FEDERAL REPUBLIC OF NIGERIA STATE EDUCATION PROGRAMME INVESTMENT PROJECT (SEPIP) Procurement Plan I. General 1. Project information: Country: Federal Republic of Nigeria Borrower: Federal Republic of Nigeria Project Name: State Education Programme Investment Project (SEPIP) Project Implementing Agency: Anambra State Government Ministry of Education Bauchi State Government Ministry of Education Ekiti State Government Ministry of Education Federal Ministry of Education Universal Basic Education Commission 2. Bank’s approval Date of the procurement Plan December 10, 2013 3. Date of General Procurement Notice: TBD 4. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 5. Prior Review Threshold Prior Review Threshold S/N Procurement Method Comments US$ ’000 1. Shopping-Works <200 None 2. International Competitive Bidding (Goods) >1000 All 3. National Competitive Bidding (Goods) <1000 None 4. Shopping (Goods) <100 None 5. Direct Contracting All values All 6. Limited International Bidding (goods) All values All 6. Prequalification: None 7. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines): None 8. Reference to (if any) Project Operational/Procurement Manual: (i) Project Implementation Manual; (ii) Procurement Manual 9. Any Other Special Procurement Arrangements: NA. 2 10. Procurement Packages with Methods and Time Schedule Procurement of Goods: A. Federal Ministry of Education Component of SEPIP Expected Estimated Domestic Review by Ref Procurement Pre or Bid- Completion Contract (Description) Cost US$ Preference Bank (Prior No. Method Post qual Opening Date '000s (yes/no) / Post) Date 1. Two Vehicle for monitoring, Vehicle insurance and June implementation support Dec. 2014 2014 89 NS Post No Post - Stationery, printing of manuals June 2. 69 NS Post No Post Dec. 2014 and operating cost 2014 3. Office Equipment and furniture consumables, photo copiers, EMIS Goods, Computers hardware , communication June equipment, Multimedia 27 NS Post No Post 2014 Dec. 2014 Projectors, Flip Chart Stands, Boards, TV/Video/Radio/Recorders, etc. 4 One Generating set 30 NS POST NO POST June Dec. 2014 2014 Total 215 B. Universal Basic Education Commission Component of SEPIP Expected Estimated Domestic Review by Ref Procurement Pre or Bid- Completion Contract (Description) Cost US$ Preference Bank (Prior No. Method Post qual Opening Date '000s (yes/no) / Post) Date 1. One Vehicle for monitoring and implementation support June Dec. 2016 2014 50 NS Post No Post Stationery, printing of manuals June 2. 50 NS Post No Post Dec. 2016 and operating cost 2014 3. Office Equipment and furniture consumables, photo copiers, EMIS Goods, Computers hardware , communication June equipment, Multimedia 100 NS Post No Post 2014 Dec. 2016 Projectors, Flip Chart Stands, Boards, TV/Video/Radio/Recorders, etc. Total 200 B. Goods – Each Participating State of Anambra, Bauchi and Ekiti 3 Domestic Review Pre- Ref. Contract Procurement Prefrence by Bank Expected Bid Opening Estimated Cost qualification Comments No. (Description) Method (Yes or (Prior Date (Yes or No) No) or Post) US$ N 000 Start Finish s Heavy duty Printing machines, computers, laptops, Dot matrix printers, UPS, Scanners, Rizo machines and Laserjet 1 contract 1 Printers 50 NS No No Post June-2014 Dec. 2016 with 2 lots Exam result sheets, flash drives, Exam question paper and accessories for printing machines (learning assessment) Network cabling, Network equipment and installation of the August- December- 2 equipments 50 NS No No Post 2014 2016 for Exam Board complex. Development of internet website (1) Procurement of laptops, Desktop computers, Printers and internet modems Equipmen Procurement March. t for 4 50 NS No No Post Sept. 2014 of training 2016 Education equipments; Districts Interactive Boards, computers, laptops, printers, multi- media projectors, public address systems etc. 4 Domestic Review Pre- Ref. Contract Procurement Prefrence by Bank Expected Bid Opening Estimated Cost qualification Comments No. (Description) Method (Yes or (Prior Date (Yes or No) No) or Post) US$ N 000 Start Finish s V-SAT internet connections 5 with 50 NS No No Post Sept-2014 Dec.