Procurement Plan Baseline Cultural Heritage and Urban Development Project Management Unit Council for Development and Reconstruction Cultural Heritage and Urban Development Project Management Unit - Projects Division 67.2 days Procurement Plan Baseline Studies Contracts Update (Completed) and New Baseline (Planned) SHORT LISTING PERIOD = 7.2 Weeks REQUEST FOR PROPOSAL & INVITATION = 8 Weeks Bidding Period = 4.8 Weeks as at February 2014 Studies Durations 3 wk 0.4 wk 1 wk 1 wk 0.8 wk 1 wk 0.4 wk 2 wk 0.4 wk 1 wk 1 wk 0.8 wk 1 wk 0.4 wk 1 wk 0.4 wk 4.4 wk Request Request Send Tenders Issue Board Board Request Tend Dept Board Board Request Open Issue REI Open EOI Board no-objection Send RFP Board no-objection Invitation Department Request For Contract Description (Shortlist) (Shortlist) Approval Approval Approval no-objection on SL to Tenders Dept Comments Approval Approval Approval no-objection on RFP to Tenders Faxes to Proposal Technical on SL notification on SL on RFP on RFP notification on RFP Proposal on SL on RFP Dept Consultants (RFP) 1. Urban Baalbeck Reference Supervision CHUD/C/baalbeck/8498 Completed 9-Jan-04 2-Feb-04 30-Mar-04 1-May-04 1-Jun-04 2-Jun-04 8-Jun-04 14-Apr-04 30-Apr-04 23-Jun-04 27-Jul-04 6-Aug-04 5-Aug-04 12-Aug-04 3-Sep-04 13-Sep-04 15-Sep-04 15-Oct-04 Planned Studies Phase II -Rehabilitation of Main Roads, Public area and Market CHUD/C/baalbeck/8498 Completed N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Supervision for Baalbeck - phase II CHUD/C/baalbeck/18383 Completed Planned 21-Jan-00 23-Jan-00 30-Jan-00 6-Feb-00 N/A N/A 25-Jun-13 9-Jul-13 11-Jul-13 18-Jul-13 25-Jul-13 N/A N/A 28-Jul-13 4-Aug-13 6-Aug-13 6-Sep-13 Byblos Supervision CHUD/C/Byblos/8502 Completed 9-Jan-04 2-Feb-04 30-Mar-04 1-May-04 1-Jun-04 2-Jun-04 8-Jun-04 14-Apr-04 30-Apr-04 23-Jun-04 27-Jul-04 6-Aug-04 5-Aug-04 12-Aug-04 21-Sep-04 24-Sep-04 24-Sep-04 24-Oct-04 Planned Studies Phase II - Byblos Mina square and Coastal path. CHUD/C/Byblos/8613 Completed NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA Planned Phase II - Supervision of a new Parking CHUD/C/Byblos/T1 Completed 20-Mar-14 Planned 10-Apr-14 12-Apr-14 19-Apr-14 26-Apr-14 N/A N/A 3-May-14 17-May-14 20-May-14 27-May-14 3-Jun-14 N/A N/A 10-Jun-14 17-Jun-14 20-Jun-14 21-Jul-14 Tripoli Supervision CHUD/C/Tripoli/8505 Completed 9-Jan-04 2-Feb-04 30-Mar-04 1-May-04 1-Jun-04 2-Jun-04 8-Jun-04 14-Apr-04 30-Apr-04 23-Jun-04 27-Jul-04 6-Aug-04 5-Aug-04 12-Aug-04 20-Sep-04 24-Sep-04 24-Sep-04 24-Oct-04 Planned Technical Control on the Construction of Abu Ali Platform CHUD/C/Tripoli/16615 Completed NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA Planned Tripoli Traffic Study CHUD/C/Tripoli/8314 Completed NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA Planned NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA Tripoli Traffic Study - Addendum No. 1 CHUD/C/Tripoli/8314 Completed N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Planned NA NA NA NA NA NA NA NA NA 1-Oct-05 8-Oct-05 15-Oct-05 NA NA NA NA NA NA Tripoli Traffic Study - Addendum No. 2 CHUD/C/Tripoli/8314 Completed N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Planned NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA Tripoli Bortasi Mosque and Abou Ali River CHUD/C/Tripoli/7888 Completed NA NA NA NA NA NA NA NA NA 30-Jan-06 7-Feb-06 10-Feb-06 NA NA NA NA NA NA Planned NA NA NA NA NA NA NA NA NA 1-Oct-05 8-Oct-05 15-Oct-05 NA NA NA NA NA NA Technical Control on Design of Abu Ali Platform CHUD/C/Tripoli/4847D Completed NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA Planned NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA Study Phase II - Public Spaces and Facades CHUD/C/Tripoli/8916 Completed N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Study Phase III -Preliminary Design for Khan Al Askar Detailled master plan CHUD/C/Tripoli/16843 Completed for the Northern Zone Adjacent to Khan Al Askar ZPE4 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A Study Phase III - Khan Al Arsat, Hammam Al Nouri, Khan El Saboun + CHUD/C/Tripoli/T2 Completed 26-Jun-07 30-Aug-07 13-Sep-07 24-Sep-07 28-Sep-07 10-Dec-14 Supervision Planned 15-May-07 5-Jun-07 7-Jun-07 14-Jun-07 21-Jun-07 27-Jun-07 4-Jul-07 7-Jul-07 24-Dec-14 26-Dec-14 2-Jan-15 9-Jan-15 15-Jan-15 22-Jan-15 25-Jan-15 1-Feb-15 4-Feb-15 6-Mar-15 Study Phase III - Facades, Stairs & Alleys rehabilitation along River side CHUD/C/Tripoli/T3 Completed +Supervision Planned 2-Dec-14 23-Dec-14 25-Dec-14 1-Jan-15 8-Jan-15 14-Jan-15 21-Jan-15 24-Jan-15 7-Feb-15 10-Feb-15 17-Feb-15 24-Feb-15 1-Mar-15 8-Mar-15 11-Mar-15 18-Mar-15 21-Mar-15 21-Apr-15 Supervision Facades and Public Spaces Op 5&7 and OP 4,6,8 Completed Planned 2-Dec-14 23-Dec-14 25-Dec-14 1-Jan-15 8-Jan-15 14-Jan-15 21-Jan-15 24-Jan-15 7-Feb-15 10-Feb-15 17-Feb-15 24-Feb-15 1-Mar-15 8-Mar-15 11-Mar-15 18-Mar-15 21-Mar-15 21-Apr-15 Saida and Tyre Supervision CHUD/C/saida-Tyre/8497 Completed 9-Jan-04 2-Feb-04 30-Mar-04 1-May-04 1-Jun-04 2-Jun-04 8-Jun-04 14-Apr-04 30-Apr-04 23-Jun-04 27-Jul-04 6-Aug-04 5-Aug-04 12-Aug-04 3-Sep-04 13-Sep-04 14-Sep-04 14-Oct-04 Planned Study for Infrastructure for Parts of Tyre City and the Public Spaces near CHUD/C/saida-Tyre/8497 Completed N/A N/A N/A N/A N/A N/A N/A N/A N/A 8-Sep-05 13-Sep-05 21-Sep-05 21-Sep-05 30-Sep-05 N/A N/A N/A N/A Khan El Franj and Fishermen Syndicate in Saida Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A 8-Sep-05 13-Sep-05 21-Sep-05 26-Sep-05 30-Sep-05 N/A N/A N/A N/A Supervision for Tyre phase III-Facades Rehabilitation & Public Spaces (the CHUD/C/Tyre/T2 Completed 15-Dec-14 Souks) Planned 20-May-12 5-Jan-15 7-Jan-15 14-Jan-15 21-Jan-15 27-Jan-15 3-Feb-15 6-Feb-15 20-Feb-15 23-Feb-15 2-Mar-15 9-Mar-15 14-Mar-15 21-Mar-15 24-Mar-15 31-Mar-15 3-Apr-15 4-May-15 Other Studies Designing and Printing Communication Tools CHUD/C/All/4361 Completed N/A N/A N/A N/A N/A N/A N/A N/A N/A 4-Mar-05 15-Mar-05 24-Mar-05 N/A N/A N/A 7-Apr-05 11-Apr-05 N/A Planned Opinion Survey CHUD/C/All/8559 Completed 4-Feb-05 18-Feb-05 1-Mar-05 3-Mar-05 N/A 15-Mar-05 23-Mar-05 31-Mar-05 20-Apr-05 Planned 25-Jun-04 3 06-Jul-04 19-Jul-04 08-Jun-04 25-Sep-04 29-Nov-04 21-Dec-04 