FEDERAL REPUBLIC OF NIGERIA Nigeria Erosion and Watershed Management Project (NEWMAP) PROCUREMENT PLAN I. GENERAL 1. Project information: Country: Nigeria Borrower: Federal Government of Nigeria Project Name: Nigeria Erosion and Watershed Management Project-(NEWMAP) Loan / Credit No.: PIA: National NEWMAP Coordinating Unit. 2. Bank’s approval Date of the procurement Plan: March, 2012 3. Date of General Procurement Notice: 4. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments (US$ equivalent) 1. ICB and LIB (Goods and services other > 750,000.00 ALL than consultancy services) 2. NCB 50,000.00 ≤ 750,000.00 NONE 3. ICB (Works) > 5,000,000.00 ALL 4. NCB (Works) 200,000 ≤ 5,000,000.00 NONE 5 Shopping-Goods < 50,000.00 NONE 6 Shopping-Works < 100,000.00 NONE 7 Training, Workshops, Study Tours All Values Based on Annual Work Plans & Budgets 2. Prequalification. Bidders for major works shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Shall apply 4. Reference to (if any) Project Operational/Procurement Manual: shall apply 5. Any Other Special Procurement Arrangements: Not Applicable 6. Procurement Packages with Methods and Time Schedule Procurement of Goods : 1 2 3 4 5 6 7 8 9 Re Contract Estimate Procure Prequalificati Domestic Review Expected Comments f. (Description) d ment on (yes/no) Preference by Bank Bid- No Cost Method (yes/no) (Prior / Post) Opening . US$’000 Date 1 Computer Systems, Office, software and Accessories Computers and 684 NCB NO NO POST June 7, Procureme Accessories, software (see 2012 nt by each remark of the 7 packages, Photo- Colum) SPMU & copiers, UPS, Printers FPMU is and Scanners, Fax estimated Machines, Laptops, at ( USD Stationeries, 85.5) Consumables, LAN, Telephony,Lasers Software Licenses and Application,. 2 Office Furniture’s and Equipment Computer workstations 680 NCB NO NO PRIOR June 7, Procureme and Office Furniture (see 2012 nt by each remark of the 7 Water Dispenser, Colum) SPMU & Refrigerators, FPMU is Airconditioners, estimated Tables, Chairs, etc at ( USD 85) 3 Operational Vehicles 4-WD Vehicles (32 1440 NCB NO NO PRIOR June 7, Procureme units) (see 2012 nt by each remark of the 7 Colum) SPMU & FPMU is estimated at (180USD 4 Generator 40KVA Sound-Proof 240 NS NO NO PRIOR June 7, Procureme Electricity Generating (see 2012 nt by each Set-Purchase and remark of the 7 Installation (8 units) Colum) SPMU & FPMU is estimated at (30 USD 5 Training Communication, Presentation, Media Equipment and materials, etc Multimedia 364 NS NO NO PRIOR June 7, Procureme Projectors, (see 2012 nt by each remark of the 7 Flip Chart Stands, Colum) SPMU & Boards, GSM FPMU is TV/Video/Radio/Reco estimated rders and Digital at (45.5 Cameras, Internet USD Facilities, GPS, Raincoats and Enumerators bags, Program information kit, Program posters Community oriented Implementation manual 6 Field Equipment Purchase of Weather 2,400 NCB NO NO PRIOR June 7, Procureme Monitoring Stations, (see 2012 nt by each GPSs, Laser Measures, remark of the 7 Measuring Wheels, 1- Colum) SPMU & 2km Range Radios and FPMU is other survey equipment estimated and tools to gauge and at (300 trace watershed, USD terrestrial carbon and water flow 7 Geographic Information System Purchase of GIS 3520 NCB NO NO PRIOR June 7, Procureme data/Satellite Imagery,, (see 2012 nt by each Overhead photography, remark of the 7 etc Colum) SPMU & FPMU is estimated at (440 USD Sub Total 9,328.00 Procurement of Civil