PROCUREMENT PLAN (Textual Part) Country: Kyrgyz Republic Full Project Name: Enhancing Resilience in the Kyrgyz Republic Project (ERIK) Project Number: P162635 Project Implementation agency Project Implementation Unit of the Project under MoES Date of the Procurement Plan: December 26, 2017 Period covered by this December 26, 2017 - December 26, 2018 Procurement Plan: Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. PROCUREMENT Kyrgyz Republic : Enhancing Resilience in Kyrgyzstan Project PLAN General Information Country: Kyrgyz Republic Bank’s Approval Date of the Original Procurement Plan: 2017-12-27 2019-09-16 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162635 GPN Date: 2017-12-08 Project Name: Enhancing Resilience in Kyrgyzstan Project Loan / Credit No: IDA / V1060, / , IDA / 62380 Executing Agency(ies): Ministry of Emergency Situations WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-CW/RFB-09 / Improving Safety and Pending Open - Single Stage - One Procurement of civil works IDA / 62380 Functionality of School Prior Request for Bids 5,350,000.00 0.00 Implementati 2020-08-25 2020-09-11 2020-11-10 2020-12-10 2021-01-21 2022-01-21 International Envelope for schools Infrastructure on KG-CW/RFB-10 / Improving Safety and Pending Open - Single Stage - One Procurement of civil works IDA / 62380 Functionality of School Prior Request for Bids 5,350,000.00 0.00 Implementati 2021-11-30 2021-12-17 2022-02-15 2022-03-17 2022-04-28 2023-04-28 International Envelope for schools Infrastructure on GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-G/RFB-02 / Equipment Open - Single Stage - One / Post Request for Bids 800,000.00 0.00 Canceled 2018-04-25 2018-05-23 2018-07-07 2018-08-04 2018-09-01 2019-02-28 for '112' Call Center International Envelope KG-G/RFB-02B / Equipment Contingent Emergency Open - Single Stage - One IDA / V1060 Post Request for Bids 240,000.00 229,590.14 Completed 2018-05-28 2018-06-08 2018-07-20 2018-08-19 2018-09-23 2019-03-22 for '112' Call Center Response International Envelope KG-G/RFQ-02/1 / Software Project Management and (1C accounting system for IDA / V1060 Post Direct Selection Direct 8,000.00 7,900.00 Completed 2018-05-29 2018-06-01 2018-06-14 2018-07-14 Monitoring & Evaluation PIU under the MOES) KG-G/RFQ-01 / Equipment Project Management and Request for Single Stage - One IDA / V1060 Post Open - National 35,000.00 0.00 Canceled 2018-04-27 2018-06-07 2018-07-17 for PIU Monitoring & Evaluation Quotations Envelope KG-G/RFQ-02 / Software Project Management and Request for Single Stage - One (1C accounting system for IDA / V1060 Post Open - National 10,000.00 0.00 Canceled 2018-05-05 2018-06-15 2018-08-14 Monitoring & Evaluation Quotations Envelope MoES) KG-G/RFB-01 / Equipment Contingent Emergency Open - Single Stage - One IDA / V1060 Post Request for Bids 200,000.00 0.00 Canceled 2018-05-15 2018-05-29 2018-07-13 2018-08-10 2018-09-07 2019-03-06 for rescue team Response International Envelope KG-G/RFB-01A / Equipment for rescue team: Lot #1- Procurement of Contingent Emergency Single Stage - One IDA / V1060 Post Request for Bids Open - National 200,000.00 98,060.00 Completed 2018-06-22 2018-06-29 2018-08-03 2018-09-02 2018-10-07 2018-11-21 rescue tools Response Envelope Lot #2- Procurement of equipment for rescue service KG-G/RFQ-01B / Furniture Project Management and Request for Single Stage - One IDA / V1060 Post Open - National 5,000.00 3,719.77 Completed 2018-06-29 2018-08-17 2018-09-16 for PIU Monitoring & Evaluation Quotations Envelope Page 1 KG-G/RFQ-01A / Computer Project Management and Request for Single Stage - One IDA / V1060 Post Open - National 30,000.00 19,146.94 Completed 2018-06-29 2018-08-10 2018-09-09 equipment for PIU Monitoring & Evaluation Quotations Envelope KG-G/RFB-02A / Software Contingent Emergency IDA / V1060 Post Direct Selection Direct 