance with Annex VI of the Regulations. Procurement of Works, Goods (Supply and Installation; and IT Equipment), Non-Consultancy Services and Consultancy Services – As per procurement plan approved in STEP. PROCUREMENT India : Assam Agribusiness and Rural Transformation Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2016-09-30 2020-02-17 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P155617 GPN Date: Project Name: Assam Agribusiness and Rural Transformation Project Loan / Credit No: / , IBRD / 87800 Executing Agency(ies): ASSAM RURAL INFRASTRUCTURE AND AGRICULTURAL SERVICES (ARIAS) SOCIETY WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-ARIAS-34967-CW-RFQ / Component A: Enabling Under Renovation and Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 79,412.00 0.00 Implementat 2018-01-15 2018-03-17 2018-09-13 refurbishment of PCU office Quotations Envelope Development ion - Block-(B&C) IN-ARIAS-34970-CW-RFQ / Component A: Enabling Under Renovation and Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 86,765.00 0.00 Implementat 2018-01-15 2018-03-17 2018-09-13 refurbishment of PCU office Quotations Envelope Development ion - Block-D IN-ARIAS-34971-CW-RFQ / Component A: Enabling Under Renovation and Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 55,882.00 0.00 Implementat 2018-01-15 2018-03-17 2018-09-13 refurbishment of PCU office Quotations Envelope Development ion - Block-F IN-ARIAS-34965-CW-RFQ / Component A: Enabling ARIAS: Renovation and Single Stage - One IBRD / 87800 Agri Enterprise Post Request for Bids Open - National 219,118.00 199,327.03 Signed 2018-03-02 2018-03-07 2018-03-22 2018-04-01 2018-05-02 2019-01-27 refurbishment of PCU office Envelope Development - Block-A IN-ARIAS-43387-CW-RFQ / Component A: Enabling Interior Furnishing works Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 92,308.00 87,935.98 Signed 2018-02-24 2018-04-05 2018-06-04 of PCU (ARIAS Society) Quotations Envelope Development Building (Part-A) IN-ARIAS-48736-CW-RFQ / Component A: Enabling Pending ARIAS: Water Supply and Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 21,538.00 0.00 Implementat 2018-03-04 2018-04-28 2018-05-28 sanitary works for Block-C Quotations Envelope Development ion of PCU building IN-ARIAS-48849-CW-RFQ / Component A: Enabling Pending ARIAS: Construction of Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 46,154.00 0.00 Implementat 2019-06-23 2019-09-21 2019-12-20 boundary wall of PCU Quotations Envelope Development ion Building IN-ARIAS-48846-CW-RFQ / Component D: Project Pending Request for Single Stage - One ARIAS : Roof treatment for IBRD / 87800 Management, Monitoring Post Open - National 46,154.00 0.00 Implementat 2019-07-13 2019-10-10 2020-01-08 Quotations Envelope existing PCU building and Learning ion IN-ARIAS-77374-CW-RFB / Component C: Fostering Pending AGRI (ATMA) : Renovation Single Stage - One IBRD / 87800 Market-led Production and Post Request for Bids Open - National 172,308.00 0.00 Implementat 2019-01-04 2019-01-09 2019-02-03 2019-03-05 2019-04-09 2019-10-06 of 16 nos. of District Envelope Resilience Enhancement ion ATMA Offices IN-ARIAS-77375-CW-RFB / Component C: Fostering Pending AGRI (ATMA-Block) : Single Stage - One IBRD / 87800 Market-led Production and Post Request for Bids Open - National 230,769.00 0.00 Implementat 2019-01-04 2019-01-09 2019-02-10 2019-03-12 2019-04-16 2019-10-13 Renovation of 30 nos. of Envelope Resilience Enhancement ion FIAC/BRC IN-ARIAS-77379-CW-RFQ / Component C: Fostering Pending Request for Single Stage - One AGRI (OPIU) : Upgradation IBRD / 87800 Market-led Production and Post Open - National 23,077.00 0.00 Implementat 2019-02-02 2019-03-30 2019-09-26 Quotations Envelope of Nodal Unit Office at HQ Resilience Enhancement ion IN-ARIAS-77387-CW-RFQ / Component C: Fostering Pending Request for Single Stage - One HORT & FP : Upgradation IBRD / 87800 Market-led Production and Post Open - National 23,077.00 0.00 Implementat 2019-01-26 2019-03-23 2019-05-22 Quotations Envelope of Nodal Unit Office at HQ Resilience Enhancement ion IN-ARIAS-77406-CW-RFQ / Component C: Fostering Pending Request for Single Stage - One AAU : Renovation of OPIU IBRD / 87800 Market-led Production and Post Open - National 38,754.00 0.00 Implementat 2019-01-12 2019-03-14 2019-09-10 Quotations Envelope at AAU, Jorhat Resilience Enhancement ion IN-ARIAS-77412-CW-RFQ / Component C: Fostering Pending DAIRY : Renovation of Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 38,462.00 0.00 Implementat 2019-01-12 2019-03-14 2019-05-13 existing PIU Building Quotations Envelope Resilience Enhancement ion including furniture IN-ARIAS-77414-CW-RFQ / Component C: Fostering Pending FISHERY : Renovation & Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 38,462.00 0.00 Implementat 2019-01-07 2019-03-25 2019-09-21 Refurbishment of OPIU, Quotations Envelope Resilience Enhancement ion Fishery IN-ARIAS-77580-CW-RFQ / Component C: Fostering Pending Request for Single Stage - One AHVD-Piggery : Renovation IBRD / 87800 Market-led Production and Post Open - National 40,000.00 0.00 Implementat 2019-01-07 2019-03-09 2019-09-05 Quotations Envelope of the OPIU, AHVD Resilience Enhancement ion IN-ARIAS-77583-CW-RFQ / AHVD-Piggery : Component C: Fostering Pending Request for Single Stage - One Establishment of 2 nos. of IBRD / 87800 Market-led Production and Post Open - National 38,462.00 0.00 Implementat 2019-01-26 2019-03-28 2019-09-24 Quotations Envelope Satellite liquid board Resilience Enhancement ion semen processing centre IN-ARIAS-77599-CW-RFQ / Component C: Fostering Pending AHVD-INFORMAL DAIRY : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 61,538.00 0.00 Implementat 2019-02-02 2019-04-04 2019-06-03 Upgradation of diagnostic Quotations Envelope Resilience Enhancement ion lab (7 nos.) Page 1 IN-ARIAS-87682-CW-RFQ / Component C: Fostering Pending AHVD-INFORMAL DAIRY : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 61,538.00 0.00 Implementat 2019-01-26 2019-03-28 2019-09-24 Up-gradation of diagnostic Quotations Envelope Resilience Enhancement ion lab (7 nos.) IN-ARIAS-88803-CW-RFB / Pending PWD : Construction of Component B: Facilitating Single Stage - One IBRD / 87800 Post Request for Bids Open - National 49,231.00 0.00 Implementat 2019-06-03 2019-06-08 2019-07-20 2019-08-19 2019-09-23 2020-03-21 Babungaon to NH-37 Road Agro Cluster Development Envelope ion in Morigaon district IN-ARIAS-88804-CW-RFB / Pending PWD : Construction of Component B: Facilitating Single Stage - One IBRD / 87800 Post Request for Bids Open - National 498,462.00 0.00 Implementat 2019-06-03 2019-06-08 2019-07-20 2019-08-19 2019-09-23 2020-03-21 Bihita to Amlighat Road in Agro Cluster Development Envelope ion Morigaon district IN-ARIAS-88807-CW-RFB / PWD : Construction of Barpeta -Hajo-Ghy Road Component B: Facilitating Single Stage - One IBRD / 87800 Post Request for Bids Open - National 119,123.00 108,056.97 Signed 2019-06-10 2019-06-15 2019-07-27 2019-08-26 2019-09-30 2020-03-28 (Pub-Adabari Galdighia to Agro Cluster Development Envelope Paddy Fields) in Nalbari District IN-ARIAS-88808-CW-RFB / PWD : Construction of Pending Kaithalkuchi PWD Barama Component B: Facilitating Single Stage - One IBRD / 87800 Post Request for Bids Open - National 180,431.00 0.00 Implementat 2019-05-27 2019-06-01 2019-07-13 2019-08-12 2019-09-16 2020-03-14 Road (From Pub-Dahkaunia Agro Cluster Development Envelope ion to Bishnupur) in Nalbari District IN-ARIAS-88810-CW-RFB / PWD : Construction of Pending Sanirod-Kumarikata Component B: Facilitating Single Stage - One IBRD / 87800 Post Request for Bids Open - National 110,677.00 0.00 Implementat 2019-06-07 2019-06-12 2019-07-24 2019-08-23 2019-09-27 2020-03-25 Saniroad Road(From Agro Cluster Development Envelope ion Bardhap LP School to Kandhbari) in Nalbari District IN-ARIAS-88811-CW-RFB / PWD : Construction of Bunbari Dhamdhama Road Pending Component B: Facilitating Single Stage - One (from Bishnu Mandir of IBRD / 87800 Post Request for Bids Open - National 166,908.00 0.00 Implementat 2019-06-17 2019-06-22 2019-08-03 2019-09-02 2019-10-07 2020-04-04 Agro Cluster Development Envelope Dhamdhama Mahina PWD ion Road to Bunbari village) in Nalbari district IN-ARIAS-88812-CW-RFB / PWD : Construction of Pending Component B: Facilitating Single Stage - One Kalbari Dhupguri namghar IBRD / 87800 Post Request for Bids Open - National 177,723.00 0.00 Implementat 2019-07-08 2019-07-13 2019-08-24 2019-09-23 2019-10-28 2020-04-25 Agro Cluster Development Envelope to uttar Satbhanitup PWD ion Road in Barpeta IN-ARIAS-88814-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One Bahari Puran Kirtan Ghar IBRD / 87800 Post Request for Bids Open - National 436,431.00 398,680.07 Signed 2019-07-15 2019-07-20 2019-08-31 2019-09-30 2019-11-04 2020-05-02 Agro Cluster Development Envelope to Uttar Haripur road in Barpeta district IN-ARIAS-88815-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One Sampupara Bazar to IBRD / 87800 Post Request for Bids Open - National 459,108.00 395,438.81 Signed 2019-06-17 2019-06-22 2019-08-03 2019-09-02 2019-10-07 2020-04-04 Agro Cluster Development Envelope Chaygaon PWD Road in Kamrup District IN-ARIAS-88816-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One Bamundi PWD Road (Beltol- IBRD / 87800 Post Request for Bids Open - National 196,462.00 176,793.28 Signed 2019-07-01 2019-07-06 2019-08-17 2019-09-16 2019-10-21 2020-04-18 Agro Cluster Development Envelope Mahkaltol Dhuliapara Road) in Kamrup district IN-ARIAS-88818-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One Rongphar Village, Phulgaon IBRD / 87800 Post Request for Bids Open - National 424,615.00 383,814.82 Signed 2019-06-24 2019-06-29 2019-08-10 2019-09-09 2019-10-14 2020-04-11 Agro Cluster Development Envelope to Sonapur Burnihat PWD Road in Kamrup district IN-ARIAS-88820-CW-RFB / PWD : Construction of Road from Irongmara Pending Component B: Facilitating Single Stage - One Dakbunglow to Harinagar IBRD / 87800 Post Request for Bids Open - National 1,080,185.00 0.00 Implementat 2019-06-04 2019-06-09 2019-07-21 2019-08-20 2019-09-24 2020-03-22 Agro Cluster Development Envelope L.P School (Ch. 1530.00 M ion to Ch. 2330.00M) in Cachar district IN-ARIAS-88823-CW-RFB / PWD : Construction of Roads from Khambar Bazar centre approx.. 