The World Bank Implementation Status & Results Report HT Sustainable Rural and Small Towns Water and Sanitation Project (P148970) HT Sustainable Rural and Small Towns Water and Sanitation Project (P148970) LATIN AMERICA AND CARIBBEAN | Haiti | Water Global Practice | IBRD/IDA | Investment Project Financing | FY 2015 | Seq No: 8 | ARCHIVED on 26-Mar-2019 | ISR35974 | Implementing Agencies: DINEPA, Ministry of Economy and Finance, MEF, Ministry of Economy and Finance, MEF Key Dates Key Project Dates Bank Approval Date: 26-May-2015 Effectiveness Date: 16-Dec-2015 Planned Mid Term Review Date: 18-Mar-2019 Actual Mid-Term Review Date: -- Original Closing Date: 30-Sep-2021 Revised Closing Date: 30-Sep-2021 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The proposed objectives of the Project are to: (i) increase access to improved water supply and sanitation in targeted rural areas and small towns in zones affected by cholera; (ii) strengthen the Recipient’s water and sanitation service delivery mechanism at thedeconcentrated level; and (iii) improve the Recipient’s capacity to respond promptly and effectively to an Eligible Emergency. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Institutional Strengthening, Capacity Building and Project Management:(Cost $19.35 M) Water Supply and Sanitation:(Cost $45.65 M) Contingent Emergency Response:(Cost $5.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions To date, DINEPA has financed through the project the rehabilitation of the water supply systems of Anse-à-Pitres (Southeast Department), Point-a- Raquette and Boucan Lamare (La Gonave Island, West Department). Construction and rehabilitation of the water supply systems of Casse, Biassou, Boc-Banic and Los Cacaos (Center Department) have been completed. The three pumps of Gonaïves utility have been restored (Cholera hot spot). In the South region: The works for the rehabilitation and extension of the water supply systems of Port-Salut, Tiburon, Roche-à-Bateau; Port-à- Piment and Les Anglais are ongoing. The pumping tests in Bodarie – Grand Gosier have shown that there is enough water and the rehabilitation 3/26/2019 Page 1 of 11 The World Bank Implementation Status & Results Report HT Sustainable Rural and Small Towns Water and Sanitation Project (P148970) works on the water system will start soon. The first phase of emergency works on the Clizan water system in Jérémie has been carried out, and the second phase will be launched shortly. In the Centre and North region, the e: emergency rehabilitation works on the Thomonde water system is ongoing. Additional The following works in several municipalities will be launched during the next months : (I) Northwest: the Andro water system, in the municipality of Chansolme, 12 small hurricane affected SAEP and 8 water points converted to solar pumping in the communal sections of Port-de-Paix ; (ii) in Center : Lascahobas, Cerca La Source, 5 small SAEP near the border, 12 small water point out of the 35 planned and, (iii) in South: La Vallée Jacmel, Latiboliere, and 7 small rural water point out of the 45 planned. For the three regions: two companies in charge of the hydrological studies and supervision for 210 boreholes have been are selected, and (v) the tender for construction of the four contractors for the 210 boreholes in rural and small towns will be launched soon are ready to be launch. So far, approximately 42,970 people have gained access to improved water supply resources thanks to the project. A large portion of the rural population is also expected to benefit with the sanitation facilities in public schools and public spaces: the construction of 11 latrines blocks in public schools and binational markets in the border with the Dominican Republic and the South region has been completed. In coordination with the World Bank Education teams project a join program restoring sanitation and water facilities in 60 public schools have started by launching 12 schools in the South department. A protocol for the maintenance and the management of these latrines is to be signed with the directors of these schools. Contracts launched to put back into WSS service infrastructure damaged by Hurricane Matthew in the Southwestern region of the country and the installation of new water disinfection equipment in all 68 localities have been finalized. It is estimated that these emergency response activities benefited approximately 270,000 people. Three consulting companies have been contracted and started for; (i) studies of the water systems of Verrettes and Anse Rouge in the Centre; (ii) the systems of Jean Rabel, Lacoma, Saint Louis du Nord and; (iii) Saint Michel de l'Attalaye, Mole Saint Nicolas and Trou du Nord. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Substantial High High Macroeconomic Substantial Substantial Substantial Sector Strategies and Policies Substantial Substantial Substantial Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Sustainability Substantial Substantial Substantial Fiduciary Substantial Substantial Substantial Environment and Social Moderate Moderate Moderate Stakeholders Substantial Substantial Substantial Other Substantial Substantial Substantial Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes PDO Indicators by Objectives/Outcomes IN00668532 ►A national programming mechanism for deconcentrated WSS service delivery is operationalized, as evidenced by tools in place (Number, Custom) 3/26/2019 Page 2 of 11 The World Bank Implementation Status & Results Report HT Sustainable Rural and Small Towns Water and Sanitation Project (P148970) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 3.00 3.00 5.00 Date 30-Sep-2015 13-Sep-2018 07-Mar-2019 30-Sep-2021 This includes the development of: (i) a national WSS baseline (rural and urban); (ii) a roadmap for universal WSS coverage by 2030;(iii) a Medium Term Expenditure Framework (MTEF) for the sector, including the definition of a long-term sustainable financing plan for DINEPA and its concentrated Comments: structures; (iv) a 3-year rolling consolidated Program Budget; and (v) a sector coordinationand joint performance mechanism to operationalize the Program Budget review process. IN00668533 ►Required functions deconcentrated to targeted OREPA (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 5.00 6.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 This includes: (i) procurement is transferred to the OREPA level; (ii) financial management is transferred to the OREPA level; (iii) payroll for URDs is managed at the OREPA level; (iv) payroll for TEPACs is managed at the OREPA level; (v) at least 50 percent of project contracts are procured and managed at Comments: the OREPA level; and (vi) reporting on the region's CAEPA/OP management contracts is done quarterly, including on operator performance indicators defined in DINEPA's SIP monitoring system and in the Projects Operation Manual. IN00668534 ►Piped water systems managed sustainably by a professional operator (OP) under the Project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 8.00 25.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 Number of systems constructed or rehabilitated under the Project with delivery of services effectively delegated to an OP. This includes: (i) evidence of contract signed; (ii) evidence of an active dedicated bank account; (iii) 100% O&M cost recovery; (iv) continuity of water service > 6 hours/day for household connections; and (v) percentage of water samples, over each year of operation, meeting DINEPA's quality requirements in terms of chlorine residual (between 0.2 and 2.0 mg/L) > 80 percent. In the case of rural areas and small towns, the systems will be considered to be managed sustainably if these conditions are Comments: met. The Project will support and rely on the monitoring system for rural and small town water supply systems put in place by DINEPA (SIP) which collects information on water sales and data on water quality will be obtained from daily analyses performed by the TEPACs, which is centralized at the DMR through DINEPA's SISKLOR water quality monitoring system. Points (iii), (iv) and (v) will be evaluated at the start of each year starting at the second year of operation. Satisfaction surveys will also be completed at the beginning, mid-term and project closure to assess service quality. IN00668535 Piped water systems managed sustainably by a professional operator (OP) in zones affected by Hurricane Matthew (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 7.00 5.00 Date 14-Jun-2017 -- 07-Mar-2019 30-Sep-2021 IN00668536 ►Number of people in rural areas provided with access to Improved Water Sources under the project (Number, Custom) 3/26/2019 Page 3 of 11 The World Bank Implementation Status & Results Report HT Sustainable Rural and Small Towns Water and Sanitation Project (P148970) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 28,620.00 235,000.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 This indicator measures the actual number of people in rural areas who benefited from improved water supply services that have been constructed under the project. Guidance on "improved water sources": "Improved water sources" include piped household connection (house or yard connections), public standpipe, boreholes, protected dug well, protected spring and rainwater collection. Hence, "Improved Water Sources" do not include, inter alia, water provided through tanker truck, or vendor, unprotected well, unprotected spring, surface water (river, pond, dam, lake, stream, irrigation channel), or bottled water. The definition of what is considered an "improved water source" follows the UNICEF-WHO Joint Monitoring Program definition. Note that "Improved Water Sources" does not refer to the question of new versus Comments: rehabilitated water sources, but is the standard definition used to track progress on the Millennium Development Goals. Guidance on people with access: The data on the number of people provided with access can be estimated by TTLs by multiplying i) the actual number of piped connections with an estimate of the number of people per household connection; and/or ii) the actual number of community water points with an estimate of the number of people per community water point. The assumptions made regarding number of people per connection made should be carefully documented in the comments' section of the indicator when data is entered in the ISR. Guidance on rural classification: The classification IN00668537 should follow the official definition used in the country. Number of people in rural areas provided with access to Improved Water Sources in zones affected by Hurricane Matthew (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 85,000.00 Date 14-Jun-2017 -- 07-Mar-2019 30-Sep-2021 IN00668538 People in rural areas provided with access to Improved Water Sources - female (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 8,427.00 117,500.