560,000.00 508,250.80 Completed 2018-07-09 2018-07-14 2018-08-30 2019-01-17 for '112' call center Response KG-G/RFB-01B / Equipment for rescue team: Lot#1 - Contingent Emergency Single Stage - One Rescue equipment, Lot#2 - IDA / V1060 Post Request for Bids Open - National 100,000.00 18,141.96 Completed 2018-08-15 2018-08-17 2018-09-14 2018-10-14 2018-11-11 2018-12-26 Response Envelope Fire equipment, Lot #3 - Diving equipment. KG-G/RFB-01C / Equipment for rescue team: Lot#1 - Contingent Emergency Single Stage - One Rescue equipment, Lot#2 - IDA / V1060 Post Request for Bids Open - National 84,600.00 45,416.74 Signed 2018-10-04 2018-10-05 2018-10-26 2018-11-15 2018-12-10 2019-01-24 Response Envelope Fire equipment Re-advertisement KG-G/RFQ-04 / Procurement Enhancing Financial Request for Single Stage - One of office equipment for IDA / 62380 Post Open - National 99,000.00 0.00 Canceled 2019-04-11 2019-05-23 2019-07-22 Protection Quotations Envelope regional offices SIO KG-G/RFQ-05 / Procurement Enhancing Financial Request for Single Stage - One of furniture for regional IDA / 62380 Post Open - National 99,000.00 0.00 Canceled 2019-04-11 2019-05-30 2019-07-29 Protection Quotations Envelope offices SIO KG-G/RFQ-07 / Procurement Enhancing Financial Request for Single Stage - One IDA / 62380 Post Open - National 99,000.00 0.00 Canceled 2019-07-14 2019-09-13 2019-12-12 of mobile devices for SIO Protection Quotations Envelope KG-G/RFB-05 / Establishing Strengthening Disaster Open - Single Stage - One the Platform to Exchange IDA / 62380 Preparedness and Response Post Request for Bids 390,000.00 0.00 Canceled 2019-03-28 2019-04-04 2019-05-19 2019-06-16 2019-07-14 2020-07-13 International Envelope the Data Systems KG-G/RFQ-10 / Procurement Strengthening Disaster of Software for development Request for Open - Single Stage - One IDA / 62380 Preparedness and Response Post 61,970.00 55,000.00 Signed 2019-04-05 2019-05-20 2019-09-17 of the Unified Duty- Quotations International Envelope Systems Dispatching Service 112 KG-G/RFB-03 / Development of the Country- Strengthening Disaster Under Open - Single Stage - One Wide Integrated Public IDA / 62380 Preparedness and Response Prior Request for Bids 1,407,325.00 0.00 Implementati 2019-04-04 2019-04-19 2019-06-03 2019-07-01 2019-08-12 2020-02-08 International Envelope Notification and Warning Systems on System - OKSION System KG-G/RFB-04 / Development of Routine Management Body - Crisis Management Center: Lot #1 Strengthening Disaster Open - Single Stage - One purchase of controller for IDA / 62380 Preparedness and Response Post Request for Bids 166,528.00 103,167.69 Signed 2019-03-25 2019-03-29 2019-05-13 2019-06-10 2019-07-08 2019-12-15 International Envelope video wall. Lot# 2 purchase Systems of satellite equipment. Lot #3 purchase of radio station equipment. KG-G/RFB-09 / Disaster Strengthening Disaster Pending Learning Platform for Open - Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids 100,000.00 0.00 Implementati 2020-06-22 2020-06-26 2020-08-07 2020-09-04 2020-10-16 2021-02-13 Professional Training Center International Envelope Systems on MES KG-G/RFB-10 / Procurement Enhancing Financial Request for Single Stage - One of furniture for regional IDA / 62380 Post Open - National 65,000.00 47,782.91 Signed 2019-04-18 2019-06-17 2019-08-16 Protection Quotations Envelope offices SIO Page 2 KG-G/RFB-12 / Procurement Enhancing Financial Request for Single Stage - One of office equipment for IDA / 62380 Post Open - National 99,000.00 67,943.35 Signed 2019-04-18 2019-06-17 2019-08-16 Protection Quotations Envelope regional offices SIO KG-G/RFQ-11 / Computer Project Management and IDA / V1060 Post Direct Selection Direct 4,000.00 3,924.70 Completed 2019-05-07 2019-05-12 2019-06-16 2019-07-31 equipment for PIU Monitoring & Evaluation KG-G/RFQ-12 / Additional Project Management