The World Bank Implementation Status & Results Report Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose) (P152281) Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose) (P152281) LATIN AMERICA AND CARIBBEAN | Bolivia | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 4 | ARCHIVED on 01-May-2019 | ISR36318 | Implementing Agencies: Administradora Boliviana de Carreteras (ABC), Plurinational State of Bolivia Key Dates Key Project Dates Bank Approval Date: 11-Jan-2017 Effectiveness Date: 21-Dec-2017 Planned Mid Term Review Date: 09-Dec-2019 Actual Mid-Term Review Date: -- Original Closing Date: 31-Dec-2021 Revised Closing Date: 31-Dec-2021 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The Project Development Objective (PDO) is to improve transport accessibility along the road corridor between San Ignacio de Velasco and San Jose de Chiquitos. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Road Upgrading:(Cost $225.05 M) Technical Studies and Project Management:(Cost $5.00 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions The Contractor for the San Ignacio-San Jose Road signed a contract for the road construction works in September 2018. The supervision consultant is being procured. The road contract implementation will be expected to initiate with both on board soon thereafter, with the undertaking of all the necessary preparatory and mobilization work. 5/1/2019 Page 1 of 6 The World Bank Implementation Status & Results Report Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose) (P152281) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Moderate Moderate Substantial Macroeconomic Moderate Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Sustainability High High High Fiduciary Substantial Substantial Substantial Environment and Social Substantial Moderate Substantial Stakeholders Moderate Moderate Moderate Other -- -- -- Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes Improve transport accessibility along the San Ignacio-San Jose road corridor IN00680599 ►Travel time along the project area (Hours, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 5.00 5.00 4.62 2.50 Date 16-Dec-2015 19-Sep-2018 08-Apr-2019 31-Dec-2020 IN00680600 ►Vehicle Operating Cost - Cars (Amount(USD), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.37 0.37 0.33 0.21 Date 16-Dec-2015 19-Sep-2018 08-Apr-2019 31-Dec-2020 IN00680646 ►Vehicle Operating Cost - Trucks (Amount(USD), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 2.50 2.50 2.39 1.60 Date 16-Dec-2015 19-Sep-2018 08-Apr-2019 31-Dec-2020 5/1/2019 Page 2 of 6 The World Bank Implementation Status & Results Report Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose) (P152281) Overall Comments PDO There are slight improvements in the indicators due to intermediate works between the baseline and today with gravel road improvements done by Government to keep the road motorable. Intermediate Results Indicators by Components Road Upgrading IN00680647 ►Roads constructed, non-rural (Kilometers, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 208.00 Date 31-Dec-2015 19-Sep-2018 08-Apr-2019 31-Dec-2020 Technical Studies and Project Management IN00680648 ►DBMOT bid documents prepared for San Matias - San Ignacio de Velasco road (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 31-Dec-2015 19-Sep-2018 08-Apr-2019 31-Dec-2020 Terms of reference have been prepared in March 2019. Comments: IN00680649 ►Direct project beneficiaries (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 125,000.00 125,000.00 125,000.00 135,325.00 Date 31-Dec-2015 19-Sep-2018 08-Apr-2019 31-Dec-2020 IN00680650 Female beneficiaries (Percentage, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 50.00 50.00 50.00 50.00 IN00680651 ►Road users satisfied with quality of roads disaggregated by gender and user mode (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 11.30 11.30 11.30 70.00 5/1/2019 Page 3 of 6 The World Bank Implementation Status & Results Report Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose) (P152281) Date 31-Dec-2015 19-Sep-2018 08-Apr-2019 31-Dec-2020 IN00680652 Road Users Satisfaction - Male Passengers (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 17.00 17.00 17.00 70.00 Date 31-Dec-2015 19-Sep-2018 08-Apr-2019 31-Jul-2020 IN00680653 Road Users Satisfaction - Female Passengers (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 12.00 12.00 12.00 70.00 Date 31-Dec-2015 19-Sep-2018 08-Apr-2019 31-Dec-2020 IN00680654 Road Users Satisfaction - Male Drivers (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 6.00 6.00 6.00 70.00 Date 31-Dec-2015 19-Sep-2018 08-Apr-2019 31-Dec-2020 IN00680655 ►Social Inclusion and Gender (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- No Yes Date 11-Jul-2016 19-Sep-2018 08-Apr-2019 31-Dec-2020 IN00680656 Improvement of access to water in indigenous communities (Text, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 4.00 Date 11-Jul-2016 19-Sep-2018 08-Apr-2019 31-Dec-2020 IN00680657 Training of construction workers on gender, gender based violence prevention and HIV/AIDS/STD (Text, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0% -- 0% 100% Date 11-Jul-2016 19-Sep-2018 08-Apr-2019 31-Dec-2020 IN00680658 Ayoreo women and men trained on HIV/AIDS/STD and Tuberculosis prevention, working in their communities. (Text, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 0.00 10.00 5/1/2019 Page 4 of 6 The World Bank Implementation Status & Results Report Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose) (P152281) Date 11-Jul-2016 19-Sep-2018 08-Apr-2019 31-Dec-2020 IN00680659 ►iRAP surveys completed showing any trends/improvements in road safety along the corridor (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 31-Dec-2015 19-Sep-2018 08-Apr-2019 31-Dec-2020 IN00680660 ►Traffic accidents on the San Ignacio de Velasco - San Jose de Chiquitos road corridor reported (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes Date 03-Aug-2016 19-Sep-2018 08-Apr-2019 31-Dec-2020 Overall Comments IR Many of the indicators will be updated after the full onboarding of the supervision consultant (expected mid- 2019). Special emphasis will be made to capture the values for the citizen engagement indicator and sub- indicators included in the project on road user satisfaction (including gender disaggregation), and fortifying the grievance redress mechanism and engagement with citizens. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P152281 IBRD-86480 Effective USD 200.00 200.00 0.00 0.50 199.50 0.3% P152281 IDA-59030 Effective USD 30.00 30.00 0.00 12.46 17.54 42% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P152281 IBRD-86480 Effective 11-Jan-2017 02-Feb-2017 21-Dec-2017 31-Dec-2021 31-Dec-2021 P152281 IDA-59030 Effective 11-Jan-2017 02-Feb-2017 21-Dec-2017 31-Dec-2021 31-Dec-2021 Cumulative Disbursements 5/1/2019 Page 5 of 6 The World Bank Implementation Status & Results Report Santa Cruz Road Corridor Connector Project (San Ignacio - San Jose) (P152281) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 5/1/2019 Page 6 of 6