2 km Component B: Facilitating Single Stage - One IBRD / 87800 Post Request for Bids Open - National 46,154.00 40,007.59 Signed 2019-06-17 2019-06-22 2019-08-03 2019-09-02 2019-10-07 2020-04-04 towards Kalain BMC Agro Cluster Development Envelope Building Kosutillain (Ch.0.0 M to Ch.250.00 M ) in Cachar District IN-ARIAS-88826-CW-RFB / PWD : Construction of Roads from Khambar Bazar Pending Component B: Facilitating Single Stage - One centre towards Silchar to IBRD / 87800 Post Request for Bids Open - National 120,000.00 0.00 Implementat 2019-06-18 2019-06-23 2019-08-04 2019-09-03 2019-10-08 2020-04-05 Agro Cluster Development Envelope Burunga-I (Ch.0.0 M to ion Ch.650.00M) in Cachar district IN-ARIAS-88828-CW-RFB / PWD : Construction of Pending Road from Kajidhar PWD Component B: Facilitating Single Stage - One IBRD / 87800 Post Request for Bids Open - National 240,000.00 0.00 Implementat 2019-06-10 2019-06-15 2019-07-27 2019-08-26 2019-09-30 2020-03-28 road to NH 54 (CH.0.00 M Agro Cluster Development Envelope ion to Ch. 1300.00M) in Cachar district Page 2 IN-ARIAS-88830-CW-RFB / PWD : Construction of Road from Sonai Miri Component B: Facilitating Single Stage - One IBRD / 87800 Post Request for Bids Open - National 605,477.00 521,668.00 Signed 2019-07-01 2019-07-06 2019-08-17 2019-09-16 2019-10-21 2020-04-18 Village to Chariduar Agro Cluster Development Envelope Bhalukpong Main Road in Sonitpur district IN-ARIAS-88833-CW-RFB / PWD : Construction of road Component B: Facilitating Single Stage - One from NKS road to Dolibari IBRD / 87800 Post Request for Bids Open - National 581,631.00 477,700.28 Signed 2019-06-03 2019-06-08 2019-07-20 2019-08-19 2019-09-23 2020-03-21 Agro Cluster Development Envelope Pathar road in Nagaon district IN-ARIAS-88837-CW-RFB / PWD : Construction of Pending Component B: Facilitating Single Stage - One Nanoi Dakhinpat PWD IBRD / 87800 Post Request for Bids Open - National 300,000.00 0.00 Implementat 2019-06-03 2019-06-08 2019-07-20 2019-08-19 2019-09-23 2020-03-21 Agro Cluster Development Envelope road to Dewrigaon No.1 ion road in Nagaon district IN-ARIAS-88838-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One Darjisit to Jamunasit via IBRD / 87800 Post Request for Bids Open - National 393,538.00 323,217.83 Signed 2019-06-04 2019-06-09 2019-07-21 2019-08-20 2019-09-24 2020-03-22 Agro Cluster Development Envelope South Laskar Pathar in Nagaon (Hojai) district IN-ARIAS-88840-CW-RFB / PWD : Construction of road Under Component B: Facilitating Single Stage - One from NH-15 to IBRD / 87800 Post Request for Bids Open - National 313,723.00 0.00 Implementat 2019-07-01 2019-07-06 2019-08-17 2019-09-16 2019-10-21 2020-04-18 Agro Cluster Development Envelope Barkumarpara in Darrang ion District IN-ARIAS-88842-CW-RFB / Pending PWD : Construction of Component B: Facilitating Single Stage - One IBRD / 87800 Post Request for Bids Open - National 364,815.00 0.00 Implementat 2019-06-17 2019-06-22 2019-08-03 2019-09-02 2019-10-07 2020-04-04 Bhuktabari Sonapur road Agro Cluster Development Envelope ion in Darrang district IN-ARIAS-88846-CW-RFB / PWD : Construction of road Component B: Facilitating Single Stage - One from Bongshigaon to IBRD / 87800 Post Request for Bids Open - National 242,108.00 197,538.38 Signed 2019-06-17 2019-06-22 2019-08-03 2019-09-02 2019-10-07 2020-04-04 Agro Cluster Development Envelope Bongshigaon H.S in Kokrajhar district IN-ARIAS-88854-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One IBRD / 87800 Post Request for Bids Open - National 559,862.00 507,538.61 Signed 2019-06-10 2019-06-15 2019-07-27 2019-08-26 2019-09-30 2020-03-28 Dillaji road (Rongklarbong) Agro Cluster Development Envelope in Karbi Anglong district IN-ARIAS-88856-CW-RFB / PWD : Construction of road Component B: Facilitating Single Stage - One IBRD / 87800 Post Request for Bids Open - National 228,231.00 190,795.38 Signed 2019-06-17 2019-06-22 2019-08-03 2019-09-02 2019-10-07 2020-04-04 from Nalbari to Batabari Agro Cluster Development Envelope in Kokrajhar district IN-ARIAS-88858-CW-RFB / PWD : Construction of road Component B: Facilitating Single Stage - One from Barmanpara to New IBRD / 87800 Post Request for Bids Open - National 212,754.00 179,848.03 Signed 2019-06-12 2019-06-17 2019-07-29 2019-08-28 2019-10-02 2020-03-30 Agro Cluster Development Envelope Kadamtola Chawk in Kokrajhar district IN-ARIAS-88861-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One IBRD / 87800 Post Request for Bids Open - National 191,492.00 152,220.52 Signed 2019-06-03 2019-06-08 2019-07-20 2019-08-19 2019-09-23 2020-03-21 Baijuri to Watrigiri road in Agro Cluster Development Envelope Goalpara district IN-ARIAS-88862-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One IBRD / 87800 Post Request for Bids Open - National 532,554.00 437,933.97 Signed 2019-06-10 2019-06-15 2019-07-27 2019-08-26 2019-09-30 2020-03-28 Jalapara to Madang road Agro Cluster Development Envelope in Goalpara district IN-ARIAS-88866-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One IBRD / 87800 Post Request for Bids Open - National 214,769.00 182,696.69 Signed 2019-06-10 2019-06-15 2019-07-27 2019-08-26 2019-09-30 2020-03-28 Deulgiri Oil Palm road in Agro Cluster Development Envelope Goalpara district IN-ARIAS-88867-CW-RFB / PWD : Construction of road from Sonaluguri Under Component B: Facilitating Single Stage - One (Kurshakati) to IBRD / 87800 Post Request for Bids Open - National 694,846.00 0.00 Implementat 2019-06-03 2019-06-08 2019-07-20 2019-08-19 2019-09-23 2020-03-21 Agro Cluster Development Envelope Ghunghunikhata via ion Banderkuti in Dhubri district IN-ARIAS-88869-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One Bokora Citador road (from IBRD / 87800 Post Request for Bids Open - National 630,369.00 571,541.96 Signed 2019-06-10 2019-06-15 2019-07-27 2019-08-26 2019-09-30 2020-03-28 Agro Cluster Development Envelope Ch.0.00km to Ch. 2.95km) in Majuli (Jorhat) district IN-ARIAS-88873-CW-RFB / PWD : Construction of road from Upper Temera to Component B: Facilitating Single Stage - One Kanphalajan via Kamala IBRD / 87800 Post Request for Bids Open - National 508,985.00 449,940.57 Signed 2019-06-03 2019-06-08 2019-07-20 2019-08-19 2019-09-23 2020-03-21 Agro Cluster Development Envelope Miri Road (from Ch.0.0km to Ch.3.0km) in Golaghat district. IN-ARIAS-88874-CW-RFB / PWD : Construction of Dhalpur Simuluguri PWD Component B: Facilitating Single Stage - One to Rangati Arimora Ghat IBRD / 87800 Post Request for Bids Open - National 756,538.00 685,933.09 Signed 2019-06-10 2019-06-15 2019-07-27 2019-08-26 2019-09-30 2020-03-28 Agro Cluster Development Envelope PWD Road via Ganakdoloni and Nidansuwa village in Lakhimpur diatrict IN-ARIAS-88875-CW-RFB / PWD : Construction of Na- Component B: Facilitating Single Stage - One Charingia Road (from IBRD / 87800 Post Request for Bids Open - National 171,231.00 155,287.85 Signed 2019-06-05 2019-06-10 2019-07-22 2019-08-21 2019-09-25 2020-03-23 Agro Cluster Development Envelope Ch.0.0 km to Ch. 1.0 km) in Sivasagar district Page 3 IN-ARIAS-88880-CW-RFB / PWD : Construction of Component B: Facilitating Single Stage - One Barbarua Tekela Road IBRD / 87800 Post Request for Bids Open - National 113,538.00 105,486.89 Signed 2019-06-13 2019-06-18 2019-07-30 2019-08-29 2019-10-03 2020-03-31 Agro Cluster Development Envelope (from Ch.0.0 km to Ch.0.7 km) in Sivasagar district IN-ARIAS-88884-CW-RFB / PWD : Construction of Pending Component B: Facilitating Single Stage - One Dhundar Mukh Road (from IBRD / 87800 Post Request for Bids Open - National 501,538.00 0.00 Implementat 2019-06-17 2019-06-22 2019-08-03 2019-09-02 2019-10-07 2020-04-04 Agro Cluster Development Envelope Ch.0.0 km to Ch.3.0 km) ion in Sivasagar district IN-ARIAS-88938-CW-RFQ / PWD : Need based renovation/refurbishment for setting up of the Operational Project Pending Implementation Unit Component B: Facilitating Request for Single Stage - One IBRD / 87800 Post Open - National 99,108.00 0.00 Implementat 2019-07-06 2019-09-05 2020-03-03 (OPIU) of Dairy Agro Cluster Development Quotations Envelope ion Development Department, Fishery Development Department, Assam State Agricultural Marketing Board and Sericulture Department. IN-ARIAS-88939-CW-RFQ / PWD : Renovation and Extension of Room for proposed OPIU at