04-Jan-05 07-Jan-05 23-Feb-05 Environmental Management Plan CHUD/C/All/9279 Completed 22-Jan-04 10-Feb-04 30-Mar-04 21-Apr-04 10-May-04 5-May-04 20-May-04 2-Jun-04 25-Jun-04 5-Sep-05 16-Sep-05 22-Sep-05 21-Oct-05 ------------- ------------ ------------- 11-Mar-05 3-Apr-05 Planned 5-May-05 12-May-05 19-May-05 24-May-05 31-May-05 3-Jun-05 10-Jun-05 13-Jun-05 14-Jul-05 2. Archeology 17-May-04 2 22-June-04 01-Jul-04 N/A N/A Tyre Archeological Mapping CHUD/C/Arch/8531 Completed 27-Mar-04 14-Apr-04 13-Aug-04 01-Sep-04 13-Sep-04 16-Sep-04 24-Sep-04 22-Jun-04 28-Jul-04 21-Sep-04 6-Oct-04 22-Oct-04 28-Oct-04 4-Feb-05 21-Feb-05 25-Feb-05 5-Mar-05 1-Apr-05 17-Dec-04 30-Dec-04 14-Jan-05 18-Jan-05 4-Feb-05 Planned Design and Supervision of Baalbeck and Tyre Archeological Project - BTAPI CHUD/C/Arch./16560 9-Sep-05 24-Oct-05 28-Nov-05 9-Dec-05 21-Dec-05 26-Dec-05 24-Jan-06 Completed 15-Mar-06 21-Mar-06 28-Mar-06 30-Mar-06 3-Apr-06 10-May-06 30-May-06 30-Jun-06 5-Sep-06 19-Sep-06 22-Sep-06 5-Oct-06 10-Oct-06 20-Oct-06 10-Nov-06 15-Nov-06 21-Nov-06 2-Jan-07 Planned 25-May-05 15-Jun-05 17-Jun-05 24-Jun-05 1-Jul-05 7-Jul-05 14-Jul-05 25-May-05 8-Jun-05 10-Jun-05 17-Jun-05 24-Jun-05 30-Jun-05 7-Jul-05 17-Jul-05 24-Jul-05 27-Jul-05 26-Aug-05 Design and Supervision of Baalbeck and Tyre Archeological Project - BTAPII 26-Jun-08 16-Oct-08 31-Oct-08 4-Sep-08 10-Nov-08 17-Nov-08 25-Nov-08 5-Nov-08 17-Nov-08 NA 17-Dec-08 26-Dec-08 26-Dec-08 4-Mar-09 Completed Planned Design and Supervision of "Tripoli Mill" Completed 26-Jun-08 16-Oct-08 31-Oct-08 4-Sep-08 10-Nov-08 17-Nov-08 25-Nov-08 5-Nov-08 17-Nov-08 NA 17-Dec-08 26-Dec-08 26-Dec-08 4-Mar-09 CHUD/C/Arch./17022 Planned Design and Supervision of "Chateau de la terre" - Saida Completed 26-Jun-08 16-Oct-08 31-Oct-08 4-Sep-08 10-Nov-08 17-Nov-08 25-Nov-08 5-Nov-08 17-Nov-08 NA 17-Dec-08 26-Dec-08 26-Dec-08 4-Mar-09 Planned Design and Supervision of Khan el Echlé and Serail of Baalbeck CHUD/C/Arch./17478 Completed 26-Jun-08 18-Dec-08 5-Jan-09 12-Jan-09 29-Aug-09 29-Sep-09 17-Mar-10 31-Mar-10 1-Apr-10 NA NA 9-Apr-10 12-Apr-10 28-Jul-10 23-Apr-10 23-Apr-10 NA NA Planned 15-Aug-09 29-Aug-09 31-Aug-09 7-Sep-09 14-Sep-09 20-Sep-09 18-Sep-09 25-Sep-09 28-Sep-09 27-Nov-09 Supervision of "Tripoli Citadel" CHUD/C/Arch./17170 Completed NA PMU-MIU 3. Suply Consultancy of technical assistance to DGA (Mme Ghoussoub) CHUD/S/16974 Completed Supply and Delivery of Equpments- CHUD Team CHUD/S/ Completed Supply and Delivery of Equpments- CHUD Team CHUD/S/teletrade Completed Supply and Delivery of Equpments- CHUD Team CHUD/S/officedesign Completed Supply and Delivery of Equpments- CHUD Team CHUD/S/AD17433 Completed Supply and Delivery of Office Furniture- CHUD Team CHUD/S/17574 Completed Maintenance and Enhacement of the PMI CHUD/S/9245 Supply and Delivery of Office equipments for TA Tyre CHUD/S/17455 Completed 28-Jul-11 CHUD – PMU – 2 Lebanon000Cult0t000procurement0plan.xls - Studies - Details Page 1 of 6 Date: 05/29/2015 Procurement Plan Baseline Cultural Heritage and Urban Development Project Management Unit Council for Development and Reconstruction Cultural Heritage and Urban Development Project Management Unit - Projects Division 67.2 days Procurement Plan Baseline Studies Contracts Update (Completed) and New Baseline (Planned) SHORT LISTING PERIOD = 7.2 Weeks REQUEST FOR PROPOSAL & INVITATION = 8 Weeks Bidding Period = 4.8 Weeks as at February 2014 Studies Durations 3 wk 0.4 wk 1 wk 1 wk 0.8 wk 1 wk 0.4 wk 2 wk 0.4 wk 1 wk 1 wk 0.8 wk 1 wk 0.4 wk 1 wk 0.4 wk 4.4 wk Request Request Send Tenders Issue Board Board Request Tend Dept Board Board Request Open Issue REI Open EOI Board no-objection Send RFP Board no-objection Invitation Department Request For Contract Description (Shortlist) (Shortlist) Approval Approval Approval no-objection on SL to Tenders Dept Comments Approval Approval Approval no-objection on RFP to Tenders Faxes to Proposal Technical on SL notification on SL on RFP on RFP notification on RFP Proposal on SL on RFP Dept Consultants (RFP) Supply and Delivery of Office Furniture for DGA CHUD/S/17469 Completed 15-Apr-10 23-Apr-10 27-Apr-10 28-Apr-10 15-Apr-10 23-Apr-10 27-Apr-10 28-Apr-10 11-May-10 7-Jun-10 28-Jul-11 Supply and Delivery of Office Equipments for DGA CHUD/S/17433 Completed 12-Jul-11 13-Jul-11 N/A Supply and Delivery of 2 Cars for DGA CHUD/S/17460 Completed Organisation of a seminar in Tyre CHUD/S/17699 Completed 12-Jan-04 19-Jan-04 Supply of Archeological equipment for DGA CHUD/S/S1 Completed cancelled 1-Dec-11 17-Feb-12 Supply of underwater Archaeological Equipments for DGA CHUD/S/17820 Completed 6-Oct-11 16-Mar-12 22-Mar-12 5-Apr-12 11-Apr-12 Supply of topographical Equipments for DGA CHUD/S/S3 Formation au benefice de la DGA (ENA) CHUD/S/17457 Formation Technique pour la DGA (IFPO) CHUD/S/17709 Completed Assistance Technique à la DGA pour la Museographie de Musée de la CHUD/S/17786 7-Feb-12 Citadelle St Gilles à Tripoli Assistance Technique à la DGA pour la préparation d'un rapport pour le CHUD/S/17788 7-Feb-12 comité du patrimoine mondial de l'UNESCO sur Tyr CHUD – PMU – 2 Lebanon000Cult0t000procurement0plan.xls - Studies - Details Page 2 of 6 Date: 05/29/2015 Procurement Plan Baseline Cultural Heritage and Urban Development Project Management Unit Council for Development and Reconstruction Cultural Heritage and Urban Development Project Management Unit - Projects Division 67.2 days 39.2 days 7 days 35 days Procurement Plan Baseline Studies Contracts Update (Completed) and New Baseline (Planned) Technical Evaluation Period = 7.2 weeks Hold Period = 0.4 week Financial Evaluation Period = 6.2 weeks Award as at February 2014 Studies Durations 2 wk 0.4 wk 1 wk 1 wk 0.8 wk 1 wk 0.2 wk 0.2 wk 1 wk 0.4 wk 1 wk 1 wk 0.8 wk 1 wk 4 wk Request Board Board Request Request Board Board Request Complete Board no-objection Open Complete Board no-objection Scheduled Estimated Approval Approval no-objection Notify Approval Approval no-objection Award Contract Last revised Funding Contract Description Technical on Technical on Technical Approval on Technical on Technical Consultants Financial Financial on Financial on Financial Approval on Financial on Financial / Notify Start Duration Completion Date Completion date Source Evaluation Notification Evaluation Proposal Evaluation Notification Evaluation date Weeks Evaluation Evaluation Evaluation Evaluation Evaluation Evaluation 1. Urban Baalbeck Reference 23-Nov-04 1 Supervision CHUD/C/baalbeck/8498 Completed 12-Nov-04 12-Nov-04 7-Jan-05 19-Jan-05 28-Jan-05 7-Feb-05 11-Feb-05 25-Feb-05 4-Mar-05 10-Mar-05 6-Apr-05 12-Jul-05 12-Jul-05 235 14-Jan-10 14-Jan-10 IBRD 23-Dec-04 1 04-Jan-05 Planned 31-May-05 31-May-05 208 26-May-09 Studies Phase II -Rehabilitation of Main Roads, Public area and Market CHUD/C/baalbeck/8498 Completed N/A N/A N/A N/A N/A N/A N/A N/A N/A 8-Feb-06 15-Feb-06 17-Feb-06 21-Feb-06 24-Mar-06 11-Apr-06 18-Apr-06 N/A N/A 4-May-06 4-May-06 167 7-Sep-06 19-Aug-09 IBRD Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A 15-Dec-05 22-Dec-05 29-Dec-05 3-Jan-06 10-Jan-06 7-Feb-06 7-Feb-06 16 30-May-06 Supervision for Baalbeck - phase II CHUD/C/baalbeck/18383 Completed 19-Sep-14 3-Nov-14 3-Nov-14 28-Dec-15 Local Planned 20-Sep-13 23-Sep-13 30-Sep-13 7-Oct-13 N/A N/A 11-Oct-13 12-Oct-13 19-Oct-13 22-Oct-13 29-Oct-13 5-Nov-13 N/A N/A 15-Nov-13 15-Nov-13 13-Jun-16 13-Jun-16 Byblos Supervision CHUD/C/Byblos/8502 Completed 8-Dec-04 8-Dec-04 21-Dec-04 4-Jan-05 7-Jan-05 19-Jan-05 28-Jan-05 7-Feb-05 11-Feb-05 25-Feb-05 4-Mar-05 10-Mar-05 6-Apr-05 25-Jul-05 25-Jul-05 248 26-Jan-09 31-Aug-11 IBRD Planned 31-May-05 31-May-05 182 25-Nov-08 Studies Phase II - Byblos Mina square and Coastal path. CHUD/C/Byblos/8613 Completed NA NA NA NA NA NA NA NA NA 8-Feb-06 15-Feb-06 22-Feb-06 21-Feb-06 22-Feb-06 6-Feb-06 6-Nov-06 26 12-Mar-07 9-May-07 IBRD Planned 7-May-05 14-May-05 19-May-05 26-May-05 28-May-05 29-May-05 5-Jun-05 8-Jun-05 15-Jun-05 22-Jun-05 27-Jun-05 4-Jul-05 1-Aug-05 1-Aug-05 26 30-Jan-06 Phase II - Supervision of a new Parking CHUD/C/Byblos/T1 Completed 10-Nov-14 12-Nov-04 14-Nov-14 Local Planned 4-Aug-14 7-Aug-14 14-Aug-14 21-Aug-14 N/A N/A 28-Aug-14 29-Aug-14 5-Sep-14 8-Sep-14 19-Nov-04 21-Nov-14 N/A N/A 28-Nov-14 28-Nov-14 40 30-Sep-15 30-Sep-15 Tripoli Supervision CHUD/C/Tripoli/8505 Completed 8-Dec-04 8-Dec-04 21-Dec-04 4-Jan-05 7-Jan-05 19-Jan-05 1-Feb-05 7-Feb-05 11-Feb-05 25-Feb-05 4-Mar-05 10-Mar-05 6-Apr-05 26-Jul-05 26-Jul-05 347 20-Jul-10 30-Dec-14 AFD Planned 31-May-05 31-May-05 208 26-May-09 End date of Technical Control on the Construction of Abu Ali Platform CHUD/C/Tripoli/16615 Completed NA NA NA NA NA NA NA NA NA 2-Jan-08 10-Jan-08 24-Jan-08 18-Feb-08 15-Apr-08 15-Apr-08 the Esplanade #REF! IBRD Project Planned Tripoli Traffic Study CHUD/C/Tripoli/8314 Completed NA NA NA NA NA NA NA NA NA NA NA NA NA NA 12-Feb-04 12-Feb-04 10 22-Apr-04 22-Apr-04 IBRD Planned NA NA NA NA NA NA NA NA NA NA NA NA NA NA 12-Feb-04 12-Feb-04 16 3-Jun-04 Tripoli Traffic Study - Addendum No. 1 CHUD/C/Tripoli/8314 Completed N/A N/A N/A N/A N/A N/A N/A N/A N/A 16-Feb-06 21-Feb-06 28-Feb-06 6-Mar-06 24-Mar-06 1-Jun-06 1-Jun-06 4 26-Jun-06 6-Jul-06 IBRD Planned NA NA NA NA NA NA NA NA NA 1-Oct-05 8-Oct-05 15-Oct-05 NA NA 12-Nov-05 12-Nov-05 5 17-Dec-05 Tripoli Traffic Study - Addendum No. 2 CHUD/C/Tripoli/8314 Completed N/A N/A N/A N/A N/A N/A N/A N/A N/A 3-May-06 9-May-06 16-May-06 19-May-06 29-May-06 29-Jun-06 16-Jun-06 3 14-Jul-06 6-Jul-06 IBRD Planned NA NA NA NA NA NA NA NA NA 31-Mar-06 7-Apr-06 14-Apr-06 19-Apr-06 26-Apr-06 31-Mar-06 31-Mar-06 4 28-Apr-06 Tripoli Bortasi Mosque and Abou Ali River CHUD/C/Tripoli/7888 Completed NA NA NA NA NA NA NA NA NA 30-Jan-06 7-Feb-06 10-Feb-06 17-Feb-06 24-Feb-06 4-May-06 5-May-06 47 28-Jul-06 30-Mar-07 AFD Planned NA NA NA NA NA NA NA NA NA NA NA NA NA NA 12-Nov-05 12-Nov-05 5 17-Dec-05 FEPP Technical Control on Design of Abu Ali Platform CHUD/C/Tripoli/4847D Completed NA NA NA NA NA NA NA NA NA NA NA NA NA NA 17-Nov-06 1-Oct-06 2 11-Oct-06 11-Oct-06 Local Planned NA NA NA NA NA NA NA NA NA 1-May-06 8-May-06 15-May-06 NA NA 12-Jun-06 12-Jun-06 1 15-Jun-06 Study Phase II - Public Spaces and Facades CHUD/C/Tripoli/8916 Completed N/A N/A N/A N/A N/A N/A N/A N/A N/A 8-Feb-06 15-Feb-06 17-Feb-06 21-Feb-06 21-Apr-07 15-Jun-07 15-Jun-07 118 14-Dec-07 18-Sep-09 AFD Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A 3-Apr-06 10-Apr-06 17-Apr-06 22-Apr-06 29-Apr-06 27-May-06 27-May-06 20 14-Oct-06 FEPP Study Phase III -Preliminary Design for Khan Al Askar Detailled master plan CHUD/C/Tripoli/16843 Completed 11-Dec-07 17-Nov-08 13-Nov-08 24-Nov-08 27-May-08 12-Jan-09 12-Jan-09 22 13-Apr-09 15-Jun-09 FEPP for the Northern Zone Adjacent to Khan Al Askar ZPE4 Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A 30-Jun-07 7-Jul-07 14-Jul-07 19-Jul-07 26-Jul-07 23-Aug-07 23-Aug-07 12 15-Nov-07 Study Phase III - Khan Al Arsat, Hammam Al Nouri, Khan El Saboun + CHUD/C/Tripoli/T2 Completed AFD Supervision Planned 20-Mar-15 23-Mar-15 30-Mar-15 6-Apr-15 12-Apr-15 19-Apr-15 20-Apr-15 22-Apr-15 29-Apr-15 1-May-15 8-May-15 15-May-15 21-May-15 28-May-15 25-Jun-15 25-Jun-15 52 23-Jun-16 Study Phase III - Facades, Stairs & Alleys rehabilitation along River side CHUD/C/Tripoli/T3 Completed AFD +Supervision Planned 5-May-15 7-May-15 14-May-15 21-May-15 27-May-15 3-Jun-15 4-Jun-15 6-Jun-15 13-Jun-15 16-Jun-15 23-Jun-15 30-Jun-15 5-Jul-15 12-Jul-15 9-Aug-15 9-Aug-15 26 7-Feb-16 7-Feb-16 Supervision Facades and Public Spaces Op 5&7 and OP 4,6,8 Completed AFD Planned 5-May-15 7-May-15 14-May-15 21-May-15 27-May-15 3-Jun-15 4-Jun-15 6-Jun-15 13-Jun-15 16-Jun-15 23-Jun-15 30-Jun-15 5-Jul-15 12-Jul-15 9-Aug-15 9-Aug-15 26 7-Feb-16 5-Feb-17 Saida and Tyre Supervision CHUD/C/saida-Tyre/8497 Completed 12-Nov-04 12-Nov-04 23-Nov-04 15-Dec-04 24-Dec-04 24-Dec-04 27-Dec-04 31-Dec-04 31-Dec-04 18-Jan-05 1-Feb-05 3-Feb-05 7-Apr-05 5-Jul-05 20-Jul-05 287 24-Jul-10 30-Nov-14 AFD Planned Study for Infrastructure for Parts of Tyre City and the Public Spaces near CHUD/C/saida-Tyre/8497 Completed N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 1-Dec-05 1-Dec-05 8 26-Jan-06 26-Jan-06 AFD Khan El Franj and Fishermen Syndicate in Saida Planned N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A N/A 28-Oct-05 28-Oct-05 12 20-Jan-06 Supervision for Tyre phase III-Facades Rehabilitation & Public