Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: 27 October 2016]: Revision 1 of Updated Procurement Plan, June 2017] 2. Date of General Procurement Notice: June 2017 3. Period covered by this procurement plan: The procurement period of project covered from year June 2017 to June 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: 2. Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: NA 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Grant (IDA D1510-BI) issued by PRODEMA- PCU. 5. Any Other Special Procurement Arrangements: NA 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness a. Procurement of works, goods, IT systems and non-consultant services 1 2 3 4 5 6 7 Ref. Estimated Procurement Domestic Review Description P-Q No. cost (US $) Method Preference by WB Prior/Post Works Rehabilitation of Nyamuswaga 1 1 154 250 NCB No N/A Post marchland (Ngozi) (285 ha)) Rehabilitation of Ndurumu 2 850 500 NCB No N/A Post Marshland (Ngozi) (210 ha) Rehabilitation of Kinywamagana and 3 635 850 NCB No N/A Post RuhoheraMarshalnd (Kirundo) (157 ha) Rehabilitation of Mwambu 4 (179 ha) and Nyanzari 470 790 NCB No N/A Post extension 2 (83 ha) marshland Rehabilitation of rural roads - 5 455 015 NCB No N/A Post Kirundo-Muyinga (8.273 km) Rehabilitation of rural roads - 6 369 270 NCB No N/A Post Cankuzo (6.714) km Rehabilitation of rural roads 7 2 475 000 NCB No N/A Post (lot No1 - 45 km ) Rehabilitation of ISABU 8 31 000 Shopping No N/A Post Invitro laboratory Maintenance work of selected 9 263 900 NCB No N/A Post irrigation schemes Maintenance work of selected 10 158 300 NCB No N/A Post damaged rural roads 1 2 3 4 5 6 7 Goods and IT systems 11 PCU vehicles (3) 108 400 UNOPS No N/A Prior Computers/scanners/photocopie No N/A Post 12 31 000 Shopping rs 13 Office furniture 23 200 Shopping No N/A Post New version of Tompro No N/A Post 14 51 600 SS software and training III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 Ref. Description of Assignment Estimated cost (US Selection Review by WB No. $) Method (Prior / Post) 1 TA to be provided by IRRI: Rice technology 298 400 SS Prior (2017-2018) 2 TA to be provided by IITA/ILRI: 224 200 SS Prior Livestock/dairy production (2017-2018) 3 TA to be provided by IITA: Nurseries and processing technology for cassava, bananas and 414 600 SS Prior other fruits (2017-2018) 4 Engineering studies and supervision of rehabilitation work related to the rural roads (65 370 500 QCBS Post km) 5 Engineering studies and supervision of work related maintenance/rehabilitation of the 80 000 SS Post irrigation schemes 6 Engineering studies and supervision of work for 45 000 SS Post the maintenance of rural roads 7 Environmental and social safeguard supervision 15 000 SS Post 8 Renewal or recruitment of new staff for the PCU Per contract SS / IC Prior 9 TA for the Batwa program/support 50 000 SS Post 10 Financial audit for 2017, 2018 and 2019 76 500 LCS Post PROCUREMENT Burundi : BI - Agro-Pastoral Productivity and Markets Development Project PLAN General Information Country: Burundi Bank’s Approval Date of the Original Procurement Plan: 2017-08-01 2019-08-06 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P107343 GPN Date: Project Name: BI - Agro-Pastoral Productivity and Markets Development Project Loan / Credit No: IDA / D1510 Executing Agency(ies): Ministry of Agriculture and Livestock WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-MINAGRIE-16791-CW- RFB-01 / Travaux de Irrigation development and Single Stage - One réhabilitation du marais de IDA / D1510 A posteriori Appel d'offres