Second Component C: Fostering Pending Floor of D.R. Office, AAU, Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 55,692.00 0.00 Implementat 2019-06-29 2019-09-03 2020-03-01 Jorhat and Renovation/ Quotations Envelope Resilience Enhancement ion Refurbishment for setting up OPIU in Director of Handloom & Textile office, Guwahati IN-ARIAS-88940-CW-RFQ / PWD : APART_ATMA _NS_1 Renovation/ Repair Component C: Fostering Request for Single Stage - One of District ATMA Offices at IBRD / 87800 Market-led Production and Post Open - National 64,615.00 52,720.42 Signed 2019-06-23 2019-08-28 2020-02-24 Quotations Envelope Sonitpur, Darrang, Nagaon, Resilience Enhancement Karbi Anglong, Morigaon and Lakhimpur IN-ARIAS-88941-CW-RFQ / PWD : APART_ATMA Component C: Fostering _NS_2 : Renovation/ Repair Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 32,308.00 26,527.06 Signed 2019-06-23 2019-08-28 2020-02-24 of District ATMA Offices at Quotations Envelope Resilience Enhancement Kokrajhar, Dhubri & Goalpara. IN-ARIAS-88942-CW-RFQ / PWD : APART_ATMA _NS_3: Renovation/ Repair Component C: Fostering Pending of District ATMA Offices at Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 33,309.00 0.00 Implementat 2019-07-06 2019-09-10 2020-03-08 Nalbari & Barpeta and Quotations Envelope Resilience Enhancement ion Need based Renovation and Repairing for setting up of the OPIU Horti & FP IN-ARIAS-88943-CW-RFQ / PWD : APART_ATMA Component C: Fostering Request for Single Stage - One _NS_4: Renovation/ Repair IBRD / 87800 Market-led Production and Post Open - National 10,769.00 8,842.35 Signed 2019-07-08 2019-09-12 2020-03-10 Quotations Envelope of District ATMA Offices at Resilience Enhancement Cachar IN-ARIAS-88944-CW-RFQ / PWD : Strengthening of Component C: Fostering Request for Single Stage - One existing Laboratory IBRD / 87800 Market-led Production and Post Open - National 15,385.00 14,035.48 Signed 2019-07-13 2019-09-17 2020-03-15 Quotations Envelope infrastructure of Dairy at Resilience Enhancement Ghungoor, Silchar IN-ARIAS-124928-CW-RFB Component D: Project Pending / PCU : Interior and Single Stage - One IBRD / 87800 Management, Monitoring Post Request for Bids Open - National 507,353.00 0.00 Implementat 2019-10-14 2019-10-19 2019-11-30 2019-12-30 2020-02-03 2020-10-30 Furnishing work of PCU Envelope and Learning ion Building [Part B ] GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-ARIAS-19762-GO-RFQ / Purchase of Computers and Component A: Enabling Pending Request for Single Stage - One Office Equipment for PCU IBRD / 87800 Agri Enterprise Post Open - National 294,118.00 0.00 Implementat 2018-04-23 2018-08-17 2018-12-15 Quotations Envelope and other implementing Development ion Agencies . IN-ARIAS-19790-GO-RFB / Component A: Enabling Pending Purchase of Bulk Milk Single Stage - IBRD / 87800 Agri Enterprise Post Request for Bids Open - National 145,588.00 0.00 Implementat 2018-07-09 2018-07-14 2018-08-08 2018-10-11 2018-11-15 2020-05-13 Coolers for Informal Milk Two Envelope Development ion Dairy Sector IN-ARIAS-48741-GO-RFQ / Component A: Enabling ARIAS: Chairs for PCU's Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 15,385.00 11,649.78 Signed 2018-03-10 2018-05-31 2018-07-30 newly developed cabins and Quotations Envelope Development cubicles (Part-A) IN-ARIAS-48827-GO-RFQ / Component A: Enabling WAMUL: Making of Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 492.00 499.11 Completed 2018-03-15 2018-04-14 2018-05-14 Promotional Banner for Quotations Envelope Development MAITs Page 4 IN-ARIAS-48835-GO-RFQ / Component A: Enabling WAMUL: Supply & Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 1,646.00 1,604.64 Signed 2018-03-31 2018-05-12 2018-06-11 Stitching of shirts & Quotations Envelope Development Trousers for MAITs IN-ARIAS-48858-GO-RFQ / Component A: Enabling Request for Single Stage - One WAMUL: Supply of Liquid IBRD / 87800 Agri Enterprise Post Open - National 1,262.00 12,484.21 Signed 2018-04-05 2018-04-30 2018-05-30 Quotations Envelope nitrogen Development IN-ARIAS-48860-GO-RFQ / Component A: Enabling Request for Single Stage - One WAMUL: Supply of Ear IBRD / 87800 Agri Enterprise Post Open - National 2,215.00 1,558.94 Signed 2018-03-28 2018-05-04 2018-06-03 Quotations Envelope Tag Development IN-ARIAS-48861-GO-RFQ / Component A: Enabling Request for Single Stage - One WAMUL : Supply of Ear IBRD / 87800 Agri Enterprise Post Open - National 1,662.00 2,690.05 Completed 2018-03-31 2018-05-12 2018-06-11 Quotations Envelope Tag & Ear Tag Applicator Development IN-ARIAS-49157-GO-RFQ / Component A: Enabling Request for Single Stage - One WAMUL : Jumbo Semen IBRD / 87800 Agri Enterprise Post Open - National 1,015.00 839.50 Signed 2018-04-28 2018-07-14 2018-08-13 Quotations Envelope storage container Development IN-ARIAS-49158-GO-RFQ / Component A: Enabling Request for Single Stage - One WAMUL : Laptop to field IBRD / 87800 Agri Enterprise Post Open - National 4,615.00 4,184.85 Signed 2018-04-28 2018-07-09 2018-08-08 Quotations Envelope staff Development IN-ARIAS-49163-GO-RFQ / Component A: Enabling Under Request for Single Stage - One WAMUL : Laser Printer IBRD / 87800 Agri Enterprise Post Open - National 308.00 0.00 Implementat 2018-04-28 2018-07-09 2018-08-08 Quotations Envelope (RO) Development ion IN-ARIAS-49165-GO-RFQ / Component A: Enabling Under Request for Single Stage - One WAMUL : Android based IBRD / 87800 Agri Enterprise Post Open - National 25,385.00 0.00 Implementat 2018-05-05 2018-07-16 2018-08-15 Quotations Envelope Mobile Tablets for MAITS Development ion IN-ARIAS-49437-GO-RFQ / Component A: Enabling Under Request for Single Stage - One WAMUL : Furnitures & IBRD / 87800 Agri Enterprise Post Open - National 4,154.00 0.00 Implementat 2018-05-12 2018-07-23 2018-09-21 Quotations Envelope Fixtures for Head Office Development ion IN-ARIAS-49439-GO-RFQ / Component A: Enabling Under Request for Single Stage - One WAMUL : AIT furniture IBRD / 87800 Agri Enterprise Post Open - National 18,923.00 0.00 Implementat 2018-05-26 2018-08-06 2018-10-05 Quotations Envelope set Development ion IN-ARIAS-49443-GO-RFQ / Component A: Enabling Under Request for Single Stage - One WAMUL : Furniture IBRD / 87800 Agri Enterprise Post Open - National 3,692.00 0.00 Implementat 2018-06-05 2018-08-01 2018-09-30 Quotations Envelope (Cluster office) Development ion IN-ARIAS-49448-GO-RFQ / Component A: Enabling Under Request for Single Stage - One WAMUL : Frozen Semen IBRD / 87800 Agri Enterprise Post Open - National 9,354.00 0.00 Implementat 2018-06-05 2018-08-24 2018-10-23 Quotations Envelope dose Development ion IN-ARIAS-49454-GO-RFQ / Component A: Enabling Request for Single Stage - One WAMUL : Walk in Coolers IBRD / 87800 Agri Enterprise Post Open - National 15,385.00 0.00 Canceled 2018-08-25 2018-11-05 2019-02-03 Quotations Envelope (5000 ltr capacity, 2 Nos.) Development IN-ARIAS-49456-GO-RFQ / Component A: Enabling WAMUL : GenSet (2 Nos) Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 10,769.00 0.00 Canceled 2018-05-28 2018-08-08 2018-10-07 for captive power back-up Quotations Envelope Development for the Walk-in Coolers IN-ARIAS-49455-GO-RFQ / Component A: Enabling Under WAMUL : Disposable Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 2,354.00 0.00 Implementat 2018-06-05 2018-08-10 2018-10-09 Gloves (50,868 Nos.) for Quotations Envelope Development ion conducting AI IN-ARIAS-49457-GO-RFQ / WAMUL : Insulated Boxes Component A: Enabling Under Request for Single Stage - One (80 Nos.) for packaged Milk IBRD / 87800 Agri Enterprise Post Open - National 7,385.00 0.00 Implementat 2018-05-26 2018-08-06 2018-10-05 Quotations Envelope and Milk products at retail Development ion level IN-ARIAS-49460-GO-RFQ / Component A: Enabling Under WAMUL : Disposable Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 554.00 0.00 Implementat 2018-06-05 2018-08-10 2018-10-09 Sheath (27997 nos.) for Quotations Envelope Development ion conducting AI Component A: Enabling IN-ARIAS-49464-GO-RFQ / Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 36,923.00 0.00 Canceled 2018-06-04 2018-08-09 2018-10-08 WAMUL : Visi coolers Quotations Envelope Development IN-ARIAS-49465-GO-RFQ / Component A: Enabling Under Request for Single Stage - One WAMUL : Ear Tags for IBRD / 87800 Agri Enterprise Post Open - National 3,369.00 0.00 Implementat 2018-06-05 2018-08-10 2018-10-09 Quotations Envelope ear-tagging inseminated Development ion animals Component A: Enabling Under IN-ARIAS-49467-GO-RFQ / Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 36,923.00 0.00 Implementat 2018-06-03 2018-08-14 2018-10-13 WAMUL : Milk Crates Quotations Envelope Development ion IN-ARIAS-49471-GO-RFQ / Component A: Enabling Request for Single Stage - One WAMUL : (LN2) Liquid IBRD / 87800 Agri Enterprise Post Open - National 6,185.00 13,939.12 Signed 2018-06-05 2018-08-10 2018-10-09 Quotations Envelope Nitrogen Development IN-ARIAS-49476-GO-RFQ / Component A: Enabling Under WAMUL : (LN2) Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 6,046.00 0.00 Implementat 2018-06-05 2018-08-10 2018-10-09 Transportation of Liquid Quotations Envelope Development ion Nitrogen IN-ARIAS-49484-GO-RFQ / Component A: Enabling Pending Request for Single Stage - One WAMUL : IT Equipment IBRD / 87800 Agri Enterprise Post Open - National 4,615.00 