Works 1 2 3 4 5 6 7 8 9 Ref. Contract Estimated Procure Prequalificati Domestic Review Expected Comments No. (Description) Cost ment on (yes/no) Preference by Bank Bid- US$’000 Method (yes/no) (Prior / Post) Opening Date 1 Civil works, and 252,000.00 ICB NO YES PRIOR October Procureme maintenance of flood 12, 2012 nt by ICB and gully erosion sites for all 7 SPMU 2 Office accommodation 240,000 NS NO NO PRIOR July, 2012 for 7 SPMU & FPCU SUB TOTAL 252,240.00 III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1 Consultant Services-QCBS- All Values ALL International 2 Consultant Services-QCBS-National > 200,000.00 ALL 3 Consultant Services-CQS < 200,000.00 NONE 4 Consultant Services-lC > 50,000.00 ALL 5 Consultant Services-lC < 50,000.00 ToR only but ALL 6 Consultant Services- Single Source All Values ALL Selection Note: All ToRs to be prior review QCBS = Quality and Cost Based Selection SSS = Single Source Selection CQ = Consultant Qualification LCS = Least Cost Selection IC = Individual Consultant 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $200,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 7 Ref. Description of Assignment Estimated Selection Review Expected Comments No. Method by Bank Proposals Cost. (Prior / Submission US$’000 Post) Date 1 Consultancy for the detailed 3,395.24 QCBS Prior On-going Consultancy for Engineering designs and data (see remark Priority sites collation for 35 sites Colum by each of the 7 SPMU (see each State Proc. Plan). 2 Consultancy for the supervision 6,824.47 QCBS Prior September Consultancy for of Civil Works for 35sites (see remark 2012 Priority sites Colum by each of the 7 SPMU (see each State Proc. Plan). 3 Consultancy for the RAP study 875.00 IC Prior On-going Consultancy for for 35 sites (see remark Priority sites Colum by each of the 7 SPMU is estimated at (25 USD. 4 Consultancy for the ESIA study 875.00 IC Prior On-going Consultancy for for 35 sites (see remark Priority sites Colum by each of the 7 SPMU is estimated at (25 USD. 5 Consultancy for the Socio- 875.00 IC Prior On-going Consultancy for Economic study 35 sites (see remark Priority sites Colum by each of the 7 SPMU is estimated at 25 USD per site 6 Consultancy for GIS data 875.00 IC Prior On-going Consultancy for collection and Mapping for 35 (see remark Priority sites sites Colum by each of the 7 SPMU is estimated at 75 USD per site 7 Consultancy for the detailed 3500.00 QCBS Prior August, 2012 Consultancy for Engineering designs and data (see remark 5 additional collation for additional 35sites Colum sites by each of the 7 SPMU is estimated at 100 USD per site 8 Consultancy for the detailed 2625.00 QCBS Prior June, 2013 Consultancy for ESIA, RAP and Socio (see remark 5 additional Economic Studies for Colum sites by each of additional 35 sites the 7 SPMU is estimated at 75 USD per site 9 Environmental engineering and 800 QCBS 9 design consultancy, 10 Procurement consultancy for 800 QCBS 10 June 1012 support of FPMU and SPMUs 11 M&E consultancy 400 QCBS 11 12 Consultancy for the support of 800.00 QCBS 12 Sept., 2012 Consultancy by SPMUs and FPMU (see remark each of the 7 Colum SPMU & FPMU is estimated at (100 USD 13 Consultancy for Legal Services 800.00 IC 13 Sept., 2012 Consultancy by each of the 7 (see remark SPMU & Colum FPMU is estimated at (100 USD 14 Consultancy for valuation and 3500.00 14 Sept., 2012 Consultancy by resettlement implementation (see remark each of