Open - National 1,323,750.00 920,614.39 Signé 2018-05-15 2018-05-20 2018-06-19 2018-07-19 2018-07-31 2019-05-27 feeder road rehabilitation Envelope Nyamuswaga (Ngozi) (285 ha) BI-MINAGRIE-16920-CW- Passation de DIR / Réalisation des Irrigation development and IDA / D1510 A priori marché de gré à Direct 250,000.00 0.00 Annulé 2017-07-05 2017-07-30 2017-09-20 2017-11-22 travaux de réfection des feeder road rehabilitation gré ouvrages hydro-gricoles BI-MINAGRIE-16792-CW- RFB-02 / Travaux de Irrigation development and Single Stage - One IDA / D1510 A posteriori Appel d'offres Open - National 978,650.00 938,397.20 Signé 2018-05-22 2018-05-27 2018-06-26 2018-07-26 2018-08-07 2019-06-03 réhabilitation du marais de feeder road rehabilitation Envelope Ndurumu (Ngozi) (210 ha) BI-MINAGRIE-16794-CW- RFB / Travaux de Irrigation development and Single Stage - One réhabilitation du marais de IDA / D1510 A posteriori Appel d'offres Open - National 735,575.00 1,173,181.74 Signé 2018-07-16 2018-07-21 2018-08-20 2018-09-05 2018-09-26 2019-05-15 feeder road rehabilitation Envelope Kinywamagana et Ruhohera (Kirundo) (157 ha) BI-MINAGRIE-16796-CW- DIR / Travaux de Passation de Irrigation development and réhabilitation des marais de IDA / D1510 A priori marché de gré à Direct 1,062,100.00 659,198.90 Signé 2018-06-25 2018-06-30 2018-07-04 2019-01-30 feeder road rehabilitation Mwambu (179 ha) et gré Nyanzari extension2 (83 ha) BI-MINAGRIE-16797-CW- DIR / Réalisation des Passation de Irrigation development and travaux de réhabilitation des IDA / D1510 A priori marché de gré à Direct 352,226.00 0.00 Annulé 2018-05-31 2018-06-03 2018-06-12 2018-11-09 feeder road rehabilitation pistes d'accès aménagé de gré Kirundo-Muyinga (8,273 km) BI-MINAGRIE-16843-CW- Support to agricultural RFQ / Renforcement des Single Stage - One IDA / D1510 productivity and access to A posteriori Demande de prix Open - National 100,000.00 0.00 Annulé 2018-07-23 2018-09-16 2018-11-18 infrastructures et Envelope markets équipements de l'ISABU BI-MINAGRIE-16840-CW- RFB / Réalisation des Passation de travaux de réhabilitation Irrigation development and IDA / D1510 A posteriori marché de gré à Direct 198,278.00 0.00 Annulé 2018-06-11 2018-06-21 2018-07-09 2018-11-06 pistes d'accès aux marais feeder road rehabilitation gré aménagés de CANKUZO (6,714 Km) Page 1 BI-MINAGRIE-77000-CW- RFB / Exécution des travaux de réhabilitation de 80 km Irrigation development and Single Stage - One En cours de pistes d'accès aux marais IDA / D1510 A posteriori Appel d'offres Open - National 4,382,000.00 0.00 2019-02-28 2019-03-02 2019-04-01 2019-04-16 2019-05-01 2019-08-29 feeder road rehabilitation Envelope d'exécution aménagés dans les Provinces de Ngozi, Kirundo, Muyinga et Cankuzo (8 lots) BI-MINAGRIE-16842-CW- Support to agricultural RFQ / Extension et Single Stage - One En attente IDA / D1510 productivity and access to A posteriori Appel d'offres Open - National 580,000.00 0.00 2019-08-09 2019-08-11 2019-09-10 2019-10-01 2019-11-03 2020-05-01 Réhabilitation du Laboratoire Envelope d'exécution markets in vitro de l'ISABU GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Passation de BI-MINAGRIE-16924-GO-UN Management and marchés auprès / Renouvellement 3 véhicules IDA / D1510 coordination of project A priori Direct 135,000.00 0.00 Annulé 2017-06-15 2017-06-28 2017-07-07 2017-10-05 des agences de UIP activities l'ONU BI-MINAGRIE-16942-GO- Management and RFQ / Renouvellement des Single Stage - One En cours IDA / D1510 coordination of project A posteriori Demande de prix Open - National 44,750.00 