Summarized Procurement Plan for NMUP I. General 1. Bank’s approval Date of the procurement Plan Updated annually procurement Plan for 2018 was approved on April 2, 2017 2. Date of General Procurement Notice: 2010 3. Period covered by this procurement plan: The procurement period of project covered calendar year 2018 and will remain valid until the project closing date in November 2020. II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Thresholds are defined based on the rating of Procurement Risk under the project as HIGH Procurement Method Prior Review Threshold Comments US$ 1. RFB (Goods) US$ 1,500,000 and above All 2. RFQ (Goods) None - 3. ICB (Works) US$ 5 million and above All 4. RFQ (Works) None - 5. (Non-Consultant Services) N/A - 2. Prequalification. _Not applicable_. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not applicable_. 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for NMUP issued on 2011. 5. Any Other Special Procurement Arrangements: Not applicable_. 6. Summary of the Procurement Packages planned for 3-year project extension until 30 November 2020 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 54 3 No Prior the ICB (Works) Summary of 35 3 No Prior the ICB (Goods) Summary of 20 2 No Prior and 1st the NCB Post contract (Works) for Prior Review Summary of 5 2 No Prior the NCB (Goods) Summary of 0 0 No N/A the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) US$ 500,000 and above 2. Single Source (Firms) US$ 500,000 and above 3. Individual Above US$ 200,000 plus procurement consultants 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not applicable 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 0 0 Prior number of contracts that will be let under QCBS Summary of 0.3 1 P0st CQS number of contracts that will be let under other methods PROCUREMENT Vietnam : Vietnam New Model University Project PLAN General Information Country: Vietnam Bank’s Approval Date of the Original Procurement Plan: 2018-04-13 2020-01-15 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P110693 GPN Date: Project Name: Vietnam New Model University Project Loan / Credit No: IDA / 47860 Executing Agency(ies): Vietnamese - German University WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual VGU-P12-Y15-G / Purchase of high - end machine tools Policy and governance Open - Single Stage - One IDA / 47860 Prior Request for Bids 1,860,000.00 1,659,765.31 Signed for GPEM program (phase development International Envelope 2). It comprises five lots. VGU-P20-Y16-G / VMU - Purchase of Texas Instruments Digital Signal Policy and governance IDA / 47860 Prior Direct Selection Direct 0.00 21,344.43 Signed Processors TMS320C6747 development kits for EEIT and MSST programs VGU-P20-Y14-G / Policy and governance Open - Single Stage - One Purchasing of high-end IDA / 47860 Prior Request for Bids 1,000,000.00 633,822.06 Signed development International Envelope machine tools for GPEM VGU-P14-Y14-G (2nd time) / VMU VGU-P14-Y14-G Policy and governance Open - Single Stage - One Purchasing of equipment of IDA / 47860 Prior Request for Bids 0.00 196,240.00 Signed development International Envelope load-pull measurement system for RF lab of EEIT VGU-P24-Y15-G / Purchase of a calibration kit 3.5mm, Policy and governance RF cable and adapter for IDA / 47860 Prior Direct Selection Direct 15,000.00 14,388.07 Signed development the Rohde & Schwarz Vector Network Analyzer ZVA40 VGU-P23-Y15-G / Pkg VGU- P23-Y15-G: Purchase of Policy and governance Extension Equipment for IDA / 47860 Prior Direct Selection Direct 0.00 9,052.56 Signed development Metrology Laboratory of EEIT Program Page 1 VGU-P11-Y18-G / Purchase of Practical training and experimental equipments for Vibration control, machining Academic and Research