Public Disclosure Copy The World Bank Implementation Status & Results Report China: Tianjin Urban Transport Improvement Project (P148129) China: Tianjin Urban Transport Improvement Project (P148129) EAST ASIA AND PACIFIC | China | Transport & ICT Global Practice | IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 3 | ARCHIVED on 13-Dec-2016 | ISR26064 | Implementing Agencies: Tianjin PMO Key Dates Key Project Dates Bank Approval Date:21-Dec-2015 Effectiveness Date:26-May-2016 Planned Mid Term Review Date:30-Nov-2018 Actual Mid-Term Review Date:-- Original Closing Date:31-Mar-2021 Revised Closing Date:31-Mar-2021 Project Development Objectives Project Development Objective (from Project Appraisal Document) The PDO is to leverage the Tianjin metro system and to promote walking and biking in the urban core (in Heping and Nankai) in order to make transport greener and safer in Tianjin and draw lessons for other large cities. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Green Transport Improvement in Heping and Nankai Districts:(Cost $89.48 M) Metro Access Improvement:(Cost $89.05 M) Public Bike Sharing System (PBS) Pilot:(Cost $23.14 M) Bus Terminal Development:(Cost $15.99 M) Technical Assistance:(Cost $2.90 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Satisfactory Overall Implementation Progress (IP)  Satisfactory  Satisfactory 12/13/2016 Page 1 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Tianjin Urban Transport Improvement Project (P148129) Overall Risk Rating  Substantial  Substantial Implementation Status and Key Decisions The project has made substantial progress in developing high quality conceptual design for initial pilots under the project to improve the quality of the urban space for pedestrians and bicycles in the center of Tianjin. The two main technical assistance to develop a green transport strategy and improve parking management in the center of the city are also progressing in line with schedule. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  Low  Low  Low Macroeconomic  Moderate  Moderate  Moderate Sector Strategies and Policies  Moderate  Moderate  Moderate Technical Design of Project or Program  Substantial  Substantial  Substantial Institutional Capacity for Implementation and Sustainability  Substantial  Substantial  Substantial Fiduciary  Moderate  Moderate  Moderate Environment and Social  Moderate  Moderate  Moderate Stakeholders  Moderate  Moderate  Moderate Other  --  --  -- Overall  Substantial  Substantial  Substantial Results Project Development Objective Indicators 12/13/2016 Page 2 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Tianjin Urban Transport Improvement Project (P148129) PHINDPDOTBL  Increase in metro ridership with the project compared to without the project (trips) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0 -- 0 85,000 Date 01-Sep-2015 19-Jul-2016 25-Nov-2016 31-Mar-2021 PHINDPDOTBL  Increase in volume of non-motorized trips by project, including Public Bike Sharing trips and increase in walking and biking trips with the project in Heping and Nankai pilot areas (trips). (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0 -- 0 135000 Date 01-Sep-2015 19-Jul-2016 25-Nov-2016 31-Mar-2021 PHINDPDOTBL  GHG emission reduction (tons) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0 -- 0 6,500 Date 01-Sep-2015 19-Jul-2016 25-Nov-2016 31-Mar-2021 PHINDPDOTBL  Reduction in number of accidents in Heping and Nankai pilot area (accidents) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0 -- 0 100 Date 01-Sep-2015 19-Jul-2016 25-Nov-2016 31-Mar-2021 PHINDPDOTBL  System of detailed performance evaluation with citizen engagement (men and women) in place (number of sites) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value Pilot selected -- 0 20 12/13/2016 Page 3 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Tianjin Urban Transport Improvement Project (P148129) Date 01-Sep-2015 -- 25-Nov-2016 31-Mar-2021 Overall Comments Intermediate Results Indicators PHINDIRITBL  Changes to project activities as a result of consultation (Yes/No) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value Yes -- 0 Yes Date 01-Sep-2015 -- 25-Nov-2016 31-Mar-2021 PHINDIRITBL  NMT Space Ratio in Nankai and Heping Districts (Percentage) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 25 -- 25 46 Date 01-Sep-2015 19-Jul-2016 25-Nov-2016 31-Mar-2021 PHINDIRITBL  Roads rehabilitated, Non-rural (Kilometers, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 50.00 Date 01-Sep-2015 -- 25-Nov-2016 31-Mar-2021 12/13/2016 Page 4 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Tianjin Urban Transport Improvement Project (P148129) PHINDIRITBL  IRAP's road safety assessment scores above 3 for streets in Heping and Nankai that are upgraded under the project (Percentage) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 30 -- 30 90 Date 01-Sep-2015 19-Jul-2016 25-Nov-2016 31-Mar-2021 PHINDIRITBL  Metro station areas improved (number) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0 -- 0 111 Date 01-Sep-2015 19-Jul-2016 25-Nov-2016 31-Mar-2021 PHINDIRITBL  PBS stations in operation (Number) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0 -- 0 446 Date 01-Sep-2015 19-Jul-2016 25-Nov-2016 31-Mar-2021 PHINDIRITBL  Bus terminals completed (number) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0 -- 0 5 Date 01-Sep-2015 19-Jul-2016 25-Nov-2016 31-Mar-2021 12/13/2016 Page 5 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Tianjin Urban Transport Improvement Project (P148129) PHINDIRITBL  Technical Assistance Leading to Changes (number) (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0 -- 0 4 Date 01-Sep-2015 19-Jul-2016 25-Nov-2016 31-Mar-2021 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P148129 IBRD-85650 Effective USD 100.00 100.00 0.00 0.25 99.75 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P148129 IBRD-85650 Effective 21-Dec-2015 26-Feb-2016 26-May-2016 31-Mar-2021 31-Mar-2021 Cumulative Disbursements 12/13/2016 Page 6 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report China: Tianjin Urban Transport Improvement Project (P148129) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 12/13/2016 Page 7 of 7 Public Disclosure Copy