0.00 Implementat 2018-08-25 2018-11-05 2019-02-03 Quotations Envelope (Hardware and Software) Development ion Component A: Enabling Under IN-ARIAS-49526-GO-RFQ / Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 4,462.00 0.00 Implementat 2018-05-19 2018-07-30 2018-09-28 WAMUL : AIT Stationeries Quotations Envelope Development ion Page 5 IN-ARIAS-49532-GO-RFQ / Component A: Enabling Under WAMUL : Support for Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 30,308.00 0.00 Implementat 2018-06-16 2018-08-27 2018-10-26 rearing heifers (Calf Quotations Envelope Development ion Starter) IN-ARIAS-49535-GO-RFQ / Component A: Enabling Under WAMUL : Support for Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 30,462.00 0.00 Implementat 2018-06-16 2018-08-27 2018-10-26 rearing heifers (Milk Quotations Envelope Development ion Replacer) IN-ARIAS-49539-GO-RFQ / Component A: Enabling Under WAMUL : Support for Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 30,585.00 0.00 Implementat 2018-06-24 2018-09-04 2018-11-03 rearing heifers (Mineral Quotations Envelope Development ion Mixtures) IN-ARIAS-49541-GO-RFQ / Component A: Enabling Request for Single Stage - One WAMUL : Automatic Milk IBRD / 87800 Agri Enterprise Post Open - National 4,923.00 0.00 Canceled 2018-06-30 2018-09-10 2018-11-09 Quotations Envelope Collection Units (AMCUs) Development Component A: Enabling IN-ARIAS-49545-GO-RFQ / Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 1,538.00 0.00 Canceled 2018-06-10 2018-08-21 2018-10-20 WAMUL : Can scrubbers Quotations Envelope Development IN-ARIAS-49548-GO-RFQ / Component A: Enabling Request for Single Stage - One WAMUL : Road milk IBRD / 87800 Agri Enterprise Post Open - National 38,462.00 0.00 Canceled 2018-06-18 2018-08-29 2018-10-28 Quotations Envelope tankers (5000 ltr capacity) Development IN-ARIAS-49551-GO-RFQ / Component A: Enabling Request for Single Stage - One WAMUL : Road milk IBRD / 87800 Agri Enterprise Post Open - National 53,846.00 0.00 Canceled 2018-07-01 2018-09-11 2018-11-10 Quotations Envelope tanker (10000 ltr capacity) Development Component A: Enabling Under IN-ARIAS-49553-GO-RFQ / Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 6,923.00 0.00 Implementat 2018-06-17 2018-08-28 2018-10-27 WAMUL : Milk Cans Quotations Envelope Development ion IN-ARIAS-49559-GO-RFQ / Component A: Enabling Under WAMUL : Solar powered Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 60,000.00 0.00 Implementat 2018-07-21 2018-10-01 2018-11-30 Data Processor Milk Quotations Envelope Development ion Collection Units (DPMCUs) Component A: Enabling IN-ARIAS-49558-GO-RFQ / Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 769.00 0.00 Canceled 2018-07-05 2018-09-18 2018-11-17 WAMUL : Adulteration kits Quotations Envelope Development IN-ARIAS-49560-GO-RFQ / Component A: Enabling Pending Request for Single Stage - One WAMUL : Milk Collection IBRD / 87800 Agri Enterprise Post Open - National 3,231.00 0.00 Implementat 2018-07-21 2018-10-01 2018-11-30 Quotations Envelope Equipments Development ion IN-ARIAS-49561-GO-RFQ / Component A: Enabling Request for Single Stage - One WAMUL : Milking IBRD / 87800 Agri Enterprise Post Open - National 1,846.00 2,482.10 Signed 2018-07-05 2018-09-15 2018-11-14 Quotations Envelope machines Development IN-ARIAS-49564-GO-RFQ / Component A: Enabling Pending Request for Single Stage - One WAMUL : Furnitures and IBRD / 87800 Agri Enterprise Post Open - National 9,231.00 0.00 Implementat 2018-07-05 2018-09-09 2018-11-08 Quotations Envelope fixtures Development ion IN-ARIAS-49563-GO-RFQ / Component A: Enabling Request for Single Stage - One WAMUL : Power driven IBRD / 87800 Agri Enterprise Post Open - National 2,308.00 0.00 Canceled 2018-07-03 2018-09-13 2018-11-12 Quotations Envelope Gerber machines Development IN-ARIAS-49566-GO-RFQ / Component A: Enabling Under Request for Single Stage - One WAMUL: Extension and IBRD / 87800 Agri Enterprise Post Open - National 19,200.00 0.00 Implementat 2018-06-05 2018-08-10 2018-10-09 Quotations Envelope Promotion Material Development ion IN-ARIAS-49571-GO-RFQ / Component A: Enabling Request for Single Stage - One WAMUL : Refrigerated IBRD / 87800 Agri Enterprise Post Open - National 61,538.00 0.00 Canceled 2018-05-29 2018-08-09 2018-10-08 Quotations Envelope vans Development IN-ARIAS-48877-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One WAMUL : Supply of AI IBRD / 87800 Market-led Production and Post Open - National 431.00 0.00 Implementat 2018-05-06 2018-06-10 2018-07-10 Quotations Envelope Kits Resilience Enhancement ion IN-ARIAS-48870-GO-RFQ / Component C: Fostering Pending WAMUL : Supply of AI Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 892.00 0.00 Implementat 2018-05-12 2018-06-23 2018-07-23 disposable gloves & AI Quotations Envelope Resilience Enhancement ion Sheets IN-ARIAS-48880-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One WAMUL : Supply of AI IBRD / 87800 Market-led Production and Post Open - National 1,815.00 0.00 Implementat 2019-01-30 2019-03-21 2019-05-20 Quotations Envelope Accessories Resilience Enhancement ion IN-ARIAS-61743-GO-DIR / PCU Solar PV Power : Installation of Grid Connected Rooftop Solar Component D: Project Pending PV Power Plants under IBRD / 87800 Management, Monitoring Post Direct Selection Direct 7,751.00 0.00 Implementat 2019-01-28 2019-02-07 2019-03-24 2019-05-23 CAPEX Model at the and Learning ion building of ARIAS Society under 70 percentage Subsidy Scheme IN-ARIAS-48749-GO-RFQ / ARIAS: Solar Power System (Roof top) for PCU Component A: Enabling Request for Single Stage - One building and Solar Power IBRD / 87800 Agri Enterprise Post Open - National 61,538.00 0.00 Canceled 2018-03-10 2018-05-31 2018-08-29 Quotations Envelope Street light in the PCU Development Campus - Supply & Installation IN-ARIAS-19789-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One Purchase of Iron IBRD / 87800 Market-led Production and Post Open - National 48,529.00 0.00 Implementat 2019-02-02 2019-06-07 2019-08-06 Quotations Envelope Supplements for piglet Resilience Enhancement ion Page 6 IN-ARIAS-19775-GO-RFB / Purchase of Vaccines for Food & Mouth Disease Component A: Enabling Pending Single Stage - (FMD) ,Haemorrhagic IBRD / 87800 Agri Enterprise Post Request for Bids Open - National 285,294.00 0.00 Implementat 2018-12-24 2018-12-29 2019-01-28 2019-04-12 2019-05-17 2024-09-30 Two Envelope Septicaemia and Black Development ion Quarter (HS & BQ) Disease and Brucellosis IN-ARIAS-67904-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One AHVD: Procurement of IBRD / 87800 Market-led Production and Post Open - National 15,385.00 0.00 Implementat 2018-09-08 2018-11-26 2019-01-25 Quotations Envelope Computer and Accessories Resilience Enhancement ion IN-ARIAS-48756-GO-RFQ / Component A: Enabling Pending ARIAS: Elevator for PCU Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 46,154.00 0.00 Implementat 2019-06-29 2019-09-27 2020-03-25 building - Supply & Quotations Envelope Development ion Installation IN-ARIAS-48820-GO-RFQ / Component D: Project Pending PCU : Supply & Request for Single Stage - One IBRD / 87800 Management, Monitoring Post Open - National 46,154.00 0.00 Implementat 2019-06-22 2019-09-08 2020-03-06 Installation of silent Quotations Envelope and Learning ion GenSet for PCU building of 450kva IN-ARIAS-77353-GO-RFQ / Component C: Fostering Pending AGRI (ATMA) : Purchase Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 33,969.00 0.00 Implementat 2019-01-12 2019-03-09 2019-05-08 of Computer with other Quotations Envelope Resilience Enhancement ion accessories (48 nos.) IN-ARIAS-77355-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One AGRI (ATMA) : 16 nos. of IBRD / 87800 Market-led Production and Post Open - National 30,769.00 0.00 Implementat 2019-01-12 2019-03-16 2019-05-15 Quotations Envelope Photocopiers with scanner Resilience Enhancement ion IN-ARIAS-77390-GO-RFQ / AAU : Purchase of 14 nos. of Laptop with other accssories for 1 no of Component C: Fostering Pending Request for Single Stage - One Project Coordinator, 11 nos. IBRD / 87800 Market-led Production and Post Open - National 32,308.00 0.00 Implementat 2019-01-09 2019-03-09 2019-04-23 Quotations Envelope of Project Scientist, 1 no Resilience Enhancement ion of Accounts Manager and 1 no of MIS Operator at OPIU IN-ARIAS-77401-GO-RFQ / AAU : Purchase of 43 nos. Component C: Fostering Pending of Laptop with other Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 99,231.00 0.00 Implementat 2019-01-07 2019-03-12 2019-05-11 accessories for Project Quotations Envelope Resilience Enhancement ion Scientist and Asstt. Project Scientist at RARS/KVKs IN-ARIAS-77403-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One AAU : Furnitures for OPIU IBRD / 87800 Market-led Production and Post Open - National 46,154.00 0.00 Implementat 2019-01-09 2019-03-09 2019-05-08 Quotations Envelope at AAU, Jorhat Resilience Enhancement ion IN-ARIAS-77410-GO-RFQ / Component C: Fostering Pending DAIRY : Procurement of Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 73,846.00 0.00 Implementat 2019-01-26 2019-03-28 2019-04-27 computers & accessories for Quotations Envelope Resilience Enhancement ion 4 District Project Offices IN-ARIAS-77568-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One AHVD-Piggery : Cost of 24 IBRD / 87800 Market-led Production and Post Open - National 11,077.00 0.00 Implementat 2019-01-26 2019-03-26 2019-04-25 Quotations Envelope nos. tablet for data entry Resilience Enhancement ion IN-ARIAS-77569-GO-RFQ / Component C: Fostering Pending AHVD Piggery : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 15,385.00 0.00 Implementat 2019-01-23 2019-03-23 2019-05-22 Procurement of Computer Quotations Envelope Resilience Enhancement ion & Accessories IN-ARIAS-77570-GO-RFQ / Component C: Fostering Pending AHVD Piggery : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 42,462.00 0.00 Implementat 2019-01-12 2019-03-14 2019-05-13 Procurement of 138,000 Quotations Envelope Resilience Enhancement ion nos. Classical swine fever vaccine IN-ARIAS-77571-GO-RFQ / Component C: Fostering AHVD Piggery : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 42,462.00 35,443.11 Signed 2019-02-02 2019-04-04 2019-06-03 Procurement of FMD Quotations Envelope Resilience Enhancement vaccine IN-ARIAS-77572-GO-RFQ / Component C: Fostering AHVD Piggery : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 42,462.00 10,644.35 Signed 2019-02-02 2019-04-04 2019-06-03 Procurement of 138,000 Quotations Envelope Resilience Enhancement nos. of Deworming IN-ARIAS-77573-GO-RFQ / Component C: Fostering AHVD Piggery : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 49,846.00 13,442.86 Signed 2019-02-09 2019-04-06 2019-10-03 Procurement of 54,000 nos. Quotations Envelope Resilience Enhancement Iron supplementation IN-ARIAS-91925-GO-DIR / Component C: Fostering AHVD Piggery : IBRD / 87800 Market-led Production and Post Direct Selection Direct 169,846.00 173,582.44 Signed 2019-02-11 2019-02-16 2019-03-28 2019-09-24 Procurement of 276,000 Resilience Enhancement nos. Cysticercosis IN-ARIAS-77579-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One AHVD Piggery : 37,920 IBRD / 87800 Market-led Production and Post Open - National 25,169.00 0.00 Implementat 2019-01-23 2019-03-25 2019-04-24 Quotations Envelope nos. of Ear tags Resilience Enhancement ion IN-ARIAS-77585-GO-RFQ / Component C: Fostering AHVD-FORMAL DAIRY : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 19,015.00 13,347.21 Signed 2019-01-23 2019-03-25 2019-09-21 Procurement of 41,200 nos. Quotations Envelope Resilience Enhancement of Brucellosis vaccination IN-ARIAS-77587-GO-RFQ / Component C: Fostering Pending AHVD-FORMAL DAIRY : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 97,154.00 0.00 Implementat 2019-01-12 2019-03-09 2019-05-08 Procurement of 631,500 Quotations Envelope Resilience Enhancement ion nos. of FMD vaccinations Page 7 IN-ARIAS-77589-GO-RFQ / AHVD-FORMAL DAIRY : Component C: Fostering Request for Single Stage - One Procurement of 316,000 IBRD / 87800 Market-led Production and Post Open - National 48,615.00 18,001.89 Signed 2019-01-26 2019-03-28 2019-05-27 Quotations Envelope nos. of Haemorrhagic Resilience Enhancement Septicaemia & Blackquarter Vaccine IN-ARIAS-77590-GO-RFQ / Component C: Fostering Pending AHVD-INFORMAL DAIRY : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 21,523.00 0.00 Implementat 2019-01-09 2019-03-11 2019-05-10 Procurement of 244,720 Quotations Envelope Resilience Enhancement ion nos. of FMD vaccinations IN-ARIAS-77592-GO-RFQ / AHVD-INFORMAL DAIRY : Component C: Fostering Request for Single Stage - One Procurement of 52,400 nos. IBRD / 87800 Market-led Production and Post Open - National 8,062.00 18,001.89 Signed 2019-01-26 2019-03-28 2019-05-27 Quotations Envelope of Haemorrhagic Resilience Enhancement Septicaemia & Blackquarter Vaccine IN-ARIAS-77593-GO-RFQ / AHVD-INFORMAL DAIRY : Procurement of 17 nos. of Component C: Fostering Pending Request for Single Stage - One Tablet for Information IBRD / 87800 Market-led Production and Post Open - National 3,923.00 0.00 Implementat 2019-01-23 2019-03-25 2019-05-24 Quotations Envelope Network for Animal Resilience Enhancement ion Productivity and Health (INAPH) IN-ARIAS-77594-GO-RFQ / Component C: Fostering Pending AHVD-INFORMAL DAIRY : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 2,492.00 0.00 Implementat 2019-01-27 2019-03-29 2019-05-28 Procurement of 1800 Ear Quotations Envelope Resilience Enhancement ion tags IN-ARIAS-77597-GO-RFQ / AHVD-INFORMAL DAIRY : Component C: Fostering Pending Request for Single Stage - One Procurement of 11 nos. of IBRD / 87800 Market-led Production and Post Open - National 7,385.00 0.00 Implementat 2019-01-16 2019-03-18 2019-05-17 Quotations Envelope Deep freezer for vaccine Resilience Enhancement ion storage IN-ARIAS-78432-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 76,923.00 0.00 Implementat 2019-01-16 2019-03-13 2019-05-12 Quotations Envelope LN2 Silo 5 KL Resilience Enhancement ion IN-ARIAS-78435-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : 3 IBRD / 87800 Market-led Production and Post Open - National 32,000.00 46,627.12 Signed 2019-01-12 2019-03-09 2019-05-08 Quotations Envelope Litre LN2 Container Resilience Enhancement IN-ARIAS-78436-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : 33 IBRD / 87800 Market-led Production and Post Open - National 47,508.00 41,901.74 Signed 2019-01-26 2019-03-23 2019-05-22 Quotations Envelope L LN2 Container Resilience Enhancement IN-ARIAS-78446-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 20,769.00 0.00 Implementat 2019-02-02 2019-03-30 2019-05-29 Quotations Envelope Lap top to field staff Resilience Enhancement ion IN-ARIAS-78455-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 39,600.00 36,665.03 Signed 2019-01-23 2019-03-20 2019-05-19 Quotations Envelope Netbooks/Tablets to MAITs Resilience Enhancement IN-ARIAS-78459-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 51,462.00 0.00 Implementat 2019-01-23 2019-03-20 2019-05-19 Quotations Envelope AIT furniture set Resilience Enhancement ion IN-ARIAS-78464-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 31,092.00 12,129.50 Signed 2019-01-24 2019-03-14 2019-05-13 Quotations Envelope Frozen Semen dose Resilience Enhancement IN-ARIAS-78476-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 28,385.00 47,225.68 Signed 2019-02-02 2019-03-23 2019-05-22 Quotations Envelope Liquid Nitrogen Resilience Enhancement IN-ARIAS-78478-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One WAMUL (AWP 18-19) : AI IBRD / 87800 Market-led Production and Post Open - National 31,185.00 0.00 Implementat 2019-01-27 2019-03-17 2019-05-16 Quotations Envelope Accessories & consumables Resilience Enhancement ion IN-ARIAS-78479-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 9,815.00 0.00 Implementat 2019-01-28 2019-03-18 2019-05-17 Quotations Envelope AIT Stationeries Resilience Enhancement ion IN-ARIAS-78482-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 29,138.00 0.00 Canceled 2019-01-16 2019-03-06 2019-05-05 Quotations Envelope Data Card cost Resilience Enhancement IN-ARIAS-78646-GO-RFB / Component C: Fostering Under WAMUL (AWP 18-19) Single Stage - One IBRD / 87800 Market-led Production and Post Request for Bids Open - National 213,785.00 0.00 Implementat 2019-01-02 2019-01-07 2019-02-06 2019-03-08 2019-04-12 2019-08-10 :Extension and Promotion Envelope Resilience Enhancement ion Material IN-ARIAS-78484-GO-RFQ / Component A: Enabling Under WAMUL (AWP 18-19) : Request for Single Stage - One IBRD / 87800 Agri Enterprise Post Open - National 35,538.00 0.00 Implementat 2019-01-26 2019-03-22 2019-06-20 Bulk Milk Coolers (BMCs) Quotations Envelope Development ion : 3000 Ltr BMCs IN-ARIAS-78485-GO-RFQ / Component C: Fostering WAMUL (AWP 18-19) : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 85,292.00 71,929.02 Signed 2019-01-12 2019-03-19 2019-06-17 Bulk Milk Coolers (BMCs) Quotations Envelope Resilience Enhancement : 2000Ltr BMCs IN-ARIAS-78486-GO-RFQ / Component C: Fostering Pending WAMUL (AWP 18-19) : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 30,769.00 0.00 Implementat 2019-01-26 2019-03-22 2019-06-20 Differential cost for the Quotations Envelope Resilience Enhancement ion solar powered BMC units IN-ARIAS-78487-GO-RFQ / Component C: Fostering Pending WAMUL (AWP 18-19) : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 14,769.00 0.00 Implementat 2019-02-06 2019-03-28 2019-09-24 Automatic Milk Collection Quotations Envelope Resilience Enhancement ion Units (AMCUs) Page 8 IN-ARIAS-78493-GO-RFB / Component C: Fostering Pending WAMUL (AWP 18-19) : Single Stage - One IBRD / 87800 Market-led Production and Post Request for Bids Open - National 115,385.00 0.00 Implementat 2019-01-11 2019-01-16 2019-02-15 2019-03-12 2019-04-16 2019-07-15 Road milk tankers (5000 Envelope Resilience Enhancement ion ltr capacity) IN-ARIAS-78494-GO-RFB / Component C: Fostering WAMUL (AWP 18-19) : Single Stage - One IBRD / 87800 Market-led Production and Post Request for Bids Open - National 161,538.00 274,288.98 Signed 2019-01-07 2019-01-12 2019-02-11 2019-03-13 2019-04-17 2019-07-16 Road milk tanker (10000 Envelope Resilience Enhancement ltr capacity) IN-ARIAS-78495-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 40,154.00 31,487.21 Completed 2019-02-02 2019-03-23 2019-06-21 Quotations Envelope Milk Cans (40 ltr capacity) Resilience Enhancement IN-ARIAS-78522-GO-RFB / WAMUL (AWP 18-19) : Component C: Fostering Single Stage - One Solar powered Data IBRD / 87800 Market-led