Open - Single Stage - One IDA / 47860 Prior Request for Bids 3,135,000.00 2,805,447.78 Signed 2018-06-18 2018-06-23 2018-08-12 2018-11-25 2018-12-09 2019-06-07 and Fluid Mechanics development International Envelope - Lot 1: USD 280,000 - Lot 2: USD 2,235,000 - Lot 3: USD 620,000 VGU-P12-Y18-G / Purchase of Practical training and experimental equipments for electric measurement, smart Academic and Research Single Stage - One grid, image processing and IDA / 47860 Post Request for Bids Open - National 960,000.00 931,249.36 Completed 2018-05-15 2018-05-18 2018-06-25 2018-10-05 2018-10-15 2019-03-06 development Envelope environmental monitoring - Lot 1: USD 475,000 - Lot 2: USD 360,000 - Lot 3: USD 125,000 VGU-P10-Y18-G / Supply and Installation of ICT system of university Policy and governance Open - Single Stage - One IDA / 47860 Prior Request for Bids 5,030,000.00 0.00 Canceled 2018-07-26 2018-08-03 2018-09-24 2019-01-22 2019-02-12 2020-05-07 management for VGU development International Envelope (including hardware & software) VGU-P13-Y18-G / VGU-P13- Y18-G: Purchase of research Academic and Research Single Stage - One IDA / 47860 Post Request for Bids Open - National 930,000.00 873,711.60 Signed 2018-07-30 2018-08-03 2018-09-07 2018-10-17 2018-11-14 2019-09-10 equipment for labs of EEIT development Envelope study program (2 Lots) VGU-P11-Y17-G / Purchase of research equipment of GPEM program - Lot 3: Academic and Research Single Stage - One Purchase of Tools for IDA / 47860 Post Request for Bids Open - National 160,000.00 156,338.74 Completed 2018-07-30 2018-08-03 2018-09-07 2018-10-19 2018-11-16 2019-06-14 development Envelope machining tools of GPEM program (2nd time rebidding) VGU-P12-Y17-G / VGU-P12- Y17-G: Purchase of Gas chromatography system, liquid chromatography system, and auxiliary, sampling kits for Water Academic and Research Single Stage - One IDA / 47860 Post Request for Bids Open - National 1,170,000.00 956,953.20 Completed 2018-07-31 2018-08-06 2018-09-10 2018-10-22 2018-11-19 2019-07-17 Technology and MSST development Envelope programs - Lot 1: Purchase of Gas chromatography system and Liquid Chromatography system (2nd time rebidding) VGU-P13-Y17-G / VGU-P13- Y17-G: Purchase of research equipment for Computer Science, CompEng, Academic and Research Single Stage - One ME and EEIT programs - IDA / 47860 Post Request for Bids Open - National 170,000.00 147,028.88 Completed 2018-07-31 2018-08-06 2018-09-10 2018-10-22 2018-11-19 2019-06-17 development Envelope Lot 4: Purchase of extension for Communications Lab of EEIT program (2nd time rebidding) VGU-P15-Y18-G / Purchase of extension for Practical training and experimental Academic and Research Single Stage - One IDA / 47860 Post Request for Bids Open - National 1,333,232.00 0.00 Canceled 2018-12-20 2018-12-25 2019-01-24 2019-02-23 2019-03-23 2020-01-25 equipments for Vibration development Envelope control, machining and Fluid Mechanics (02 Lots) Page 2 VGU-P16-Y18-G / Purchase of extension for Practical training and experimental Academic and Research Single Stage - One equipments for electric IDA / 47860 Post Request for Bids Open - National 160,899.00 159,472.44 Signed 2018-12-20 2018-12-25 2019-01-24 2019-02-23 2019-03-23 2019-11-04 development Envelope measurement, smart grid, image processing and environmental monitoring VGU-P17-Y18-G / Purchase Academic and Research Single Stage - One of management software for IDA / 47860 Post Request for Bids Open - National 269,622.00 264,921.29 Signed 2018-12-20 2018-12-25 2019-01-24 2019-02-23 2019-03-23 2019-12-02 development Envelope VGU library VGU-P18-Y18-G / Purchase of text books and electronic Academic and Research Request for Single Stage - One IDA / 47860 Post Open - National 77,808.00 71,059.01 