and IDA / V1060 Post Direct Selection Direct 950.00 909.09 Completed 2019-05-07 2019-05-12 2019-05-24 2019-06-23 furniture for PIU Monitoring & Evaluation KG-G/RFQ-09 / Procurement of office equipment for Contingent Emergency Request for Single Stage - One IDA / 62380 Post Open - National 11,000.00 0.00 Canceled 2019-03-22 2019-05-08 2019-06-24 Unified Duty- Dispatching Response Quotations Envelope Service 112 KG-G/RFQ-09A / Strengthening Disaster Under Request for Single Stage - One Procurement of computer IDA / 62380 Preparedness and Response Post Open - National 11,000.00 0.00 Implementati 2019-06-14 2019-07-24 2019-09-12 Quotations Envelope equipment for 112 system Systems on Under KG-G/RFB-11 / Procurement Enhancing Financial Open - Single Stage - One IDA / 62380 Post Request for Bids 170,000.00 0.00 Implementati 2019-06-24 2019-06-28 2019-08-09 2019-08-23 2019-09-20 2019-11-19 of server equipment for SIO Protection International Envelope on KG-G/RFB-08 / Strengthening the capacity of the newly created 15 cluster interdistrict points (points) of Strengthening Disaster Open - Single Stage - One monitoring of hazardous IDA / 62380 Preparedness and Response Post Request for Bids 167,000.00 0.00 Canceled 2019-06-17 2019-06-21 2019-08-02 2019-08-16 2019-09-13 2019-12-12 International Envelope natural processes within the Systems framework of the creation of mobile monitoring points of the ESCMP Strengthening Disaster KG-G/RFQ-13 / Procurement Request for Single Stage - One IDA / V1060 Preparedness and Response Post Open - National 23,700.00 0.00 Canceled 2019-06-16 2019-07-31 2019-09-29 of compressed air apparatus Quotations Envelope Systems KG-G/RFB-13 / Procurement of hardware for Web portal and newly created 15 cluster interdistrict points (points) of Strengthening Disaster Under Open - Single Stage - One monitoring of hazardous IDA / 62380 Preparedness and Response Post Request for Bids 307,000.00 0.00 Implementati 2019-08-07 2019-08-09 2019-09-20 2019-10-21 2019-11-25 2020-02-24 International Envelope natural processes within the Systems on framework of the creation of mobile monitoring points of the ESCMP. KG-G/RFB-14 / Production Pending Enhancing Financial Single Stage - One of Branded and Promotional IDA / 62380 Post Request for Bids Open - National 23,000.00 0.00 Implementati 2019-08-12 2019-08-15 2019-09-26 2019-10-26 2019-11-26 2020-02-24 Protection Envelope Products for SIO on KG-G/RFB-04A / Development of Routine Strengthening Disaster Under Management Body - Crisis Open - Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids 44,000.00 0.00 Implementati 2019-08-02 2019-08-05 2019-09-19 2019-10-17 2019-11-14 2020-02-12 Management Center: International Envelope Systems on Purchase of satellite equipment Under KG-G/RFB-15 / Procurement Enhancing Financial Open - Single Stage - One IDA / 62380 Post Request for Bids 99,000.00 0.00 Implementati 2019-08-07 2019-08-09 2019-09-23 2019-10-23 2019-11-25 2020-01-24 of mobile devices for SIO Protection International Envelope on Page 3 KG-G/RFB-06A / Goods for operational survey of landslides: Lot #1 - Equipment and car. Lot # Strengthening Disaster Open - Single Stage - One 2 - Mobile meteorological IDA / 62380 Preparedness and Response Post Request for Bids 193,817.00 0.00 Canceled 2019-06-03 2019-06-06 2019-07-18 2019-08-01 2019-08-29 2019-12-17 International Envelope station and measuring Systems equipment. Lot #3 - UAV and land surveying equipment KG-G/RFB-06C / Strengthening Disaster Pending Single Stage - One Procurement of Off-road IDA / 62380 Preparedness and Response Post Request for Bids Open - National 59,000.00 0.00 Implementati 2019-09-27 2019-09-30 2019-11-11 2019-12-26 2020-01-23 2020-05-22 Envelope Vehicle Systems on KG-G/RFB-06D / Strengthening Disaster Pending Single Stage - One Procurement of UAV and IDA / 62380 Preparedness and Response