Procurement Plan – Additional financing (AF) USD 27,000,000-TSRP- I. General 1. Project information: Country: Republic of Cabo Verde Borrower: Government of the Republic of Cabo Verde Project Name: Additional financing (AF) Transport Sector Reform Project ID: P126516 Credit No.: IDA 6100 Project Implementing Agency (PIA): Project Coordination Unit (PCU), located at the Ministry of Finance- MF. Implementation of Procurement: Procurement activities will be carried out by the PCU except for the road works activities which will be carried-out by the Road Institute under the supervision of the PCU. 2. Date of General Procurement Notice: May 26, 2013 3. Period covered by this procurement plan: January to December 2018. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Prior Review No. Comments Method Threshold 1. ICB and LIB = or ICB and LIB for goods will be used for (Goods) >US$2,000,000 US$500,000 and above 2. NCB (Goods) = or NCB for goods will be used for less than >US$2,000,000 US$500,000 3. ICB (Works) = or ICB for works will be used for >US$10,000,000 US$5,000,000 and above 4. NCB (Works) = or NCB for works will be used for less than >US$10,000,000 US$5,000,000 5. ICB (Non- = or ICB for non-consultant services will be used Consultant >US$2,000,000 for US$2,000,000 and above Services), if any 6. NCB (Non- = or NCB for non-consultant services will be Consultant >US$2,000,000 used for less than US$2,000,000 Services) 7. Shopping None Shopping for goods and non-consultants services, will be used for less than or equivalent to US$100,000. For works, it will be used for less than or equivalent to US$200,000. Shopping in the = or >US$200,000 This method will be used only in case of case of emergency emergency situation when a more competitive method cannot be used. All contracts under this procedure will be audited. 8. Direct contracting . Works: = or > The thresholds for competitive bidding US$ 10,000,000 processes for contracts of same nature apply . Goods : = or > US$ 2,000,000 2. Prequalification. None. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: No CDD component in the project design. 4. Reference to (if any) Project Operational/Procurement Manual: (i) Project Implementation Manual, and (ii) financial management manual. 5. Any Other Special Procurement Arrangements: None. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: No. Selection Method Prior Review Comments Threshold 1. Competitive Methods (Firms) = or >US$1,000,000 None 2. Single Source (Firms) = or >US$1,000,000 The thresholds for competitive bidding processes for selection of firms apply 3. Individual Consultants = or >US$300,000 None 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 300,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None CQS-The contracts for services estimated to cost the equivalent of US$200,000 or less per contract may be procured under contracts based on Consultants' Qualifications in accordance with the provisions of paragraphs 3.1 and 3.7 of the Consultant Guidelines. Individual Consultants-Consulting services meeting the requirements of Section V of the Consultant Guidelines may be selected under the provisions for the Selection of Individual Consultants, i.e. in essence through the comparison of the qualifications of at least three (3) qualified individuals. All TORs, regardless of the estimated cost of the contract, must be submitted to the World Bank for prior review. PROCUREMENT Cabo Verde : Cabo Verde - Transport Sector Reform Project PLAN General Information Country: Cabo Verde Bank’s Approval Date of the Original Procurement Plan: 2018-03-13 2019-11-12 