Completed 2018-12-25 2019-02-26 2019-07-16 resources for VGU Library development Quotations Envelope (02 Lots) VGU-P19-Y18-G / Purchase Project management, Request for Single Stage - One IDA / 47860 Post Open - National 10,798.00 3.00 Terminated 2018-12-25 2019-02-19 2019-05-21 of office facilities for VMU monitoring and evaluation Quotations Envelope VGU-P11-Y17-G-3 LOTS / Purchase of research Academic and Research Single Stage - One IDA / 47860 Post Request for Bids Open - National 1,420,000.00 1,106,264.94 Completed 2019-01-21 2019-01-26 2019-03-09 2019-04-08 2019-05-13 2019-11-09 equipment of GPEM program development Envelope (including 03 Lots) VGU-P12-Y17-G-2 LOTS / Purchase of Gas chromatography system, liquid chromatography Academic and Research Single Stage - One IDA / 47860 Post Request for Bids Open - National 1,020,000.00 117,172.98 Completed 2019-01-21 2019-01-26 2019-03-09 2019-04-08 2019-05-13 2019-11-09 system, and auxiliary, development Envelope sampling kits for Water Technology and MSST programs (2 Lots) VGU-P13-Y17-G-4 LOTS / Purchase of research Academic and Research Single Stage - One equipment for Computer IDA / 47860 Post Request for Bids Open - National 405,000.00 216,004.74 Completed 2019-01-21 2019-01-26 2019-03-09 2019-04-08 2019-05-13 2019-11-09 development Envelope Science, CompEng, ME and EEIT programs VGU-P15-Y17-G / Purchase Academic and Research Single Stage - One of extension and research IDA / 47860 Post Request for Bids Open - National 275,000.00 229,467.45 Completed 2019-01-21 2019-01-26 2019-03-09 2019-04-08 2019-05-13 2019-11-09 development Envelope equipment of EEIT program VGU-P11-Y19-G / Provide of software for Information Policy and governance Open - Single Stage - One IDA / 47860 Post Request for Bids 1,045,918.00 0.00 Canceled 2019-04-08 2019-04-13 2019-05-25 2019-06-24 2019-07-29 2020-11-20 and Communications development International Envelope Technology System for VGU VGU-P12-Y19-G / Provide Under of hardware for Information Policy and governance Open - Single Stage - One IDA / 47860 Prior Request for Bids 3,980,289.00 0.00 Implementati 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-07-30 and Communications development International Envelope on Technology System for VGU VGU-P13-Y19-G / Purchase of teaching and research equipment for synthesis and fabrication of conventional Academic and Research Open - Single Stage - One IDA / 47860 Prior Request for Bids 3,226,600.00 112,484.23 Signed 2019-04-15 2019-04-20 2019-06-01 2019-07-01 2019-08-05 2020-07-30 materials, advanced development International Envelope materials, and for material testing and characterization (1st stage) (3 lots) VGU-P14-Y19-G / Purchase of equipment for construction materials, soil mechanics Academic and Research Single Stage - One labs of Civil Engineering IDA / 47860 Prior Request for Bids Open - National 2,025,112.00 1,952,635.80 Signed 2019-04-15 2019-04-20 2019-05-20 2019-06-19 2019-07-24 2020-07-18 development Envelope and for workshop of Architecture (1st stage) (3 lots) Page 3 VGU-P15-Y19-G / Purchase of equipment for Computer Academic and Research Single Stage - One Science, IT Security, EEIT IDA / 47860 Prior Request for Bids Open - National 2,005,752.00 0.00 Canceled 2019-04-15 2019-04-20 2019-05-20 2019-06-19 2019-07-24 2020-07-18 development Envelope and MSST study programs (2 Lots) VGU-P11-Y19-G (REBIDDING) / Supply and Under Installation of software for Policy and governance Open - Single Stage - One IDA / 47860 Post Request for Bids 1,045,918.00 0.00 Implementati 2019-09-12 2019-09-16 2019-11-15 2019-12-15 2020-01-12 2020-10-08 Information and development International Envelope on Communications Technology System for VGU (Rebidding) VGU-P33-Y19-G / VGU-P33- Y19-G: Supply and Under