Spaces (the CHUD/C/Tyre/T2 Completed local Souks) Planned 18-May-15 20-May-15 27-May-15 3-Jun-15 9-Jun-15 16-Jun-15 17-Jun-15 19-Jun-15 26-Jun-15 29-Jun-15 6-Jul-15 13-Jul-15 18-Jul-15 25-Jul-15 22-Aug-15 22-Aug-15 52 20-Aug-16 Other Studies Designing and Printing Communication Tools CHUD/C/All/4361 Completed N/A N/A N/A N/A N/A N/A N/A 25-Apr-05 24-May-05 24-May-05 31-May-05 8-Jun-05 10-Jun-05 N/A 14-Jul-05 14-Jul-05 102 6-Oct-05 28-Jun-07 IBRD Planned 17-May-05 19-May-05 26-May-05 2-Jun-05 8-Jun-05 15-Jun-05 13-Jul-05 13-Jul-05 84 21-Feb-07 Opinion Survey CHUD/C/All/8559 Completed 11-May-05 11-May-05 17-May-05 24-May-05 27-May-05 19-Jul-05 12-Sep-05 22-Sep-05 22-Sep-05 4-Oct-05 13-Oct-05 18-Oct-05 5-Dec-05 20-Jan-06 20-Jan-06 280 15-Jan-10 30-Nov-15 IBRD Planned 11-May-05 13-May-05 20-May-05 27-May-05 2-Jun-05 9-Jun-05 10-Jun-05 12-Jun-05 19-Jun-05 22-Jun-05 29-Jun-05 6-Jul-05 11-Jul-05 18-Jul-05 15-Aug-05 15-Aug-05 182 9-Feb-09 Environmental Management Plan CHUD/C/All/9279 Completed 13-Nov-05 15-Nov-05 23-Nov-05 1-Dec-05 5-Dec-05 26-Dec-05 27-Dec-05 3-Jan-06 6-Feb-06 6-Feb-06 15-Feb-06 17-Feb-06 21-Feb-06 2-May-07 24-Sep-07 9-Oct-07 190 27-Mar-10 30-Nov-15 IBRD Planned 28-Jul-05 30-Jul-05 6-Aug-05 13-Aug-05 19-Aug-05 26-Aug-05 27-Aug-05 29-Aug-05 5-Sep-05 8-Sep-05 15-Sep-05 22-Sep-05 27-Sep-05 4-Oct-05 30-May-07 30-May-07 139 27-Jan-10 2. Archeology Tyre Archeological Mapping CHUD/C/Arch/8531 Completed 20-Apr-05 20-Apr-05 5-May-05 19-May-05 20-May-05 2-Jun-05 13-Jun-05 23-Jun-05 20-Jul-05 20-Jul-05 26-Jul-05 5-Aug-05 10-Aug-05 3-Sep-05 17-Oct-05 1-Nov-05 57 31-Oct-06 1-Dec-06 IBRD Planned 8-May-05 15-May-05 20-May-05 27-May-05 29-May-05 30-May-05 6-Jun-05 9-Jun-05 16-Jun-05 23-Jun-05 28-Jun-05 5-Jul-05 2-Aug-05 2-Aug-05 52 1-Aug-06 Design and Supervision of Baalbeck and Tyre Archeological Project - BTAPI CHUD/C/Arch./16560 Completed 2-Mar-07 2-Mar-07 8-Mar-07 16-Mar-07 21-Mar-07 28-Mar-07 30-Mar-07 10-Apr-07 17-Apr-07 19-Apr-07 17-May-07 24-May-07 3-Oct-07 31-Oct-07 Italy 29-Nov-07 10-Dec-07 25-Jan-08 5-Feb-08 26-Feb-16 Planned 9-Sep-05 12-Sep-05 19-Sep-05 26-Sep-05 2-Oct-05 9-Oct-05 10-Oct-05 12-Oct-05 19-Oct-05 21-Oct-05 28-Oct-05 4-Nov-05 10-Nov-05 17-Nov-05 15-Dec-05 15-Dec-05 104 Design and Supervision of Baalbeck and Tyre Archeological Project - BTAPII 6-May-09 NA NA NA NA NA 11-May-09 28-May-09 11-Jun-09 23-Jun-09 9-Oct-09 13-Nov-09 13-Nov-09 Italy Completed 16-Jul-15 26-Feb-16 23-Jun-09 6-Jul-09 Planned 6-May-09 8-May-09 15-May-09 22-May-09 28-May-09 4-Jun-09 5-Jun-09 7-Jun-09 14-Jun-09 17-Jun-09 24-Jun-09 1-Jul-09 6-Jul-09 13-Jul-09 10-Aug-09 10-Aug-09 182 4-Feb-13 Design and Supervision of "Tripoli Mill" Completed 6-May-09 NA NA NA NA NA 11-May-09 28-May-09 11-Jun-09 23-Jun-09 9-Oct-09 13-Nov-09 13-Nov-09 40 24-Apr-15 24-Apr-15 Italy CHUD/C/Arch./17022 23-Jun-09 6-Jul-09 Planned 6-May-09 8-May-09 15-May-09 22-May-09 28-May-09 4-Jun-09 5-Jun-09 7-Jun-09 14-Jun-09 17-Jun-09 24-Jun-09 1-Jul-09 6-Jul-09 13-Jul-09 10-Aug-09 10-Aug-09 28 20-Feb-10 Design and Supervision of "Chateau de la terre" - Saida Completed 6-May-09 NA NA NA NA NA 11-May-09 28-May-09 11-Jun-09 23-Jun-09 9-Oct-09 13-Nov-09 13-Nov-09 284 24-Apr-15 24-Apr-15 Italy 23-Jun-09 6-Jul-09 Planned 6-May-09 8-May-09 15-May-09 22-May-09 28-May-09 4-Jun-09 5-Jun-09 7-Jun-09 14-Jun-09 17-Jun-09 24-Jun-09 1-Jul-09 6-Jul-09 13-Jul-09 10-Aug-09 10-Aug-09 35 11-Apr-10 Design and Supervision of Khan el Echlé and Serail of Baalbeck CHUD/C/Arch./17478 Completed 29-Sep-10 NA NA NA NA NA 30-Sep-10 1-Oct-10 1-Oct-10 7-Oct-10 12-Oct-10 Italy 4-Nov-10 5-Nov-10 28-Oct-10 9-Nov-10 25-Aug-11 25-Aug-11 120 9-Dec-13 6-Jan-16 Planned 25-Aug-10 NA NA NA NA NA 27-Aug-10 28-Aug-10 25-Sep-10 28-Sep-10 5-Oct-10 12-Oct-10 17-Oct-10 1-Jun-11 29-Jun-11 13-Jul-11 26 12-Jan-12 11-Jan-12 Supervision of "Tripoli Citadel" CHUD/C/Arch./17170 Completed NA NA NA NA NA 26-Oct-09 19-Nov-09 Local NA NA 18-Jan-10 NA NA 23-Apr-10 NA NA 7-Dec-09 11-Jun-10 52 10-Jun-11 10-Nov-12 PMU-MIU IBRD 3. Suply Consultancy of technical assistance to DGA (Mme Ghoussoub) CHUD/S/16974 Completed NA NA NA NA NA NA NA 9-Apr-09 30-Apr-09 14-May-09 Supply and Delivery of Equpments- CHUD Team CHUD/S/ Completed 19-Jan-06 IBRD Supply and Delivery of Equpments- CHUD Team CHUD/S/teletrade Completed 26-May-10 11-Aug-10 2-Sep-10 IBRD Supply and Delivery of Equpments- CHUD Team CHUD/S/officedesign Completed 26-May-10 11-Aug-10 3-Dec-10 IBRD Supply and Delivery of Equpments- CHUD Team CHUD/S/AD17433 Completed GL Supply and Delivery of Office Furniture- CHUD Team CHUD/S/17574 Completed IBRD Maintenance and Enhacement of the PMI CHUD/S/9245 IBRD Supply and Delivery of Office equipments for TA Tyre CHUD/S/17455 Completed 26-Aug-10 15-Sep-10 27-Sep-10 20-Oct-10 1 27-Oct-10 CANCELED AFD Grant CHUD – PMU – 2 Lebanon000Cult0t000procurement0plan.xls - Studies - Details Page 3 of 6 Date: 05/29/2015 Procurement Plan Baseline Cultural Heritage and Urban Development Project Management Unit Council for Development and Reconstruction Cultural Heritage and Urban Development Project Management Unit - Projects Division 67.2 days 39.2 days 7 days 35 days Procurement Plan Baseline Studies Contracts Update (Completed) and New Baseline (Planned) Technical Evaluation Period = 7.2 weeks Hold Period = 0.4 week Financial Evaluation Period = 6.2 weeks Award as at February 2014 Studies Durations 2 wk 0.4 wk 1 wk 1 wk 0.8 wk 1 wk 0.2 wk 0.2 wk 1 wk 0.4 wk 1 wk 1 wk 0.8 wk 1 wk 4 wk Request Board Board Request Request Board Board Request Complete Board no-objection Open Complete Board no-objection Scheduled Estimated Approval Approval no-objection Notify Approval Approval no-objection Award Contract Last revised Funding Contract Description Technical on Technical on Technical Approval on Technical on Technical Consultants Financial Financial on Financial on Financial Approval on Financial on Financial / Notify Start Duration Completion Date Completion date Source Evaluation Notification Evaluation Proposal Evaluation Notification Evaluation date Weeks Evaluation Evaluation Evaluation Evaluation Evaluation Evaluation Supply and Delivery of Office Furniture for DGA CHUD/S/17469 Completed N/A N/A N/A N/A N/A N/A