the 7 Colum SPMU, to cover all sites is estimated at (500 USD per SPMU 15 Consultancy for Training and 1600.00 QCBS Prior August, 2012 Consultancy by Capacity Building (see remark each of the 7 Colum SPMU & FPMU is estimated at (200 USD 16 Consultancy-External Auditor 400.00 QCBS Prior March, 2013 Consultancy by (see remark FPMU to cover Colum each SPMU 17 Consultancy on Community 800.00 IC Prior Sept., 2012 Consultancy by consultation, Public Education (see remark each of the 7 and Erosion Management and Colum SPMU & awareness Techniques, FPMU is estimated at (100 USD Sub Total 27,744.71 IV. Implementing Agency Capacity Building Activities with Time Schedule 1. In this section the agreed Capacity Building Activities are listed with time schedule below; No. Expected outcome / Estimated Estimated Start Date Com Activity Description Cost US$ Duration m ‘000 e n t s A. TRAINING 1 3. Nos. Training courses for August 2012 Capacity Building PMU staff; Project activities for each Coordinator, Procurement of the 7 SPMU & Specialist, and financial mgt, FPMU is estimated at (90 USD M&E, Environmental specialists, Communication, Livelihood, Engineering 720.00(see 2WKS, specialists remark Colum each 2 Training of project finance August 2012 Capacity Building staff(FMS, APA, FO, IA) on 160.00(see activities for each flexible accounting software remark Colum 1wk of the 7 SPMU & FPMU is estimated at (20 USD B. WORKSHOP 3 September Capacity Building 2012 activities for each of the 7 SPMU & Capacity Building for key 240.00(see FPMU is estimated stakeholders remark Colum 3 days at (30 USD 4 September, Capacity Building 2012 activities for each of the 7 SPMU & 160(see FPMU is estimated ICT Training remark Colum 1 wk at (20 USD 5 Various Capacity Building activities for each Professional of the 7 SPMU & Seminars/Workshops/ 120.00(see FPMU is estimated subscriptions remark Colum Various at (15 USD 6 September Capacity Building 2 Days Sensitization/ activities for each 2012 Workshop for State and Local of the 7 SPMU & Govt. Officials on erosion and 200.00(see FPMU is estimated watershed management remark Colum 2 days at (25 USD 7 October Capacity Building 3 Day workshop for Line activities for each 2012 Ministries and MDAs on of the 7 SPMU & addressing and prevention of 240.00(see FPMU is estimated Land Degradation remark Colum 3- days at (30 USD 8 3 Day workshop for local October Capacity Building Govt. Focal Persons and 2012 activities for each Community Erosion watch of the 7 SPMU & Dogs on prevention of erosion FPMU is estimated 240.00(see at (30 USD and land degradation remark Colum 3-days 9 2013 Capacity Building activities for each Capacity Building on use of of the 7 SPMU & Metrological and GPS 200.00(see FPMU is estimated Equipment remark Colum 5-days at (25 USD C. STUDY/TOURS 10 240.00(see Various October Capacity Building remark Colum times 2012 activities for each Baseline survey/ Community of the 7 SPMU & needs assessment and capacity FPMU is estimated building at (30 USD 11 240.00(see Various August, Capacity Building remark Colum times 2012 activities for each Sensitization/ Awareness of the 7 SPMU & creation of NEWMAP in the FPMU is estimated 18 LGA at (30 USD 12 160.00(see WB and Capacity Building remark Colum FAO to activities for each Participation in watershed of the 7 SPMU & determine studies organized by the world FPMU is estimated bank and FAO at (20 USD 13 240.00(see Various