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P126516 GPN Date: Project Name: Cabo Verde - Transport Sector Reform Project Loan / Credit No: IDA / 52660, IDA / 61000 Executing Agency(ies): TRANSPORT SECTOR REFORM WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FA O017 / Rehabitation Component 1 : Road Asset Single Stage - One IDA / 61000 A priori Appel d'offres Limited 3,500,000.00 9,203,762.71 Signé 2017-08-10 2017-08-15 2017-09-26 2017-10-26 2017-11-30 2018-05-29 route Santo Antao Preservation Envelope FA O019 / Travaux Component 1 : Road Asset Single Stage - One d'urgence de l'île de IDA / 61000 A posteriori Appel d'offres Limited 2,500,000.00 963,091.44 Signé 2017-08-10 2017-08-15 2017-09-26 2017-10-26 2017-11-30 2018-05-29 Preservation Envelope Santiago FA O018 / Réhabilitation Component 1 : Road Asset Single Stage - One IDA / 61000 A posteriori Appel d'offres Limited 2,500,000.00 0.00 Annulé 2017-08-10 2017-08-15 2017-09-26 2017-10-26 2017-11-30 2018-05-29 route Piorno Fogo Preservation Envelope Passation de O 020 / 2 PH DE L'ÎLE Component 1 : Road Asset IDA / 52660 A priori marché de gré à Direct 350,000.00 0.00 Annulé 2017-07-31 2017-08-05 2017-09-09 2018-03-08 DE FOGO Preservation gré O-020 / Réhabilitation route à aménager en pavés Chã de Tanque-Entre Picos de Component 1 : Road Asset Single Stage - One Reda, + manutention + IDA / 61000 A posteriori Appel d'offres Open - National 4,000,000.00 4,167,024.58 Signé 2018-05-14 2018-05-19 2018-06-30 2018-07-30 2018-09-03 2020-03-04 Preservation Envelope amélioration + travaux urgences Lot 03 sur l'île de Santiago. O-021 / Réhabilitation route à aménager en pavés - Ribeira dos Picos + Component 1 : Road Asset Single Stage - One IDA / 61000 A posteriori Appel d'offres Open - National 4,900,000.00 4,263,946.98 Résilié 2018-05-14 2018-05-19 2018-06-30 2018-07-30 2018-09-03 2020-03-04 manutention + amélioration Preservation Envelope + travaux urgences Lot 02 sur l'île de Santiago. O-022 / Réhabilitation route à aménager en pavés - Cidade Velha - Santa Ana + Component 1 : Road Asset Single Stage - One IDA / 61000 A posteriori Appel d'offres Open - National 4,000,000.00 3,169,704.78 Signé 2018-05-14 2018-05-19 2018-06-30 2018-07-30 2018-09-03 2020-03-04 manutention + amélioration Preservation Envelope + travaux urgences Lot 04 sur l'île de Santiago TSRP-O-023 / REMADOR pour les travaux de Réhabilitation de la route EN3-ST-19 Bretelle EN1-ST- Component 1 : Road Asset Single Stage - One IDA / 61000 A posteriori Appel d'offres Open - National 3,100,000.00 4,561,539.70 Signé 2018-08-10 2018-08-15 2018-09-26 2018-10-26 2018-11-30 2020-05-31 01 - Chão de Formoso/Gil Preservation Envelope Bispo (12,2 kilomètre) et d'entretien des routes de l´île de Santiago- Lote 5 O-024- TSRP / Travaux d'urgence dans l`Île de Fogo Passation de Component 1 : Road Asset sur un route en pavé (EN1- IDA / 61000 A posteriori marché de gré à Direct 650,000.00 689,361.95 Signé 2018-08-30 2018-09-10 2018-09-12 2018-12-11 Preservation FG-01), au km 47+927, dans gré le région de Sumbango Page 1 AV O 17-TSRP / Travaux de réhabilitation de route Passation de Component 1 : Road Asset EN3-SA-10, Chã de Escudela IDA / 61000 A posteriori marché de gré à Direct 400,000.00 392,562.85 Signé 2019-04-26 2019-04-26 2019-04-30 2020-06-30 Preservation - Tarrafal de Monte Trigo, gré dans l'île de Santo Antão. TSRP- O 025 / REHABILITATION DE LA ROUTE EN3-BR-02 – VILA NOVA SINTRA/NOSSA SENHORA DO MONTE ET Component 1 : Road Asset Single Stage - One REHABILITATIONS IDA / 61000 A posteriori Appel d'offres Open - National 2,300,000.00 1,903,616.04 Signé 2019-07-26 2019-07-31 2019-08-30 