The World Bank Report No: ISR9100 Implementation Status & Results Bulgaria ROAD INFRASTRUCTURE REHABILITATION PROJECT (P099894) Public Disclosure Copy Operation Name: ROAD INFRASTRUCTURE REHABILITATION PROJECT Project Stage: Implementation Seq.No: 13 Status: ARCHIVED Archive Date: 25-Dec-2012 (P099894) Country: Bulgaria Approval FY: 2007 Product Line: IBRD/IDA Region: EUROPE AND CENTRAL ASIA Lending Instrument: Specific Investment Loan Implementing Agency(ies): Key Dates Board Approval Date 26-Jun-2007 Original Closing Date 30-Jun-2011 Planned Mid Term Review Date 01-Jun-2009 Last Archived ISR Date 22-Oct-2012 Effectiveness Date 13-Dec-2007 Revised Closing Date 30-Jun-2013 Actual Mid Term Review Date 12-Oct-2009 Project Development Objectives Project Development Objective (from Project Appraisal Document) The development objective of the proposed project would be to assist Bulgaria to reduce road transport costs by improving the condition and quality of its roads network during the first years of EU accession. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Rehabilitation of selected roads 129.39 Institutional Development 12.41 Road Safety 1.96 Overall Ratings Public Disclosure Copy Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Implementation Status Overview Overall Project implementation progress is good with construction works completed at 100% (307km), a highway adviser is operational, road safety consultants hired, and adequate project management. Locations Page 1 of 6 The World Bank Report No: ISR9100 Country First Administrative Division Location Planned Actual Bulgaria Burgas Zvezdets ✔ Public Disclosure Copy Bulgaria Sofiya Zlatitsa ✔ Bulgaria Oblast Vratsa Vratsa ✔ Bulgaria Oblast Vidin Vidin ✔ Bulgaria Oblast Varna Varna ✔ Bulgaria Oblast Lovech Troyan ✔ Bulgaria Oblast Dobrich Dobrich ✔ Bulgaria Oblast Sofiya-Grad Sofia ✔ Bulgaria Oblast Silistra Silistra ✔ Bulgaria Oblast Ruse Ruse ✔ Bulgaria Oblast Turgovishte Popovo ✔ Bulgaria Oblast Pleven Pleven ✔ Bulgaria Blagoevgrad Pirin ✔ Bulgaria Oblast Sofiya Pirdop ✔ Bulgaria Burgas Marinka ✔ Bulgaria Oblast Burgas Malko Turnovo ✔ Bulgaria Oblast Lovech Lovech ✔ Bulgaria Oblast Montana Lom ✔ Public Disclosure Copy Bulgaria Pleven Gulyantsi ✔ Bulgaria Blagoevgrad Gotse Delchev ✔ Bulgaria Oblast Silistra Glavinitsa ✔ Bulgaria Blagoevgrad Petrich ✔ Bulgaria Sofiya Dolno Kamartsi ✔ Bulgaria Oblast Burgas Burgas ✔ Page 2 of 6 The World Bank Report No: ISR9100 Results Project Development Objective Indicators Public Disclosure Copy Indicator Name Core Unit of Measure Baseline Current End Target Percentage of improved Class I roads initially Text Value 0 3.6 % 3.6 % in poor condition, measured in IRI Date 01-Jan-2007 12-Dec-2012 30-Jun-2013 (International Road Roughness Index) - Comments cumulativevalues Percentage of improved Class II roads initially Text Value 0 3.2 % 3.2 % in poor condition, measured in IRI Date 01-Jan-2007 12-Dec-2012 31-Dec-2013 (International Road Roughness Index) - Comments cumulative values Percentage of improved Class III roads initially Text Value 0 0.5 % 0.5 % in poor condition, measured in IRI Date 01-Jan-2007 12-Dec-2012 31-Dec-2013 (International Road Roughness Index) - Comments cumulative values Vehicle Operating Cost on roads to be Text Value 0.250 0.225 0.225 rehabilitated under the Project (Average, 2005 Date 01-Jan-2007 12-Dec-2012 31-Dec-2013 EUR per vehicle-kilometer) Comments on completed sections Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Consultant services for project management Text Value 0 staff - months 84 staff - months 260 cumulative staff - months support for operational programs provided Date 01-Jan-2007 12-Dec-2012 31-Dec-2013 Comments Services provided by Jaspers