The World Bank Implementation Status & Results Report LB - Improve Capacity for Env. Compliance (P143701) LB - Improve Capacity for Env. Compliance (P143701) MIDDLE EAST AND NORTH AFRICA | Lebanon | Environment & Natural Resources Global Practice | Institutional Development Fund| FY 2013 |Seq No: 2 | ARCHIVED on 21-Dec-2015 | ISR21735 | Implementing Agencies: Key Dates Key Project Dates Bank Approval Date:25-Feb-2013 Effectiveness Date:07-Oct-2013 Planned Mid Term Review Date:-- Actual Mid-Term Review Date:-- Original Closing Date:07-Oct-2016 Revised Closing Date:07-Oct-2016 Project Development Objectives Project Development Objective (from IDF Proposal) The grant's overall development objective is to improve the environmental compliance of the industrial sector in Lebanon through three inter-related objectives: (1) Institutionalize industrial audits/Compliance Action Plans (CAPs) by improving environmental standards, regulations and guidelines relating to industrial pollution management; (2) Enhance the general administrative and technical capacity of the Ministry of Environment (MoE) to better manage industrial audits/CAPs and programs supporting cleaner production; (3) Build knowledge among SMEs / industrial associations to better comply with environmental regulations. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Environmental Audits:(Cost $130700.00 ) Compliance Action Plans:(Cost $94200.00 ) Training and communications:(Cost $75100.00 ) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating -- Moderate 12/21/2015 Page 1 of 4 The World Bank Implementation Status & Results Report LB - Improve Capacity for Env. Compliance (P143701) Implementation Status and Key Decisions All the planned tasks are in contract execution stage and are well underway and on target for completion on time. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- -- Moderate Macroeconomic -- -- Moderate Sector Strategies and Policies -- -- Moderate Technical Design of Project or Program -- -- Moderate Institutional Capacity for Implementation and Sustainability -- -- Moderate Fiduciary -- -- Moderate Environment and Social -- -- Moderate Stakeholders -- -- Moderate 12/21/2015 Page 2 of 4 The World Bank Implementation Status & Results Report LB - Improve Capacity for Env. Compliance (P143701) Other -- -- -- Overall -- -- Moderate Results Indicators PHINDPDOTBL A system is established for implementing Lebanon's Compliance decree(Text,Custom) Baseline Actual (Previous) Actual (Current) End Target The decree calls for CAPs which will be developed and implemented in at least 5 industrial The contract for enterprises. The decree was issued in The consulting firm to preparing the CAPs has This will allow Value 2012 and no compliance prepare CAPs is in the been awarded and the MoE and other plans are available to date. process of hiring. work is well underway. concerned stakeholders to identify and provide needed technical assistance for its continued implementation. Date 06-Nov-2012 10-Jun-2014 08-Dec-2015 07-Oct-2016 PHINDPDOTBL A coordination mechanism for CAP is in place(Text,Custom) Baseline Actual (Previous) Actual (Current) End Target Clear guidelines and consultations for permitting, inspection and The permitting, inspection monitoring and monitoring modalities Cap manual was CAP Manual was modalities Value for industrial pollution prepared prepared through the abatement are weak. CAP Manual will strengthen coordination mechanism among institutions. Date 06-Nov-2012 10-Jun-2014 08-Dec-2015 07-Oct-2016 12/21/2015 Page 3 of 4 The World Bank Implementation Status & Results Report LB - Improve Capacity for Env. Compliance (P143701) PHINDPDOTBL Information exchange is strengthened(Text,Custom) Baseline Actual (Previous) Actual (Current) End Target Appropriate communication tools will be provided to the industrial The consulting firm to The consulting firm to enterprises and Limited information is prepare communication prepare communication the Value available in Lebanon tools is in the process tools has been hired and governmental regarding CAP of hiring. work is well underway. institutions for promoting the implementation of the compliance decree. Date 06-Jun-2012 10-Jun-2014 08-Dec-2015 07-Oct-2016 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P143701 TF-14421 Effective USD 0.30 0.30 0.00 0.11 0.19 37% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P143701 TF-14421 Effective 07-Oct-2013 07-Oct-2013 07-Oct-2013 07-Oct-2016 07-Oct-2016 Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 12/21/2015 Page 4 of 4