2019-09-29 2019-12-21 2020-11-28 Preservation Envelope PONCTUELLES SUR LA ROUTE EN3-BR-03 – BRETELLE EN3-BR- 02/ESPERADINHA sur l’île de Brava O-021 R-TSRP / Réhabilitation route à aménager en pavés - Ribeira Component 1 : Road Asset Single Stage - One dos Picos + manutention + IDA / 61000 A posteriori Appel d'offres Open - National 4,200,000.00 4,104,402.32 Signé 2018-10-01 2018-10-29 2018-11-19 2019-04-15 2019-05-30 2020-12-31 Preservation Envelope amélioration + travaux urgences Lot 02 sur l'île de Santiago. GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 2 : Institutional Passation de B-010 / Supply of software IDA / 61000 Strengthening and Project A posteriori marché de gré à Direct 15,000.00 13,988.81 Signé 2018-04-20 2018-08-17 2018-11-06 2019-05-05 Management gré TSRP- B-011 / « Upgrade du software » primavera de Component 4 : Inter-island Single Stage - One En attente IDA / 61000 A posteriori Demande de prix Limited 50,000.00 0.00 2019-11-14 2019-12-19 2020-06-16 l'Institut Maritime Transport Strategy Envelope d'exécution Portuaire (IMP). NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual FA C038 / Supervision de Sélection fondée la route de Chã de Escudela- Component 1 : Road Asset Open - IDA / 61000 A posteriori sur la qualité et 75,000.00 0.00 Annulé 2017-08-25 2017-09-15 2017-10-29 2017-11-26 2017-12-26 2018-01-30 2018-03-06 2019-03-06 Tarrafal de Monte Trigo-l'île Preservation International le coût de Santo Antão FA C040 / Supervision de Sélection fondée Component 1 : Road Asset Open - la route de Campanas de IDA / 61000 A posteriori sur la qualité et 50,000.00 0.00 Annulé 2017-08-25 2017-09-15 2017-10-29 2017-11-26 2017-12-26 2018-01-30 2018-03-06 2019-03-06 Preservation International Cima-Piorno-l'île de Fogo le coût Page 2 FA C039 / Supervision des Sélection fondée Component 1 : Road Asset Open - travaux d'urgence de l'île de IDA / 61000 A posteriori sur la qualité et 50,000.00 0.00 Annulé 2017-08-25 2017-09-15 2017-10-29 2017-11-26 2017-12-26 2018-01-30 2018-03-06 2019-03-06 Preservation International Santiago le coût Sélection fondée TSRP-C050 / Study to sur les IDA / 61000 Component 3: Road Safety A posteriori Open - National 100,000.00 100,000.00 Signé 2018-04-30 2018-05-21 2018-07-04 2018-08-03 2018-09-07 2019-03-06 restructure the DGTR qualifications des consultants Sélection fondée TSRP-C049 / Study on the sur les causes of road accidents in IDA / 61000 Component 3: Road Safety A posteriori Open - National 40,000.00 120,000.00 Signé 2018-04-30 2018-05-21 2018-07-04 2018-08-03 2018-09-07 2019-03-06 qualifications des Cabo Verde consultants TSRP-C038 / Supervision of the rehabilitation of road Component 1 : Road Asset Sélection au Chã de Escudela-Tarrafal de IDA / 61000 A posteriori Open - National 95,000.00 86,558.40 Signé 2017-09-01 2017-09-06 2017-10-24 2017-11-24 2017-12-20 2018-03-01 2018-04-18 2020-06-18 Preservation moindre coût Monte Trigo in Santo Antão Island. TSRP-C039 / Supervision of the rehabilitation of Component 1 : Road Asset Sélection au IDA / 61000 A posteriori Open - National 60,000.00 55,706.18 Signé 2017-09-01 2017-09-06 2017-10-24 2017-11-24 2017-12-20 2018-03-01 2018-04-18 2019-06-02 emergency works in Santiago Preservation moindre coût Island. TSRP-C060 / Contrôle et Surveillance des Travaux de la Route ER-ST-09, Pedra Badejo-Ribeira dos Picos, sur Sélection fondée Component 1 : Road Asset L'ile de Santiago (7,5 IDA / 61000 A posteriori sur la qualité et Open - National 140,000.00 194,922.67 Signé 2018-05-23 2018-06-20 2018-08-03 2018-08-31 2018-09-30 2018-11-04 2018-12-09 2020-05-02 Preservation Kilomètres) Et la