-2015 installation and accessories 6 Hilux truck/ 50 NS No No Post June 2014 Dec 2015 14 seat Hiace bus Total 250 III. Selection of Consultants 11. Prior Review Threshold Prior Review Threshold Item No. Selection Method Comments US$ ’000 1. Quality and Cost Based Selection (QCBS) >300 All 2. Single Source (Firms) (SSS) All values All 3 Consultants Qualification (CQ) <300 None 4 Least cost selection (LS) <200 None 5 Selection of Individual Consultants (IC) >100 All 6 Single Source Selection (Individuals) All values All 7 Quality Base Selection (QBS) >300 All 12. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $300,000.00 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 13. Any Other Special Selection Arrangements: NA IV. Procurement of Consultants with Assignments, Selection Methods and Time Schedule A. Federal Ministry of Education Component of NIPEP Review Expected Ref. Estimated Cost Selection by Bank Proposals Completion Description of Assignment No. US$ '000s Method (Prior / Submission date Post) Date 1 Individual Consultant (IC) Consultancy on up-grading of 23 IC Prior June Dec. 2015 NEMIS Unit 2014 2 Consultancy for capacity building for 22 IC Prior June Dec. 2015 5 procurement and supporting officers of 2014 SEPIP project 3 Consultancy for capacity building on 20 IC Post June Dec. 2015 monitoring and evaluation of SEPIP project 2014 in the three (3) participating States 4 Consultancy on Flexible 14 IC Post June Dec. 2015 Accounting Software 2014 Firms 1 Consultancy for capacity building for 70 CQS Post June Dec. 2015 SEPIP stakeholders, CSO and SBMC 2014 Consultancy on Third Party Monitoring 45 CQS Post Sept. 2014 Jun. 2015 of DLIs in the 3 states External Audit 2 Monitoring & Evaluation of state 20 CQS Post Sept. 2014 Jun. 2015 activities Annual Audit 100 Least Cost Post Sept. 2014 Jun. 2015 Audit of IDA support to states, 150 CQS Post Sept. 2014 Jun. 2015 assessment of progress, review and evaluation by external consultant TOTAL 464 B. Universal Basic Education Commission Component of SEPIP Review Expected Ref. Estimated Cost Selection by Bank Proposals Completion Description of Assignment No. US$ '000s Method (Prior / Submission date Post) Date 1 Individual Consultant (IC) Preparation for Selected State Pre- 100 IC Prior June Dec. 2014 primary and primary School 2014 improvement Plan 1 Short Term Procurement consultant 100 IC Post June Dec. 2014 2014 1 Short Term Financial Management 100 IC Post June Dec. 2014 Consultant 2014 I Short term Monitoring and Evaluation 100 IC Post June Dec. 2014 Consultant 2014 2 Firms Consultancy for assessment of 150 CQS Post Sept. 2014 Jun. 2014 infrastructure improvement, cost and financial management review to scale up integration of Islamiyya and pre-primary schools within basic education service delivery 3 External Audit Monitoring & Evaluation of state 150 CQS Post Sept. 2014 Jun. 2014 activities Annual Audit 120 Least Cost Post Sept. 2014 Jun. 2014 Audit of IDA support to states, 150 CQS Post Sept. 2014 Jun. 2014 assessment of progress, review and 6 evaluation by external consultant Total 970 C. Consultancy- For each of the five Participating states Review by Ref. Description of Selection Bank Expected Proposal Estimated Cost Comments No. Assignment Method (Prior or Submission Date Post) N US$ ‘000s Start Finish I Long Term National Consultant Support Dec- 1 IC Post July 2014 Project 2014 Implementati 100 on I Long term To support international and assist on Consultant Project Implementati Dec- on on 2 IC Post July 2014 2014 activities