AIDE MEMOIRE The Gambia Commercial Agriculture and Value Chain Management Project IDA Credit No 5399-GM; IDA Grant No H920-GM -------- Implementation Support Mission and Validation of The Gambia Agriculture Engagement Note May 6-16, 2019 I. INTRODUCTION 1. The World Bank conducted from May 6 to 16, 2019 the implementation support mission of The Gambia Commercial Agriculture and Value Chain Management Project (GCAV) combined with workshops to present and discuss the Gambia Agriculture Engagement Note. The team was led by Ms. Aifa Fatimata Ndoye Niane, Senior Agriculture Economist, Task Team Leader of the GCAV. The mission team included Nicolas Ahouissoussi and Sheu Salau (Sr. Agriculture Economists), Mouhamadou Kabir Ndoye (Procurement Specialist), Lydia Mesfin Asseres (Operation Officer) and Muhammed Lang Kinteh (Consultant, Program Assistant). Fatou Mbacke Dieng (Financial Management Specialist) and Ahmed Fall (Environmental Safeguards Specialist) visited The Gambia a few weeks ahead the mission (in April 25th and February 26 - March 1st, respectively). 2. The objectives of the GCAV mission were to: (i) assess progress made towards the project’s development objectives and target indicators; (ii) review the financial management of the project and government commitment to fully pay all the pending contracts; (iii) discuss with the project team the preparation of the implementation completion results report; (iv) conduct an ex-post financial and economic assessment of the project as part of the World Bank’s final evaluation of the project’s performance and results; (v) agree on the remaining actions until the closing of the project; and (vi) discuss with government and other stakeholders the draft Agriculture Engagement Note which will guide future dialogue in the sector. 3. The team is grateful to the Government for their availability and excellent cooperation during the mission. The draft Aide Memoire was discussed at the wrap-up meeting on May 15, 2019, chaired by Mr. Hassan Jallow, the Ministry of Agriculture’s Permanent Secretary. II. PROJECT DATA AND RATINGS Table 1: Key Project Data and Ratings Project Data USD (millions) Original Project Amount 15.92 Total Disbursement 14.54 Disbursement in FY2019 100 Closing Date November 30, 2019 Project Ratings: Previous Current PDO MU MS IP MU MS 1 Component 1: Support for the Development of Irrigation and MS MS Key Productive Infrastructure Component 2: Support to Value Chain Management MS MS Component 3: Project Administration and Institution Building MS MS Project Management MS MS Procurement MS MS III. IMPLEMENTATION PROGRESS AND KEY FINDINGS Overall project progress 4. The project is making good progress towards achieving the development objective of improving productivity and access to market of targeted agricultural commodities for smallholders in the Project Area. This progress is attested by the following achievements: 1) The rehabilitation of the 2,500 hectares of irrigation schemes has been completed and they have been under double cropping since June 2018; 2) The modernization of 21 women vegetable gardens covering 105 hectares provided with a peri-meter fence, borehole and a tank powered with solar energy system and equipped with drip irrigation systems has been completed. In terms of land certification, all the 21 women vegetable gardens got the transfer certificates from the heads of their villages (Alcalo) and districts (chief). Official transfer request through land office was made to get the leasing titles that could be used as warranty if need be. All the 21 women vegetables gardens are into production and half of them, located in the North Bank Region, have benefited from a contract farming with Radville Farms Ltd to produce baby corn every two months destined for exports to the EU markets. Although the investments made in the vegetable gardens are much higher than the initial cost estimates (US$882,590 against US$3,835,528), they are bringing a transformational change in gardening with efficient water and labor-saving irrigation technologies decreasing women’s irrigation burden and giving them more time to devote to off-farm activities and other labor-paid farm activities, working with Radville Farms in harvesting and processing horticultural crops. With a net income of GMD230,000 (US$4,650) earned from 2.5 hectare of baby corn every two-month, vegetable gardens are becoming a good source of income. In total, the 10 gardens benefiting from contract farming with Radville Farms have realized a total production of 267MT of baby corn providing a total revenue of GMD3,333,713 (US$67,130), benefiting 2,055 farmers of which 83% are women. However, the high number of women per garden, exceeding 100, makes the level of individual earning still very low with about GMD2,000 (US$40) per harvest every two months in