Procurement Plan for Punjab RWSS (P150520) I. General 1. Bank’s approval Date of the procurement Plan 2012 2. Date of General Procurement Notice: [October 01, 2014 ] 3. Period covered by this procurement plan: January 2017 onwards II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: 2. Procurement Method Prior Review Threshold US$ 1. ICB and LIB (Goods) Above US$ 500,000 2. NCB (Goods) Above US$ 100,000 3. ICB (Works) Above US$ 40 million 4. NCB (Works) Above US$ 10 million 5. (Non-Consultant Services) Below US$ 100,000 2. Prequalification for Bidders _Not applicable_ 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project P150520 5. Any Other Special Procurement Arrangements: In addition, the justification for all contracts to be issued on the basis of LIB, single-source or direct contracting (except for contracts less than US$50,000 in value) will be subject to prior review. Justification for all contracts to be issued on the basis of LIB, single-source or direct contracting (except for contracts less than US$50,000 in value) will be subject to prior review. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) Above US$ 50,000 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. PROCUREMENT India : IN Punjab Rural Water and Sanitation Sector Improvement Project PLAN General Information Country: India Bank’s Approval Date of the Original Procurement Plan: 2019-03-12 2019-11-22 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P150520 GPN Date: Project Name: IN Punjab Rural Water and Sanitation Sector Improvement Project Loan / Credit No: IBRD / 84870 Executing Agency(ies): Division No. 1, Ferozepur WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual DWSS-W-DIV43-6356-1 / WSS Village Fattu Wala, Block and District Pending Ferozepur: Tubewell, OHSR, Transformation - Improved Request for Single Stage - One IBRD / 84870 Post Open - National 71,100.00 0.00 Implementati 2019-08-23 2019-12-02 2020-09-27 Pump Chamber and other Livability of Villages Quotations Envelope on work contingent there to under component 1A(iii) of PRWSSIp. DWSS-W-DIV43-6357-1 / WSS Village Sidhu, Block Ghuli Khurd and Dsirtict Pending Ferozepur: Tubewell, OHSR, Transformation - Improved Request for Single Stage - One IBRD / 84870 Post Open - National 41,100.00 0.00 Implementati 2019-08-23 2019-12-02 2020-09-27 Pump Chamber and other Livability of Villages Quotations Envelope on work contingent there to.under component 1A(iii) of PRWSSIP. PRWSS-W-DIV43-6234-1 / WSS Village Gulam Hussain Wala, Block and District Pending Ferozepur: Tubewell, OHSR, Transformation - Improved Request for Single Stage - One IBRD / 84870 Post Open - National 78,000.00 0.00 Implementati 2019-08-23 2019-12-02 2020-09-27 Pump Chamber and other Livability of Villages Quotations Envelope on work contingent there to.under component 1A(iii) of PRWSSIP. DWSS-W-DIV43-6235-1 / WSS Village Qutbe Wala, block and District Ferozepur: Tubewell, OHSR, Pump Transformation - Improved Request for Single Stage - One IBRD / 84870 Post Open - National 43,500.00 37,990.87 Signed 2019-08-23 2019-12-02 2020-09-27 Chamber and other work Livability of Villages Quotations Envelope contingent there to. under component 1A(iii0 of PRWSSIP. DWSS-W-DIV43-6095-1 / WSs Village Daoulat Pura block and District Ferozepur: Tubewell, OHSR, Pump Transformation - Improved Request for Single Stage - One IBRD / 84870 Post Open - National 41,000.00 39,912.07 Signed 2019-08-23 2019-12-02 2020-09-27 Chamber and other work Livability of Villages Quotations Envelope contingent there to under component 1A(iii) of PRWSSIP. DWSS-W-DIV43-6656-1 / WSS Village Kmala Bodia , Block and District Ferozepur: Tubewell, OHSR, Transformation - Improved Request for Single Stage - One IBRD / 84870 Post Open - National 38,500.00 36,381.37 Signed 2019-08-23 2019-12-02 2020-09-27 Pump Chamber and other Livability of Villages Quotations Envelope work contingent there to under component 1A(iii) of PRWSSIP. Page 1 DWSS-W-DIV43-6657-1 / WSS Village Akku Wala, Block and District Pending Ferozepur: Tubewell, OHSR, Transformation - Improved Request for Single Stage - One IBRD / 84870 Post Open - National 42,000.00 0.00 Implementati 2019-08-23 2019-12-02 2020-09-27 Pump Chamber and other Livability of Villages Quotations Envelope on work contingent there to under component 1A(iii) of PRWSSIP DWSS-W-DIV43-6658-1 / WSS Village Alle Wala, Block and District Ferozepur,: Tubewell, OHSR, Transformation - Improved Request for Single Stage - One IBRD / 84870 Post Open - National 44,500.00 37,458.50 Signed 2019-08-23 2019-12-02 2020-09-27 Pump Chamber and other Livability of Villages Quotations Envelope work contingent there to under component 1A(iii) of PRWSSIP PRWSS-W-DIV43-6201-1 / WSS Village Wara Bhai Ke, Block Ghall Khurd, District Pending Ferozepur: Provision of Inclusive Household Water Request for Single Stage - One IBRD / 84870 Post Open - National 11,000.00 0.00 Implementati 2019-08-23 2019-12-02 2020-01-31 Pipeline, Distribution, Water and Sanitation Services Quotations Envelope on connection and works under component 2A(i) of PRWSSIP. DWSS-W-DIV43-6200-1 / WSS Village Langiana, Block Ferozpur, District Ferozepur: Provision of Pipeline, Inclusive Household Water Request for Single Stage - One IBRD / 84870 Post Open - National 5,300.00 4,096.10 Signed 2019-03-23 2019-05-18 2019-11-14 Distribution, Water and Sanitation Services Quotations Envelope connection and works under component 2A(i) of PRWSSIP. PRWSS-W-DIV43-6199-1 / WSS Village Mohkam Khan Wali, Block Ghall Khurd, District Ferozepur: Providing and installing Tubewell . Transformation - Improved Request for Single Stage - One IBRD / 84870 Post Open - National 44,500.00 34,411.10 Signed 2019-08-23 2019-12-02 2020-08-28 Construction of OHSR, Pump Livability of Villages Quotations Envelope chamber and other contingent to under component 1A(iii) of PRWSSIP. PRWSS-W-DIV43-6050-1 / WSS Village Gamme Wala, Block and District Pending Ferozepur: Provision of Inclusive Household Water Request for Single Stage - One IBRD / 84870 Post Open - National 8,000.00 0.00 Implementati 2019-08-23 2019-12-02 2020-01-31 Pipeline, Distribution, Water and Sanitation Services Quotations Envelope on connection and works under component 2A(i) of PRWSSIP. DWSS-W-DIV43-7053-1 / WSS Village Attari, Blockand District Ferozepur: Pending Providingh Improved Inclusive Household Water Request for Single Stage - One IBRD / 84870 Post Open - National 15,500.00 0.00 Implementati 2019-11-25 2020-03-30 2020-04-08 Distribution of Pipeline, and Sanitation Services Quotations Envelope on House Hold connection, repair of Pump Chamber etc. GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 3