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 IN00668539 ►People provided with access to "improved sanitation facilities” under the proj. (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 12,849.00 30,000.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 This indicator measures the cumulative number of people who benefited from improved sanitation facilities that have been constructed under the project. This includes people newly provided with access to Comments: “improved sanitation facilities” and does not include people benefiting from rehabilitation works. IN00668540 The baseline value is expected to be zero. People provided with access to “improved sanitation facilities”- rural (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 14,367.00 30,000.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 IN00668541 People in rural areas provided with access to "improved sanitation facilities" - female (Number, Custom Breakdown) 3/26/2019 Page 4 of 11 The World Bank Implementation Status & Results Report HT Sustainable Rural and Small Towns Water and Sanitation Project (P148970) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 6,532.00 15,000.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 IN00668542 ►Priority cholera communes targeted under the Project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 6.00 6.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 Priority communes include the most vulnerable commune in each one of the ten departments (selected by Government in the context of the Total Sanitation Campaign) and six communes that have proven the most vulnerable during the cholera epidemic on the basis of high incidence rates (including the origin of Comments: cases whenever available) in the dry seasons of 2012 and 2013, as well as alerts from January 2013 to May 2014. These communes are illustrated in Annex 7. Additionally, communes represented in the GoH?s 10-year Cholera Elimination Plan, as well as communes identified following new alerts or outbreaks would also be considered as priority. IN00668543 ►Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 312,989.00 685,000.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 Direct beneficiaries are people or groups who directly derive benefits from an intervention (i.e., children who benefit from an immunization program; families that have a new piped water connection). Please note Comments: that this indicator requires supplemental information. Supplemental Value: Female beneficiaries (percentage). Based on the assessment and definition of direct project beneficiaries, specify what IN00668544 proportion of the direct project beneficiaries are female. This indicator is calculated as a percentage. Project beneficiaries of small repairs and rehabilitation works following the passage of Hurricane Matthew (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 270,019.00 385,000.00 Date 14-Jun-2017 -- 07-Mar-2019 30-Sep-2021 IN00668545 Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 50.00 50.00 50.00 IN00668546 Project beneficiaries in localities on the border with the DR including bi-national markets (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 11,766.00 75,000.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 3/26/2019 Page 5 of 11 The World Bank Implementation Status & Results Report HT Sustainable Rural and Small Towns Water and Sanitation Project (P148970) Intermediate Results Indicators by Components Institutional Strengthening, Capacity Building and Project Management IN00668547 ►Departments covered by WSS baseline information (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 10.00 10.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 This includes inventory of water sources, systems and distribution points (kiosks, standposts, boreholes, household connections, etc.), as well as surveys for sub-national levels of open defecation, improved vs Comments: unimproved latrines. This baseline information will be collected by DINEPA's local actors, under the supervision of a contracted entity and will be disaggregated by sex. IN00668550 ►DINEPA conducts an annual joint Government/ partners sector review (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 A sector coordination and joint performance review mechanism is put in place with DINEPA, relevant Comments: ministries and financial and technical partners to operationalize the Program Budget review process. IN00668553 ►At least one OREPA uses the baseline developed under the Project to prioritize interventions and inform DINEPA?s Program Budget (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- Yes Yes Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 This indicator will measure the use of the baseline generated under Component 1 for planning, prioritizing Comments: and budgeting purposes at the deconcentrated level. IN00668555 ►At least one OREPA has installed an accounting system which facilitates the consolidation of financial information at the central level (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 This includes: (i) the implementation and operationalization of the accounting system; and (ii) the Comments: functional accounting system facilitates the consolidation of financial information at the central level IN00668557 ►CAEPAs that include at least 20 percent female representation in project area (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 33.00 70.