such as grants and scholarship 100 components 6 local consultants Each State consultants to Dec- be selected at 3 CQ Post July 2014 2014 1 consultant per sub- 150 component 1 long term international Dec- for learning 4 CQ Post July 2014 consultant for 2014 assessment in learning assessment 200 each state Consultancy for test item development on learning Dec- 5 achievement in Core SSS Prior July 2014 For pre- 2014 primary and subjects primary 100 schools Consultancy for test item moderation on learning Dec- 6 achievements in core SSS Prior July 2014 For pre- 2014 primary and subjects primary 50 schools Advisory on Exam procedure and Dec- 7 IC Post July 2014 editing of test items 2014 50 System Aug- Feb- programming/ 2014 2015 engineering, 8 IC Post system/network administration 100 7 Review by Ref. Description of Selection Bank Expected Proposal Estimated Cost Comments No. Assignment Method (Prior or Submission Date Post) N US$ ‘000s Start Finish Data analysis and Oct-2014 Feb- 9 statistical tracking of IC Post 2015 pupils performance 50 Consultancy services Nov- March- The 3 subject to CSO/NGO 2014 15 associations already exist 10 SSS Prior and the objective is to strengthen 200 them 1 week Training Nov- March 11 Teachers in Literacy QCBS Prior 2014 -15 200 1 week Training of Nov- March 12 Teachers in QCBS Prior 2014 -15 Numeracy 200 1 week Training of Nov- March teachers in Pedagogy 2014 -15 13 QCBS Prior & Psychosocial support. 200 Development and Dec-2014 Aug-15 administration of 14 CQ Post conversion test for teachers 150 Conversion courses Sept- Aug-15 15 for teachers QCBS Prior 2014 500 5 long-term local Sept- Aug-15 consultant to support 2014 16 CQ Post the M & E unit of the FPSU/SPTC 100 Local consultant to Sept- Aug-15 support the Teacher 2014 17 professional CQ Post Development Component 100 Technical Assistance Sept- Aug-15 18 to conduct project IC Post 2014 evaluation 50 Total 2,600 D. Others including Grants and training – For each of the Five Participating States 1 Total Grants for five participating states 20,000 2 Total training 8,250 2a Federal Ministry of Education 1,000 2b UBEC 1,000 2c Five Participating states 6,250 ‘Summary of procurement items 1 Goods 665 8 2 Consultancy 4,034 3 Grants for five participating states 20,000 4 Training 8,250 Grand Total 32,949 9 PROCUREMENT Nigeria : Nigeria - State Education Program Investment Project PLAN General Information Country: Nigeria Bank’s Approval Date of the Original Procurement Plan: 2018-04-19 2020-01-10 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P122124 GPN Date: Project Name: Nigeria - State Education Program Investment Project Loan / Credit No: IDA / 52200 Executing Agency(ies): FME SEPIP WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Component 3: Improving Access to Quality Education and Learning Environment in North East States NG-FME SEPIP-104077-NC- Pending Request for Single Stage - One RFQ / Printing of project IDA / 52200 Post Limited 8,100.00 0.00 Implementati 2019-03-10 2019-05-05 2019-11-01 Component 3.1: Improving Quotations Envelope bronchure on Access to Quality Education Component 3.2: Improving Learning Environment Component 3: Improving Access to Quality Education and Learning Environment in North East States NG-FME SEPIP-104079-NC- Pending Request for Single Stage - One RFQ / Printing of project IDA / 52200 Post Limited 4,800.00 0.00 Implementati 2019-03-10 2019-05-05 2019-11-01 Component 3.1: Improving Quotations Envelope bronchure on Access to Quality Education Component 3.2: Improving Learning Environment Component 3: Improving Access to Quality Education and Learning Environment NG-FME SEPIP-104083-NC- in North East States Pending RFQ / Purchase of office Request for Single Stage - One IDA / 52200 Post Limited 29,850.00 0.00 Implementati 2019-03-30 2019-05-25 2019-11-21 