addition to what they earn from their other traditional vegetable crops. A proper financial and economic analysis and an impact study will be conducted to assess the soundness of these investments, their reproducibility and sustainability; 3) The Small and Medium Enterprise (SME) beneficiaries of the project’s matching grants are operating, exporting and creating jobs for women, particularly. In 2018, the Gambia Horticultural Enterprise (GHE) exported 333MT of fresh mango. About 40MT of dried mango was exported by GHE and Tropingo, and about 9MT of assorted cereal products by Jals Yassin Healthy Foods. A total of 371 persons have been employed directly of which 87% women in addition to indirect employment with 175 out growers for mango. 4) In terms of finance, in addition to 100% disbursement of the International Development Association funding, the Government made a great effort respecting its 2 commitment. This is a strong signal of Government ownership and real interest in the project. The Government has made the last disbursement of counterpart funds bringing its total contribution to the project to US$1.79 million against an original expected contribution of US$0.74 million. This allows the project to resolve the financial gap that it has been facing, to fully pay the remaining pending contracts and to fund the remaining activities including the project’s completion results report, the impact study and the agreed activities of the annual work plan. 5. Given all these achievements and efforts, the project ratings have been upgraded to Moderately Satisfactory both for progress towards the achievement of the PDO and for implementation progress. The different components are rated Moderately Satisfactory. 6. However, some PDO and results indicators are not yet met despite the project restructuring approved in November 2017 (see annex 2). A big push is needed to reach the end- project indicators’ targets through close monitoring and support to the project team for a smooth and satisfactory closing. Given this situation, an early project closing is no longer a good option. Status of components and key issues Component 1: Support for the Development of Irrigation and Key Productive Infrastructure 7. The performance of the component remains Moderately Satisfactory. All the irrigation infrastructures and equipment have been completed for the 2,500 hectares of tidal irrigated rice schemes and for the 21 women vegetable gardens. 8. However, the water users’ associations (WUA) remain a big challenge as they are still not-functioning properly resulting in the rehabilitated canals not being well maintained and already fully covered with grass. Only, 12 out of a target of 20 WUAs have been trained and strengthened. The mission visited rehabilitated rice schemes and found in Wassu perimeter that the gate was facing problems and the WUA is requesting support from the project to solve it. In 2018, heavy floods have affected some perimeters making them inaccessible and inapt for rice cropping. In addition, lack of labor and equipment for land preparation have delayed the start of the dry season production during the last cropping season and even prevented some farmers from cropping all their land. This shortage of agricultural machinery that affected rice production at country-wide was due to the fact that all available tractors were sealed as part of the ex-president assets while waiting for the court conclusion. Rice producers were depending on machineries from Senegal which were also delayed in providing services. All these constraints decreased the cropped areas and compromised the rice production which decreased drastically from 25,240MT in 2017 to 15,786MT in 2018 against a project target of 34,000MT. The yield decreased from 5.09MT/ha in 2017 to 4.5MT/ha in 2018 but remains over the target of 4MT/ha. Consequently, while the project achieved the target of increased production in 2017, that is not the case in 2018. To address these problems and preserve upcoming rainy season cropping, the mission recommended to the project team to work with the water and land department to remobilize the WUAs through sensitization and training program to reengage on the maintenance of the canals by conducting urgent collective weeding and cleaning operations. The enterprise which made the rehabilitation has been contacted to do an assessment of the gate problems and to propose urgent solution to address it with the contribution of the WUAs. Agricultural machinery provided to agricultural cooperatives and producers groups by two on- going donors-funded projects will help to resolve the shortage while waiting the court decision. 