Route EN3- le coût ST-06, Cidade Velha - Santana sur l'ile de Santiago (12,5 Kilomètres). TSRP-C053 / Contrôle et Surveillance des Travaux de la Route ER-ST-08, Entroncamento EN3-ST- Sélection fondée 22_Entre Picos de Reda Sur Component 1 : Road Asset IDA / 61000 A posteriori sur la qualité et Open - National 145,000.00 159,365.30 Signé 2018-05-23 2018-06-21 2018-08-04 2018-09-01 2018-10-01 2018-11-05 2018-12-10 2020-05-03 L'ile de Santiago (10 Preservation le coût Kilomètres) et Entroncamento EN1-ST-01 - Chão de Formoso/Gil Bispo (12,2 Kilomètres) TSRP-C047 / CONSULTING SERVICES TO CONDUCT A STUDY ON IMPROVING Sélection fondée THE EFFICIENCY AND Component 4 : Inter-island Open - IDA / 61000 A posteriori sur la qualité et 100,000.00 135,614.54 Signé 2018-06-20 2018-08-10 2018-09-23 2018-10-21 2018-11-20 2018-12-25 2019-01-29 2019-07-28 EFFICACY OF THE Transport Strategy International le coût AUTONOMOUS FUND FOR ROAD MAINTENANCE (FAMR). TSRP-C052 / Definition de Sélection fondée la Comission de Prévention Component 4 : Inter-island sur les IDA / 61000 A posteriori Open - National 100,000.00 0.00 Annulé 2018-08-31 2018-09-21 2018-11-04 2018-12-04 2019-01-08 2019-07-07 et Investigation des Transport Strategy qualifications des Accidents Maritimes consultants TSRP-C 055 / Climate Change and Natural Hazard Vulnerability and Risk Sélection fondée Component 4 : Inter-island Open - Assessment and Climate IDA / 61000 A posteriori sur la qualité et 400,000.00 376,000.00 Signé 2018-06-27 2018-08-10 2018-09-23 2018-10-21 2018-11-20 2018-12-25 2019-01-29 2020-01-29 Transport Strategy International Resilience and Adaptation le coût Strategy for the Cabo Verde Road Network. Page 3 TSRP-C055 / Climate Change and Natural Hazard Vulnerability and Risk Sélection fondée Component 4 : Inter-island Open - Assessment and Climate IDA / 61000 A priori sur la qualité et 400,000.00 0.00 Annulé 2018-06-27 2018-08-10 2018-09-23 2018-10-21 2018-11-20 2018-12-25 2019-01-29 2020-01-29 Transport Strategy International Resilience and Adaptation le coût Strategy for the Cabo Verde Road Network Sélection fondée TSRP-C067 / Révision et Component 4 : Inter-island sur les Open - En attente plan de réforme de l'aviation IDA / 61000 A posteriori 200,000.00 0.00 2019-01-24 2019-02-14 2019-03-30 2019-04-29 2019-06-03 2019-11-30 Transport Strategy qualifications des International d'exécution civil au Cabo Verde consultants TSRP-C 064 / Sélection fondée TRANSACTION ADVISOR Component 4 : Inter-island sur les Open - En cours FOR THE PREPARATION IDA / 61000 A posteriori 200,000.00 0.00 2019-02-01 2019-02-22 2019-04-07 2019-05-07 2019-06-11 2020-06-10 Transport Strategy qualifications des International d'examen OF PRIVATIZATION consultants MODEL OF CV HANDLING TSRP-C 069 / ASSISTANCE TECHNIQUE A LA DIRECTION Sélection fondée GENERALE DE sur les TRANSPORTS ET IDA / 61000 Component 3: Road Safety A posteriori Open - National 120,000.00 147,267.73 Signé 2019-03-27 2019-04-03 2019-05-17 2019-06-16 2019-07-21 2020-07-15 qualifications des SECURITÉ ROUTIERE consultants (DGTR) - Mise à jour de la plateforme d'ordinateur SIGR. TSRP-C 071 / Assistance Sélection fondée Technique pour la mise en Component 4 : Inter-island sur les IDA / 61000 A posteriori Open - National 120,000.00 121,600.54 Signé 2019-03-31 2019-04-21 2019-06-04 2019-07-04 2019-08-08 2020-06-03 œuvre de Système de Transport Strategy qualifications des Gestion de Qualité LEC. consultants TSRP- C 072 / Contrôle et Sélection fondée Surveillance des Travaux de Component 1 : Road Asset sur les En cours IDA / 61000 A posteriori Open - National 60,000.00 0.00 2019-05-14 2019-06-04 