0.00 2017-07-18 2017-08-31 2017-09-30 équipements informatiques et Envelope d'exécution activities de reprographie BI-MINAGRIE-16947-GO- Management and Single Stage - One RFQ / Renouvellement IDA / D1510 coordination of project A posteriori Demande de prix Open - National 22,500.00 11,606.38 Signé 2017-06-19 2017-07-19 2017-07-26 Envelope climatiseurs de bureaux activities BI-MINAGRIE-16949-GO- DIR / Acquisition de la Management and Passation de nouvelle version du logiciel IDA / D1510 coordination of project A posteriori marché de gré à Direct 50,000.00 28,519.39 Signé 2017-06-07 2017-06-14 2017-06-14 2017-07-14 de gestion Tompro et activities gré formation sur site du personnel utilisateur BI-MINAGRIE-16943-GO- Management and RFQ / Mobilier, Equipements Single Stage - One IDA / D1510 coordination of project A posteriori Demande de prix Open - National 22,500.00 5,689.60 Signé 2017-09-15 2017-10-29 2017-11-16 et matériels de de bureau Envelope activities pour l'UNCP et les UIP) BI-MINAGRIE-43811-GO- Management and Single Stage - One RFQ / Rétroprojecteur et IDA / D1510 coordination of project A posteriori Demande de prix Limited 4,500.00 4,272.11 Signé 2018-05-05 2018-06-30 2018-07-30 Envelope accessoires (écran, pointeur) activities BI-MINAGRIE-55624-GO- RFB / Acquisition de trois Management and Single Stage - One véhicules pour les Unités IDA / D1510 coordination of project A posteriori Appel d'offres Open - National 135,000.00 165,659.66 Signé 2018-04-02 2018-04-04 2018-05-04 2018-05-19 2018-05-26 2018-06-10 Envelope Interprovinciales de activities coordination du Projet BI-MINAGRIE-95885-GO- RFQ / Acquisition du matériel pour la collecte des Management and Single Stage - One En attente données GEMS(18 IDA / D1510 coordination of project A posteriori Demande de prix Limited 3,600.00 0.00 2019-03-20 2019-05-15 2019-06-14 Envelope d'exécution smartphones pour les activities ODPCs, les RSE des UIPs et de l'UNCP) Page 2 BI-MINAGRIE-96042-GO- RFQ / Acquisition des Management and Single Stage - One En attente équipements et d'un kit IDA / D1510 coordination of project A posteriori Demande de prix Limited 25,000.00 0.00 2019-02-06 2019-03-05 2019-03-26 Envelope d'exécution médical pour les descentes activities sur terrain BI-MINAGRIE-26800-GO- RFQ / Acquisition de trois Management and (03) groupes électrogène pour Single Stage - One En attente IDA / D1510 coordination of project A posteriori Demande de prix Limited 15,000.00 0.00 2019-05-05 2019-06-05 2019-07-20 les Unités Interprovinciales Envelope d'exécution activities de Coordination du Projet (UICP) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-MINAGRIE-24023-CS- QCBS / Etudes techniques Sélection fondée et surveillance des travaux Irrigation development and Open - IDA / D1510 A posteriori sur la qualité et 370,500.00 198,365.42 Signé 2017-09-04 2017-09-18 2017-10-08 2017-11-05 2017-11-20 2017-12-04 2017-12-19 2018-10-15 de réhabilitation de 65 km feeder road rehabilitation International le coût de pistes d'accès aux marais aménagés BI-MINAGRIE-37883-CS- Management and LCS / Audit comptable et Sélection au IDA / D1510 coordination of project A posteriori Open - National 50,000.00 0.00 Annulé 2017-12-15 2017-12-29 2018-01-29 2018-02-26 2018-03-19 2018-04-09 2018-05-08 2018-05-29 Financier du PRODEMA moindre coût activities (Exercices 2017 et 2018). BI-MINAGRIE-37883BIS-CS- LCS / Audit Comptable et Management and Sélection au Open - En attente Financier du PRODEMA& IDA / D1510 coordination of project A posteriori 50,000.00 0.00 2017-12-15 2017-12-15 2017-12-15 