3 9. Vegetable gardens are facing water deficits constraining women from fully cropping the 5 hectares available. This deficit is probably due to an inadequate management of the irrigation system even though 140 women and 4 men have been trained. The mission met and discussed with the enterprises-contractors and agreed with them to conduct an assessment and propose solutions including training as women still need additional capacity building in managing the drip system technologies in terms of scheduling daily the irrigation over plots and time. The team has advised the project team to keep consulting with Radville Farms and Gai Farm to strengthen existing agreements and to negotiate diversification into other high value crops and get contracts for the remaining women vegetable gardens located in the North Bank Region. 10. Technical support from advisory services of the Direction of Agriculture (DOA) and other private extensions agents from producers’ organizations such as Radville Farms would be important both for vegetables gardens and rice perimeters, as producers still require such support. The project is urged to complete the training plan to reach the end-project target and give more capacity to farmers to improve their cropping systems. Particularly, training in Intensive Rice Production System (SRI) for rice producers and training in drip irrigation management and entrepreneurial management and marketing skill for women, are recommended to meet the target of 500 trained (400 done so far). Component 2: Support to Value Chain Management 11. The performance of the component is still rated Moderately Satisfactory. For the two SME beneficiaries of matching grants, while GHE is operating well, Tropingo is facing some challenges to get the organic certification to be able to export in the European market in line with their business plan. Tropingo’s dried processed mango of last year has been partially exported to Nigeria with many difficulties related to sea and road freight. A stock of dried mango is still waiting for certification and other market opportunities. 12. A rice milling unit has been rehabilitated but it is not used by producers as it should be. The mission team wished to meet with the producer organization operating the mill but did not find the leader in the field. The mission recommended that the project team should meet with this organization, the regional agricultural directorate and rice producers to assess the situation and propose solutions to address it and ensure that the investment made to rehabilitate the mill is not lost and contributes to improving the quality of local rice commercialized to meet consumers requirements and better compete with imported rice. Component 3: Project Administration and Institution Building 13. The performance of the component remains Moderately Satisfactory. Project implementation is still challenged by the high turnover of the coordinators of the CPCU. Less than one year from project closing, the coordinator has been changed again. The M&E specialist is the acting coordinator and his confirmation (or designation of a new coordinator) needs to be done for a better focus on the coordination and management of the project for the achievement of the end-project targets. These cumulative functions affected the M&E system with delay in updating the new results framework resulting from the project restructuring. The project team needs to be remobilized through a strong leadership of the coordinator for the implementation of the last remaining activities and to ensure a satisfactory closing by meeting all the end project indicators targets. 14. The mission discussed with the project team the preparation of the Government’s completion results report and a plan for its preparation has been agreed upon. The mission informed the project team about the upcoming financial and economic assessment that a FAO consultant will conduct over the coming weeks and requested the PCU to support him during 4 his field mission, to make all useful documents available and to plan field visits to collect required data. Procurement 15. The mission reviewed the procurement plan of the project consisting of 25 activities and noted that most of the contracts have been awarded and their implementation completed. Few delays were noted. The contracts for the annual audit of the project awarded to DT Associates is still ongoing (78% of implementation) and it is proposed that an addendum be signed with the firm to complete the final year of audit (2019). An action plan will be prepared by the project for its implementation. As the activity is a post review, the addendum will be only submitted for the technical clearance of the World Bank. Regarding the contract for the revitalization of the cooperative awarded to Daniyako Company, it was signed on October 18, 2017 for 45 days but is still under implementation (about 60% implemented). The draft report has been submitted to the Ministry of Agriculture and waiting for the