2019-07-18 2019-08-17 2019-09-21 2020-10-14 Réhabilitation des deux Preservation qualifications des d'exécution routes sur l'île de BRAVA. consultants Sélection fondée TSRP-C058 / STRATEGIC Component 4 : Inter-island sur les Open - PLAN FOR TRANSPORT IDA / 61000 A posteriori 150,000.00 0.00 Annulé 2018-08-07 2018-08-28 2018-10-11 2018-11-10 2018-12-15 2019-10-11 Transport Strategy qualifications des International AND INFRASTRUCTURE consultants TSRP-C056 / Transaction Sélection fondée Advisor pour élaborer le Component 4 : Inter-island sur les Open - IDA / 61000 A posteriori 200,000.00 0.00 Annulé 2018-08-24 2018-09-14 2018-10-28 2018-11-27 2018-12-21 2019-06-19 Modèle de Concession/ Transport Strategy qualifications des International Privatisation de l'ASA consultants INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Sélection de C 044 / Restruturation de Component 4 : Inter-island IDA / 52660 A priori consultants par Direct 1,250,000.00 1,250,000.00 Signé 2017-06-18 2017-06-28 2017-09-01 2018-02-28 la dette de TACV Transport Strategy entente directe FA C032 / Avenant au Component 2 : Institutional Sélection de contrat de l'Audit Financier- IDA / 61000 Strengthening and Project A posteriori consultants par Direct 30,000.00 58,011.07 Signé 2018-03-21 2018-03-31 2018-06-04 2018-12-01 TSRP Management entente directe TSRP-C045 A / Technical Sélection de Component 4 : Inter-island Assistance to update the IDA / 61000 A priori consultants par Direct 300,000.00 298,190.65 Signé 2017-12-08 2017-12-18 2018-02-21 2018-08-20 Transport Strategy valuation of TACV entente directe Page 4 TSRP-C037 / Technical Sélection de Assistance-Determining Key Component 4 : Inter-island IDA / 52660 A priori consultants par Direct 45,000.00 40,569.95 Signé 2017-05-17 2017-05-19 2017-05-22 2017-05-22 Parameters of a Public Transport Strategy entente directe Services Obligations TSRP-C048 / Technical Component 4 : Inter-island Assistance to Maritime IDA / 61000 A posteriori Individuel Direct 50,000.00 49,800.00 Signé 2018-04-30 2018-05-10 2018-05-31 2018-07-05 2019-01-01 Transport Strategy Economy TSRP-C046 / Ex-ante evaluations 3 roads Santiago Component 4 : Inter-island IDA / 61000 A posteriori Individuel Direct 64,750.00 64,750.00 Signé 2018-03-07 2018-03-27 2018-03-29 2018-04-04 2018-10-01 and elaboration of ToRs- Transport Strategy TSRP TSRP-C051 / Assistance Technique à la règlementation du Système Component 4 : Inter-island IDA / 61000 A posteriori Individuel Direct 40,000.00 43,712.65 Signé 2018-04-16 2018-04-26 2018-05-17 2018-06-21 2018-10-19 de Certification des navires Transport Strategy du transport maritimes inter- îles. TSRP-C-054 / CVFF Asset Sélection de Component 4 : Inter-island Evaluation and Transaction IDA / 61000 A posteriori consultants par Direct 100,000.00 58,452.50 Signé 2018-07-11 2018-07-17 2018-09-20 2019-03-19 Transport Strategy Advice for Privatization entente directe TSRP-C005 / NATIONAL COORDINATOR OF THE Component 2 : Institutional PROGRAM COORDINATION IDA / 61000 Strengthening and Project A posteriori Individuel Direct 49,000.00 46,335.16 Signé 2018-06-05 2018-06-05 2018-06-05 2018-06-08 2019-06-30 OF THE TRANSPORT Management SECTOR REFORM PROJECT-TSRP Component 2 : Institutional TSRP-C006 / Program IDA / 61000 Strengthening and Project A posteriori Individuel Direct 35,000.00 30,117.85 Signé 2018-06-05 2018-06-05 2018-06-05 2018-06-08 2019-06-30 Officer Sénior - UCP-TSRP Management TSRP-C057 / ASSISTANCE TECHNIQUE A LA PREPARATION DES Component 1 : Road Asset DOCUMENTS DE IDA / 61000 A posteriori Individuel Direct 90,000.00 113,163.44 Signé 2018-05-12 2018-05-12 