Academic and Research Request for Single Stage - One installation equipment for IDA / 47860 Post Open - National 65,933.00 0.00 Implementati 2019-12-20 2020-02-14 2020-08-12 development Quotations Envelope laboratory chemical on wastewater treatment system VGU-P34-Y19-G / VGU-P34- Academic and Research Request for Single Stage - One Y19-G: Purchase of 5-ton IDA / 47860 Post Open - National 66,930.00 66,891.80 Signed 2019-12-20 2020-02-14 2020-08-12 development Quotations Envelope Crane for VGU VGU-P35-Y19-G / VGU-P35- Y19-G: Purchase of CES Under Academic and Research EduPack software for IDA / 47860 Post Direct Selection Direct 29,200.00 0.00 Implementati 2019-12-15 2019-12-20 2020-01-24 2020-07-22 development Material Science study on program VGU-P19-Y19-G / VGU-P19- Y19-G: Purchase of Under equipment for Computer Academic and Research Single Stage - One IDA / 47860 Prior Request for Bids Open - National 2,136,382.00 0.00 Implementati 2019-11-15 2019-11-20 2020-01-01 2020-01-31 2020-03-06 2020-11-01 Science, IT Security, EEIT development Envelope on programs. (2 lots) VGU-P22-Y19-G / "VGU-P22- Y19-G: Purchase of teaching Pending and research equipment for Academic and Research Single Stage - One IDA / 47860 Post Request for Bids Open - National 932,232.00 0.00 Implementati 2019-12-15 2019-12-20 2020-01-31 2020-03-01 2020-04-05 2020-11-01 Water Technology and development Envelope on Environemental and Process Engineering" (4 lots) VGU-P27-Y19-G / VGU-P27- Y19-G: Provide and install specialized furniture and electrical system, gas Under Academic and Research Single Stage - One treatment and air compresor IDA / 47860 Post Request for Bids Open - National 513,516.00 0.00 Implementati 2019-12-15 2019-12-20 2020-01-31 2020-03-01 2020-04-05 2020-10-02 development Envelope system for VGU labs and on piping works of various gases in VGU wet lab (3 lots) VGU-P28-Y19-G / VGU-P28- Y19-G: Purchase of Smart Pending Academic and Research Single Stage - One Factory equipment and IoT IDA / 47860 Post Request for Bids Open - National 557,950.00 0.00 Implementati 2019-12-15 2019-12-20 2020-01-31 2020-03-01 2020-04-05 2020-10-02 development Envelope for Industry 4.0 Lab on (2 lots) VGU-P29-Y19-G / VGU-P29- Under Y19-G: Purchase of Audio Academic and Research Single Stage - One IDA / 47860 Post Request for Bids Open - National 397,430.00 0.00 Implementati 2019-12-15 2019-12-20 2020-01-31 2020-03-01 2020-04-05 2020-10-02 system for Ceremony hall development Envelope on for VGU New campus VGU-P30-Y19-G / VGU-P30- Under Y19-G: Purchase of Academic and Research Single Stage - One IDA / 47860 Post Request for Bids Open - National 497,204.00 0.00 Implementati 2019-11-15 2019-11-20 2020-01-01 2020-01-31 2020-03-06 2020-09-02 Equipment for VGU's development Envelope on Library (3 lots) Page 4 VGU-P32-Y19-G / VGU-P32- Y19-G: Purchase of text Academic and Research Single Stage - One books and electronic IDA / 47860 Post Request for Bids Open - National 134,152.00 128,719.63 Signed 2019-11-15 2019-11-20 2020-01-01 2020-01-31 2020-03-06 2020-09-02 development Envelope resources for VGU Library (2 lots) VGU-P31-Y19-G / "VGU-P31- Under Y19-G: Purchase of Academic and Research Single Stage - One IDA / 47860 Post Request for Bids Open - National 616,833.00 0.00 Implementati 2019-12-15 2019-12-20 2020-01-31 2020-03-01 2020-04-05 2020-10-02 furniture for VGU Library" development Envelope on (2 lots) VGU-P20-Y19-G / VGU-P20- Y19-G: Purchase of teaching Academic and Research Single Stage - One and research equipment for IDA / 47860 Post Request for Bids Open - National 998,000.00 630,077.60 Signed 2019-11-15 2019-11-20 2020-01-01 2020-01-31 2020-03-06 2020-09-02 development Envelope Material Science study program (2nd stage) (2 lots) VGU-P23-Y19-G / "VGU-P23- Y19-G: Purchase of equipment for Building Materials Lab and Building Under Information Modelling (BIM) Academic and Research Single Stage - One IDA / 47860 Prior Request for Bids Open - National 2,009,609.00 0.00 Implementati 2019-12-15 2019-12-20 2020-01-31 2020-03-01 2020-09-11 2020-10-02 Lab of Civil Engineering development Envelope on program (2nd stage), equipment for workshop of Architecture program (2nd stage)" (3 lots) VGU-P26-Y19-G / VGU-P26- Y19-G: Purchase of Under equipment for EEIT Program Academic and Research Single Stage - One IDA / 47860 Post Request for Bids Open - National 585,465.00 0.00 Implementati 2019-12-15 2019-12-20 2020-01-31 2020-03-01 2020-04-05 2020-10-02 (2nd stage) and Vietnamese- development Envelope on German Transport Research Center (VGTRC) (3 lots) VGU-P25-Y19-G / VGU-P25- Y19-G: Purchase of extension machine tools and equipment for workshop, Academic and Research Single Stage - One Teaching and research IDA / 47860 Post Request for Bids Open - National 1,290,679.00 1,227,421.89 Signed 2019-12-15 2019-12-20 2020-01-31 2020-03-01 2020-04-05 2020-10-02 development Envelope equipment for Fluid mechanics Lab of Mechanical Engineering program (2nd stage) (2 lots) VGU-P36-Y19-G / VGU-P36- Y19-G: Purchase of Upgrade Academic and Research Single Stage - One of Real time digital power IDA / 47860 Post Request for Bids Open - National 350,000.00 350,986.02 Signed 2019-11-15 2019-11-20 2020-01-01 2020-01-31 2020-03-06 2020-09-02 development Envelope system simulator (RTDPSS) for EEIT program VGU-P21-Y19-G / VGU-P21- Y19-G: Purchase of metal Under 3D printer systems for Academic and Research Single Stage - One IDA / 47860 Post Request for Bids Open - National 727,580.00 0.00 Implementati 2019-11-15 2019-11-20 2020-01-01 2020-01-31 2020-03-06 2020-11-01 Mechanical Engineering and development Envelope on interdisciplinary study programs (3 lots) VGU-P20-Y19-G (LOT 2- REBIDDING) / Purchase of teaching and research Pending equipment for Material Academic and Research Single Stage - One IDA / 47860 Post Request for Bids Open - National 371,000.00 0.00 Implementati 2020-01-15 2020-01-20 2020-02-26 2020-03-20 2020-03-25 2020-09-21 Science study program (2nd development Envelope on stage) - Lot 2: Optically measured equipment and chemical storages Page 5 VGU-P24-Y19-G / VGU-P24- Y19-G: Purchase of software for Civil Engineering program; Vietnamese-German Academic and Research Single Stage - One IDA / 47860 Post Request for Bids Open - National 895,855.00 0.00 Canceled 2019-12-15 2019-12-20 2020-01-31 2020-03-01 2020-04-05 2020-10-02 Transport Research Center development Envelope (VGTRC); EEIT and Material Science program (4 lots) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual VGU-P3-Y12-CS / VMU: Policy and governance Quality And Cost- Open - VGU-P3-Y12-CS Developing IDA / 47860 Prior 187,000.00 114,492.48 Signed development Based Selection International Human Resource policy VGU-P2-Y11-CS / VGU-P2- Y11-CS Developing Policy and governance Quality Based Open - Guidelines for Financial IDA / 47860 Prior 0.00 81,833.02 Signed development Selection International Operation Management and Controlling VGU-P9-Y18-CS / Hiring Consultant Consulting firm to support Policy and governance Open - IDA / 47860 Post Qualification 250,000.00 245,030.80 Signed 2018-05-20 2018-06-12 2018-08-28 2018-10-28 2018-11-15 2020-08-27 for VGU 's Marketing development International Selection activities VGU-P9-Y17-CS / Consultant Policy and governance Development of five year IDA / 47860 Post Qualification Open - National 250,000.00 249,145.00 Signed 2019-01-21 2019-02-04 2019-03-04 2019-03-18 2019-04-08 2020-04-07 development Marketing plan Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual VGU-IC-04-04c / VGU-IC-04- Individual Policy and governance 04c - Accountant for PMU IDA / 47860 Prior Consultant Open 0.00 15,000.00 Signed development Sounthern Office Selection Individual VGU-P3-Y16-CS-b / VMU Policy and governance IDA / 47860 Prior Consultant Open 0.00 15,501.08 Signed Procurement Officer development Selection Individual VGU-P5-Y14-CS / VMU Policy and governance IDA / 47860 Prior Consultant Open 0.00 11,944.05 Signed Accountant development Selection 17/2014/VMU-H /P11-Y13- CS / VGU-P11-Y13-CS Individual Policy and governance National Procurement Staff IDA / 47860 Prior Consultant Open 0.00 14,349.26 Signed development for VMU at VGU Selection (Procurement Officer) Page 6 Individual VGU-P1-Y18-CS / Project Project management, IDA / 47860 Post Consultant Open 24,000.00 23,399.51 Completed 2018-07-16 2018-09-03 2018-09-13 2018-10-01 2019-09-30 Manager monitoring and evaluation Selection Individual VGU-P2-Y18-CS / Civil Project management, IDA / 47860 Post Consultant Open 24,000.00 19,558.75 Terminated 2018-03-01 2018-03-27 2018-04-02 2018-04-12 2019-04-11 Engineer monitoring and evaluation Selection Individual VGU-P6-Y18-CS / Project management, IDA / 47860 Post Consultant Open 20,000.00 16,702.92 Completed 2018-05-15 2018-07-03 2018-07-24 2018-08-28 2019-08-27 Interpreters/Translators monitoring and evaluation Selection VGU-P8-Y18-CS-A / Hiring Individual Academic and Research International Senior IDA / 47860 Prior Consultant Open 300,000.00 169,000.00 Signed 2018-05-10 2018-07-03 2018-07-16 2018-07-23 2020-09-10 development Researchers ( 1 position) Selection VGU-P3-Y18-CS -B / Individual Project management, Procurement Consultant 2 IDA / 47860 Prior Consultant Open 24,000.00 16,986.42 Signed 2018-05-07 2018-06-25 2018-07-16 2018-08-20 2019-08-19 monitoring and evaluation (2/3) Selection VGU-P3-Y18-CS -A / Individual Project management, Procurement Consultant 1 IDA / 47860 Prior Consultant Open 24,000.00 18,742.32 Completed 2018-05-02 2018-06-20 2018-07-11 2018-08-15 2019-08-14 monitoring and evaluation (1/3) Selection VGU-P4-Y18-CS / Financial Individual Management Consultant Project management, IDA / 47860 Post Consultant Open 24,000.00 22,760.76 Completed 2018-04-02 2018-04-13 2018-04-16 2018-04-16 2019-04-15 (cum leader of Financial monitoring and evaluation Selection Unit) Individual VGU-P5-Y18-CS-A / VMU Project management, IDA / 47860 Post Consultant Open 18,000.00 16,764.40 Completed 2018-05-04 2018-06-22 2018-07-13 2018-08-18 2019-08-17 Accountant 1 (1/2) monitoring and evaluation Selection VGU-P7-Y18-CS-A / Lab Individual Project management, Equipment Coordinator 1 IDA / 47860 Post Consultant Open 24,000.00 23,389.23 Signed 2018-05-07 2018-06-25 2018-07-16 2018-08-20 2019-08-19 monitoring and evaluation (1/2) Selection VGU-P7-Y18-CS-B / Lab Individual Project management, Equipment Coordinator 2 IDA / 47860 Post Consultant Open 24,000.00 0.00 Canceled 2018-06-29 2018-08-17 2018-09-07 2018-10-12 2019-10-11 monitoring and evaluation (2/2) Selection VGU-P3-Y18-CS -C / Individual Project management, Procurement Consultant 3 IDA / 47860 Prior Consultant Open 24,000.00 17,410.96 Signed 2018-08-01 2018-09-19 2018-10-10 2018-11-01 2019-10-31 monitoring and evaluation (3/3) Selection Individual VGU-P5-Y18-CS-B / VMU Project management, IDA / 47860 Post Consultant Open 18,000.00 14,416.08 Signed 2018-10-01 2018-10-27 2018-11-03 2018-11-24 2019-11-23 Accountant 2 (2/2) monitoring and evaluation Selection VGU-P8-Y18-CS-B / Hiring Individual Academic and Research International Senior IDA / 47860 Prior Consultant Open 250,000.00 0.00 Canceled 2018-12-20 2019-01-22 2019-02-12 2019-03-12 2020-12-11 development Researcher ( 1 position) (1/2) Selection VGU-P8-Y18-CS-C / Hiring Individual Academic and Research Under