national validation. With the turnover of the staff of the Ministry, a close follow up of the report review needs to be done by the project to avoid additional delay. The procurement performance of the project is Moderately Satisfactory while the risk is Substantial. Financial Management 16. The overall financial management performance of the project has improved to Satisfactory because all unfunded commitments will now be paid through government own funds which were transferred into the project’s account. The financial gap has been covered. The mission has also noted some improvements in budget management and in the quality of supporting documents in respect of all expenditures. A proper cash book and supporting documents have been kept. However, the interim un-audited financial reports (IFRs) have not been submitted on time and there are still some improvement points related to the overall quality. A budget execution table and the expenses budgeted for the next semester should be included to make it satisfactory per the World Bank Standards. The external auditor has issued an unqualified (clean) opinion on the 2017 Financial Statements, but highlighted an overpayment and an unidentified debit of the project account by the Central Bank, for respectively 1,303.78 USD and 32,000 GMD. At the time of the mission, despite letters sent to the Central Bank by the CPCU the situation was not yet regularized. 17. The mission team recommended the project team to (i) submit on time the IFRs with all relevant documents; (ii) submit the 2018 audit report no later than June 30th, 2019; and (iii) regularize with the Central Bank the unauthorized debits. Environmental Safeguards 18. The mission conducted in March 2019 focused on reviewing the environmental and social (E&S) audit report, visiting some vegetable gardens sites (Kampant, Kappa, Buniadu and Pirang) and discussing with key stakeholders including the project team, the National Environmental Agency (NEA), etc. The mission has found that the E&S compliance plan proposed during the mid-term review (MTR) mission to address the E&S shortcomings was not implemented. Moreover, because of budget constraint, the project team failed to recruit a part-time or a short-term expert to address the non-compliance with E&S safeguards and make appropriate recommendations to remedy the shortcomings as recommended by the MTR report. 19. Consequently, the main findings during the field visit in the vegetable gardens were consistent with those in the E&S audit report: lack of appropriate training, no public awareness on the environmental friendly use of chemical pesticide, no personal protective equipment to the farmers, wastage of water from tank overflow, no ground water monitoring, lack of support 5 to NEA in order to enable it to conduct frequent site visits and monitoring of all project interventions to advise on potential E&S safeguards related impacts, etc. 20. Based on the above-mentioned shortcomings, the implementation of the environmental safeguard measures is rated Moderately Unsatisfactorily (MU). 21. The mission recommended to finalize the review of the E&S audit report so the CPCU can formally submit it to the NEA for review and validation by the Environmental Impact Assessment (EIA) technical working group to ensure E&S concerns are adequately addressed. This is in line with the Gambian National Environment Management Act, 1994 and EIA Regulations 2014. Once reviewed and validated by NEA & EIA Working Group, an endorsement/approval will be granted, and actions can be taken to fix the E&S shortcomings. Dissemination of the Gambia Agriculture Engagement Note 22. The second part of the mission related to the validation of the Agriculture Engagement Note, which was carried out through four focus-groups to make the discussion open and constructive. The four focus-groups or audiences included: (i) the Ministry of Agriculture, CPCU team and the managing directors. It was opened by the Minister of Agriculture and chaired by the Permanent Secretary; (ii) leaders of producers’ organizations; (iii) technical and financial partners; and (iv) private sector representatives involved in agribusiness. The note was positively appreciated by the different audiences finding it informative and targeting the right country priorities. Relevant comments and suggestions were made to further emphasize : (i) the livestock sector and particularly, small ruminants given their importance in the sector and as a source of income for women - even used as a criterion for poverty assessment; (ii) private extension services from producers’ organizations, NGOs and others to complement limited public extension services; (iii) holistic approach when building climate-smart agriculture; (iv) food safety and quality control particularly for agricultural products consumed in