equipment, Stationaries and Component 3.1: Improving Quotations Envelope on Computer accessories Access to Quality Education Component 3.2: Improving Learning Environment Page 1 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FME SEPIP-51510-CS- INDV / Capacity building for teachers in core subjects in North East states on cutting Consultant Technical Assistance Pending edge skill in science IDA / 52200 Post Qualification Open - National 96,000.00 0.00 2018-06-04 2018-06-25 2018-08-08 2018-09-07 2018-10-12 2019-04-10 Component Implementation teaching in collaboration Selection with the science Teachers Association of Nigeria (STAN) NG-FME SEPIP-51521-CS- CQS / Workshop on Consultant Technical Assistance Pending Emergency Response and IDA / 52200 Post Qualification Open - National 110,000.00 0.00 2018-06-10 2018-07-01 2018-08-14 2018-09-13 2018-10-18 2019-04-16 Component Implementation Management relieve Selection Operation. NG-FME SEPIP-51522-CS- CQS / Project Key Performance Indicators (KPI) Consultant Technical Assistance Pending and Fund Distribution Link IDA / 52200 Post Qualification Open - National 130,000.00 0.00 2018-07-10 2018-07-31 2018-09-13 2018-10-13 2018-11-17 2019-05-16 Component Implementation Indicators Management, Selection Setting , Monitoring and Evaluation NG-FME SEPIP-52383-CS- CQS / Independent Consultant Verification of Performance Technical Assistance Under IDA / 52200 Post Qualification Open - National 100,000.00 0.00 2018-04-10 2018-05-01 2018-06-14 2018-07-14 2018-08-18 2019-02-14 Grant Indicators (PGIs) 2017 Component Implementation Selection is the Additional Financing (AF) Component 3: Improving Access to Quality Education NG-FME SEPIP-104126-CS- and Learning Environment CQS / Engagement of in North East States Consultant consulting firm to conduct Pending IDA / 52200 Post Qualification Open - National 54,800.00 0.00 2019-04-12 2019-05-03 2019-06-16 2019-07-16 2019-08-20 2020-02-16 Studies on project impacts Component 3.1: Improving Implementation Selection and National Level Technical Access to Quality Education Assistance. Component 3.2: Improving Learning Environment Component 3: Improving Access to Quality Education NG-FME SEPIP-104130-CS- and Learning Environment CQS / Consultancy on video in North East States Documentary on SEPIP Consultant Pending success stories in SEPIP IDA / 52200 Post Qualification Open - National 92,407.00 0.00 2019-04-03 2019-04-24 2019-06-07 2019-07-07 2019-08-11 2020-02-07 Component 3.1: Improving Implementation original States and Selection Access to Quality Education additional financing of North East Component 3.2: Improving Learning Environment Component 3: Improving NG-FME SEPIP-104134-CS- Access to Quality Education CQS / Engagement of and Learning Environment cosulting firm to conduct in North East States Consultant second level Independent Pending IDA / 52200 Post Qualification Open - National 155,573.00 0.00 2019-05-14 2019-06-04 2019-07-18 2019-08-17 2019-09-21 2020-03-19 verification of Performance Component 3.1: Improving Implementation Selection Grant Indicators (PGIs) Access to Quality Education achievement in the SEPIP North East State of Nigeria Component 3.2: Improving Learning Environment Page 2 Component 3: Improving Access to Quality Education NG-FME SEPIP-104135-CS- and Learning Environment CQS / Engagement of in North East States Consultant consulting firm to conduct Pending IDA / 52200 Post Qualification Open - National 71,500.00 0.00 2019-05-20 2019-06-10 2019-07-24 2019-08-23 2019-09-27 2020-03-25 Procurement Audit training Component 3.1: Improving Implementation Selection for Federal Project Finance Access to Quality Education Management Division Staff Component 3.2: Improving Learning Environment Component 3: Improving Access to Quality Education and Learning Environment NG-FME SEPIP-52394-CS- in North East