December, Capacity Building remark Colum 2012 activities for each of the 7 SPMU & Launching of ESIA and RAP FPMU is estimated for priority sites at (30 USD 14 160.00(see Various Oct., 2012 Capacity Building remark Colum activities for each of the 7 SPMU & FPMU is estimated livelihood studies at (20 USD 15 160.00(see Various World Bank Capacity Building Participation in remark Colum activities for each determined Biodiversity/forest carbon of the 7 SPMU & study organized by the World FPMU is estimated Bank at (20 USD 16 120.00(see 4-days each July 2012 Capacity Building remark Colum activities for each Recognizance survey of of the 7 SPMU & Project sites (Erosion and FPMU is estimated Watershed) at (15 USD 17 2480.00(see 4-wks February., Capacity Building remark Colum 2013 activities for each of the 7 SPMU & International Training and FPMU is estimated study tours at (310 USD 18 Various World Bank Capacity Building determined activities for each Attendance of World Bank of the 7 SPMU & Organized training, meetings, 800.00(see FPMU is estimated seminar and workshops remark Colum at (100 USD Sub Total 6,880.00 PROCUREMENT Nigeria : Nigeria Erosion and Watershed Management Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2017-07-14 2019-08-30 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P124905 GPN Date: Project Name: Nigeria Erosion and Watershed Management Project Loan / Credit No: IDA / 51050 Executing Agency(ies): Sokoto SPMU WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SOK/NEWMAP/WK/NS/001/17 Under Component 4: Project Single Stage - One / Renovation of NEWMAP IDA / 51050 Post Request for Bids Open - National 70,000.00 0.00 Implementati 2017-02-03 2017-02-10 2017-03-31 2017-04-21 2017-05-19 2017-07-18 Management Envelope SPMU office on SOK/NEWMAP/WK/NS/002/17 Component 4: Project Single Stage - One / Drilling of borehole and IDA / 51050 Post Request for Bids Open - National 45,000.00 12,560.63 Completed 2017-02-03 2017-02-03 2017-03-14 2017-06-03 2017-06-17 2017-09-15 Management Envelope overhead tank SKO/NEWMAP/WK/NS/003/07 / Degraded land Component 4: Project Single Stage - One IDA / 51050 Post Request for Bids Open - National 300,000.00 147,834.98 Completed 2017-02-14 2017-02-21 2017-03-07 2017-03-21 2017-04-11 2017-07-10 rehabilitation, Establishment Management Envelope of wood lots and orchards SOK/NEWMAP/CW/1CB/01/18 Component 1: Erosion and Pending / Reconstruction of Lugu Single Stage - One IDA / 51050 Watershed Management Prior Request for Bids Open - National 24,000,000.00 0.00 Implementati 2018-06-25 2018-06-30 2018-08-11 2018-09-10 2018-10-15 2019-04-13 Dam and Rehabilitation of Envelope Infrastructure Investments on Irrigation Scheme SOK/NEWMAP/CW/NS/01/18 Component 1: Erosion and Pending / Revegetation/Restoration of Request for Single Stage - One IDA / 51050 Watershed Management Post Open - National 200,000.00 0.00 Implementati 2018-06-09 2018-08-04 2019-01-31 Degraded Watersheds ( Quotations Envelope Infrastructure Investments on Vegetation Cover) SOK/NEWMAP/CW/NCB/02/1 Component 1: Erosion and Pending 8 / Storm Water Single Stage - One IDA / 51050 Watershed Management Prior Request for Bids Open - National 14,000,000.00 0.00 Implementati 2018-10-11 2018-10-16 2018-11-27 2018-12-27 2019-01-31 2019-07-30 Management Works at Envelope Infrastructure Investments on Tudun wada SOK/NEWMAP/CW/NCB/01/1 8 / Storm Water Component 1: Erosion and Pending Single Stage - One