Production and Post Request for Bids Open - National 506,000.00 298,634.53 Signed 2019-01-18 2019-01-23 2019-02-22 2019-03-24 2019-04-28 2019-07-27 Envelope Processor Milk Collection Resilience Enhancement Units (DPMCUs) IN-ARIAS-78523-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 27,246.00 17,189.87 Signed 2019-01-13 2019-03-15 2019-05-14 Quotations Envelope Milk Collection Equipments Resilience Enhancement IN-ARIAS-78544-GO-RFQ / Component C: Fostering WAMUL (AWP 18-19) : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 19,462.00 17,536.92 Signed 2019-01-27 2019-03-15 2019-05-14 Power driven Gerber Quotations Envelope Resilience Enhancement machines IN-ARIAS-78545-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 21,000.00 19,095.21 Completed 2019-01-07 2019-02-25 2019-04-26 Quotations Envelope Adulteration kits Resilience Enhancement IN-ARIAS-78548-GO-RFQ / Component C: Fostering Pending WAMUL (AWP 18-19) : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 77,846.00 0.00 Implementat 2019-01-08 2019-02-26 2019-04-27 Furnitures and fixtures (for Quotations Envelope Resilience Enhancement ion MPIs/DCSs) IN-ARIAS-78550-GO-RFQ / Component C: Fostering Pending WAMUL (AWP 18-19) : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 10,385.00 0.00 Implementat 2019-01-09 2019-02-27 2019-04-28 Furnitures and fixtures (for Quotations Envelope Resilience Enhancement ion field offices) IN-ARIAS-78551-GO-RFQ / Component C: Fostering WAMUL (AWP 18-19) : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 15,385.00 28,142.36 Signed 2019-01-10 2019-02-28 2019-04-29 Provision of Walk in Quotations Envelope Resilience Enhancement Coolers (5000 ltr capacity) IN-ARIAS-78552-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 7,662.00 14,446.49 Completed 2019-02-02 2019-03-30 2019-05-29 Quotations Envelope Provision of genset Resilience Enhancement IN-ARIAS-78638-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 42,462.00 0.00 Implementat 2019-02-06 2019-03-27 2019-05-26 Quotations Envelope Visi coolers Resilience Enhancement ion IN-ARIAS-78641-GO-RFQ / Component C: Fostering Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 79,662.00 25,870.06 Signed 2019-01-27 2019-03-24 2019-06-22 Quotations Envelope Milk Crates Resilience Enhancement IN-ARIAS-78642-GO-RFQ / Component C: Fostering Pending Request for Single Stage - One WAMUL (AWP 18-19) : IBRD / 87800 Market-led Production and Post Open - National 61,538.00 0.00 Implementat 2019-01-26 2019-03-23 2019-06-21 Quotations Envelope Refrigerated vans Resilience Enhancement ion IN-ARIAS-87683-GO-RFQ / Component C: Fostering Pending AHVD-INFORMAL DAIRY : Request for Single Stage - One IBRD / 87800 Market-led Production and Post Open - National 21,523.00 0.00 Implementat 2019-02-02 2019-04-04 2019-06-03 Procurement of 244,720 Quotations Envelope Resilience Enhancement ion nos. of FMD vaccinations IN-ARIAS-115292-GO-RFQ / PCU : Procurement of 21 Component D: Project Pending Nos. of Laptops through Request for Single Stage - One IBRD / 87800 Management, Monitoring Post Open - National 19,500.00 0.00 Implementat 2019-06-01 2019-07-27 2019-08-26 GeM for officials under Quotations Envelope and Learning ion International Agency for APART NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) Amount (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-ARIAS-3142-NC-RFQ / Hiring of Consultancy Firm for Digital mapping and plotting of Block/Village wise Prioritized Clusters of Request for Single Stage - One / Post Open - National 30,303.00 26,591.46 Completed 2016-11-15 2016-12-06 2017-03-06 APART together with other Quotations Envelope resources in Google Map and development of a web- enabled Application Software . IN-ARIAS-5209-NC-RFB / Hiring of Manpower Agency Component A: Enabling Single Stage - for recruitment and IBRD / 87800 Agri Enterprise Post Request for Bids Open - National 463,235.00 0.00 Canceled 2018-02-01 2018-02-01 2018-02-22 2018-05-05 2018-06-09 2018-12-06 Two Envelope management of Projects Development Support staff CONSULTING FIRMS Page 9 Activity Reference No. / Short List and Draft Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Request for Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Request for Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Proposals as Issued Proposals / Minutes Technical Proposal Proposals Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-ARIAS-1741-CS-CQS / Consulting Services for Conducting Environmental and Social Assessment of Consultant the Project APART and / Post Qualification Open - National 103,470.00 105,933.49 Completed 2016-09-29 2016-10-20 2016-12-03 2017-01-02 2017-02-06 2017-08-05 Preparation of management Selection plans and/or framework for managing Adverse Environmental and Social impacts, risks and benefits IN-ARIAS-1954-CS-QCBS / Project Baseline Survey and Monitoring & Component A: Enabling Quality And Evaluation of the proposed IBRD / 87800 Agri Enterprise Post Cost-Based Open - National 250,145.00 125,004.28 Signed 2016-09-30 2016-10-28 2016-11-27 2016-12-27 2017-01-26 2017-02-25 2017-03-19 2019-03-19 World Bank aided Assam Development Selection Agribusiness & Rural Transformation Project (APART) IN-ARIAS-3143-CS-CQS / Consultancy Service to conduct "Diagnostic Study Component A: Enabling Consultant on Finance Opportunities IBRD / 87800 Agri Enterprise Post Qualification Open - National 75,758.00 112,402.44 Signed 2016-11-09 2016-11-23 2016-12-22 2017-01-01 2017-01-03 2017-04-03 for Producers and Micro Development Selection Entrepreneurs in the Selected Agri Value Chains" IN-ARIAS-5195-CS-QCBS / Consultancy Service for formation of Farmer Component A: Enabling Quality And Producer Under IBRD / 87800 Agri Enterprise Post Cost-Based Open - National 1,014,706.00 0.00 2017-01-25 2017-01-27 2017-04-03 2017-05-03 2017-06-17 2017-07-04 2017-08-04 2020-08-03 Organizations(FPOs) for Implementation Development Selection Zone 1(Lakhimpur, Sonitpur, Darrang, Nalbari and Barpeta) IN-ARIAS-5197-CS-QCBS / Consultancy Service for formation of Farmer Component A: Enabling Quality And Producer Under IBRD / 87800 Agri Enterprise Post Cost-Based Open - National 1,014,706.00 632,889.98 2017-01-25 2017-01-27 2017-04-03 2017-05-03 2017-06-17 2017-07-04 2017-08-04 2020-08-03 Organizations(FPOs) for Implementation Development Selection Zone 2(Sivasagar, Jorhat, Golaghat, Karbi-Anglong and Cachar) IN-ARIAS-5198-CS-QCBS / Consultancy Service for formation of Farmer Component A: Enabling Quality And Producer Under IBRD / 87800 Agri Enterprise Post Cost-Based Open - National 1,014,706.00 0.00 2017-01-25 2017-01-27 2017-04-03 2017-05-03 2017-06-17 2017-07-04 2017-08-04 2020-08-03 Organizations(FPOs) for Implementation Development Selection Zone 3(Nagaon, Morigaon, Kamrup, Goalpara, Dhubri and Kokrajhar) IN-ARIAS-5204-CS-QCBS / Sector and Subsector scan Component A: Enabling Quality And study for Assam Burea of IBRD / 87800 Agri Enterprise Post Cost-Based Open - National 132,353.00 69,023.18 Signed 2017-02-25 2017-03-07 2017-05-12 2017-06-09 2017-07-24 2017-08-02 2017-09-02 2018-09-02 Investment Promotion Development Selection (ABIP) IN-ARIAS-5206-CS-QCBS / Consultancy Services for Component A: Enabling Quality And Technical Assistance to IBRD / 87800 Agri Enterprise Post Cost-Based Open - National 152,940.00 0.00 Under Review 2017-05-02 2017-05-04 2017-07-24 2017-09-07 2017-10-22 2017-12-01 2018-01-03 2019-01-03 Stewardship Council in Development Selection Fisheries, Piggery , Spices and Perishables IN-ARIAS-5230-CS-QCBS / Component A: Enabling Quality And Under Consultancy Service for IBRD / 87800 Agri Enterprise Post Cost-Based Open - National 735,294.00 0.00 2017-03-03 2017-03-08 2017-05-03 2017-06-17 2017-08-01 2017-08-23 2017-10-07 2024-10-05 Implementation Central IEC Campaign Development Selection IN-ARIAS-8684-CS-CDS / Component A: Enabling Consultant Pending Muga seed production and IBRD / 87800 Agri Enterprise Post Qualification Open - National 30,770.00 0.00 2018-06-11 2018-07-02 2018-08-15 2018-09-14 2018-10-19 2019-01-17 Implementation certification feasibility study Development Selection Component A: Enabling Consultant IN-ARIAS-10724-CS-CQS / IBRD / 87800 Agri Enterprise Post Qualification Open - National 38,465.00 35,399.50 Signed 2018-02-27 2018-03-04 2018-05-03 2018-05-13 2018-06-17 2018-09-15 FISHFED Revival Study Development Selection IN-ARIAS-5207-CS-QCBS / CDTA: Consultancy Component A: Enabling Quality And Services for hiring a IBRD / 87800 Agri Enterprise Prior Cost-Based Open - National 514,706.00 3,041,509.33 Signed 2017-12-30 2018-01-03 2018-02-22 2018-04-03 2018-05-03 2018-06-07 2018-07-17 2023-07-16 Technical Agency for Development Selection Cluster Development IN-ARIAS-5229-CS-CQS / Financial services diagnostic survey: Component A: Enabling Consultant Under Consulting Agency for IBRD / 87800 Agri Enterprise Post Qualification Open - National 29,411.00 0.00 2018-01-03 2018-01-09 2018-02-13 2018-02-15 2018-03-15 2018-09-11 Implementation conducting diagnostic Development Selection survey for status of financial literacy of financial services IN-ARIAS-35798-CS-CQS / Hiring of Architectural Component A: Enabling Consultant Firm for preparation design IBRD / 87800 Agri Enterprise Post Qualification Open - National 13,235.00 13,812.16 Completed 2017-12-15 