2018-05-12 2018-05-22 2019-05-22 Preservation SAUVEGARDE ENVIRONNEMENTALE ET SOCIALE Component 2 : Institutional TSRP-C009 / ASSISTANTE IDA / 61000 Strengthening and Project A posteriori Individuel Direct 15,000.00 11,583.79 Signé 2018-01-31 2018-01-31 2018-01-31 2018-02-15 2019-02-23 TRADUCTRICE- UCP-TSRP Management TSRP-C-059 / ASSISTANCE TECHNIQUE JURIDIQUE Component 4 : Inter-island IDA / 61000 A posteriori Individuel Direct 50,000.00 99,600.00 Signé 2018-07-24 2018-08-03 2018-08-24 2018-09-28 2019-09-28 AU MINISTERE DE Transport Strategy L'ECONOMIE MARITIME TSRP-C016 / Maritime and Component 4 : Inter-island IDA / 61000 A posteriori Individuel Direct 50,000.00 49,600.00 Signé 2017-11-07 2017-11-07 2017-11-07 2017-12-02 2018-12-01 Port Specialist Transport Strategy TSRP-C061 / Consultant Services for Cabo Verde: Climate Change Adaptation Component 4 : Inter-island IDA / 61000 A posteriori Individuel Open 50,000.00 54,882.10 Signé 2018-08-24 2018-10-03 2018-10-24 2018-11-28 2019-11-28 & Disaster Risk Transport Strategy Management Technical Advisory Consultant TSRP-C 066 / AT Component 4 : Inter-island Élaboration de la Carte de IDA / 61000 A posteriori Individuel Limited 50,000.00 44,800.00 Signé 2018-12-21 2018-12-26 2019-01-16 2019-02-20 2019-08-19 Transport Strategy la Politique des Transports Page 5 TSRP-C041 / TACV - Component 4 : Inter-island HUMAN RESOURCE IDA / 52660 A priori Individuel Direct 12,000.00 0.00 Annulé 2017-07-12 2017-07-21 2017-08-02 2017-10-12 2017-10-19 Transport Strategy CONSULTANT TSRP-C042 / TACV - Component 4 : Inter-island LOCAL LAWYER IDA / 52660 A priori Individuel Direct 12,000.00 0.00 Annulé 2017-07-12 2017-07-21 2017-07-24 2017-08-01 2017-10-12 Transport Strategy CONSULTANT TSRP-C043 / TACV - Local Component 4 : Inter-island IDA / 52660 A priori Individuel Direct 12,000.00 0.00 Annulé 2017-07-12 2017-07-21 2017-08-02 2017-10-12 2017-10-19 Psychologist Consultant Transport Strategy TSRP-C 065 / Etude Sélection de comparative des petits pays Component 4 : Inter-island IDA / 61000 A posteriori consultants par Direct 40,000.00 43,075.83 Signé 2019-01-16 2019-01-26 2019-04-01 2019-09-28 insulaires. Procédures de Transport Strategy entente directe fixation des tarifs. TSRP C 063 / ASSISTANCE TECHNIQUE À LA DIRECTION Sélection de GÉNÉRALE DES IDA / 61000 Component 3: Road Safety A posteriori consultants par Direct 20,000.00 19,531.97 Signé 2018-10-18 2018-12-13 2019-02-16 2019-08-15 TRANSPORTS ROUTIERS - entente directe Formation dans le domaine du service client. TSRP-C 068 / Senior Advisor for Civil Aviation Component 4 : Inter-island IDA / 61000 A priori Individuel Open 300,000.00 0.00 Annulé 2019-03-07 2019-04-25 2019-05-16 2019-06-20 2020-12-30 and Air Transport Sector Transport Strategy Reform in Cabo Verde TSRP C 062 / ASSISTANCE TECHNIQUE POUR APPUI AU Sélection de PROCESSUS DE MISE EN Component 4 : Inter-island IDA / 61000 A posteriori consultants par Direct 85,000.00 107,391.74 Signé 2018-12-05 2018-12-11 2019-01-15 2019-07-14 OEUVRE DE LA Transport Strategy entente directe SOLUTION POUR LE SYSTÈME DE TRANSPORT MARITIME INTER-ÎLES. TSRP-C 070 / Identification Sélection de Component 4 : Inter-island Professionnelle maritime, IDA / 61000 A posteriori consultants par Direct 60,000.00 0.00 Annulé 2019-05-03 2019-05-13 2019-07-17 2020-01-13 Transport Strategy (cédula Maritime) entente directe TSRP-C-073 / Conseiller pour le développement du Component 4 : Inter-island IDA / 61000 A posteriori Individuel Limited 50,000.00 49,800.00 Signé 2019-09-17 2019-09-22 2019-10-13 2019-11-17 2020-12-30 transport aérien à Cabo Transport Strategy Verde Page 6