States QCBS / Consultancy services Consultant Pending of project impact and IDA / 52200 Post Qualification Open - National 220,000.00 0.00 2019-06-05 2019-06-26 2019-08-09 2019-09-08 2019-10-13 2020-04-10 Component 3.1: Improving Implementation National technical Selection Access to Quality Education assisstance Component 3.2: Improving Learning Environment INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NG-FME SEPIP-51504-CS- INDV / Education planning Individual Technical Assistance Pending management through IDA / 52200 Post Consultant Limited 8,400.00 0.00 2018-03-30 2018-04-04 2018-04-25 2018-05-30 2018-11-26 Component Implementation effective management Selection information system (EMIS) NG-FME SEPIP-51486-CS- INDV / New approach to Individual Technical Assistance Pending information control, store, IDA / 52200 Post Consultant Limited 7,872.00 0.00 2018-08-13 2018-08-18 2018-09-08 2018-10-13 2019-04-11 Component Implementation record and achieve inventory Selection management NG-FME SEPIP-51519-CS- INDV / Leadership and Individual Technical Assistance Pending Good Governance in IDA / 52200 Post Consultant Limited 7,872.00 0.00 2018-05-05 2018-05-10 2018-05-31 2018-07-05 2019-01-01 Component Implementation Management of Donor Selection Assisted Project NG-FME SEPIP-51523-CS- Individual INDV / Procurement training Technical Assistance Pending IDA / 52200 Post Consultant Limited 6,557.00 0.00 2018-05-15 2018-05-20 2018-06-10 2018-07-15 2019-01-11 for the stakeholders and Component Implementation Selection Project staff. NG-FME SEPIP-51527-CS- Individual Technical Assistance Pending INDV / Capacity building on IDA / 52200 Post Consultant Limited 7,872.00 0.00 2018-04-10 2018-04-15 2018-05-06 2018-06-10 2018-12-07 Component Implementation ICT Selection NG-FME SEPIP-51529-CS- INDV / Advanced Monitoring Individual and Evaluation of Project Technical Assistance Pending IDA / 52200 Post Consultant Limited 7,872.00 0.00 2018-05-10 2018-05-15 2018-06-05 2018-07-10 2019-01-06 input, outputs, impact and Component Implementation Selection outcome for improved performance. NG-FME SEPIP-52384-CS- Individual INDV / Annual Review of Technical Assistance Pending IDA / 52200 Post Consultant Limited 65,400.00 0.00 2018-10-10 2018-10-15 2018-11-05 2018-12-10 2019-06-08 Public Expenditure in the Component Implementation Selection Education Sector Page 3 NG-FME SEPIP-52391-CS- INDV / Assessment study to Individual Technical Assistance Pending determine the effectiveness IDA / 52200 Post Consultant Limited 57,870.00 0.00 2018-09-20 2018-09-25 2018-10-16 2018-11-20 2019-05-19 Component Implementation in the use of the grants Selection provided to SBMCs NG-FME SEPIP-52393-CS- INDV / Assessment study to examine the impact of the Individual partnerships between the Technical Assistance Pending IDA / 52200 Post Consultant Limited 67,650.00 0.00 2018-07-20 2018-07-25 2018-08-15 2018-09-19 2019-03-18 SEPIP states and the Component Implementation Selection private sectors in the area of technical vocational education. NG-FME SEPIP-52397-CS- Individual INDV / Consultancy on the Technical Assistance Pending IDA / 52200 Post Consultant Limited 68,500.00 0.00 2018-08-10 2018-08-15 2018-09-05 2018-10-10 2019-04-08 Result Driven Monitoring Component Implementation Selection and Evaluation of PGI NG-FME SEPIP-52398-CS- Individual INDV / Consultancy on Technical Assistance Pending IDA / 52200 Post Consultant Limited 60,000.00 0.00 2018-11-23 2018-11-28 2018-12-19 2019-01-23 2019-07-22 Grievance Management and Component Implementation Selection Resolution NG-FME SEPIP-52399-CS- INDV / Consultancy on Individual Technical Assistance Pending Beneficiary Assessment and IDA / 52200 Post Consultant Limited 70,000.00 0.00 2018-09-16 2018-09-21 2018-10-12 2018-11-16 2019-05-15 Component Implementation Review of Additional