2017-12-25 2018-01-28 2018-02-17 2018-03-24 2018-06-22 & plan etc for renovation Development Selection of existing PCU building Page 10 IN-ARIAS-35802-CS-QBS / Fund Feasibility Study: Consultancy Services for Conducting Feasibility Component A: Enabling Quality Based Assessment to set up an IBRD / 87800 Agri Enterprise Post Open - National 29,412.00 154,334.26 Signed 2017-12-29 2018-01-03 2018-01-27 2018-02-24 2018-03-26 2018-04-25 2018-05-30 2018-08-28 Selection Investment Fund for Small Development and Medium Enterprises in the Agribusiness Sector of Assam IN-ARIAS-5205-CS-QCBS / Investment Fund Feasibility Component A: Enabling Consultant Study and Preparation of / Agri Enterprise Post Qualification Open - National 29,412.00 0.00 Canceled 2017-01-31 2017-02-21 2017-05-07 2017-06-06 2017-07-11 2017-10-09 TOR for hiring the Fund Development Selection Manager IN-ARIAS-5335-CS-QCBS / Consultancy Services for hiring an Architectural Component A: Enabling Quality And Firm for Survey , / Agri Enterprise Post Cost-Based Open - National 729,412.00 0.00 Canceled 2017-02-14 2017-03-07 2017-05-21 2017-06-20 2017-08-04 2017-08-24 2017-09-21 2017-12-20 Feasibility Studies, Design Development Selection etc for Markets and Warehouses IN-ARIAS-42777-CS-CQS / Component A: Enabling Consultant ARIAS: Architectural Firm Under IBRD / 87800 Agri Enterprise Post Qualification Open - National 23,077.00 0.00 2018-02-28 2018-03-05 2018-03-15 2018-03-25 2018-04-23 2018-05-23 for Interior design of PCU Implementation Development Selection building (Pt-A) IN-ARIAS-8972-CS-QCBS / Market-Warehouse: Consultancy services for Survey, Feasibility Study, Design, Layout, DPR Component A: Enabling Quality And Preparation, for IBRD / 87800 Agri Enterprise Post Cost-Based Open - National 1,686,154.00 0.00 Canceled 2018-03-26 2018-03-31 2018-05-21 2018-06-20 2018-08-04 2018-09-02 2018-10-08 2022-10-07 modernization & Development Selection upgradation of Agricultural & allied Markets and Warehouses and Technical Quality Assurance during construction period IN-ARIAS-48691-CS-CQS / Eri&Muga: Market players, Component A: Enabling Consultant market share, market size IBRD / 87800 Agri Enterprise Post Qualification Open - National 38,462.00 42,231.25 Signed 2018-02-26 2018-02-26 2018-04-11 2018-05-06 2018-06-10 2018-09-08 and growth trends study of Development Selection eri and muga silk in Assam & India IN-ARIAS-48699-CS-CQS / GIFT: Consultancy services Component A: Enabling Consultant for rapid risk assessment IBRD / 87800 Agri Enterprise Post Qualification Open - National 40,000.00 0.00 Under Review 2018-02-26 2018-02-26 2018-05-01 2018-05-21 2018-06-19 2018-09-02 of the potential Development Selection invasiveness of Genetiaclly Improved Farmed Tilapia (GIFT) IN-ARIAS-48705-CS-QCBS / EDPF: Consultancy Component A: Enabling Quality And Service for setting up and Under IBRD / 87800 Agri Enterprise Prior Cost-Based Open - National 3,076,923.00 0.00 2018-03-15 2018-04-05 2018-05-19 2018-06-16 2018-07-31 2018-09-04 2018-10-09 2024-10-07 Managing Enterprise Implementation Development Selection Development Promotion Facility (EDPF) IN-ARIAS-5203-CS-QCBS / EDPF: Consultancy Service Component A: Enabling Quality And for setting up and / Agri Enterprise Post Cost-Based Open - National 773,530.00 0.00 Canceled 2017-01-06 2017-02-01 2017-04-14 2017-04-17 2017-06-06 2017-07-01 2017-08-01 2019-08-01 Managing Enterprise Development Selection Development Promotion Facility (EDPF) IN-ARIAS-8693-CS-CDS / Silkworm disease study: Component A: Enabling Consultant Study on threats to Assam Pending IBRD / 87800 Agri Enterprise Post Qualification Open - National 29,412.00 0.00 2018-10-22 2018-11-01 2018-12-16 2019-01-15 2019-02-09 2019-05-10 silkworm industry from Implementation Development Selection disease, and key solutions to manage them. IN-ARIAS-8689-CS-CDS / Seri: Silk food plantation entrepreneurship: Component A: Enabling Consultant Pending Feasibility study of an IBRD / 87800 Agri Enterprise Post Qualification Open - National 30,770.00 0.00 2018-07-16 2018-08-06 2018-09-19 2018-10-19 2018-11-23 2019-05-22 Implementation entrepreneurship model in Development Selection silk food plantation through vegetative nurseries. IN-ARIAS-8969-CS-CQS / Weavers' Needs Study: Component A: Enabling Consultant Pending Consultancy services for IBRD / 87800 Agri Enterprise Post Qualification Open - National 38,465.00 0.00 2018-12-17 2018-12-22 2019-02-10 2019-02-20 2019-03-16 2019-06-14 Implementation conducting Diagnostic Study Development Selection on Weavers' Needs IN-ARIAS-49490-CS-CQS / WAMUL : Techno- Component A: Enabling Consultant Pending commercial feasibility study IBRD / 87800 Agri Enterprise Post Qualification Open - National 15,385.00 0.00 2018-06-25 2018-07-16 2018-08-29 2018-09-28 2018-11-02 2019-05-01 Implementation and DPR preparation for Development Selection milk processing infrastructure IN-ARIAS-49496-CS-CQS / Component A: Enabling Consultant WAMUL : HACCP study IBRD / 87800 Agri Enterprise Post Qualification Open - National 12,308.00 0.00 Under Review 2018-05-14 2018-06-04 2018-07-18 2018-08-17 2018-09-21 2019-06-18 for complete value chain Development Selection IN-ARIAS-49498-CS-CQS / Component A: Enabling Consultant WAMUL : Benchmarking of IBRD / 87800 Agri Enterprise Post Qualification Open - National 15,385.00 0.00 Under Review 2018-05-28 2018-06-18 2018-08-01 2018-08-31 2018-10-05 2019-07-02 various operating Development Selection parameters Page 11 IN-ARIAS-4490-CS-LCS / Hiring a Human Resource Agency for facilitating recruitment of Senior Component A: Enabling Least Cost Specialists for the proposed / Agri Enterprise Post Open - National 76,471.00 0.00 Canceled 2016-12-13 2016-12-20 2017-01-24 2017-02-23 2017-03-16 2017-03-29 2017-04-16 2018-04-11 Selection World Bank aided Project Development Assam Agribusiness and Rural Transformation Project (APART) IN-ARIAS-5210-CS-QCBS / Consultancy Service for Component A: Enabling Quality And Technical Assistance on IBRD / 87800 Agri Enterprise Post Cost-Based Open - National 831,470.00 0.00 Canceled 2017-05-22 2017-05-26 2017-07-31 2017-09-14 2017-10-29 2017-11-28 2018-01-03 2025-01-01 setting up of Market Development Selection Intelligence Cell IN-ARIAS-5351-CS-LCS / ARIAS : Consultancy Component D: Project Least Cost Pending service to conduct Internal IBRD / 87800 Management, Monitoring Post Open - National 73,529.00 0.00 2019-08-01 2019-08-03 2019-10-08 2019-11-22 2020-01-06 2020-02-10 2020-03-16 2025-03-15 Selection Implementation Procurement audits(for 5 and Learning years) IN-ARIAS-5208-CS-QCBS / Hiring of a Training and Component A: Enabling Quality And Capacity Building Agency IBRD / 87800 Agri Enterprise Post Cost-Based Open - National 514,706.00 0.00 Canceled 2018-05-07 2018-05-13 2018-07-27 2018-08-24 2018-09-13 2018-09-27 2018-10-28 2022-10-27 for preparation of modules Development Selection and imparting training to the project stakeholders IN-ARIAS-5232-CS-QCBS / PCU : Hiring of Software Component D: Project Quality And Pending Development agency for IBRD / 87800 Management, Monitoring Post Cost-Based Open - National 446,154.00 0.00 2019-06-03 2019-06-07 2019-08-16 2019-09-15 2019-10-15 2019-12-04 2020-01-04 2020-09-30 Implementation Project MIS and and Learning Selection Management support IN-ARIAS-5339-CS-QCBS / Hiring of software development agency for developing mobile based Component D: Project Quality And Pending application for community IBRD / 87800 Management, Monitoring Post Cost-Based Open - National 179,412.00 0.00 2018-12-12 2018-12-16 2019-03-01 2019-03-29 2019-04-28 2019-06-18 2019-07-23 2024-11-10 Implementation led procurement for and Learning Selection facilitation, monitoring support for 7 years and database generation. IN-ARIAS-76149-CS-CQS / Component D: Project Consultant Labour Influx : Study on Under IBRD / 87800 Management, Monitoring Post Qualification Open - National 35,400.00 0.00 2019-01-07 2019-01-28 2019-03-13 2019-04-12 2019-05-17 2019-09-14 Labour Influx under the Implementation and Learning Selection Civil Works of APART IN-ARIAS-5345-CS-QBS- REBID / TA for ABIP: Component A: Enabling Providing Technical Quality Based Under IBRD / 87800 Agri Enterprise Post Open - National 1,470,588.00 0.00 2018-11-01 2018-11-22 2019-01-05 2019-02-04 2019-03-06 2019-03-26 2019-04-30 2023-04-29 Assistance to the Assam Selection Implementation Development Bureau of Investment Promotion (ABIP) IN-ARIAS-5345-CS-QCBS / TA for ABIP: Consultancy Component A: Enabling Quality And Agency for Providing IBRD / 87800 Agri Enterprise Post Cost-Based Open - National 1,470,588.00 0.00 Canceled 2018-01-03 2018-01-07 2018-02-21 2018-04-07 2018-05-07 2018-06-21 2018-07-26 2022-07-25 Technical Assistance to Development Selection Assam Bureau of Investment Promotion (ABIP) IN-ARIAS-5350-CS-QCBS / PCU : Hiring a Fund Component A: Enabling Quality And Open - Under Manager for setting up and IBRD / 87800 Agri Enterprise Prior Cost-Based 4,633,571.00 0.00 2019-03-07 2019-03-07 2019-04-20 2019-05-18 2019-06-17 2019-07-22 2019-08-26 2025-08-24 International Implementation managing an Agribusiness Development Selection Investment Fund IN-ARIAS-104630-CS-QCBS / Financial Education & Component C: Fostering Quality And Counselling : Consultancy Open - Pending IBRD / 87800 Market-led Production