Management Works and IDA / 51050 Watershed Management Prior Request for Bids Open - National 18,000,000.00 0.00 Implementati 2018-08-15 2018-08-20 2018-10-01 2018-10-31 2018-12-05 2019-06-03 Envelope Constrution of Earth Dam Infrastructure Investments on at Tambuwal and Tureta SOK/NEWMAP/CW/NCB/03/1 Component 1: Erosion and Pending Single Stage - One 8 / River Bank Erosion IDA / 51050 Watershed Management Prior Request for Bids Open - National 18,000,000.00 0.00 Implementati 2018-06-25 2018-06-30 2018-08-11 2018-09-10 2018-10-15 2019-04-13 Envelope Control Works at Yarbulutu Infrastructure Investments on SOK/NEWMAP/CW/NS/01/19 / Degraded land Component 4: Project Request for Single Stage - One Rehabilitation, Establishment IDA / 51050 Post Limited 200,000.00 147,834.98 Completed 2019-04-27 2019-06-22 2019-12-19 Management Quotations Envelope of 150 hectares of woodLots & Orchads SOK/NEWMAP/CW/NS/02/19 / Sustainability of Planted Pending Component 4: Project Request for Single Stage - One Seedlings (Drilling of Two IDA / 51050 Post Limited 70,000.00 0.00 Implementati 2019-04-14 2019-06-09 2019-12-06 Management Quotations Envelope Motorised Boreholes and on Overhead Tanks ) Page 1 NG-SOKOTO SPMU-122429- CW-RFQ / Rehabilitation of Pending Component 4: Project Request for Single Stage - One 150 Ha degraded land at IDA / 51050 Post Limited 200,000.00 0.00 Implementati 2019-08-06 2019-10-01 2020-03-29 Management Quotations Envelope Goronyo, Sabon Birni and on Sifawa Forest Reserves SOK/NEWMAP/WKS/NS/02/19 Pending / CONSTRUCTION OF Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 195,000.00 0.00 Implementati 2019-09-12 2019-11-07 2020-05-05 1.8KM DRAINAGE IN Management Quotations Envelope on TURETA SOK/NEWMAP/WKS/NS/03/19 Pending / DESILTING OF 26 KM Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 110,000.00 0.00 Implementati 2019-08-30 2019-10-25 2020-04-22 NETWORK OF DRAINAGES Management Quotations Envelope on IN SOKOTO METROPOLIS SOK/NEWMAP/WKS/NS/04/19 Pending Component 4: Project Request for Single Stage - One / RIVER SOKOTO IDA / 51050 Post Limited 190,000.00 0.00 Implementati 2019-09-25 2019-11-20 2020-05-18 Management Quotations Envelope RETRAINING WORKS on SOK/NEWMAP/WKS/NS/05/19 Pending / FLOOD CONTROL Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 195,000.00 0.00 Implementati 2019-09-04 2019-10-30 2020-04-27 WORKS AT SPECIALIST Management Quotations Envelope on HOSPITAL SOK/NEWMAP/WKS/NS/06/19 / 100 HA FOREST Pending Component 4: Project Request for Single Stage - One RESERVE ENRICHMENT IDA / 51050 Post Limited 200,000.00 0.00 Implementati 2019-09-25 2019-11-20 2020-05-18 Management Quotations Envelope PLANTING IN GORONYO, on TURETA AND TAMBUWAL SOK/NEWMAP/WKS/NS/006/1 Pending 9 / PRODUCTION OF 1 Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 150,000.00 0.00 Implementati 2019-09-28 2019-11-23 2020-05-21 MILLION TREE Management Quotations Envelope on SEEDLINGS SOK/NEWMAP/NS/01/2019 / Construction of 1.5km Pending Component 4: Project Request for Single Stage - One Drainage in Sanyinna IDA / 51050 Post Limited 185,000.00 0.00 Implementati 2019-09-06 2019-11-01 2020-04-29 Management Quotations Envelope Tambuwal Local Government on Area. GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SKO/NEWMAP/GD/NS/005/17 Pending / PROCUREMENT OF Component 4: Project Request for Single Stage - One IDA / 51050 Post Open - National 50,000.00 0.00 Implementati 2017-03-02 