The World Bank Report No: ISR8580 Implementation Status & Results Chile CHILE - Chacabuquito Hydro Power Project (P074619) Public Disclosure Copy Operation Name: CHILE - Chacabuquito Hydro Power Project (P074619) Project Stage: Implementation Seq.No: 5 Status: ARCHIVED Archive Date: 19-Nov-2012 Country: Chile Approval FY: 2002 Product Line: Carbon Offset Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: UNIDENTIFIED Implementing Agency(ies): Key Dates Board Approval Date 04-Feb-2002 Original Closing Date 31-Dec-2012 Last Archived ISR Date 14-Aug-2011 Effectiveness Date 04-Feb-2002 Revised Closing Date 31-Dec-2012 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Implementation Status Overview The project is commissioned and has been generating electricity since 2002. The registration under the CDM Board took place on July of 2007. Locations Country First Administrative Division Location Planned Actual Chile Not Entered Los Andes Chile Not Entered Río Aconcagua Key Decisions Regarding Implementation Public Disclosure Copy N/A Related Projects There are no related projects. Page 1 of 1