Public Disclosure Copy The World Bank Implementation Status & Results Report GN-Rural Roads Emergency Improvement Project (P156557) GN-Rural Roads Emergency Improvement Project (P156557) AFRICA | Guinea | Transport Global Practice | Recipient Executed Activities | Investment Project Financing | FY 2016 | Seq No: 3 | ARCHIVED on 25-Apr-2019 | ISR36400 | Implementing Agencies: Ministry of Finance, National Directorate of Rural Engineering Key Dates Key Project Dates Bank Approval Date:08-Mar-2016 Effectiveness Date:10-Jun-2016 Original Closing Date:31-Dec-2017 Revised Closing Date:21-Apr-2019 Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to improve the accessibility of local communities to health services and Ebola treatment facilities in the targeted area by mitigating key bottlenecks along selected rural roads. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Moderately Unsatisfactory  Moderately Satisfactory Overall Implementation Progress (IP)  Moderately Unsatisfactory  Moderately Unsatisfactory Implementation Status and Key Decisions This is the final ISR. After 4 extensions of closing dates, all activities of the project meaning the rehabilitation of 50 km of rural roads and the construction of 10 pre- fabricated steel bridges are finally completed. The provisional acceptance of the installation of the 10 steel bridges was conducted on April 19, 2019. 4/25/2019 Page 1 of 4 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report GN-Rural Roads Emergency Improvement Project (P156557) Risks Overall Risk Rating Risk Category Rating at Approval Previous Rating Current Rating Overall  --  Substantial  Substantial Results Project Development Objective Indicators PHINDPDOTBL Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 66,000.00 66,000.00 Date 01-Jan-2016 -- 19-Apr-2019 19-Apr-2019 PHINDPDOTBL Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 33,000.00 33,000.00 PHINDPDOTBL Travel time reduction (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 50.00 50.00 Date 01-Jan-2016 -- 19-Apr-2019 19-Apr-2019 Overall Comments 4/25/2019 Page 2 of 4 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report GN-Rural Roads Emergency Improvement Project (P156557) Intermediate Results Indicators PHINDIRITBL Roads rehabilitated, Rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 50.00 50.00 Date 01-Jan-2016 -- 19-Apr-2019 19-Apr-2019 PHINDIRITBL Length of constructed bridges (Meter(m), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 135.00 135.00 Date 01-Jan-2016 -- 19-Apr-2019 19-Apr-2019 PHINDIRITBL Number of Ebola Treatment Unit served (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- 7.00 7.00 Date 01-Jan-2016 -- 19-Apr-2019 19-Apr-2019 Overall Comments Data on Financial Performance Disbursements (by loan) 4/25/2019 Page 3 of 4 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report GN-Rural Roads Emergency Improvement Project (P156557) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P156557 TF-A2432 Closed USD 2.85 2.85 0.00 2.81 0.04 98% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P156557 TF-A2432 Closed 08-Mar-2016 10-Jun-2016 10-Jun-2016 31-Dec-2017 21-Apr-2019 Cumulative Disbursements Restructuring History Level 2 Approved on 21-Dec-2017 ,Level 2 Approved on 28-Jun-2018 ,Level 2 Approved on 31-Mar-2019 Related Project(s) There are no related projects. 4/25/2019 Page 4 of 4 Public Disclosure Copy