2017-04-13 2017-05-13 OFFCE AC Management Quotations Envelope on &REPRIGERATORS SKO/NEWMAP/GD/NS/009/17 Component 4: Project Request for Single Stage - One / PROCUREMENT OF IDA / 51050 Post Open - National 35,000.00 22,550.00 Completed 2017-03-03 2017-05-05 2017-08-03 Management Quotations Envelope 50KVA GENERATOR SKO/NEWMAP/GD/NS/010/17 / PROCUREMENT Component 4: Project Request for Single Stage - One IDA / 51050 Post Open - National 5,000.00 26,651.63 Completed 2017-03-24 2017-05-19 2017-06-18 OF/PRINT OF TV/RADIO Management Quotations Envelope JINGLES SKO/NEWMAP/GD/NS/011/17 Component 4: Project Request for Single Stage - One / PROCUREMENT OF IDA / 51050 Post Open - National 5,000.00 4,022.15 Completed 2017-03-17 2017-05-05 2017-06-02 Management Quotations Envelope OFFICE STATIONARIES Page 2 SKO/NEWMAP/GD/NS/001/17 / Procurement of vehicles: Component 4: Project Request for Single Stage - One IDA / 51050 Post Open - National 400,000.00 350,831.25 Completed 2017-02-12 2017-04-02 2017-07-01 1no 18 seater bus, 1no SUV Management Quotations Envelope and 3no double cabin 4WD SKO/NEWMAP/GD/NS/002/17 / Furnishing of SPMU Component 4: Project Request for Single Stage - One Offices and procurement of IDA / 51050 Post Open - National 50,000.00 23,751.75 Completed 2017-02-09 2017-04-06 2017-05-04 Management Quotations Envelope office furniture and equipment SKO/NEWMAP/GD/NS/004/17 / Procurement and Component 4: Project Request for Single Stage - One IDA / 51050 Post Open - National 5,000.00 4,687.66 Completed 2017-03-03 2017-04-14 2017-05-12 installation of internet Management Quotations Envelope facilities SKO/NEWMAP/GD/NS/003/17 / Procurement of laptops, desktops computers, Component 4: Project Request for Single Stage - One printers, photocopiers, IDA / 51050 Post Open - National 50,000.00 29,901.22 Completed 2017-02-15 2017-04-12 2017-05-12 Management Quotations Envelope scanners, cameras, projector, screen and relevant software and accessories SOK/NEWMAP/GO/NS/01/19 / Procurement of Information, Education and Pending Component 4: Project Request for Single Stage - One Communication Materials IDA / 51050 Post Limited 15,000.00 0.00 Implementati 2019-05-13 2019-07-08 2020-01-04 Management Quotations Envelope (NEWMAP Branding, TV & on Radio Jingles, Stickers, Posters, T-shirts). SOK/NEWMAP/NS/GO/01/19 / PROCUREMENT OF 20,000 FRUIT TREES SEEDLINGS (10,000 Pending MANGOS, 5,000 GUAVA Component 4: Project Request for Single Stage - One IDA / 51050 Post Limited 45,000.00 0.00 Implementati 2019-09-15 2019-11-10 2020-05-08 AND 5,000 CAHEW) AND Management Quotations Envelope on INPUTS FOR DISTRIBUTION TO FARMERS IN PROJECT INTERVENTION AREAS. NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SOK/NEWMAP/QCBS/O1/17 / Procurement of consultant Component 1: Erosion and Quality And Cost- Open - Under for Designs of Eight (8) IDA / 51050 Watershed Management Prior 1,750,000.00 1,145,836.48 2017-02-02 2017-02-16 2017-04-13 2017-04-27 2017-05-11 2017-06-01 2017-06-22 2019-05-23 Based Selection International Implementation and Supervision of Ten (10) Infrastructure Investments erosion/flood sites. SOK/NEWMAP/CQS/O1/17 / Consultant Procurement of consultant Component 4: Project Pending IDA / 51050 Post Qualification Open - National 297,000.00 0.00 2017-02-13 2017-02-27 2017-03-06 2017-03-13 2017-04-03 2017-05-01 for Designs of Two (2) Management Implementation Selection erosion/flood sites. Page 3 