Post Request for Bids Open - National 48,600.00 0.00 Implementati 2019-10-03 2019-10-07 2019-11-18 2020-01-02 2020-01-30 2020-05-29 Envelope land survey equipment Systems on Strengthening Disaster Pending KG-G/RFB-06Е / Procureme Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids Open - National 34,117.00 0.00 Implementati 2019-09-27 2019-09-30 2019-11-11 2019-12-26 2020-01-23 2020-05-22 nt of Measuring Equipment Envelope Systems on KG-G/RFB-06F / Strengthening Disaster Pending Procurement of Mobile Open - Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids 52,100.00 0.00 Implementati 2019-09-27 2019-09-30 2019-11-14 2019-12-30 2020-02-03 2020-06-02 Weather Station and International Envelope Systems on Forecast Equipment KG-G/RFQ-13A / Strengthening Disaster Pending Request for Single Stage - One Procurement of compressed IDA / V1060 Preparedness and Response Post Open - National 23,700.00 0.00 Implementati 2019-10-02 2019-12-30 2020-02-28 Quotations Envelope air apparatus Systems on Strengthening Disaster Pending KG-G/RFB-07 / Scaling-up Open - Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids 403,045.00 0.00 Implementati 2021-01-25 2021-02-01 2021-03-18 2021-04-15 2021-05-13 2021-11-09 of the operational monitoring International Envelope Systems on KG-G/DC-01 / Procurement of Software for newly created 15 cluster interdistrict points (points) of Strengthening Disaster Pending monitoring of hazardous IDA / 62380 Preparedness and Response Post Direct Selection Direct 176,315.00 0.00 Implementati 2019-09-30 2019-10-11 2019-11-08 2020-03-07 natural processes within the Systems on framework of the creation of mobile monitoring points of the ESCMP NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KG-G/RFB-06B / Strengthening Disaster Procurement of Digital Open - Single Stage - One IDA / 62380 Preparedness and Response Post Request for Bids 131,500.00 0.00 Canceled 2019-04-05 2019-04-12 2019-05-24 2019-06-21 2019-08-02 2019-12-20 terrain model (DTM) and International Envelope Systems orthophotographs CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 4 KG-CS/QCBS-02 / Business process review for Enhancing Financial Quality And Cost- Open - catastrophe insurance and IDA / V1060 Prior 1,000,000.00 1,333,333.33 Signed 2018-03-15 2018-04-14 2018-05-12 2018-06-09 2018-06-29 2018-08-03 2018-09-18 2020-09-17 Protection Based Selection International supporting IT customization services KG-CS/LCS-01 / Financial Least Cost Open - audit (annual) of project for / Post 15,000.00 0.00 Canceled 2018-02-25 2018-03-27 2018-04-24 2018-05-22 2018-06-11 2018-07-09 2018-07-23 2019-12-31 Selection International 2018-2020 KG-CS/QCBS-01 / Preparation of Feasibility Studies and Designs for Quality And Cost- Open - Improved Seismic Safety and / Prior 1,300,000.00 0.00 Canceled 2018-04-25 2018-05-25 2018-06-22 2018-07-20 2018-08-09 2018-09-13 2018-10-29 2020-10-28 Based Selection International Energy Efficiency of Schools and Technical Supervision of construction. KG-CS/QCBS-01/2 / Preparation of Feasibility Studies and Designs for Improving Safety and Quality And Cost- Open - Improved Seismic Safety and IDA / V1060 Functionality of School Post 400,000.00 0.00 Canceled 2020-03-02 2020-03-23 2020-04-27 2020-06-08 2020-06-28 2020-08-02 2020-09-11 2021-04-09 Based Selection International Energy Efficiency of Schools Infrastructure and Technical Supervision of construction. KG-CS/LCS-01/A / Financial Project Management and Least Cost Open - IDA / 62380 Post 100,000.00 76,832.00 Signed 2019-01-18 2019-02-03 2019-02-24 2019-03-24 2019-04-07 2019-04-22 2019-05-13 2024-01-31 audit of project (annual) Monitoring & Evaluation Selection International KG-CS/QCBS-03 / Enhancing Financial Quality And Cost- Open - Pending Optimisation of SIO core IDA / 62380 Prior 818,167.00 0.00 2019-10-15 2019-11-07 2019-12-21 2020-01-18 2020-02-17 