2018-03-01 2018-04-11 2018-05-04 2018-05-08 2019-02-28 moindre coût International d'exécution PADZOC (Exercices activities 2017&2018) BI-PRODEMA-FA-004-CS- CQS / Enquêtes sur (i)l'adoption des pratiques pour la résilience des Sélection fondée changements climatiques, (ii) Management and sur les En cours l' adoption des techniques IDA / D1510 coordination of project A posteriori Open - National 75,000.00 0.00 2019-07-21 2019-08-14 2019-09-05 2019-09-09 2019-09-17 2019-11-03 qualifications des d'exécution d'élevage moderne pour la activities consultants production du lait et (iii) l'étude pour la satisfaction des bénéficiaires du PRODEMA BI-PRODEMA-FA-005-CS- Sélection fondée CQS / Evaluation Management and sur les Open - En attente indépendante finale des IDA / D1510 coordination of project A posteriori 95,000.00 0.00 2019-07-16 2019-08-06 2019-08-25 2019-09-15 2019-09-22 2019-11-20 qualifications des International d'exécution réalisations et impact du activities consultants PRODEMA-FA. Page 3 BI-PRODEMA-FA-002-CS- INDV / Sélection d'un bureau pour l'évaluation Sélection fondée quantitative des travaux (i) Irrigation development and sur les En attente sur les ouvrages dans les IDA / D1510 A posteriori Open - National 50,000.00 0.00 2019-08-01 2019-08-15 2019-08-30 2019-08-31 2019-09-14 2019-11-28 feeder road rehabilitation qualifications des d'exécution marais et (ii) sur les pistes consultants en vue de leur réfection, surveillance et contrôle de ces travaux. INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BI-MINAGRIE-24130-CS- Support to agricultural Sélection de CDS / Assistance technique IDA / D1510 productivity and access to A posteriori consultants par Direct 75,000.00 72,696.76 Signé 2017-08-28 2017-09-17 2017-09-28 2019-12-31 de l'UNIPROBA aux Batwa markets entente directe BI-MINAGRIE-24132-CS- CDS / Assistance technique Support to agricultural Sélection de de l'ODP Caritas Burundi IDA / D1510 productivity and access to A posteriori consultants par Direct 24,918.97 34,100.99 Signé 2017-08-28 2017-09-17 2017-09-28 2019-12-31 pour l'appui aux OPs dans markets entente directe la Province de Mwaro BI-MINAGRIE-24133-CS- CDS / Assistance technique Support to agricultural Sélection de de l'ODP COPED aux OPs IDA / D1510 productivity and access to A posteriori consultants par Direct 67,802.21 84,651.59 Signé 2017-08-28 2017-09-17 2017-09-28 2019-12-31 dans les provinces de markets entente directe Rutana, Makamba, Bururi et Rumonge BI-MINAGRIE-24236-CS- CDS / Assistance technique Support to agricultural Sélection de de l'ODP INADES IDA / D1510 productivity and access to A posteriori consultants par Direct 49,837.94 78,664.08 Signé 2017-08-28 2017-09-17 2017-09-28 2019-12-31 FORMATION aux OPs dans markets entente directe les provinces de Kirundo et Muramvya BI-MINAGRIE-24243-CS- CDS / Assistance technique Support to agricultural Sélection de de l'ODP UCODE aux OPs IDA / D1510 productivity and access to A posteriori consultants par Direct 71,569.85 84,775.62 Signé 2017-08-28 2017-09-17 2017-09-28 2019-12-31 dans les provinces de markets entente directe NGOZI et CANKUZO BI-MINAGRIE-24646-GO- Support to agricultural Sélection de DIR / ASSISTANCE IDA / D1510 productivity and access to A priori consultants par Direct 1,094,435.00 1,094,435.00 Signé 2017-07-15 2017-07-25 2017-07-30 2019-12-31 TECHNIQUE DE L'IRRI AU markets entente directe PRODEMA (2017-2019) BI-MINAGRIE-24645-GO- Support to agricultural Sélection de DIR / ASSISTANCE IDA / D1510 productivity and access to A priori consultants par Direct 1,503,181.00 1,503,181.00 