SOK/NEWMAP/CQS/O2/17 / Consultant Generation of LRID for / Component 4: Project IDA / 51050 Post Qualification Open - National 200,000.00 149,480.83 Completed 2017-02-08 2017-02-15 2017-04-10 2017-04-10 2017-05-01 2018-01-06 erosion and watershed Management Selection management. SOK/NEWMAP/CQS/O3/17 / Component 1: Erosion and Consultant Consultancy for sensitization, Pending IDA / 51050 Watershed Management Prior Qualification Open - National 100,000.00 0.00 2017-01-03 2017-01-17 2017-02-14 2017-02-21 2017-03-14 2017-11-19 design and supervision of Implementation Infrastructure Investments Selection water harvesting systems. Component 1: Erosion and Consultant SOK/NEWMAP/CQS/O4/17 / IDA / 51050 Watershed Management Post Qualification Open - National 200,000.00 152,515.69 Signed 2017-02-06 2017-02-08 2017-03-17 2017-03-31 2017-04-21 2019-10-08 Engagement of Focal NGO Infrastructure Investments Selection SOK/NEWMAP/CQS/O5/17 / Component 1: Erosion and Consultant Consultancy for integrated Pending IDA / 51050 Watershed Management Post Qualification Open - National 100,000.00 0.00 2017-01-16 2017-02-08 2017-03-17 2017-03-31 2017-04-21 2017-07-20 subwatershed management Implementation Infrastructure Investments Selection and monitoring. SOK/NEWMAP/CQS/O6/17 / Component 1: Erosion and Consultant Pending Consultancy for RAP studies IDA / 51050 Watershed Management Post Qualification Open - National 100,000.00 0.00 2017-02-08 2017-03-03 2017-03-24 2017-03-31 2017-04-21 2017-07-20 Implementation for 10 priority project sites Infrastructure Investments Selection SOK/NEWMAP/CQS/O7/17 / Consultancy for Livelihood Consultant Component 4: Project Pending Needs Assesment for IDA / 51050 Post Qualification Open - National 100,000.00 0.00 2017-01-24 2017-02-08 2017-03-17 2017-03-31 2017-04-21 2017-07-20 Management Implementation Communities in all the 10 Selection sites. SOK/NEWMAP/CQS/O8/17 / Consultant Component 4: Project Consultancy for M & E IDA / 51050 Post Qualification Open - National 100,000.00 70,869.76 Completed 2017-01-10 2017-02-08 2017-03-17 2017-03-31 2017-04-21 2017-07-20 Management Baseline for State Selection SOK/NEWMAP/CQS/O9/17 / Consultant Consultancy for ESMP Component 4: Project Pending IDA / 51050 Post Qualification Open - National 100,000.00 0.00 2017-01-23 2017-02-08 2017-03-17 2017-03-31 2017-04-21 2017-07-20 Studies for the 10 Project Management Implementation Selection Sites SOK/NEWMAP/CQS/011/017 / Consultancy for the GIS survey of the state to map Component 1: Erosion and Consultant Under erosion sites, infrastructure, IDA / 51050 Watershed Management Post Qualification Open - National 200,000.00 0.00 2017-02-08 2017-03-08 2017-04-13 2017-04-27 2017-05-11 2017-10-08 Implementation watersheds, wetlands and Infrastructure Investments Selection drainage basins in Sokoto state INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual SOK/NEWMAP/IC/10/17 / Individual Component 4: Project Engagement of Procurement IDA / 51050 Post Consultant Open 50,000.00 41,250.00 Completed 2017-02-08 2017-03-15 2017-03-29 2017-04-26 2018-04-26 Management consultant. Selection SOK/NEWMAP/CS/IC/01/20 Component 2: Erosion and / Consultancy for Individual Watershed Management Under development of watershed IDA / 51050 Post Consultant Open 100,000.00 0.00 2019-03-18 2019-05-06 2019-05-27 2019-07-01 2019-12-28 Institutions and Information Implementation management plans for 3 Selection Services sites. Page 4