N/A 28-May-10 18-Jun-10 20-Jun-10 16-Sep-10 24-Sep-10 16-Sep-10 26-Oct-10 29-Oct-10 4 26-Nov-10 1-Feb-11 IBRD Supply and Delivery of Office Equipments for DGA CHUD/S/17433 Completed 28-May-10 N/A N/A N/A N/A N/A N/A 26-Aug-10 IBRD N/A N/A N/A N/A N/A N/A N/A 27-Jul-11 17-Aug-11 17-Aug-11 8-Sep-11 19-Sep-11 21-Sep-11 23-Sep-11 2-Nov-11 2-Nov-11 4 30-Nov-11 30-Dec-11 Supply and Delivery of 2 Cars for DGA CHUD/S/17460 Completed 15-Apr-10 27-Jan-11 10-Feb-11 23-Jun-11 23-Jun-11 15-Oct-11 15-Nov-11 IBRD 6-May-11 12-May-11 Organisation of a seminar in Tyre CHUD/S/17699 Completed 10-Oct-11 2-Oct-11 4 30-Oct-11 AFD Grant Supply of Archeological equipment for DGA CHUD/S/S1 Completed NA NA NA NA NA NA NA 14-Mar-12 14-Mar-12 2-Apr-12 5-Apr-12 CANCELED AFD Grant 14-May-12 24-May-12 4-Jun-12 15-Jun-12 6 Supply of underwater Archaeological Equipments for DGA CHUD/S/17820 Completed NA NA NA NA NA NA NA 26-Jan-12 2-Feb-12 AFD 5-Apr-12 26-Apr-12 3-May-12 22-May-12 22-May-12 8 3-Aug-12 Grant Supply of topographical Equipments for DGA CHUD/S/S3 8-Feb-12 9-Mar-12 19-Mar-12 19-Mar-12 8 14-May-12 AFD Grant Formation au benefice de la DGA (ENA) CHUD/S/17457 30-Sep-10 14-Nov-10 24 1-May-11 AFD Grant Formation Technique pour la DGA (IFPO) CHUD/S/17709 Completed NA NA NA NA NA NA NA 8-Sep-11 15-Sep-11 25-Oct-11 3-Nov-11 26-Oct-11 15-Nov-11 20-Dec-11 20-Dec-11 41 30-Sep-12 AFD Grant Assistance Technique à la DGA pour la Museographie de Musée de la CHUD/S/17786 7-Feb-12 22-Feb-12 1-Mar-12 22-Feb-12 1-Mar-12 19-Mar-12 26-Mar-12 7-May-12 7-May-12 13 7-Aug-12 AFDGrant Citadelle St Gilles à Tripoli Assistance Technique à la DGA pour la préparation d'un rapport pour le CHUD/S/17788 7-Feb-12 7-Mar-12 8-Mar-12 7-Mar-12 8-Mar-12 20-Mar-12 26-Mar-12 27-Apr-12 27-Apr-12 13 27-Jul-12 AFD Grant comité du patrimoine mondial de l'UNESCO sur Tyr CHUD – PMU – 2 Lebanon000Cult0t000procurement0plan.xls - Studies - Details Page 4 of 6 Date: 05/29/2015 Procurement Plan Baseline Cultural Heritage and Urban Development Project Management Unit Council for Development and Reconstruction Cultural Heritage and Urban Development Project Management Unit - Projects Division NB: Finished Date 22.4 days 14 days 42 days 29.4 days 7 days 35 days Procurement Plan Baseline Works Contracts Actual Ending Date Update (Completed) and New Baseline (Planned) Tender Documents Approvals Period = 4.2 weeks Adv Period = 1 weeks Bid Pd = 6 weeks Bid Evaluation Period = 5.2 weeks Award=5 weeks Ongoing Projects as at February 2014 Works Durations 0.4 wk 1 wk 1 wk 0.8 wk 1 wk 0.5 wk 0.5 wk 6 wk 1 wk 0.4 wk 1 wk 1 wk 0.8 wk 1 wk 4 wk 1 wk Request Board Board Request Board Request Complete Board no-objection Tenders Issue Complete Request Board Board no-objection Award Contract Funding Original Loan Amount AF Loan Amount Approval Approval on no-objection Bids Approval no-objection Notice to Dur Last revised Funding % of Contract Description Reference US$ US$ Tender Approval on Tender Department Tender Bids Approval on Approval on Bids Notification Completion Status Source Documents on Tender Tender Notification on Tender Documents Advertisement Documents Opening Evaluation Bids Evaluation on Bids Notification on Bids Evaluation and Signature Commence Wks Date Completion date Source Completion Documents Documents Documents Evaluation Evaluation Foreign Local Foreign Local 1. Urban Baalbeck Works Phase I - Southern Access and Hay Al Qalaa 1,583,115.11 285,598.03 Completed 25-Jun-04 6-Jul-04 20-Jul-04 27-Jul-04 12-Aug-04 20-Sep-04 24-Sep-04 24-Nov-04 100% CHUD/W/baalbeck/3843 IBRD 31-Jan-05 11-Feb-05 25-Feb-05 N/A N/A 16-Mar-05 17-Mar-05 14-Apr-05 Contract breached. Taking over 11-May-05 6-Jun-05 6-Jun-05 14-Jun-05 22-Jun-05 24-Jun-05 30-Jun-05 18-Aug-05 19-Sep-05 115 18-Sep-06 21-Sep-09 IBRD completed Planned 29-May-05 31-May-05 7-Jun-05 14-Jun-05 20-Jun-05 27-Jun-05 25-Jul-05 1-Aug-05 52 31-Jul-06 Works Phase I - Northern Access and Pedestrian Paths CHUD/W/baalbeck/3470 IBRD 972,977.81 201,618.90 Completed 25-Jun-04 6-Jul-04 20-Jul-04 27-Jul-04 12-Aug-04 20-Sep-04 24-Sep-04 24-Nov-04 100% 31-Jan-05 11-Feb-05 25-Feb-05 N/A N/A 16-Mar-05 17-Mar-05 14-Apr-05 Contract breached. Taking over 27-Apr-05 2-Jun-05 2-Jun-05 8-Jun-05 15-Jun-05 22-Jun-05 30-Jun-05 18-Aug-05 19-Sep-05 115 18-Sep-06 21-Sep-09 IBRD completed Planned 15-May-05 22-May-05 24-May-05 31-May-05 7-Jun-05 13-Jun-05 20-Jun-05 18-Jul-05 25-Jul-05 52 24-Jul-06 Works Phase I - Baalbeck Hay Qalaa Housing CHUD/W/baalbeck/4451 IBRD 232,615.89 24,996.24 Completed 21-Jul-05 26-Jul-05 5-Aug-05 10-Aug-05 5-Sep-05 19-Aug-05 24-Aug-05 20-Sep-05 24-Oct-05 27-Oct-05 1-Nov-05 1-Nov-05 21-Nov-05 26-Dec-05 7-Feb-06 14-Mar-06 83 13-Sep-06 16-Oct-07 IBRD 100% Planned 13-May-05 15-May-05 22-May-05 29-May-05 4-Jun-05 11-Jun-05 14-Jun-05 18-Jun-05 30-Jul-05 6-Aug-05 9-Aug-05 16-Aug-05 23-Aug-05 28-Aug-05 4-Sep-05 2-Oct-05 9-Oct-05 26 9-Apr-06 Works Completed 17-Aug-07 9 16-Oct-07 Works Phase I - Rehabilitation of selected historic streets and Parkings CHUD/W/baalbeck/18315 IBRD 2,376,399.36 Completed 30-May-11 9-Jun-11 20-Jun-11 21-Sep-11 28-Jun-11 28-Apr-14 13-May-14 17-Jun-14 30-Jun-14 10-Nov-14 59 28-Dec-15 IBRD (Ph1 Completion) the contractor will have to finalize 18-Aug-11 12-Sep-11 15-Sep-11 4-Nov-11 22-Dec-11 22-Dec-11 78 the works before december 2015 Planned 21-Dec-10 30-May-11 6-Jun-11 13-Jun-11 18-Jun-11 25-Jun-11 29-Jun-11 2-Jul-11 13-Aug-11 20-Aug-11 23-Aug-11 30-Apr-14 7-May-14 12-May-14 19-May-14 16-Jun-14 16-Jun-14 104 13-Jun-16 13-Jun-16 Byblos Works Phase I - Communication Center, Market Area and Al-Mina Road CHUD/W/byblos/4397 IBRD 1,759,795.18 173,421.58 Completed 31-Aug-04 8-Sep-04 21-Sep-04 21-Sep-04 24-Sep-04 19-Oct-04 19-Oct-04 16-Dec-04 IBRD Works Completed 100% 4-Feb-05 18-Feb-05 1-Mar-05 3-Mar-05 7-Apr-05 16-Mar-05 21-Mar-05 4-Apr-05 final taking over from 18/03/2010 26-Apr-05 9-May-05 9-May-05 17-May-05 24-May-05 31-May-05 15-Jul-05 10-Aug-05 12-Sep-05 167 12-Mar-07 24-Nov-08 Planned 4-May-05 6-May-05 13-May-05 20-May-05 26-May-05 2-Jun-05 30-Jun-05 7-Jul-05 78 4-Jan-07 Wokrs Phase II - Rehabilitation of Byblos old city PII- Byblos Mina square CHUD/W/byblos/16677 IBRD 1,249,279.52 343,551.86 