2020-03-23 2020-04-20 2021-04-20 Protection Based Selection International Implementation business processes KG-CS/QCBS-04 / Risk Enhancing Financial Quality And Cost- Open - Pending management and regulatory IDA / 62380 Prior 333,000.00 0.00 2020-09-15 2020-10-06 2020-11-09 2020-12-09 2021-01-08 2021-02-12 2021-03-22 2022-03-22 Protection Based Selection International Implementation compliance KG-CS/QCBS-01/1 / Preparation of Feasibility Improving Safety and Studies and Designs for Quality And Cost- Open - Pending IDA / V1060 Functionality of School Prior 800,000.00 0.00 2019-06-28 2019-07-12 2019-08-12 2019-09-11 2019-10-09 2019-11-13 2019-12-18 2020-12-17 Improved Seismic Safety and Based Selection International Implementation Infrastructure Energy Efficiency of Schools and Author supervision KG-CS/QCBS-01/3 / Preparation of Feasibility Improving Safety and Studies and Designs for Quality And Cost- Open - IDA / V1060 Functionality of School Prior 400,000.00 0.00 Canceled 2020-07-28 2020-08-27 2020-09-27 2020-10-27 2020-11-24 2020-12-29 2021-02-02 2022-10-25 Improved Seismic Safety and Based Selection International Infrastructure Energy Efficiency of Schools and Author supervision Improving Safety and Consultant KG-CS/CQS-02 / IDA / V1060 Functionality of School Post Qualification Open - National 200,000.00 0.00 Canceled 2021-04-01 2021-04-15 2021-05-13 2021-05-27 2021-07-03 2022-06-28 Supervision and monitoring Infrastructure Selection Improving Safety and KG-CS/QCBS-05 / Quality And Cost- Open - Pending IDA / V1060 Functionality of School Prior 400,000.00 0.00 2021-02-02 2021-02-23 2021-04-08 2021-05-06 2021-06-05 2021-07-10 2021-08-14 2022-12-27 Supervision and monitoring Based Selection International Implementation Infrastructure KG-CS/CQS-03 / Strengthening Disaster Consultant Open - Under Establishing a Platform to IDA / 62380 Preparedness and Response Post Qualification 150,000.00 0.00 2019-08-05 2019-08-26 2019-10-09 2019-10-16 2019-11-13 2020-02-11 International Implementation Exchange the Data Systems Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 5 KG-IOC/IC-07 / Local Individual Project Management and Coordinator for the IDA / V1060 Post Consultant Open 27,000.00 12,731.86 Signed 2018-02-15 2018-03-29 2018-03-30 2018-04-17 2020-04-06 Monitoring & Evaluation Component 1 Selection KG-IOC/IC-08 / Local Individual Project Management and Coordinator for the IDA / V1060 Post Consultant Open 27,000.00 11,086.74 Signed 2018-02-15 2018-03-29 2018-03-30 2018-04-17 2020-04-06 Monitoring & Evaluation Component 2 Selection KG-IOC/IC-09 / Local Individual Project Management and Coordinator for the IDA / V1060 Post Consultant Open 27,000.00 13,404.13 Signed 2018-02-15 2018-03-29 2018-03-30 2018-04-17 2020-04-06 Monitoring & Evaluation Component 3 Selection Individual KG-IOC/IC-03 / Local Project Management and IDA / V1060 Prior Consultant Direct 21,500.00 20,923.36 Signed 2018-02-15 2018-03-08 2018-03-22 2018-03-29 2019-11-19 Financial Manager Monitoring & Evaluation Selection Individual KG-IOC/IC-04 / Local Project Management and IDA / V1060 Post Consultant Open 11,500.00 11,986.87 Signed 2018-02-15 2018-03-20 2018-03-22 2018-04-08 2019-04-03 Disbursment Specialist Monitoring & Evaluation Selection KG-IOC/IC-05 / Local Individual Project Management and assistant of Procurement IDA / V1060 Post Consultant Open 7,500.00 4,791.60 Terminated 2018-02-15 2018-03-29 2018-03-30 2018-04-19 2019-04-14 Monitoring & Evaluation Specialist Selection Individual KG-IOC/IC-06 / Local Project Management and IDA / V1060 Post Consultant Open 10,500.00 8,286.74 Terminated 2018-02-15 2018-03-29 2018-03-30 2018-04-19 2019-04-14 Translator-office-manager Monitoring & Evaluation Selection Individual KG-CS/IC-02 / Selection of Project Management and / Post Consultant Limited 10,000.00 3,235.30 Terminated 2017-12-29 2017-12-30 