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 3/26/2019 Page 6 of 11 The World Bank Implementation Status & Results Report HT Sustainable Rural and Small Towns Water and Sanitation Project (P148970) This indicator will measure the results of the promotion of women?s participation in WSS-related decision- making at the local level. Under the standard articles creating the committees, CAEPAs are required to include at least two women representatives (out of at least four members). The members are elected by the community to assume one of the following functions: President, Treasurer, Secretary or Adviser. This Comments: indicator is consistent with one of the seven citizen engagement approaches used in Bank operations (see OPSPQ 2014 Results Framework and M&E Guidance Note), namely? Empowering citizens/communities with resources and decision-making powers?. IN00668559 ►DINEPA supports the design of a Regional joint monitoring mechanism for pandemics is established, as evidenced by triannual meetings with the MSPP and biannual meetings with DR representatives (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 Support to design the mechanism includes: (i) identifying key actors that can lead the dialogue from each country; (ii) assessing in each country the feasibility (and associated risks) of implementing joint monitoring; (iii) identify options for establishing the joint system, including requirements to create the Comments: enabling environment for joint monitoring; (iv) agreeing with both countries on what option to pursue, including their respective roles and areas of accountability in the process; (iv) helping to address any capacity constraints that may hinder process of joint monitoring; and (v) supporting the establishment of the joint monitoring mechanism. IN00668562 ►A fecal sludge management service chain for rural areas and small towns is defined (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 The fecal sludge service chain to be defined could include containment, emptying, transport, treatment and reuse/disposal, as well as an assessment of the involvement of the private sector in the service chain Comments: and helping define models for its implementation. While containment will largely be covered by household onsite facilities and project-financed institutional sanitation facilities, the last four steps of the service chain could be defined with the support of the Project and WSP, where appropriate. IN00668564 ►Communities where DINEPA and MSPP local structures have jointly been trained or collaborated in water supply, hygiene promotion and sanitation themes and activities (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 6.00 20.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 This indicator will allow tracking the integration of health and WSS actors at the local level. Community is Comments: defined here as the rural area or small town benefiting from water supply. IN00668566 ►Grievances registered related to delivery of project benefits addressed (%) (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 75.00 80.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 This indicator measures the transparency and accountability mechanisms established by the project so the target beneficiaries have trust in the process and are willing to participate, and feel that their Comments: grievances are attended to promptly. It is understood that local sensitivities and tensions will not allow grievance or redress mechanisms to be established in all projects. 3/26/2019 Page 7 of 11 The World Bank Implementation Status & Results Report HT Sustainable Rural and Small Towns Water and Sanitation Project (P148970) IN00668568 Grievances related to delivery of project benefits that are addressed-(number) (Number, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 15.00 100.00 Water Supply and Sanitation IN00668549 ►New piped household water connections that are resulting from the project intervention (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 199.00 7,750.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 Number of new piped household water connections which result from the project intervention. A piped household water connection is defined as a connection that provides piped water to the consumer through Comments: either a house or yard connection. Hence, they do not include, inter alia, standpipes, protected well, borehole, protected spring, piped water provided through tanker trucks, or vendors, unprotected wells, IN00668551 unprotected spring, rivers, ponds and other surface water bodies, or bottled water. New piped household water connections that are resulting from project interventions in zones affected by Hurricane Matthew (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1,000.00 Date 14-Jun-2017 -- 07-Mar-2019 30-Sep-2021 IN00668554 ►Improved community water points constructed or rehabilitated under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 59.00 135.