Annexure.II : PROCUREMENT SCHEDULE FOR WORKS Country: INDIA Borrower: GOVERNMENT OF ANDHRA PRADESH Project: A.P.M.D.P. Status as on 23rd Feb. 2013 Initiate preparation of Specification and Bid Estimated Cost (Million Estimated Cost (Rs. Crores) local currency) Approval of IFB and Bid documents by the Publication of IFB in Newspapers / UNDB Preparation of IFB and submission to the Preparation of DPR/ Submission of DPR Submission of BER to Bank for approval Beginning of Sale of Bid document Submission of the Bid Document Issue of contract award notice Technical sanction from PHED USD) Method of Procurement Procurement Authority Signing of the contract Agreemet No.& Dt. Quantity (Number) Proir/Post Review Approval of BER Opening of Bids World Bank Description Document WBR No. Stage Bank S No 1 US $ = Rs. 55 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Comprehensive Water Supply Improvement of services in Markapur MSU/U 58/2012-13 Dt: 1 NCB 1 37.70 6.85 Prior Comlpeted 19/4/2012 26/7/2012 14/2/2012 19/4/2012 23/6/2012 15/7/2012 30/7/2012 30/7/2012 17/9/2012 18/10/2012 1/11/2012 1/12/2012 7/1/2013 LB 7-1-2013 Comprehensive Water Supply Improvement of services in Vizianagaram(Package-I) MSU/U Actual 11/1/2013 2 NCB 1 8.40 1.53 Post 11/1/2013 15/2/2013 Post Review - 31/3/2013 28/4/2013 LB Estimated 3rd call Comprehensive Water Supply Improvement of services in Vizianagaram(Package-II a) MSU/U Actual 14/11/2012 3 NCB 1 41.00 7.45 Prior 12/1/2012 30/4/2012 9/1/2012 20/4/2012 23/4/2012 10/5/2012 14/11/2012 17/12/2012 19/1/2013 3/2/2013 15/2/2013 31/3/2013 LB Estimated 2nd call Comprehensive Water Supply Improvement of services in Kakinada(Package-I) MSU/U Actual 4 NCB 1 4.01 Prior 31/3/2012 30/4/2012 31/3/2012 10/9/2012 10/9/2012 24/9/2012 31/10/2012 31/10/2012 14/12/2012 19/1/2013 7/2/2013 15/2/2013 31/3/2013 LB Estimated 22.03 Comprehensive Water Supply Improvement of services in Kakinada(Package-IV) MSU/U Actual 5 NCB 1 5.42 Prior 31/3/2012 30/4/2012 31/3/2012 10/9/2012 10/9/2012 24/9/2012 31/10/2012 31/10/2012 14/12/2012 24/1/2013 7/2/2013 28/2/2013 31/3/2013 LB Estimated 29.83 Comprehensive Water Supply Improvement of services in Kakinada(Package-II) MSU/U Actual 6 ICB 1 112.68 20.49 Prior 31/3/2012 30/4/2012 31/3/2012 17/9/2012 17/9/2012 12/10/2012 30/1/2013 31/1/2013 15/3/2013 31/3/2013 15/4/2013 30/4/2013 31/5/2013 LB Estimated Comprehensive Water Supply Improvement of services in Badvel MSU/U Actual 7 ICB 1 94.60 17.20 Prior 31/3/2012 30/4/2012 31/3/2012 10/9/2012 10/9/2012 24/9/2012 5/11/2012 5/11/2012 7/1/2013 6/2/2013 28/2/2013 31/3/2013 30/4/2013 LB Estimated Comprehensive Water Supply Improvement of services in Ananatapur MSU/U Actual 8 ICB 1 117.72 21.40 Prior 12/1/2012 30/4/2012 9/1/2012 17/9/2012 17/9/2012 15/10/2012 30/11/2012 30/11/2012 1/2/2013 28/2/2013 15/3/2013 31/3/2013 30/4/2013 LB Estimated Comprehensive Water Supply Improvement of services in Guntur(Package-I) MSU/U Actual 9 ICB 1 291.60 53.02 Prior 15/4/2012 30/5/2012 31/3/2012 12/9/2012 12/9/2012 3/10/2012 13/12/2012 13/12/2012 5/3/2013 15/3/2013 31/3/2013 15/4/2013 15/5/2013 LB Estimated Comprehensive Water Supply Improvement of services in Guntur(Package-II) MSU/U Actual 10 ICB LB 1 100.95 18.35 Prior Estimated 15/4/2012 30/5/2012 31/3/2012 12/9/2012 12/9/2012 3/10/2012 12/11/2012 12/11/2012 5/1/2013 30/1/2013 28/2/2013 31/3/2013 30/4/2013 Comprehensive Water Supply Improvement of services in Armoor MSU/U Actual 11 ICB 1 93.11 16.93 Prior 1/1/2013 21/1/2013 15/12/2012 15/2/2013 15/2/2013 28/2/2013 11/3/2013 11/3/2013 30/4/2013 15/5/2013 31/5/2013 30/6/2013 31/7/2013 LB Estimated Comprehensive water supply service improvements In Malkajgiri(part of GHMC) MSU/U 12 NCB package-I 1 50.00 9.09 Prior Estimated 15/12/2012 28/2/2013 1/2/2013 11/3/2013 11/3/2013 31/3/2013 15/4/2013 15/4/2013 20/5/2013 31/5/2013 15/6/2013 10/7/2013 14/8/2013 LB Comprehensive water supply service improvements In Malkajgiri(part of GHMC) MSU/U 13 ICB Package-II 1 240.20 43.67 Prior Estimated 15/12/2012 28/2/2013 1/2/2013 11/3/2013 11/3/2013 31/3/2013 15/4/2013 15/4/2013 15/6/2013 30/6/2013 15/7/2013 14/8/2013 15/9/2013 LB Comprehensive Water Supply Improvement of services in Manuguru MSU/U 14 NCB 1 25.00 4.55 Post Estimated 15/12/2012 15/3/2013 1/2/2013 15/3/2013 15/3/2013 31/3/2013 15/4/2013 15/4/2013 20/5/2013 15/6/2013 15/7/2013 LB