79,802.43 237,727.52 Completed 18-Dec-06 2-Mar-07 8-Mar-07 16-Mar-07 22-Mar-07 2-May-07 7-May-07 14-May-07 20-Jun-07 25-Jun-07 30-Aug-07 13-Sep-07 28-Sep-07 2-Nov-07 IBRD 100% and Coastal Path Final taking over 21-Nov-07 7-Dec-07 3-Jan-08 29-Feb-08 6-Mar-08 17-Mar-08 9-Apr-08 14-Jul-08 29-Aug-08 156 26-Apr-10 23-Aug-11 Planned 9-May-07 11-May-07 18-May-07 25-May-07 31-May-07 7-Jun-07 11-Jun-07 14-Jun-07 26-Jul-07 2-Aug-07 5-Aug-07 12-Aug-07 19-Aug-07 24-Aug-07 31-Aug-07 28-Sep-07 5-Oct-07 78 26-Feb-10 Wokrs Phase II - Construction of a new Parking Area CHUD/W/byblos/T1 IBRD 907,759.60 Completed 28-Oct-14 12-Nov-14 14-Nov-14 IBRD Tender Dossier under peparation Planned 25-Apr-14 27-Apr-14 4-May-14 11-May-14 17-May-14 24-May-14 27-May-14 31-May-14 12-Jul-14 19-Jul-14 22-Jul-14 29-Jul-14 21-Nov-14 26-Nov-14 3-Dec-14 17-Dec-14 24-Dec-14 40 30-Sep-15 30-Sep-15 Saida Works Phase I -Bab Al Serail Square section 1,Touristic Path section 2& CHUD/W/Saida/3472 IBRD 990,339.74 55,622.08 Completed 3-Jan-05 27-Jan-05 1-Feb-05 11-Feb-05 14-Feb-05 27-Feb-05 22-Mar-05 28-Mar-05 10-May-05 24-May-05 24-May-05 31-May-05 8-Jun-05 10-Jun-05 15-Jun-05 29-Jul-05 19-Sep-05 101 19-Mar-07 27-Aug-07 IBRD Works Completed 100% Electrical Works Planned 10-May-05 17-May-05 19-May-05 26-May-05 2-Jun-05 8-Jun-05 15-Jun-05 13-Jul-05 20-Jul-05 78 17-Jan-07 Works Phase I - The souks (markets) - section 3 & Electrical Works CHUD/W/Saida/4424 IBRD 936,875.48 257,640.76 Completed 10-Nov-05 16-Nov-05 23-Nov-05 1-Dec-05 5-Dec-05 26-Dec-05 3-Jan-06 3-Jan-06 28-Feb-06 23-Mar-06 23-Mar-06 28-Mar-06 4-Apr-06 12-Apr-06 29-May-06 20-Jun-06 26-Oct-06 162 25-Oct-07 30-Nov-09 IBRD Works Completed 100% Planned 10-Nov-05 12-Nov-05 19-Nov-05 26-Nov-05 2-Dec-05 9-Dec-05 12-Dec-05 16-Dec-05 27-Jan-06 3-Feb-06 6-Feb-06 13-Feb-06 20-Feb-06 25-Feb-06 4-Mar-06 1-Apr-06 8-Apr-06 78 6-Oct-07 Woks Phase II - Touristic Path, joumaa and salameh buildings & Electrical CHUD/W/Saida/17235 IBRD 2,418,950.50 665,211.39 1,000,000.00 100,000.00 Completed 8-Jan-09 15-Jan-09 26-Jan-09 29-Jan-09 30-Mar-09 27-Apr-09 14-May-09 30-Jun-09 26-Oct-09 4-Nov-09 12-Nov-09 IBRD 97% Works 3-Feb-10 5-Feb-10 15-Feb-10 17-Feb-10 24-Feb-10 7-Apr-10 31-May-10 235 30-May-11 30-Nov-14 Planned 24-Oct-08 26-Oct-08 2-Nov-08 9-Nov-08 15-Nov-08 22-Nov-08 25-Nov-08 29-Nov-08 10-Jan-09 17-Jan-09 20-Jan-09 27-Jan-09 3-Feb-09 8-Feb-09 15-Feb-09 15-Mar-09 22-Mar-09 52 21-Mar-10 21-Mar-10 private the completion date will be Works phase II - Sea Front (Electrical Cables, Facades, Public Spaces) CHUD/W/Saida/17171 Private 2,390,000.00 17-Jun-09 3-Sep-09 5-Nov-09 20% Sector extended 24-Nov-09 26-Nov-09 NA NA 29-Apr-10 5-May-10 NA NA 15-Feb-10 20-Apr-10 240 25-Nov-14 25-Nov-14 30-Mar-09 1-Apr-09 8-Apr-09 15-Apr-09 21-Apr-09 28-Apr-09 1-May-09 5-May-09 16-Jun-09 23-Jun-09 26-Jun-09 3-Jul-09 3-Dec-09 NA NA 14-Jan-10 21-Jan-10 78 21-Jul-11 21-Jul-11 Saida & Baalbeck Only one bid received.Waiting Woks Phase II - Khan El Echlé and Serail of Baalbeck CHUD/W/baal-Saida/T1 Italy 2,136,000.00 1,875,000.00 Completed 16-Dec-13 10-Jan-14 3-Feb-14 NA NA 8-Feb-14 Italy Board decision on next step Planned 2-Dec-10 4-Dec-10 11-Dec-10 17-Jan-14 22-Jan-14 29-Jan-14 2-Feb-14 5-Feb-14 29-Apr-14 6-May-14 8-May-14 15-May-14 22-May-14 28-May-14 4-Jun-14 2-Jul-14 9-Jul-14 78 6-Jan-16 Tripoli Works Phase I - Northern Souks Facades CHUD/W/Tripoli/3473 IBRD 865,377.46 173,450.74 Completed 31-Aug-04 8-Sep-04 21-Sep-04 21-Sep-04 24-Sep-04 20-Oct-04 22-Oct-04 22-Dec-04 28-Jan-05 28-Jan-05 11-Feb-05 25-Feb-05 100% 6-Apr-05 6-Apr-05 15-Apr-05 25-Apr-05 15-Apr-05 24-May-05 1-Aug-05 13-Sep-05 71 13-Mar-07 20-Jan-07 IBRD Works Completed Planned 5-May-05 2-Jun-05 9-Jun-05 78 7-Dec-06 Works Phase I - Resettlement Housing - Block A CHUD/W/Tripoli/4433 IBRD 650,644.09 221,738.49 Completed 22-Sep-04 22-Sep-04 6-Oct-04 22-Oct-04 26-Oct-04 20-Dec-04 28-Dec-04 30-Dec-04 2-Mar-05 23-Mar-05 23-Mar-05 29-Mar-05 8-Apr-05 15-Apr-05 8-Jun-05 15-Dec-05 3-Jan-06 72 2-Jan-07 18-May-07 IBRD Works Completed 100% Planned 5-May-05 2-Jun-05 9-Jun-05 78 7-Dec-06 Works Phase I - Resettlement Housing - Block B CHUD/W/Tripoli/3572 IBRD 803,673.46 273,890.66 Completed 10-Oct-04 27-Jan-05 1-Feb-05 11-Feb-05 14-Feb-05 27-Feb-05 16-Mar-05 18-Mar-05 4-May-05 26-May-05 26-May-05 31-May-05 8-Jun-05 10-Jun-05 15-Jun-05 23-Aug-06 26-Sep-06 74 25-Sep-07 24-Feb-08 IBRD Works Completed 100% Planned 4-May-05 11-May-05 13-May-05 20-May-05 27-May-05 2-Jun-05 9-Jun-05 7-Jul-05 14-Jul-05 78 11-Jan-07 Works Phase I - Northern Souks Public Spaces CHUD/W/Tripoli/4496 AFD 1,644,280.11 Completed 1-Oct-05 27-Oct-05 1-Nov-05 16-Nov-05 21-Nov-05 21-Nov-05 22-Dec-05 26-Dec-05 25-Jan-06 10-Feb-06 10-Feb-06 21-Feb-06 28-Feb-06 2-Mar-06 11-Apr-06 9-May-06 19-Jun-06 88 18-Jun-07 24-Aug-08 AFD Works Completed 100% Planned 13-Jun-05 1-Oct-05 8-Oct-05 15-Oct-05 20-Oct-05 27-Oct-05 31-Oct-05 3-Nov-05 15-Dec-05 22-Dec-05 25-Dec-05 1-Jan-06 8-Jan-06 14-Jan-06 21-Jan-06 18-Feb-06 25-Feb-06 52 24-Feb-07 Works Phase II - Northern Souks Facades Package 2 CHUD/W/Tripoli/4454 IBRD 664,326.77 85,328.90 Completed 15-Feb-06 23-Feb-06 28-Feb-06 8-Mar-06 13-Mar-06 27-Mar-06 8-Apr-06 11-Apr-06 10-May-06 7-Jun-06 7-Jun-06 13-Jun-06 20-Jun-06 21-Jun-06 3-Jul-06 19-Sep-06 27-Nov-06 65 26-Nov-07 15-May-08 IBRD Works Completed 100% Planned 15-Feb-06 17-Feb-06 24-Feb-06 3-Mar-06 9-Mar-06 16-Mar-06 19-Mar-06 23-Mar-06 4-May-06 11-May-06 14-May-06 21-May-06 28-May-06 2-Jun-06 9-Jun-06 7-Jul-06 14-Jul-06 52 13-Jul-07 Works Phase II - Facades Rehabilitation of "Dahir Il Mughur" Buildings CHUD/W/Tripoli/4675 IBRD 779,034.34 64,740.26 Completed 12-Apr-06 27-Apr-06 3-May-06 8-May-06 12-May-06 22-May-06 1-Jun-06 2-Jun-06 22-Jun-06 14-Sep-06 14-Sep-06 22-Sep-06 5-Oct-06 10-Oct-06 20-Oct-06 8-Feb-07 21-Mar-07 33 20-Sep-07 5-Nov-07 IBRD Works Completed 100% Planned 31-Mar-06 2-Apr-06 9-Apr-06 16-Apr-06 22-Apr-06 29-Apr-06 2-May-06 6-May-06 17-Jun-06 24-Jun-06 27-Jun-06 4-Jul-06 11-Jul-06 16-Jul-06 23-Jul-06 20-Aug-06 27-Aug-06 39 27-May-07 Works Phase II - Rehabilitation of Abu Ali River Banks CHUD/W/Tripoli/4836 AFD 9,513,734.71 353,182.25 635,255.43 63,525.54 Completed 22-Apr-04 31-Aug-06 14-Sep-06 25-Sep-06 