the domestic market given the public health implication (case of aflatoxin on groundnut but also on maize) rather than focusing only on exported products to international market; (v) storage and agro-processing facilities for better conservation and marketing of horticultural products, in particular; (vi) the need to have reliable agricultural statistics and an early warning system for producers; and (vii) a strong mechanism led by the Ministry of Agriculture for better coordination of development partners’ interventions. On the policy reform agenda, the Ministry of Agriculture recognized its necessity, arguing that in 2018, US$7 million were spent in fertilizer and groundnut price subsidy alone. IV. NEXT STEPS AND AGREED ACTIONS 23. The actions agreed with the project team during this mission are summarized in table 2 with the responsible party and deadline. The implementation of these agreed actions would help closing smoothly and satisfactorily the project. Table 3 presents the previous mission’s agreed actions of which most have been implemented. The financial and economic analysis will be conducted by an FAO consultant starting May 21st, 2019. The government’s project completion report is expected by the end of September 2019. The next and final implementation support mission is scheduled for early November 2019. 6 Table 2: Summary of Agreed Actions Action Responsible Due Date Status 1. Recruitment of consultant for the CPCU June 30, 2019 ToR to be Government implementation completion prepared and results report and the impact study shared with WB team for approval. 2. Preparation and finalization of the CPCU September 30, Government implementation completion 2019 results report and impact study 3. Undertake massive advocacy campaign CPCU July 31, 2019 and sensitization of WUA on the consistent SWMS maintenance (cleaning or weeding) of the DCD rehabilitated canals 4. Support WUA to repair damaged main CPCU June 30, 2019 gate/bridge to avoid last year flooding SWMS DCD 5. Undertake an independent assessment of CPCU June 30, 2019 actual capacity of solar equipment and HTS explore options for addressing water use constraints and improving water management through targeted technical support to women vegetable garden (daily irrigation schedule) 6. Continuous consultation with Radville CPCU June 30, 2019 Rad Ville is Farms and Gai Farm to strengthen HTS looking for agreements, negotiate diversification into strategy to high value crops and get contract for contract with remaining women vegetable gardens those remoted women vegetable gardens despite river crossing constraint 7. Build marketing partnership arrangement CPCU September 30, An initial between the gardens and the Gambia HTS 2018 discussion to Hotel Association introduce the partnership to the Gambia Hotel Association has started 8. Capacity building of women vegetables CPCU July 30, 2019 producers in management skills - business planning, financial management, marketing, savings management, contract negotiation and review 9. Conduct SRI training for at least 100 rice CPCU July 31, 2019 producers to meet the target DOA 10. Close monitoring of rice and vegetable CPCU October 30, production to update the results 2019 framework and get the end project targets 11. Completion of the land transfer process CPCU August 31, for women groups’ vegetable gardens 2019 7 12. Produce a sensitization report on the CPCU June 30, 2019 creation and operation of revolving funds HST or other financial mechanisms used by ABS project beneficiaries to facilitate procurement and access to inputs (seeds, fertilizer) 13. Develop guidelines and templates for a one CPCU June 30, 2019 The delay was stop shop for agricultural investments GIEPA due to the resignation of the Focal Person at the Agency (GIEPA). 14. Strengthen advisory services to meet CPCU June 30, 2019 offtake produce quality and target, and link NSS beneficiaries to source(s) of quality seed 15. Develop a transition plan to hand over CPCU September201 management of gardens and rice field to 9 DoA 16. Monitoring the maintenance services CPCU November201 On-going contract between contractors and women’s 9 vegetable gardens CPCU September 17. Finalize the review of the 2019 environmental and social audit report and to ensure that the concerns raised with regards to compliance with the project’s environmental and social safeguards are adequately addressed through: appropriate training, public awareness on the environmental friendly use of chemical pesticide, personal protective equipment to the farmers, reduction of wastage of water from tank overflow, ground water monitoring, support to the National Environmental Agency to conduct site visits and monitoring) Table 3: Status of Agreements from the previous aide-mémoire Sr. Action Responsible Due Date Status No 1 Recruit consultant