2018-01-05 2018-01-17 2018-02-28 Local Social Consultant Monitoring & Evaluation Selection KG-CS/IC-01 / Selection of Individual Local Environmental / Post Consultant Limited 10,000.00 3,970.59 Completed 2017-12-29 2017-12-31 2018-01-05 2018-01-17 2018-02-28 Consultant Selection KG-IOC/IC-02 / Local Individual Project Management and Senior Procurement IDA / V1060 Prior Consultant Direct 21,500.00 20,923.36 Signed 2018-02-22 2018-02-22 2018-02-22 2018-04-01 2019-11-22 Monitoring & Evaluation Specialist Selection Individual KG-MES-54500-CS-INDV / Project Management and IDA / V1060 Prior Consultant Limited 35,500.00 14,390.21 Signed 2018-03-19 2018-03-19 2018-04-02 2018-04-26 2019-04-21 Local Director PIU Monitoring & Evaluation Selection Individual KG-IOC/IC-01 / Local / Prior Consultant Open 35,500.00 0.00 Canceled 2018-02-15 2018-03-29 2018-04-12 2018-05-17 2020-05-06 Director PIU Selection KG-CS/IC-03 / Selection of Local Consultant for Individual preparation of bidding / Post Consultant Open 10,000.00 0.00 Canceled 2018-04-15 2018-05-27 2018-06-10 2018-06-24 2019-06-19 documents for goods for Selection MoES KG-CS/IC-03-2 / Local IT Consultant for preparation of Individual Project Management and bidding documents for IDA / V1060 Post Consultant Limited 10,000.00 0.00 Canceled 2018-05-10 2018-05-15 2018-06-05 2018-07-03 2019-07-03 Monitoring & Evaluation Component #1 and Selection Component #3 KG-CS/IC-03/1 / Local Individual Consultant for Business Project Management and IDA / V1060 Post Consultant Open 11,000.00 12,778.57 Signed 2018-06-21 2018-07-30 2018-08-02 2018-08-21 2019-08-21 Processes and Information Monitoring & Evaluation Selection Technologies Page 6 Improving Safety and Individual KG-CS/IC-04 / International IDA / V1060 Functionality of School Post Consultant Open 100,000.00 0.00 Canceled 2018-10-26 2018-12-05 2018-12-21 2019-01-09 2020-12-29 Сivil engineer Infrastructure Selection Improving Safety and Individual KG-CS/IC-04/A / Local civil IDA / 62380 Functionality of School Post Consultant Open 45,000.00 15,219.03 Signed 2019-02-17 2019-03-14 2019-03-21 2019-04-11 2020-04-10 engineer Infrastructure Selection Improving Safety and Individual KG-CS/IC-05 / Local Social IDA / 62380 Functionality of School Post Consultant Open 45,000.00 0.00 Canceled 2019-02-27 2019-04-04 2019-04-11 2019-05-02 2020-05-01 & Environment Consultant Infrastructure Selection Strengthening Disaster Individual KG-CS/IC-07 / Local IT IDA / V1060 Preparedness and Response Post Consultant Open 20,000.00 16,883.13 Signed 2019-03-25 2019-04-19 2019-04-22 2019-05-10 2020-05-09 Consultant for MES KR Systems Selection KG-CS/IC-09 / Local Improving Safety and Individual Translator Consultant for IDA / 62380 Functionality of School Post Consultant Open 10,000.00 0.00 Canceled 2019-03-25 2019-04-11 2019-04-12 2019-04-29 2020-04-28 Component #2 Infrastructure Selection KG-CS/IC-10 / Local Individual Enhancing Financial Translator Consultant for IDA / 62380 Post Consultant Open 10,000.00 0.00 Canceled 2019-03-25 2019-04-11 2019-04-12 2019-04-29 2020-04-28 Protection Component #3 Selection KG-CS/IC-05-2 / Local Improving Safety and Individual Social&Enviroment IDA / 62380 Functionality of School Post Consultant Limited 45,000.00 12,936.22 Signed 2019-05-03 2019-05-10 2019-05-24 2019-06-14 2020-06-13 Consultant Infrastructure Selection KG-CS/IC-08 / Local Strengthening Disaster Individual Translator Consultant for IDA / 62380 Preparedness and Response Post Consultant Open 10,000.00 0.00 Canceled 2019-03-25 2019-04-11 2019-04-12 2019-04-29 2020-04-28 Component #1 Systems Selection KG-CS/IC-03/2 / Local Individual Consultant for Business Enhancing Financial IDA / 62380 Post Consultant Direct 12,900.00 12,808.23 Signed 2019-08-21 2019-08-21 2019-08-21 2019-08-22 2020-08-31 Processes and Information Protection Selection Technologies Page 7