YESSO 18 Months Procurement I. General 2. Bank’s approval Date of the procurement Plan : Original: December 2013 3. Date of General Procurement Notice: 2013 4. Period covered by this procurement plan: The procurement period of project covered from year December 2013 to August 2015 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement 2. Procurement Method Prior Review Threshold Comments US$ 2. NCB (Goods) packages Above US$ 750,000 All 3. Non-Consultant Services (packages) Above US$ 750,000 All 5. Shopping (Goods) Below US$ 100,000 None 6. Shopping (Works) Below US$200,00 None 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: YESSO will take a CDD approach to governance, including an anti- corruption plan and objective mechanisms for selecting beneficiaries such as community- based targeting (CBT) and proxy means tests (PMT) backed up by community validation. Community committees to also be involved in public works supervision. 4. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual prepared by the YESSO Federal Coordinating Office in December 2013. 5. Any Other Special Procurement Arrangements: N/A 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce July 9, 2010 (yes/no) Summary of 8.34 5 No Post 1st the NCB contract (Goods) for Prior Review Grants for 20.00 N/A N/A N/A payment of stipends to participants of public workfare, skills for job training and internshio and cash transfer under CCT. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 N/A 2. Single Source (Firms) All N/A 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.: N/A July 9, 2010 PROCUREMENT Nigeria : Nigeria Youth Employment & Social Support Operation PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2018-05-14 2019-04-15 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P126964 GPN Date: Project Name: Nigeria Youth Employment & Social Support Operation Loan / Credit No: IDA / 52120 Executing Agency(ies): Gombe YESSO WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GMYESSO/GDS/COM/NS/02/1 Under Request for Single Stage - One 8 / Supply of Computers /IT IDA / 52120 Post Limited 0.00 Implementati 2018-02-19 2018-04-16 2027-05-29 Quotations Envelope Equipments on Under GMYESSO/GDS/OE/NS/03/18 Request for Single Stage - One IDA / 52120 Post Limited 0.00 Implementati 2018-02-24 2018-04-21 2018-05-21 / Supply of Office Equipment Quotations Envelope on GMYESSO/GDS/IT/NS/04/18 Under Request for Single Stage - One / Supply of Internet IDA / 52120 Post Limited 14,265.63 Implementati 2018-02-27 2018-04-24 2018-05-24 Quotations Envelope Facilities on NG-GOMBE YESSO-48096- Under GO-RFQ / Supply of Request for Single Stage - One IDA / 52120 Post Limited 0.00 Implementati 2018-03-03 2018-04-28 2018-05-28 Communication Quotations Envelope on Gadgets/Equipments Under GMYESSO/GDS/OF/NS/06/18 Request for Single Stage - One IDA / 52120 Post Limited 14,887.44 Implementati 2018-02-17 2018-04-14 2018-05-14 / Supply of Office Furniture Quotations Envelope on GMYESSO/GDS/ST/NS/07/18 Under / Printing of Domesticated Request for Single Stage - One IDA / 52120 Post Limited 0.00 Implementati 2018-02-17 2018-04-14 2018-05-14 Manuals and supply of Quotations Envelope on Stationary GMYESSO/GDS/GP/NS/01/18 Pending Request for Single Stage - One / Supply of 40 kva IDA / 52120 Post Limited 0.00 Implementati 2018-02-17 2018-04-14 2018-04-17 Quotations Envelope Generator Plant for PIUs on NG-GOMBE YESSO-103408- Pending Request for Single Stage - One GO-RFQ / IDA / 52120 Post Limited 0.00 Implementati 2019-04-08 2019-06-03 2019-07-15 Quotations Envelope Generator/Equipment on GMYESSO/GDS/RFQ/02/19 / Pending Request for Single Stage - One Supply of Computers /Office IDA / 52120 Post Limited 0.00 Implementati 2019-04-13 2019-06-08 2019-07-20 Quotations Envelope Equipments on Page 1 Pending GMYESSO/GDS/RFQ/03/19 / Request for Single Stage - One IDA / 52120 Post Limited 0.00 Implementati 2019-04-20 2019-06-15 2019-07-27 Supply of Safety Equipment Quotations Envelope on NG-GOMBE YESSO-103387- Pending Request for Single Stage - One GO-RFQ / Supply of IDA / 52120 Post Limited 0.00 Implementati 2019-04-20 2019-06-15 2019-07-27 Quotations Envelope Promotional Materials on NG-GOMBE YESSO-103442- Pending Request for Single Stage - One GO-RFQ / Printing of IDA / 52120 Post Limited 0.00 Implementati 2019-04-22 2019-06-17 2019-07-29 Quotations Envelope Instructional manuals on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Page 2