and Prior Cost-Based 2,007,143.00 0.00 2019-05-21 2019-06-11 2019-07-25 2019-08-22 2019-09-21 2019-10-26 2019-11-30 2024-08-09 services to develop financial International Implementation Resilience Enhancement Selection education and counselling program for farmers IN-ARIAS-104684-CS-CQS / Legal Counsel : hiring the Consultancy Services of Component A: Enabling Consultant Under a Corporate Law Firm as IBRD / 87800 Agri Enterprise Post Qualification Open - National 70,000.00 0.00 2019-03-07 2019-03-28 2019-05-11 2019-06-10 2019-07-15 2021-03-06 Implementation Legal Counsel for An Development Selection Agribusiness Investment Fund IN-ARIAS-93109-CS-CQS / Baseline Environmental Component D: Project Consultant Monitoring : Consultancy IBRD / 87800 Management, Monitoring Post Qualification Open - National 36,923.00 35,798.63 Signed 2019-03-20 2019-05-24 2019-06-01 2019-07-01 2019-08-05 2020-02-01 Services for conducting and Learning Selection Baseline Environmental Monitoring for APART IN-ARIAS-105830-CS-CQS / PCU-CA Firm: Conducting Audit of the Component D: Project Consultant Accounts of the ARIAS Under IBRD / 87800 Management, Monitoring Post Qualification Open - National 10,000.00 0.00 2019-03-15 2019-05-24 2019-06-14 2019-06-29 2019-06-29 2019-08-28 Society (both for APART & Implementation and Learning Selection ACCSDP) and Sample Verification of the Procurements & Physical Assets Created Page 12 IN-ARIAS-105284-CS-QCBS / PCU MW-1 : Consulting Service for "Survey, Feasibility Study, Design and Layout, DPR Quality And Component B: Facilitating Pending Preparation for IBRD / 87800 Post Cost-Based Open - National 221,429.00 0.00 2019-05-27 2019-05-28 2019-06-21 2019-07-19 2019-08-18 2019-09-22 2019-10-27 2020-10-26 Agro Cluster Development Implementation Modernization and Selection Upgradation of Rural Agricultural Markets and Warehouses (For Package No. MW-1)" IN-ARIAS-105288-CS-QCBS / PCU MW-2 : Consulting Service for "Survey, Feasibility Study, Design and Layout, DPR Quality And Component B: Facilitating Pending Preparation for IBRD / 87800 Post Cost-Based Open - National 221,429.00 0.00 2019-05-27 2019-05-28 2019-06-21 2019-07-19 2019-08-18 2019-09-22 2019-10-27 2020-10-26 Agro Cluster Development Implementation Modernization and Selection Upgradation of Rural Agricultural Markets and Warehouses (For Package No. MW-2)" IN-ARIAS-105290-CS-QCBS / PCU MW-3 : Consulting Service for "Survey, Feasibility Study, Design and Layout, DPR Quality And Component B: Facilitating Pending Preparation for IBRD / 87800 Post Cost-Based Open - National 221,429.00 0.00 2019-05-27 2019-05-28 2019-06-21 2019-07-19 2019-08-18 2019-09-22 2019-10-27 2020-10-26 Agro Cluster Development Implementation Modernization and Selection Upgradation of Rural Agricultural Markets and Warehouses (For Package No. MW-3)" IN-ARIAS-105299-CS-QCBS / PCU MW-4 : Consulting Service for "Survey, Feasibility Study, Design and Layout, DPR Quality And Component B: Facilitating Pending Preparation for IBRD / 87800 Post Cost-Based Open - National 221,429.00 0.00 2019-05-27 2019-05-28 2019-06-21 2019-07-19 2019-08-18 2019-09-22 2019-10-27 2020-10-26 Agro Cluster Development Implementation Modernization and Selection Upgradation of Rural Agricultural Markets and Warehouses (For Package No. MW-4)" IN-ARIAS-105300-CS-QCBS / PCU MW-5 : Consulting Service for "Survey, Feasibility Study, Design and Layout, DPR Quality And Component B: Facilitating Pending Preparation for IBRD / 87800 Post Cost-Based Open - National 221,429.00 0.00 2019-03-18 2019-05-27 2019-06-20 2019-07-18 2019-08-17 2019-09-21 2019-10-26 2020-10-25 Agro Cluster Development Implementation Modernization and Selection Upgradation of Rural Agricultural Markets and Warehouses (For Package No. MW-5)" IN-ARIAS-157949-CS-QCBS / Direct RFP for ACFIFA : Hiring of the Implementing agency for Assam Challenge Fund for Component C: Fostering Quality And Pending Innovative Finance in IBRD / 87800 Market-led Production and Post Cost-Based Open - National 778,571.00 0.00 2020-02-16 2020-03-08 2020-04-21 2020-05-19 2020-06-18 2020-07-23 2020-08-27 2024-09-30 Implementation Agriculture (ACFIFA) for Resilience Enhancement Selection supporting innovative approaches to deliver financial services at scale for value chains under APART INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IN-ARIAS-2159-CS-CDS / Consultancy assignment for conducting for 'as is' assessment of the District / Post Direct Selection Direct 15,606.00 16,008.08 Completed 2016-10-04 2016-10-07 2016-10-07 2016-11-06 Industries & Commerce Centers (DICC) in selected districts of Assam IN-ARIAS-2829-CS-CDS / Consultancy Service Data / Post Direct Selection Direct 45,742.00 47,137.95 Signed 2016-11-03 2016-11-05 2016-11-12 2017-01-11 validation for sectoral interventions under APART IN-ARIAS-2163-CS-CDS / Study on 'Preparation of draft District Agro Industrial Cluster Development Plan' Component A: Enabling Under (DAICDP) in the districts IBRD / 87800 Agri Enterprise Prior Direct Selection Direct 34,858.00 0.00 2016-10-04 2016-10-07 2016-10-20 2016-12-19 Implementation of Nagaon & Darrang for Development the proposed World Bank aided Assam Agri-Business and Rural Transformation Project (APART) IN-ARIAS-5328-CS-CDS / ILRI: Technical Assistance Component A: Enabling for the Livestock (Dairy & IBRD / 87800 Agri Enterprise Prior Direct Selection Direct 1,427,858.00 1,429,576.56 Signed 2018-01-17 2018-02-01 2018-03-15 2023-03-14 Piggery) Sub-Component of Development the World Bank Financed APART Page 13 IN-ARIAS-5329-CS-CDS / Component A: Enabling WVC: Technical Advisory IBRD / 87800 Agri Enterprise Prior Direct Selection Direct 1,400,197.00 1,400,197.00 Signed 2018-01-15 2018-02-14 2018-04-01 2023-03-31 Assistance to APART for Development the Vegetable Value Chains IN-ARIAS-5325-CS-QCBS / WF: Technical Assistance Component A: Enabling for the Fisheries Sub- IBRD / 87800 Agri Enterprise Prior Direct Selection Direct 1,062,699.00 1,062,699.00 Signed 2017-12-26 2018-01-03 2018-01-23 2023-01-22 Component of the World Development Bank Financed APART IN-ARIAS-5327-CS-CDS / IRRI: Technical Assistance To Increasing Productivity Component A: Enabling And Profitability of Small IBRD / 87800 Agri Enterprise Prior Direct Selection Direct 8,000,000.00 4,577,412.00 Signed 2018-01-10 2018-01-31 2018-04-02 2025-03-31 And Marginal Farmers In Development Rice-Based Cropping Systems IN-ARIAS-1740-CS-CDS / Technical collaborative support by WorldFish during the design phase of APART with thrust on Component A: Enabling market-led climate smart IBRD / 87800 Agri Enterprise Post Direct Selection Direct 33,824.00 34,401.66 Completed 2017-12-22 2017-12-31 2018-01-08 2018-03-13 intensification of production Development systems, setting up of farmers' Common Service Centres (managed by FPOs) and implement value chain plans IN-ARIAS-40003-CS-CDS / CIP: Technical Assistance for improving farmers' Component A: Enabling livelihoods through IBRD / 87800 Agri Enterprise Prior Direct Selection Direct 3,348,378.00 3,348,378.00 Signed 2018-01-10 2018-01-20 2018-03-06 2023-03-05 sustainable intensification Development & diversification of agri food systems with Climate Smart Potato Technologies IN-ARIAS-5332-CS-CDS / Component A: Enabling NRC-P: Consultancy IBRD / 87800 Agri Enterprise Post Direct Selection Direct 242,308.00 0.00 Canceled 2018-01-17 2018-02-11 2018-04-23 2023-04-22 Services of National Development Research Centre on Pig IN-ARIAS-47147-CS-CDS / NRC-P: Consultancy Component A: Enabling Services to support the IBRD / 87800 Agri Enterprise Prior Direct Selection Direct 242,308.00 231,006.20 Signed 2018-02-28 2018-03-10 2018-04-04 2023-04-03 Pork Value Chain Development interventions by ICAR- National Research Centre on Pig (NRC-P) IN-ARIAS-5330-CS-CDS / Component A: Enabling WUR: Pilot Implementation IBRD / 87800 Agri Enterprise Prior Direct Selection Direct 1,825,820.00 0.00 Canceled 2018-01-31 2018-02-25 2018-04-16 2023-04-15 and Redesign of Agri-Food Development value Chains under APART IN-ARIAS-78907-CS-CDS / PCU : Engagement of Component D: Project Individual Pending Auditor for conducting IBRD / 87800 Management, Monitoring Post Consultant Direct 2,000.00 0.00 2019-02-18 2019-02-28 2019-03-21 2019-04-25 2019-06-24 Implementation audit of ARIAS for and Learning Selection Financial Year 2017-18 IN-ARIAS-88761-CS-INDV / Counsel : Individual Component D: Project Individual consultant to advice the IBRD / 87800 Management, Monitoring Prior Consultant Open 2,769,231.00 0.00 Canceled 2019-08-04 2019-09-22 2019-10-13 2019-11-17 2024-11-15 PCU on the establishment and Learning Selection of the Investment fund IN-ARIAS-112738-CS-INDV / PCU - Tech Expert : Component A: Enabling Individual Technical Expert to Pending IBRD / 87800 Agri Enterprise Post Consultant Direct 19,800.00 0.00 2019-08-01 2019-08-11 2019-09-01 2019-10-06 2019-11-05 Support the Procurement of Implementation Development Selection Agri Business Investment Fund Manager IN-ARIAS-118406-CS-INDV / SABA : Hiring of a short Component D: Project Individual Pending term Senior Agri Business IBRD / 87800 Management, Monitoring Post Consultant Direct 12,857.00 0.00 2019-07-22 2019-08-01 2019-08-22 2019-09-26 2020-03-24 Implementation Advisor (SABA) As and Learning Selection Consultant for APART Page 14