26-Sep-06 25-Apr-07 14-May-07 16-May-07 3-Jul-07 1-Sep-07 1-Sep-07 13-Sep-07 20-Sep-07 29-Oct-07 15-Nov-07 3-Jan-08 261 2-Jan-10 31-Dec-12 AFD 90% final amount under preparation IBRD Planned 30-Mar-07 1-Apr-07 8-Apr-07 15-Apr-07 21-Apr-07 28-Apr-07 1-May-07 5-May-07 16-Jun-07 10-Jul-07 12-Jul-07 19-Jul-07 26-Jul-07 1-Aug-07 8-Aug-07 5-Sep-07 12-Sep-07 104 9-Sep-09 IBRD The CDR Board approved to Works Phase II - Resettlement Housing -Block C CHUD/W/Tripoli/16783 IBRD 1,476,545.60 671,572.55 Completed 16-Jan-08 24-Jan-08 5-Feb-08 4-Feb-08 18-Feb-08 13-Mar-08 24-Mar-08 27-May-08 26-Aug-08 4-Sep-08 15-Sep-08 17-Sep-08 2-Oct-08 14-Nov-08 29-Sep-09 58 28-Sep-10 31-Dec-10 IBRD 100% convert the remaining amount in Works Phase II - Resettlement Housing -Block C - Additional works CHUD/W/Tripoli/16783 IBRD 128,664.00 25,021.80 Completed 22-Aug-11 22 23-Jan-12 31-Mar-12 IBRD this contract to a “Security and 70% maintenance contract� for Khan el Planned 15-Jun-07 17-Jun-07 24-Jun-07 1-Jul-07 7-Jul-07 14-Jul-07 17-Jul-07 21-Jul-07 1-Sep-07 8-Sep-07 11-Sep-07 18-Sep-07 25-Sep-07 30-Sep-07 7-Oct-07 4-Nov-07 11-Nov-07 78 10-May-09 Askar Works Phase II - Khan Al Askar CHUD/W/Tripoli/T17332 IBRD 500,000.00 2,964,652.38 296,465.25 Completed 30-Mar-09 8-Jul-09 16-Jul-09 27-Jul-09 29-Jul-09 12-Aug-09 12-Feb-10 GL 100% 11-Nov-09 26-Oct-09 18-Nov-09 9-Dec-09 10-Dec-09 12-Feb-10 16-Mar-10 16-Mar-10 23-Mar-10 6-Apr-10 12-Apr-10 19-Apr-10 IBRD 17-Jun-10 1-Jul-10 13-Jul-10 7-Sep-10 23-Oct-10 108 18-Nov-12 18-Nov-12 Planned 15-Mar-09 17-Mar-09 24-Mar-09 31-Mar-09 6-Apr-09 13-Apr-09 15-Aug-09 19-Aug-09 30-Sep-09 7-Oct-09 9-Oct-09 16-Oct-09 23-Oct-09 29-Oct-09 5-Nov-09 3-Dec-09 10-Dec-09 78 Works Phase II -Khan el Arasat, Hammam El Nouri, Khan el Saboun CHUD/W/Tripoli/T3 AFD 3,500,000.00 Completed AFD Planned 23-Jul-16 26-Jul-16 2-Aug-16 9-Aug-16 14-Aug-16 21-Aug-16 25-Aug-16 28-Aug-16 9-Oct-16 16-Oct-16 19-Oct-16 26-Oct-16 2-Nov-16 8-Nov-16 15-Nov-16 13-Dec-16 20-Dec-16 78 19-Jun-18 Works Phase II -Traditional houses (Lot 131) CHUD/W/Tripoli/T4 AFD 3,000,000.00 Completed AFD Planned 1-Dec-14 4-Dec-14 11-Dec-14 18-Dec-14 24-Dec-14 31-Dec-14 3-Jan-15 7-Jan-15 18-Feb-15 25-Feb-15 27-Feb-15 6-Mar-15 13-Mar-15 19-Mar-15 26-Mar-15 23-Apr-15 30-Apr-15 78 27-Oct-16 Works Phase III - Facades and Public Spaces Op 5&7 CHUD/W/Tripoli/T5 AFD 2,500,000.00 Completed AFD Planned 1-Dec-14 3-Dec-14 10-Dec-14 17-Dec-14 23-Dec-14 30-Dec-14 2-Jan-15 6-Jan-15 17-Feb-15 24-Feb-15 27-Feb-15 6-Mar-15 13-Mar-15 18-Mar-15 25-Mar-15 22-Apr-15 9-Aug-15 78 5-Feb-17 Works Phase III - Facades and Public Spaces Op 4,6,8 CHUD/W/Tripoli/T6 AFD 5,000,000.00 Completed AFD Planned 1-Dec-14 3-Dec-14 10-Dec-14 17-Dec-14 23-Dec-14 30-Dec-14 2-Jan-15 6-Jan-15 17-Feb-15 24-Feb-15 27-Feb-15 6-Mar-15 13-Mar-15 18-Mar-15 25-Mar-15 22-Apr-15 9-Aug-15 78 5-Feb-17 Works Phase III - Facades rehabilitation along Abu Ali CHUD/W/Tripoli/T7 AFD 3,000,000.00 Completed AFD River side. Planned 28-Feb-16 2-Mar-16 9-Mar-16 16-Mar-16 22-Mar-16 29-Mar-16 1-Apr-16 5-Apr-16 17-May-16 24-May-16 26-May-16 2-Jun-16 9-Jun-16 15-Jun-16 22-Jun-16 20-Jul-16 27-Jul-16 78 24-Jan-18 CHUD – PMU – 2 Lebanon000Cult0t000procurement0plan.xls - works details Page 5 of 6 Date: 05/29/2015 Procurement Plan Baseline Cultural Heritage and Urban Development Project Management Unit Council for Development and Reconstruction Cultural Heritage and Urban Development Project Management Unit - Projects Division NB: Finished Date 22.4 days 14 days 42 days 29.4 days 7 days 35 days Procurement Plan Baseline Works Contracts Actual Ending Date Update (Completed) and New Baseline (Planned) Tender Documents Approvals Period = 4.2 weeks Adv Period = 1 weeks Bid Pd = 6 weeks Bid Evaluation Period = 5.2 weeks Award=5 weeks Ongoing Projects as at February 2014 Works Durations 0.4 wk 1 wk 1 wk 0.8 wk 1 wk 0.5 wk 0.5 wk 6 wk 1 wk 0.4 wk 1 wk 1 wk 0.8 wk 1 wk 4 wk 1 wk Request Board Board Request Board Request Complete Board no-objection Tenders Issue Complete Request Board Board no-objection Award Contract Funding Original Loan Amount AF Loan Amount Approval Approval on no-objection Bids Approval no-objection Notice to Dur Last revised Funding % of Contract Description Reference US$ US$ Tender Approval on Tender Department Tender Bids Approval on Approval on Bids Notification Completion Status Source Documents on Tender Tender Notification on Tender Documents Advertisement Documents Opening Evaluation Bids Evaluation on Bids Notification on Bids Evaluation and Signature Commence Wks Date Completion date Source Completion Documents Documents Documents Evaluation Evaluation Foreign Local Foreign Local Tyre Works Phase I - Coast Line Preservation CHUD/W/Tyre/3859 IBRD 906,606.50 170,446.59 Completed 25-Jun-04 6-Jul-04 20-Jul-04 27-Jul-04 12-Aug-04 16-Sep-04 23-Sep-04 23-Nov-04 21-Dec-04 21-Dec-04 30-Dec-04 14-Jan-05 18-Jan-05 4-Feb-05 22-Mar-05 29-Jul-05 81 28-Jul-06 12-Feb-07 IBRD Works 100% Planned 8-Jun-05 15-Jun-05 52 14-Jun-06 Completed CHUD/W/Tyre/3474 IBRD 1,488,382.60 200,202.06 Completed 25-Jun-04 6-Jul-04 20-Jul-04 27-Jul-04 12-Aug-04 16-Sep-04 23-Sep-04 23-Nov-04 21-Dec-04 21-Dec-04 30-Dec-04 14-Jan-05 Works 100% 28-Jan-05 28-Jan-05 11-Feb-05 25-Feb-05 25-Feb-05 27-Feb-05 4-Apr-05 29-Jul-05 145 26-Jan-07 8-May-08 IBRD Completed Planned 8-Jun-05 15-Jun-05 78 13-Dec-06 Works Phase II - Infrastructure Works for parts of Tyre City CHUD/W/Tyre/4495 IBRD 801,325.74 300,007.74 Completed 29-Nov-05 9-Dec-05 9-Dec-05 9-Dec-05 26-Dec-05 28-Dec-05 30-Dec-05 30-Jan-06 6-Feb-06 6-Feb-06 15-Feb-06 17-Feb-06 21-Feb-06 22-Feb-06 31-Mar-06 10-May-06 251 9-Jan-07 28-Feb-11 IBRD 100% 2-Mar-06 7-Mar-06 13-Mar-06 16-Mar-06 11-Apr-06 Works Completed Planned 26-Jan-06 28-Jan-06 4-Feb-06 11-Feb-06 17-Feb-06 24-Feb-06 27-Feb-06 3-Mar-06 14-Apr-06 21-Apr-06 24-Apr-06 1-May-06 8-May-06 13-May-06 20-May-06 17-Jun-06 24-Jun-06 43 24-Apr-07 Works Phase II - Fishing Port Area Waterfront, Public Spaces CHUD/W/Tyre/17073 AFD 3,000,000.00 547,424.41 592,279.32 167,303.99 Completed 23-Jan-09 28-Jan-09 12-Feb-09 26-Feb-09 10-Mar-09 24-Mar-09 14-Apr-09 27-Apr-09 15-Jun-09 14-Jul-09 14-Jul-09 16-Jul-09 27-Jul-09 23-Jul-09 7-Sep-09 AFD 87% 10-Sep-09 