International Senior IDA / 47860 Prior Consultant Open 250,000.00 0.00 2018-12-20 2019-01-22 2019-02-12 2019-03-12 2020-12-11 development Implementation Researcher ( 1 position) (2/2) Selection VGU-P14-Y18-CS / Hiring Individual Policy and governance consultant for Quality IDA / 47860 Post Consultant Open 66,000.00 57,000.00 Signed 2018-12-20 2019-01-29 2019-02-12 2019-03-19 2020-03-18 development management guidelines Selection Individual VGU-P4-Y19-CS-B / VMU Project management, IDA / 47860 Post Consultant Open 17,000.00 15,276.82 Signed 2019-11-01 2019-11-20 2019-11-27 2019-12-06 2020-11-30 Accountant 2 (2/2) monitoring and evaluation Selection Page 7 Individual VGU-P7-Y19-CS / Project management, Pending IDA / 47860 Post Consultant Open 24,000.00 0.00 2019-04-15 2019-06-19 2019-07-03 2019-07-17 2020-07-16 Component Coordinator monitoring and evaluation Implementation Selection VGU-P8-Y19-CS / Individual Project management, Monitoring and Evaluation IDA / 47860 Post Consultant Open 24,000.00 18,834.88 Signed 2019-04-15 2019-06-19 2019-07-03 2019-07-17 2020-07-16 monitoring and evaluation Specialist Selection VGU-P3-Y19-CS / Team Individual Project management, leader of Financial Unit and IDA / 47860 Post Consultant Open 24,000.00 24,046.86 Signed 2019-04-01 2019-04-09 2019-04-11 2019-04-16 2020-04-15 monitoring and evaluation Assistant to VMU Director Selection Individual VGU-P1-Y19-CS / Project Project management, IDA / 47860 Post Consultant Open 30,000.00 27,522.53 Signed 2019-08-22 2019-09-08 2019-09-15 2019-10-01 2020-09-30 Manager monitoring and evaluation Selection VGU-P2-Y19-CS-A / Individual Project management, Procurement Consultant 1 IDA / 47860 Post Consultant Open 21,000.00 19,923.01 Signed 2019-07-01 2019-07-18 2019-07-23 2019-08-01 2020-07-31 monitoring and evaluation (1/3) Selection Individual VGU-P4-Y19-CS-A / VMU Project management, IDA / 47860 Post Consultant Open 18,000.00 18,045.53 Signed 2019-07-15 2019-07-31 2019-08-07 2019-08-18 2020-08-17 Accountant 1 (1/2) monitoring and evaluation Selection Individual VGU-P5-Y19-CS / Project management, IDA / 47860 Post Consultant Open 18,500.00 17,933.88 Signed 2019-05-01 2019-05-17 2019-05-24 2019-06-01 2020-05-31 Interpreter/Translator monitoring and evaluation Selection Individual VGU-P6-Y19-CS / Lab Project management, IDA / 47860 Post Consultant Open 24,000.00 24,048.68 Signed 2019-09-12 2019-09-28 2019-10-04 2019-10-12 2020-10-11 Equipment Coordinator monitoring and evaluation Selection VGU-P2-Y19-CS-B / Individual Project management, Procurement Consultant 2 IDA / 47860 Post Consultant Open 19,000.00 18,009.00 Signed 2019-11-01 2019-11-18 2019-11-23 2019-12-06 2020-11-30 monitoring and evaluation (2/3) Selection VGU-P2-Y19-CS-C / Individual Project management, Procurement Consultant 3 IDA / 47860 Prior Consultant Open 21,000.00 21,053.11 Signed 2019-09-18 2019-09-26 2019-09-27 2019-10-01 2020-09-30 monitoring and evaluation (3/3) Selection VGU-P16-Y19-CS / VGU- P16-Y19-CS: Hiring Individual Academic and Research Pending International Consultant for IDA / 47860 Post Consultant Open 33,000.00 0.00 2020-01-15 2020-03-04 2020-03-25 2020-04-29 2020-10-26 development Implementation develop EHS for VGU new Selection campus VGU-P17-Y19-CS-A / VGU- Individual P17-Y19-CS-a: Hiring Project management, Pending IDA / 47860 Post Consultant Open 38,000.00 0.00 2020-01-15 2020-03-04 2020-03-25 2020-04-29 2020-10-26 International Consultant for monitoring and evaluation Implementation Selection ICR VGU-P17-Y19-CS-B / VGU- Individual Project management, Pending P17-Y19-CS-b: Hiring IDA / 47860 Post Consultant Open 12,000.00 0.00 2020-01-15 2020-03-04 2020-03-25 2020-04-29 2020-10-26 monitoring and evaluation Implementation National Consultant for ICR Selection Page 8