for CPCU September Done the environmental audit 5, 2018 2 Completion of the CPCU October Done environmental and 25, 2018 social audit 3 Adoption of the CPCU/NEA November Ongoing, adopted and environmental and 5, 2018 implementation is in progress social mitigation plan 8 4 Engage discussions with CPCU/HTS September Done as the project has the Gambia Hotel 10, 2018 already facilitated the Association to explore establishment of production partnership with the and market linkages between vegetable gardens and RADVILLE Farms and Gai report on outcome Enterprise. The Gambia Hotel Association is somehow limited to conducting advocacy and lobbying role. However, with regard to the latter, CPCU will continue to engage the Gambia Hotel Association 5 Produce a sensitization CPCU/HST/DCD September Not yet done report on the creation 30, 2018 and operations of revolving funds or other financial mechanisms used by project beneficiaries to facilitate procurement and access to inputs (seeds, fertilizer) 6 Produce an interim CPCU/SWMS/Lands September Done, vegetable producers progress report of the 10, 2018 i.e. three members from each capacity building of the 21 gardens were trained activities benefiting rice on the method of and vegetable producers. operationalizing and maintenance of the dripline irrigation systems. Equally, Rice producers were also train on the application of lime and phosphor-gypsium application method 7 Develop guidelines and CPCU &GIEPA November CPCU will Liaise with templates for a one stop 31, 2018 GIEPA and work on it. shop for agricultural investments 8 Prepare an update M&E CPCU July 31, Done - Following the plan including data 2018 dropping of some indicators, collection methods for M&E plan matrix has been the revised Results revised Framework of the restructured project Percentage completed 62.5% 9 Annexes Annex 1: List of officials met and composition of WB team FULL NAME DESIGNATION INSTITUTION TEL. EMAIL ADDRESS Hon Amie Hon Minister Ministry of Fabureh Agriculture (MOA) Mod Secka Permanent Ministry of Secretary Finance and Economic Affairs (MoFEA) Hassan Jallow Permanent MoA 9923084 hmjallow@gmail.com Secretary Lamin Permanent MoA 7799346 dambelkoto1@gmail.com Camara Secretary Abdoulie Acting Project CPCU/GCAV 7431591 Laye20002001@yahoo.com Touray Coordinator Molpha Procurement CPCU/GCAV 3971756 molpha.sanyang@gmail.com Sanyang Officer Bakary O. Assistant M&E CPCU/GCAV 6564308 baksca@yahoo.com Camara Sarjo Marenah Financial CPCU 9986715 Smarenah75@gmail.com controller Molipha Accountant CPCU/GCAV 9966765 darboe.molipha@yahoo.com Darboe Modou Sowe M&E CPCU 9969931 mswsowe@gmail.com Momodou Contractor Solar 23 Wone Ebrima sallah Internal Auditor CPCU 9914648 sallbrima@gmail.com Reynold Consultant RC 9909434 reycarrol@gmail.com Carroll ENGINEERIN G Mamour Sey Farm Marger Radville Farms 7760314 mamoursey@yahoo.com Président Alkali Kunda Garden Sally Badjie Secretary Kampant garden Ramatoulie President Kampant Garden Ceesay Kaddy Bojang President Mayork Garden Abdoulie Farmer (WUA) Wassu Rice Field 3390828 Sillah Malick Nyang Farmer (WUA) Wassu Rice Field 9755439 Farmer (WUA) Jahally Rice Field Lamin Senior Agric RAD – Sapu 6174928 Saidyleigh Officer Abdou Ceesay Director General DLS 2341040 Abdousungie2002@yahoo.co m Ansumana Director General NARI 9935282 Akjarju2013@gmail.com Jarju Demba Jallow Director General GLMA demsondoe@yahoo.co.uk Kebba L. Jarju Director FASDEP Project 9964392 kljarju@gmail.com Momar Taal CEO Tropingo Foods 7222202 10 Famara Sayang Project Director AVCDP 9963810 fbsanyang@gmail.com Darrel Programme EU Delegation Darrel.sextone@eeas.europa. Sextone Manager eu Sirra Njai Programme FAO Sirra.njai@fao.org Sanyang Officer Jose del Charge d’affaires Spanish Embassy Jose.delpalacio@maec.es Palacio Tamarit Anta kah Programme WFP Anta.kahjanneh@wfp.org Janneh Officer Abdoulie National UNDP Abdoulie.janneh@undp.org Janneh Economist Samuel Sarre Economic/Comm U.S. Embassy sarresj@state.gov Specialist Aifa Fatimata Sr Agriculture World Bank +221338 andoye@worldbank.org Ndoye Niane Economist 5941 42 Nicolas Sr Agriculture World Bank nahouissoussi@worldbank.or Ahouissoussi Economist g Sheu Salau Sr Agriculture World Bank ssalau@worldbank.org Economists Mouhamado Procurement World Bank mndoye@worldbank.org u Kabir Specialist Ndoye Lydia Mesfin Operation Officer World Bank lasseres@worldbank.org Asseres Muhammed Consultant, World Bank mkinteh@worldbank.org Lang Kinteh Program Assistant Ousman Consultant N/A Ousman_g@yahoo.com Gajigo EbrimaSallah Internal Auditor CPCU sallbrima@gmail.com Momodou A. Managing Gambia 77585088 Ceesay Director Horticultural Enterprise Dembo (BK) Component Head African Farmers ebrimadnyassi@gmail.com Gibba group Mamour Sey HR and CSR Rad Ville Farms 11 Annex 2: Results Framework Updated Results Framework as at 