Public Disclosure Copy The World Bank Implementation Status & Results Report GY Flood Risk Management (P147250) GY Flood Risk Management (P147250) LATIN AMERICA AND CARIBBEAN | Guyana | Social, Urban, Rural and Resilience Global Practice Global Practice | IBRD/IDA | Investment Project Financing | FY 2014 | Seq No: 5 | ARCHIVED on 15-Nov-2016 | ISR25750 | Implementing Agencies: Agriculture Sector Development Unit (ASDU), Ministry of Agriculture Key Dates Key Project Dates Bank Approval Date:04-Jun-2014 Effectiveness Date:25-Nov-2014 Planned Mid Term Review Date:06-Feb-2017 Actual Mid-Term Review Date:-- Original Closing Date:31-Jan-2019 Revised Closing Date:31-Jan-2019 Project Development Objectives Project Development Objective (from Project Appraisal Document) The objective of the project is to reduce the risk of flooding in the low-lying areas of the East Demerara. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Priority Works for Flood Risk Reduction:(Cost $10.30 M) Institutional Strengthening for Flood Risk Reduction:(Cost $0.40 M) Project Management and Implementation Support:(Cost $1.20 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Satisfactory  Satisfactory Overall Implementation Progress (IP)  Satisfactory  Moderately Satisfactory Overall Risk Rating  Moderate  Moderate Implementation Status and Key Decisions 11/15/2016 Page 1 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report GY Flood Risk Management (P147250) The Ministry of Agriculture has completed the consultancies that will inform the works, and has published tender documents for the major bid packages i.e. Construction of the North Eastern Dams, the Construction of Pump Stations and the Supply and Delivery of Earth Moving Equipment. Risks 11/15/2016 Page 2 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report GY Flood Risk Management (P147250) Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance  --  Moderate  Moderate Macroeconomic  --  Moderate  Moderate Sector Strategies and Policies  --  Low  Low Technical Design of Project or Program  --  Moderate  Moderate Institutional Capacity for Implementation and Sustainability  --  Substantial  Substantial Fiduciary  --  Moderate  Moderate Environment and Social  --  Low  Low Stakeholders  --  Moderate  Moderate Other  --  --  -- Overall  --  Moderate  Moderate Results Project Development Objective Indicators PHINDPDOTBL  Area with improved protection against breach of EDWC dams (Hectare(Ha), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 15700.00 Date 31-Aug-2014 05-May-2016 10-Nov-2016 31-Jan-2019 PHINDPDOTBL  Area provided with irrigation and drainage services (ha) (Hectare(Ha), Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 7864.00 Date 31-Aug-2014 05-May-2016 10-Nov-2016 31-Jan-2019 PHINDPDOTBL  Area provided with irrigation and drainage services - New (ha) (Hectare(Ha), Core Breakdown) Baseline Actual (Previous) Actual (Current) End Target 11/15/2016 Page 3 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report GY Flood Risk Management (P147250) Value 0.00 0.00 0.00 0.00 Date 31-Aug-2014 05-May-2016 10-Nov-2016 31-Jan-2019 PHINDPDOTBL  Area provided with irrigation and drainage services - Improved (ha) (Hectare(Ha), Core Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 7864.00 Date 31-Aug-2014 05-May-2016 10-Nov-2016 31-Jan-2019 Overall Comments Intermediate Results Indicators PHINDIRITBL  Direct project beneficiaries (Number, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 113066.00 Date 31-Aug-2014 05-May-2016 05-May-2016 31-Jan-2019 PHINDIRITBL  Female beneficiaries (Percentage, Core Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 51.00 11/15/2016 Page 4 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report GY Flood Risk Management (P147250) PHINDIRITBL  Water users provided with new/improved irrigation and drainage services (number) (Number, Core) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 47638.00 Date 31-Aug-2014 05-May-2016 05-May-2016 31-Jan-2019 PHINDIRITBL  Water users provided with irrigation and drainage services - female (number) (Number, Core Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 24010.00 Date 31-Aug-2014 05-May-2016 05-May-2016 31-Jan-2019 PHINDIRITBL  Adoption of operational procedures and surveillance systems for the EDWC dams (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N Y Y Y Date 31-Aug-2014 05-May-2016 05-May-2016 31-Jan-2019 PHINDIRITBL  Length of dam upgraded (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 4.00 Date 31-Aug-2014 05-May-2016 05-May-2016 31-Jan-2019 11/15/2016 Page 5 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report GY Flood Risk Management (P147250) PHINDIRITBL  Increased drainage capacity (capacity of drainage pumps or canals) (Cubic Meter(m3), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 31-Aug-2014 05-May-2016 05-May-2016 31-Jan-2019 PHINDIRITBL  Expanded meteorological, hydrological monitoring network installed and active (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N N N Y Date 31-Aug-2014 05-May-2016 05-May-2016 31-Jan-2019 PHINDIRITBL  Adoption of dam safety measures including procedures for emergency preparedness in case of dam breach (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value N Y Y Y Date 31-Aug-2014 05-May-2016 05-May-2016 31-Jan-2019 Overall Comments Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P147250 IDA-54740 Effective XDR 7.70 7.70 0.00 1.91 5.79 25% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P147250 IDA-54740 Effective 04-Jun-2014 10-Oct-2014 25-Nov-2014 31-Jan-2019 31-Jan-2019 11/15/2016 Page 6 of 7 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report GY Flood Risk Management (P147250) Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 11/15/2016 Page 7 of 7 Public Disclosure Copy