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 Number of improved community water points constructed or rehabilitated under the project in rural and urban areas. A community water point is defined as a public outlet for the provision of water supply to a Comments: number of households. Improved community water points refer to standpipes, protected dug well, borehole, or protected spring. Hence, improved community water points do not include, inter alia, unprotected wells or unprotected springs. IN00668556 ►People trained to improve hygiene behavior/sanitation practices under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 7,615.00 75,000.00 Date 30-Sep-2015 -- 01-Feb-2019 30-Sep-2021 This indicator measures the cumulative number of people who have participated in a training activity to conduct improved hygiene behavior or sanitation practices. This does not include people who have been Comments: educated and/or informed through public information or mass publication campaigns. The baseline value for this indicator is expected to be zero. IN00668558 People trained to improve hygiene behavior/sanitation practices - female (Number, Custom Breakdown) 3/26/2019 Page 8 of 11 The World Bank Implementation Status & Results Report HT Sustainable Rural and Small Towns Water and Sanitation Project (P148970) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 3,530.00 37,500.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 IN00668560 ►Students and teachers benefitting from improved sanitation facilities in public schools under the Project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 2,550.00 20,000.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 For this indicator, the beneficiaries will be gender-disaggregated and data will be collected with the Comments: support of the MENFP's departmental directorates. IN00668561 Students and teachers benefitting from improved sanitation facilities in public schools - female (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 1,271.00 10,000.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 IN00668563 ►Latrine blocks for public institutions or spaces constructed or rehabilitated with management and maintenance arrangements in place under the Project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 11.00 80.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 Public institutions include: schools, health facilities, markets, beaches and other areas where significant concentration of peopleoccurs on a regular basis in a given locality. Management and maintenance arrangements include, where appropriate: definition of responsibilities for cleaning and repairing in case of Comments: malfunction, for both drinking water equipment and sanitation facilities, availability of cleaning tools and supplies (paper, soap, chlorine, broom, disinfectant, gloves, pump and cleaning brushes, etc.), and anadequate budget for these arrangements. IN00668565 ►Female and youth beneficiaries rating safety in access to water and sanitation services as satisfactory or better (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 60.00 70.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 This indicator enables DINEPA to monitor the quality of WSS services from the point of view of safety and Comments: vulnerability of women and youth. IN00668567 ►Households with latrine built during project implementation and of which use is verified (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 1,900.00 3/26/2019 Page 9 of 11 The World Bank Implementation Status & Results Report HT Sustainable Rural and Small Towns Water and Sanitation Project (P148970) Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 This indicator would allow DINEPA to monitor progress on the population moving from open defecation to Comments: unimproved or improved sanitation facilities. Surveys would be required to verify use. IN00668569 ►People benefitting from consolidation work (small repairs and expansions) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 3,000.00 400,000.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 Number of people from communities which benefitted from interventions from DINEPA?s EPAR Program Comments: in the South Region and which require small repairs and expansions to increase sustainability. IN00668570 People benefitting from consolidation work - female (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 200,000.00 Date 30-Sep-2015 -- 07-Mar-2019 30-Sep-2021 Contingent Emergency Response IN00668548 ►Latrine blocks for public institutions or spaces constructed or rehabilitated with management and maintenance arrangements in place in zones affected by Hurricane Matthew (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 3.00 4.00 20.00 Date 14-Jun-2017 13-Sep-2018 07-Mar-2019 30-Sep-2021 IN00668552 ►People benefitting from consolidation work (small repairs and expansions) in zones affected by Hurricane Matthew (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 270,000.00 270,019.00 300,000.00 Date 14-Jun-2017 13-Sep-2018 07-Mar-2019 30-Sep-2021 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P148970 IDA-D0680 Effective USD 50.00 50.00 0.00 20.25 30.57 40% P148970 IDA-D2010 Effective USD 20.00 20.00 0.00 4.00 16.40 20% 3/26/2019 Page 10 of 11 The World Bank Implementation Status & Results Report HT Sustainable Rural and Small Towns Water and Sanitation Project (P148970) Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P148970 IDA-D0680 Effective 26-May-2015 21-Jul-2015 16-Dec-2015 30-Sep-2021 30-Sep-2021 P148970 IDA-D2010 Effective 14-Jun-2017 29-Jun-2017 04-Dec-2017 30-Sep-2021 30-Sep-2021 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) P163194-Sustainable Rural and Small Town Water Supply and Sanitation Additional Financing 3/26/2019 Page 11 of 11