5-Nov-09 7-Dec-09 4-Feb-10 236 4-Aug-11 12-Aug-14 Planned 4-Nov-08 6-Nov-08 13-Nov-08 20-Nov-08 26-Nov-08 3-Dec-08 6-Dec-08 10-Dec-08 21-Jan-09 28-Jan-09 31-Jan-09 7-Feb-09 14-Feb-09 19-Feb-09 26-Feb-09 26-Mar-09 2-Apr-09 78 30-Sep-10 Woks Phase II - Bawabeh Square, Hammam Square and Hamra Street CHUD/W/Tyre/16954 IBRD 2,831,104.96 778,553.86 2,375,757.85 237,575.79 Completed 23-Apr-08 27-May-08 12-Jun-08 23-Jun-08 24-Jun-08 IBRD 100% 18-Nov-08 25-Nov-08 16-Dec-08 22-Dec-08 22-Dec-08 4-Feb-09 3-Mar-09 3-Mar-09 5-Mar-09 13-Mar-09 20-Mar-09 7-Apr-09 15-May-09 30-Jun-09 219 28-Dec-10 12-Sep-13 Planned 23-Apr-08 25-Apr-08 2-May-08 9-May-08 15-May-08 22-May-08 25-May-08 29-May-08 10-Jul-08 17-Jul-08 20-Jul-08 27-Jul-08 3-Aug-08 8-Aug-08 15-Aug-08 12-Sep-08 19-Sep-08 78 19-Mar-10 Woks Phase II -Bawabah Saha and Market improvements (direct Contract) 2,042,459.10 IBRD and Construction of a new Parking Area Planned 15-Dec-14 22-Dec-14 52 21-Dec-15 Works Phase III -Extension of Coastal Promenade (Ras el Jamal) CHUD/W/Tyre/T1 AFD 1,000,000.00 Completed AFD Planned 20-Dec-14 22-Dec-14 29-Dec-14 5-Jan-15 11-Jan-15 18-Jan-15 21-Jan-15 25-Jan-15 8-Mar-15 15-Mar-15 18-Mar-15 25-Mar-15 1-Apr-15 6-Apr-15 13-Apr-15 22-Aug-15 29-Aug-15 78 25-Feb-17 Works Phase III -Facades Rehabilitation & Public Spaces (the Souks) CHUD/W/Tyre/T3 AFD 1,000,000.00 Completed AFD Planned 20-Dec-14 22-Dec-14 29-Dec-14 5-Jan-15 11-Jan-15 18-Jan-15 21-Jan-15 25-Jan-15 8-Mar-15 15-Mar-15 18-Mar-15 25-Mar-15 1-Apr-15 6-Apr-15 13-Apr-15 11-May-15 18-May-15 104 15-May-17 2. Archeology Works Phase II - Tyre Sea Wall CHUD/W/Arch./16610 IBRD 247,477.28 68,056.25 Completed 22-Mar-07 1-Mar-07 8-Mar-07 15-Mar-07 26-Mar-07 2-May-07 16-May-07 28-May-07 10-Jul-07 24-Sep-07 6-Dec-07 18-Dec-07 18-Dec-07 12-Mar-08 10-Apr-08 35 10-Dec-08 9-Dec-08 IBRD Works Completed 100% Planned 15-Oct-06 18-Oct-06 25-Oct-06 1-Nov-06 7-Nov-06 14-Nov-06 17-Nov-06 21-Nov-06 2-Jan-07 17-Jul-07 19-Jul-07 26-Jul-07 2-Aug-07 8-Aug-07 15-Aug-07 12-Sep-07 19-Sep-07 26 19-Mar-08 Prequalification for Baalbeck and Tyre Archeological Works BTAP I CHUD/Prequ./Arch/1 Completed 27-Oct-05 1-Nov-05 16-Nov-05 21-Nov-05 26-Dec-05 3-Jan-06 3-Jan-06 6-Feb-06 4-Apr-06 4-Apr-06 11-Apr-06 19-Apr-06 28-Apr-06 13-Jun-06 7-Nov-06 13-Nov-06 11-Dec-06 28-May-07 7-Jun-07 20-Jun-07 22-Jun-07 26-Jun-07 Prequalification 26-Jun-07 1-Aug-07 N/A N/A Completed Planned 15-Oct-05 22-Oct-05 29-Oct-05 3-Nov-05 10-Nov-05 14-Nov-05 17-Nov-05 29-Dec-05 5-Jan-06 8-Jan-06 15-Jan-06 22-Jan-06 28-Jan-06 4-Feb-06 Packeging & Cancelled & divided into 2 Baalbeck and Tyre Archeological Works Phase I Completed 15-Jul-08 11-Aug-08 21-Aug-08 1-Sep-08 5-Sep-08 29-Sep-08 15-Oct-08 27-Oct-08 IBRD Rebidding Packages Cancelled divided into 2 packages (package1 Infrastructures and package 2 30-Oct-08 11-Aug-08 21-Aug-08 5-Sep-08 29-Sep-08 15-Oct-08 2-Apr-09 17-Jun-09 17-Jun-09 23-Jun-09 6-Jul-09 13-Jul-09 5-Aug-09 Conservation Works) Planned 6-Jul-09 8-Jul-09 15-Jul-09 22-Jul-09 28-Jul-09 4-Aug-09 7-Aug-09 11-Aug-09 22-Sep-09 29-Sep-09 2-Oct-09 9-Oct-09 16-Oct-09 21-Oct-09 28-Oct-09 25-Nov-09 2-Dec-09 78 1-Jun-11 Baalbeck and Tyre Archeological Works Phase I- Infrastructures CHUD/W/Arch./17327 IBRD 3,083,551.80 847,976.80 1,905,887.16 190,588.72 Completed 10-Sep-09 16-Sep-09 29-Sep-09 6-Oct-09 9-Oct-09 19-Oct-09 12-Jan-10 1-Mar-10 1-Mar-10 4-Mar-10 16-Mar-10 18-Mar-10 IBRD 97% the remaining works were removed 5-May-10 13-May-10 31-May-10 29-Jun-10 52 28-Jun-11 3-Mar-14 from this contract. Works will be handed over in their actual situation Planned 6-Aug-09 8-Aug-09 15-Aug-09 22-Aug-09 28-Aug-09 4-Sep-09 7-Sep-09 11-Sep-09 23-Oct-09 30-Oct-09 2-Nov-09 9-Nov-09 20-May-10 25-May-10 1-Jun-10 29-Jun-10 6-Jul-10 52 5-Jul-11 the contractor express his capability Baalbeck and Tyre Archeological Works Phase I- Conservation Works CHUD/W/Arch./17748 IBRD 3,677,837.00 367,783.70 Completed 13-May-11 20-May-11 30-May-11 1-Jun-11 10-Jun-11 29-Jun-11 4-Jul-11 27-Sep-11 22-Dec-11 13-Jan-12 31-Jan-12 6-Mar-12 28-Feb-14 104 26-Feb-16 IBRD to finalise the works before dec 20% 2015 Planned 21-Dec-10 22-Dec-10 29-Dec-10 5-Jan-11 10-Jan-11 17-Jan-11 21-Jan-11 24-Jan-11 7-Mar-11 14-Mar-11 17-Mar-11 24-Mar-11 31-Mar-11 5-Jan-00 12-Jan-00 9-Feb-00 16-Feb-00 104 13-Feb-02 Baalbeck and Tyre Archeological Works Phase II CHUD/W/Arch./T3 Italy 4,487,000.00 Completed 25-Apr-12 6-Dec-12 27-Dec-12 21-Jan-13 NA NA 24-Apr-13 1-Nov-13 25-Nov-13 10-Sep-14 Italy 5-Sep-11 23-Dec-10 30-Dec-10 5-Jan-11 10-Jan-11 17-Jan-11 30-Jan-13 30-Jan-13 Planned 11-Feb-00 15-May-13 17-May-13 24-May-13 31-May-13 6-Jun-13 13-Jun-13 11-Jul-13 18-Jul-13 104 16-Jul-15 Saida - Chateau de la terre CHUD/W/Arch./T4 Italy Completed 23-Jan-12 2-Feb-12 20-Feb-12 NA NA 2-Mar-12 5-Mar-12 14-Jun-12 14-Sep-12 1-Oct-12 4-Oct-12 28-Mar-14 56 24-Apr-15 Italy The start of works in Tripoli Mill is Planned 10-Aug-11 16-Jan-12 23-Jan-12 30-Jan-12 4-Feb-12 11-Feb-12 15-Feb-12 18-Feb-12 31-Mar-12 7-Apr-12 10-Apr-12 17-Apr-12 24-Apr-12 30-Apr-12 7-May-12 4-Jun-12 11-Jun-12 56 8-Jul-13 pending The municipality capability 1,100,000.00 € Tripoli Mill CHUD/W/Arch./T5 Italy Completed 23-Jan-12 2-Feb-12 20-Feb-12 NA NA 2-Mar-12 5-Mar-12 14-Jun-12 14-Sep-12 1-Oct-12 4-Oct-12 29-Dec-12 28-Mar-14 38 19-Dec-14 Italy on removing The shoes vendors Planned 10-Aug-11 12-Aug-11 19-Aug-11 26-Aug-11 1-Sep-11 8-Sep-11 11-Sep-11 15-Sep-11 27-Oct-11 3-Nov-11 6-Nov-11 13-Nov-11 11-Oct-12 16-Oct-12 23-Oct-12 26-Jan-13 2-Feb-13 38 26-Oct-13 from The entrance of The Mill. Works Phase II - Tripoli Citadel CHUD/W/Arch./17101 AFD 1,167,206.10 412,632.56 32,017.31 Completed 7-Oct-08 20-Oct-08 30-Oct-08 17-Nov-08 24-Nov-08 11-Dec-08 23-Jul-09 30-Jul-09 AFD 99% 28-Nov-08 4-Dec-08 22-Dec-08 12-Jan-09 24-Mar-09 19-Mar-09 30-Mar-09 19-May-09 10-Jul-09 10-Jul-09 10-Sep-09 18-Sep-09 28-Sep-09 15-Oct-09 7-Dec-09 11-Jun-10 126 10-Jun-11 10-Nov-12 Planned 14-Oct-06 17-Oct-06 24-Oct-06 31-Oct-06 6-Nov-06 13-Nov-06 16-Nov-06 20-Nov-06 1-Jan-07 8-Jan-07 10-Jan-07 17-Jan-07 24-Jan-07 30-Jan-07 6-Feb-07 6-Mar-07 13-Mar-07 52 11-Mar-08 CHUD – PMU – 2 Lebanon000Cult0t000procurement0plan.xls - works details Page 6 of 6 Date: 05/29/2015