still in progress. Consultant and advisory services for road Text Value 0 staff - months 11 staff - months 24 cumulative staff - months sector management Date 01-Jan-2007 30-Nov-2012 31-Dec-2013 Public Disclosure Copy Comments Contract signed and Final number of staff-months consultant in place is likely to be 18 months until the project closing date - June 30, 2012. Project management manuals reviewed, Text Value No Yes Yes finalized and in use Date 01-Jan-2007 06-Dec-2012 31-Dec-2013 Comments Page 3 of 6 The World Bank Report No: ISR9100 Studies on institutional set up, human Text Value No Yes resources and development of competencies in Date 01-Jan-2007 30-Aug-2012 31-Dec-2013 the sector carried out Comments Institutional assessment study Public Disclosure Copy of RIA carried out. Number of kilometers of Class I roads Text Value 0 km 117Km 117KM rehabilitated under the Project Date 01-Jan-2007 12-Dec-2012 31-Dec-2013 Comments Number of kilometers of Class II roads Text Value 0 km 127Km 127Km rehabilitated under the Project Date 01-Jan-2007 12-Dec-2012 31-Dec-2013 Comments Number of kilometers of Class III roads Text Value 0 km 63Km 63km rehabilitated under the Project Date 01-Jan-2007 12-Dec-2012 31-Dec-2013 Comments Works (W), Goods (G), and Consulting Text Value 0 (W), 0 (G), 0 (CS) 9 (W); 8 (G); 2 (CS) 9 (W); 8 (G); 2 (CS) Services (CS) contracts processed and Date 01-Jan-2007 12-Dec-2012 31-Dec-2013 managed by Management Consultant Comments Training received by NRIF staff from Text Value 0 staff-hours 720 2200 management Consultant (in staff-hours) Date 01-Jan-2007 12-Dec-2012 31-Dec-2013 Comments Updating of road data for Class I roads (% of Text Value 0% 100% 100% total length per year) Date 01-Jan-2007 12-Dec-2012 31-Dec-2013 Comments Updating of road data for Class II roads (% of Text Value 0% 50% total length per year) Date 01-Jan-2007 31-Aug-2012 31-Dec-2013 Comments The figure is as of August 30. The target will be achieved by the end of 2012. Public Disclosure Copy Updating of road data for Class III roads (% of Text Value 0% 15% total length per year) Date 01-Jan-2007 31-Aug-2012 31-Dec-2013 Comments road data collected only on recently rehabilitated road sections. Implementation and Effective use of Road Text Value No Yes Yes Management System by NRIF Date 01-Jan-2007 12-Dec-2012 31-Dec-2013 Comments Page 4 of 6 The World Bank Report No: ISR9100 Rolling Multi-year road maintenance and Text Value No Yes Yes rehabilitation program established Date 01-Jan-2007 12-Dec-2012 31-Dec-2013 Comments Public Disclosure Copy Capacity of NRIF to manage road Text Value 0 3 maintenance: number of area-wide Date 01-Jan-2007 12-Dec-2012 31-Dec-2013 maintenance contracts prepared Comments Road safety strategy and plans prepared Text Value No Date 01-Jan-2007 12-Dec-2012 31-Dec-2013 Comments Review of Road Safety Management Capacity completed. Action Plans prepared but only partially implemented. Data on Financial Performance (as of 25-Sep-2012) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date P099894 IBRD-48650 Effective 26-Jun-2007 19-Sep-2007 13-Dec-2007 30-Jun-2011 30-Jun-2013 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P099894 IBRD-48650 Effective USD 122.50 122.50 0.00 92.44 27.49 75.00 Disbursement Graph Public Disclosure Copy Page 5 of 6 The World Bank Report No: ISR9100 Public Disclosure Copy Key Decisions Regarding Implementation RIA should send the request for cancellation of the funds related to the Consulting Services for Project Management Support for Operational Programmes for Transport and Regional Development. Restructuring History Level two Approved on 14-Apr-2011 Related Projects There are no related projects. Public Disclosure Copy Page 6 of 6