Procurement Plan Urban Development Project July 9, 2010 PROCUREMENT Kyrgyz Republic : Urban Development Project PLAN General Information Country: Kyrgyz Republic Bank’s Approval Date of the Original Procurement Plan: 2017-02-23 2019-07-19 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P151416 GPN Date: Project Name: Urban Development Project Loan / Credit No: TF / 19293, IDA / 57620, IDA / D1010, TF / A1993 Executing Agency(ies): Community Development and Investment Agency WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual IDA-UDP-CW-2017-3 / Single Stage - One Improvement of street IDA / 57620 Post Request for Bids Open - National 144,840.63 Signed 2017-05-21 2017-05-26 2017-07-07 2017-07-27 2017-08-31 2018-02-27 Envelope lightning in Toktogul/ IDA-UDP-CW-17-1 / "Rehabilitation of water Single Stage - One supply system in Kerben IDA / 57620 Post Request for Bids Open - National 2,984,436.44 Signed 2017-10-17 2017-10-22 2017-12-03 2018-01-02 2018-02-06 2018-08-05 Envelope city, Djalal-Abad oblast" (2 lots). IDA-UDP-CW-2017-4 / Request for Single Stage - One Improvement of street IDA / 57620 Post Open - National 0.00 Canceled 2018-02-06 2018-02-11 2018-03-24 2018-04-23 2018-05-28 2019-01-10 Proposals Envelope lightning in Balykchy IDA-UDP-CW-2018-5 / Construction works of Single Stage - One IDA / 57620 Post Request for Bids Open - National 849,451.05 Signed 2018-04-29 2018-05-04 2018-06-15 2018-07-15 2018-08-19 2019-02-15 Aytmatov school, Balykchy Envelope city. IDA-UDP-CW-2018-6 / Construction works of Single Stage - One IDA / 57620 Post Request for Bids Open - National 884,766.49 Signed 2018-04-29 2018-05-04 2018-06-15 2018-07-15 2018-08-19 2019-02-15 Toktogul school, Toktogul Envelope city IDA-UDP-CW-2018-2 / Rehabilitation of water Single Stage - One IDA / 57620 Post Request for Bids Open - National 3,194,335.04 Signed 2018-04-25 2018-05-04 2018-06-15 2018-07-15 2018-08-19 2019-11-30 supply system in Sulyukta Envelope city Batken oblast (5 Lots) IDA-UDP-CW-2018-7 / Construction works of Single Stage - One Jakypov school and Ak-Tilek TF / A1993 Post Request for Bids Open - National 740,789.72 Signed 2018-08-10 2018-08-15 2018-09-26 2018-10-26 2018-11-30 2019-05-29 Envelope kindergarten, Balykchy city (2 Lots) IDA-UDP-CW-2018-8 / Construction works of Single Stage - One Bokonbaev school and Archa- TF / A1993 Post Request for Bids Open - National 1,154,757.65 Signed 2018-08-10 2018-08-15 2018-09-26 2018-10-26 2018-11-30 2019-05-29 Envelope Beshik kindergarten, Toktogul city (2 Lots) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 ARIS-UDP-G-18-1 / Purchase of special machinery (back loading Single Stage - One TF / A1993 Post Request for Bids Open - National 131,057.90 Signed 2018-08-10 2018-08-17 2018-09-28 2018-10-28 2018-12-02 2019-05-31 waste machinery) for Envelope Toktogul, Kerben, Balykchy and Sulyukta towns NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual UDP PPG-FBS-2015-3 / Preparation of Feasibility Fixed Budget Open - Studies and Detailed Designs TF / 19293 Prior 346,000.00 Signed Selection International of water supply systems in Sulukta and Kerben UDP PPG-QCBS-2016-4 / Preparation of Feasibility Studies and Designs for Improved Seismic Safety and Quality And Cost- Open - IDA / 57620 Prior 647,522.22 Signed Energy Efficiency of Schools Based Selection International and Kindergartens and Technical Supervision of construction. ARIS-AUDIT-LCS-2017-1 / Least Cost Open - IDA / 57620 Post 71,433.00 Signed 2017-10-17 2017-11-07 2017-12-21 2018-01-18 2018-02-17 2018-03-24 2018-04-28 2018-10-25 Audit of project funds Selection International Consultant IDA-UDP-CQ-2019-3 / Pending IDA / 57620 Post Qualification Open - National 0.00 2020-01-30 2020-02-20 2020-04-04 2020-05-04 2020-06-08 2020-12-05 Impact Assesment Implementation Selection IDA-UDP-CS-CQS-2018-1 / Consultant Contract supervision for IDA / 57620 Post Qualification Open - National 145,010.04 Signed 2018-10-03 2018-10-24 2018-12-07 2019-01-06 2019-02-10 2019-08-09 schools local company Selection IDA-UDP-CQS-2018-2 / Consultants services to carry out hydrogeological studies of Consultant Under springs pinching out on the IDA / 57620 Post Qualification Open - National 0.00 2019-03-05 2019-03-26 2019-05-09 2019-06-08 2019-07-13 2020-01-09 Implementation left bank of the Padysha-Ata Selection river in Kerben town, Jalal- Abad oblast INDIVIDUAL CONSULTANTS Page 2