Signé 2017-07-02 2017-08-01 2017-08-21 2019-12-31 TECHNIQUE DE L'IITA AU markets entente directe PRODEMA (2017-2019) BI-MINAGRIE-24022-CS- CDS / Actualisation des Sélection de Irrigation development and études techniques pour les IDA / D1510 A priori consultants par Direct 224,122.00 543,662.41 Signé 2017-09-12 2017-09-22 2017-10-17 2017-12-01 feeder road rehabilitation travaux d'AHA pour la entente directe réhabilitation de 914 ha BI-MINAGRIE-16951-CS- CDS / Actualisation des Etudes techniques Sélection de Irrigation development and d'exécution des travaux de IDA / D1510 A posteriori consultants par Direct 10,500.00 10,855.31 Signé 2017-09-15 2017-09-25 2017-10-09 2017-11-08 feeder road rehabilitation réhabilitation des pistes entente directe d'accès aux marais aménagés (Lot de 15 km) Page 4 BI-MINAGRIE-37894-CS- Management and Sélection de CDS / Elaboration des IDA / D1510 coordination of project A posteriori consultants par Direct 30,000.00 9,975.36 Signé 2017-11-26 2017-12-06 2017-12-19 2018-01-09 documents de Sauvegarde du activities entente directe Projet EECAT BI-MINAGRIE-24095-CS- Sélection de Irrigation development and CDS / Gestion IDA / D1510 A posteriori consultants par Direct 7,500.00 0.00 Annulé 2017-11-27 2017-12-14 2018-01-02 2018-01-22 feeder road rehabilitation environnementale et sociale entente directe BI-MINAGRIE-24240-CS- CDS / Assistance technique Support to agricultural Sélection de de l'ODP ASBL IDA / D1510 productivity and access to A posteriori consultants par Direct 71,366.03 99,364.71 Signé 2017-08-28 2017-09-17 2017-09-28 2019-12-31 TWITEZIMBERE aux OPs markets entente directe dans les provinces de Bubanza et Muyinga BI-MINAGRIE-43658-CS- INDV / Etude technique et Management and En cours surveillance des travaux de IDA / D1510 coordination of project A posteriori Individuel Open 20,000.00 0.00 2018-04-02 2018-05-21 2018-06-11 2018-07-16 2019-01-12 d'exécution réhabilitation du Laboratoire activities in Vitro de l'ISABU. BI-MINAGRIE-60376-CS- CDS / Elaboration d'un Management and Sélection de manuel de procédures IDA / D1510 coordination of project A posteriori consultants par Direct 30,000.00 19,550.00 Signé 2018-04-25 2018-04-29 2018-05-02 2018-05-31 administratives, financières activities entente directe et comptables ainsi que la Passation de Marchés BI-MINAGRIE-37884-CS- INDV / Recrutement d'un Responsable Management and Environnementaliste à IDA / D1510 coordination of project A priori Individuel Open 32,500.00 0.00 Annulé 2018-01-12 2018-01-17 2018-01-19 2018-01-26 2018-12-31 l'Unité Nationale de activities Coordination du Projet PRODEMA-FA. BI-MINAGRIE-37884-BIS-CS- INDV / Recrutement d'un Management and expert en mesures de IDA / D1510 coordination of project A posteriori Individuel Limited 32,500.00 30,000.00 Signé 2018-04-03 2018-04-03 2018-04-20 2018-06-18 2019-03-31 sauvegarde activities environnementales et sociales BI-MINAGRIE-43816-CS- CDS / Surveillance et Sélection de Irrigation development and En cours contrôle des travaux de IDA / D1510 A posteriori consultants par Direct 60,000.00 0.00 2019-01-25 2019-02-04 2019-04-10 2019-08-08 feeder road rehabilitation d'exécution réhabilitation des travaux entente directe pour 15 km de pistes BI-MINAGRIE-95871-CS- INDV / Assistance technique Support to agricultural En attente de la facilitation de l'accès IDA / D1510 productivity and access to A posteriori Individuel Limited 15,000.00 0.00 2019-03-22 2019-03-27 2019-04-11 2019-04-22 2019-05-22 d'exécution aux marchés-Marketing et markets commercialisation BI-MINAGRIE-43678-CS- INDV / Formation