Selection Financing (AF) states NG-FME SEPIP-52400-CS- INDV / Consultancy on the Individual Evaluation of Teacher's/ Technical Assistance Pending IDA / 52200 Post Consultant Limited 51,500.00 0.00 2018-06-18 2018-06-23 2018-07-14 2018-08-18 2019-02-14 SBMCs personnel trained on Component Implementation Selection Psychosocial and pedagogy in the North East States. Component 3: Improving NG-FME SEPIP-104084-CS- Access to Quality Education INDV / Engagement of and Learning Environment Individual consultant to in North East States Individual Conduct Media outreach of Pending IDA / 52200 Post Consultant Limited 4,500.00 0.00 2019-03-27 2019-04-01 2019-04-22 2019-05-27 2019-11-23 State Education Programme Component 3.1: Improving Implementation Selection Investment Project (SEPIP) Access to Quality Education programmes on radio and Television Component 3.2: Improving Learning Environment Component 3: Improving Access to Quality Education NG-FME SEPIP-104081-CS- and Learning Environment INDV / Engagement of in North East States Individual Individual consultant for Pending IDA / 52200 Post Consultant Limited 2,250.00 0.00 2019-08-12 2019-08-17 2019-09-07 2019-10-12 2020-04-09 Disclosure of relevant Component 3.1: Improving Implementation Selection information on project Access to Quality Education website Component 3.2: Improving Learning Environment Component 3: Improving NG-FME SEPIP-104116-CS- Access to Quality Education INDV / Engagement of and Learning Environment Individual consultant for in North East States training of SEPIP staff and Individual Pending key stakeholders on New IDA / 52200 Post Consultant Limited 9,840.00 0.00 2019-03-10 2019-03-15 2019-04-05 2019-05-10 2019-11-06 Component 3.1: Improving Implementation approaches to Information Selection Access to Quality Education Control, Store, Records, Information and Archival Component 3.2: Improving Inventory Management Learning Environment Page 4 Component 3: Improving Access to Quality Education and Learning Environment NG-FME SEPIP-104122-CS- in North East States INDV / Engagement of Individual Pending Individual consultant to IDA / 52200 Post Consultant Limited 12,000.00 0.00 2019-04-23 2019-04-28 2019-05-19 2019-06-23 2019-12-20 Component 3.1: Improving Implementation Conduct Annual School Selection Access to Quality Education Census (ASC) data analysis Component 3.2: Improving Learning Environment NG-FME SEPIP-104124-CS- Component 3: Improving INDV / Engagement of Access to Quality Education Individual consultant to and Learning Environment Conduct comparative in North East States Individual disaggregation study of Under IDA / 52200 Post Consultant Limited 18,000.00 0.00 2019-03-11 2019-03-16 2019-04-06 2019-05-11 2019-11-07 students performance in Component 3.1: Improving Implementation Selection WAEC, NECO, and Access to Quality Education NABTEB examination in SEPIP North East State of Component 3.2: Improving Nigeria Learning Environment Component 3: Improving Access to Quality Education NG-FME SEPIP-104132-CS- and Learning Environment INDV / Engagement of in North East States Individual to carry out Individual Pending Annual Education Sector IDA / 52200 Post Consultant Limited 45,400.00 0.00 2019-03-25 2019-03-30 2019-04-20 2019-05-25 2019-11-21 Component 3.1: Improving Implementation Performance Review in Selection Access to Quality Education SEPIP North East State of Nigeria Component 3.2: Improving Learning Environment NG-FME SEPIP-148641-CS- INDV / The Engagement of Individual Consultants to Results-based Component: Individual Develop Implementation Pending IDA / 52200 Support to States' Education Post Consultant Limited 32,670.00 0.00 2019-12-04 2019-12-09 2019-12-30 2020-02-03 2020-08-01 Completion Report (ICR )in Implementation Sector Program Selection the Three Original SEPIP States of Anambra, Bauchi and Ekiti Page 5