du personnel du laboratoire du Management and CNTA sur l'utilisation du En attente IDA / D1510 coordination of project A posteriori Individuel Open 10,000.00 0.00 2019-01-30 2019-02-28 2019-03-05 2019-03-15 2019-03-25 chromatographe en phase d'exécution activities gazeuse couplé a un spectromètre de masse GC/MS. BI-MINAGRIE-95893-CS- CQS / Archivage électronique Management and En cours des documents du Projet IDA / D1510 coordination of project A posteriori Individuel Limited 35,000.00 0.00 2019-04-15 2019-04-20 2019-05-11 2019-06-15 2019-08-14 d'exécution PODEMA initial et activities Financement additionnel Page 5 BI-MINAGRIE-43814-CS- INDV / Etude technique et Irrigation development and En attente surveillance des travaux de IDA / D1510 A posteriori Individuel Limited 10,000.00 0.00 2019-03-15 2019-03-20 2019-03-25 2019-04-09 2019-05-09 feeder road rehabilitation d'exécution réfection des ouvrages endommagés sur pistes BI-MINAGRIE-43702-CS- INDV / Renforcement des capacités en Gestion des Irrigation development and En attente IDA / D1510 A posteriori Individuel Limited 20,000.00 0.00 2019-08-06 2019-08-11 2019-09-01 2019-10-06 2019-11-05 Pistes et ouvrages sur pistes feeder road rehabilitation d'exécution et en Gestion de l'Eau et des ouvrages BI-MINAGRIE-43350-CS- CDS / Renforcement des Capacités des Usagers de Irrigation development and En attente IDA / D1510 A posteriori Individuel Limited 40,000.00 0.00 2019-08-14 2019-08-19 2019-09-09 2019-10-14 2019-11-13 l'Eau et des Pistes en feeder road rehabilitation d'exécution Gestion Environnementale et sociale BI-MINAGRIE-43813-CS- Support to agricultural Sélection de CDS / Logiciel TOMPROJET IDA / D1510 productivity and access to A posteriori consultants par Direct 35,000.00 0.00 Annulé 2018-04-16 2018-04-26 2018-05-16 2018-06-15 de suivi des sous-projets du markets entente directe PRODEMA-FA BI-MINAGRIE-43812-CS- Management and Sélection de CDS / Logiciel de Suivi- IDA / D1510 coordination of project A posteriori consultants par Direct 35,000.00 0.00 Annulé 2018-03-19 2018-03-29 2018-04-18 2018-05-18 Evaluation activities entente directe BI-MINAGRIE-43681-CS- CDS / Formation des Formateurs sur l'analyse Support to agricultural Sélection de Economique et Financière , IDA / D1510 productivity and access to A posteriori consultants par Direct 40,000.00 0.00 Annulé 2018-03-26 2018-04-05 2018-04-25 2018-04-28 Etablissement des Fiches markets entente directe Technico-Economiques des SP et Mise en place d'un Panel des bénéficiaires du PRODEMA BI-MINAGRIE-95987-CS- Management and Sélection de LCS / Audit comptable et En attente IDA / D1510 coordination of project A posteriori consultants par Direct 20,000.00 0.00 2019-07-10 2019-07-20 2019-09-23 2020-03-01 financier exercices 2018-2019 d'exécution activities entente directe et 2019-2020 BI-MINAGRIE-110244-CS- INDV / Appui à l'élaboration des Plans Communaux de Développement Support to agricultural En cours Communautaire (PCDC) IDA / D1510 productivity and access to A posteriori Individuel Limited 7,000.00 0.00 2019-04-23 2019-04-28 2019-05-13 2019-05-24 2019-08-22 d'exécution 3ème génération des markets communes KIGANDA et BUKEYE de la Province de Muramvya BI-PRODEMA-FA-001-CS- INDV / Recrutement de deux (02) ingénieurs en Management and Génie Civil pour appuyer le En cours IDA / D1510 coordination of project A posteriori Individuel Limited 16,000.00 0.00 2019-07-10 2019-07-15 2019-07-24 2019-07-30 2019-12-01 Responsable Irrigation et d'exécution activities Infrastructures dans le suivi des activités de marais et Pistes Page 6