23-May-2019 PDO Indicators by Objectives / Outcomes To increased total production of targeted crops ►Increase in production of targeted commodities due to the project (rice) (Metric ton, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 30,424.00 15,786.00 46,000.00 Date 30-Jun- 29-Dec- 23-May-19 29-Nov- 14 17 19 ►Increase in production of targeted commodities due to the project (vegetables) (Metric ton, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 44.2 1203 2,000.00 Date 30-Jun- 28-Jun-18 23-May-19 29-Nov- 14 2019 Output per unit area has increased for the targeted crops; i.e., rice and vegetables ►Increase in yield of rice (Metric ton, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 2 4.7 4.6 4 Date 30-Jun- 31-May- 23-May-19 29-Nov- 14 18 2019 ►Increase in yield of vegetables (Metric ton, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 6 9.4 20 15 Date 30-Jun- 31-May- 23-May-19 29-Nov- 14 18 19 To improve market access for smallholders producing the targeted commodities ►Increase in volume of market sales of target commodities by selected producer organizations supported by the project (Metric ton, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 85 3,201 10,800.00 Date 1-Jan-14 12-Feb- 23-May-19 29-Nov- 2018 19 ►Increase of volume of market sales by rice producers (beneficiaries of the project) (Metric ton, Custom Breakdown) Baseline Actual Actual End (Previous) (Current) Target Value 0 6,500.00 2,500.00 9,200.00 Date 30-Jun- 31-Oct- 23-May-19 29-Nov- 14 2017 19 ►Increase of volume of market sales by vegetable producers (beneficiaries of the project) (Metric ton, Custom Breakdown) Baseline Actual Actual End (Previous) (Current) Target Value 300 400 490 1,600.00 12 Date 27-Oct- 29-Jun-18 23-May-19 29-Nov- 17 19 ►Share of production of targeted commodities marketed by participating producers (Percentage, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 30 24 22.5 Date 1-Jan-14 29-Dec- 23-May-19 29-Nov- 17 19 To benefit farmers living in the project area ►Direct project beneficiaries including household members (Number, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 24,990.00 28,532.00 40,000.00 Date 30-Jun- 29-Dec- 23-May-19 29-Nov- 14 17 2019 Comments: Direct beneficiaries are people or groups who directly derive benefits from an intervention (i.e., children who benefit from an immunization program; families that have a new piped water connection). Please note proportion of the direct project beneficiaries are female. This indicator is calculated as a percentage. ►Male producers of rice (Number, Custom Breakdown) Baseline Actual Actual End (Previous) (Current) Target Value 0 5,655 8,662 2,500 Date 30-Jun- 31-Jul- 23-May-19 29-Nov- 14 2018 19 ►Female rice producers (Number, Custom Breakdown) Baseline Actual Actual End (Previous) (Current) Target Value 0 5,395.00 9,870.00 2,500.00 Date 30-Jun- 31-Jul-18 23-May-19 29-Nov- 14 19 ►Female vegetable producers (Number, Custom Breakdown) Baseline Actual Actual End (Previous) (Current) Target Value 225 3,480.00 8,779.00 4,000.00 Date 30-Jun- 31-Jul- 23-May-19 29-Nov- 14 2018 19 ►Female beneficiaries (Percentage, Custom Supplement) Baseline Actual Actual End (Previous) (Current) Target Value 0 57 65 70 23-May-19 30-May- 19 Intermediate Results Indicators by Components Component 1: Support for development of irrigation and key productivie infrastructure ►Area with improved irrigation and drainage services planned by the project (Hectare(Ha), Custom) Rice 13 Baseline Actual Actual End (Previous) (Current) Target Value (Rice) 0 2,500.00 2,500.00 2,500.00 Date 30-Jun- 30-Jul-18 23-May-19 29-Nov- 14 19 Baseline Actual Actual End (Previous) (Current) Target Value (Veg) 0 26.50 105.00 100.00 Date 30-Jun- 30-Jul-18 23-May-19 29-Nov- 14 19 ►Operational water user associations created and/or strengthened (number) (Number, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 12 12 15 Date 1-Jan-14 29-Dec- 23-May-19 29-Nov- 17 19 ►Network of water users associations created (Number, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 0 3 2 Date 30-Jun- 29-Dec- 23-May-19 29-Nov- 14 2017 2019 ►Project beneficiary farmers using improved varieties of rice and vegetables (Number, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 4,913.00 6,275.00 9,000.00 Date 30-Jun- 29-Dec- 23-May-19 29-Nov- 14 2017 2019 ►Farmers trained in good agricultural practices (including System of Rice Intensification techniques) (Number, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 793 3,450 6,000.00 Date 30-Jun- 29-Dec- 23-May-19 29-Nov- 14 17 19 Component 2: Support to value chain management ►Number of processing and marketing facilities constructed/rehabilitated (Number, Custom) Actual Baseline Actual End (Previous) (Current) Target Value 0 2 2 3 Date 30-Jun- 29-Dec- 29-Dec-17 29-Nov- 14 17 19 ►Number of FBOs/Coops/SMEs/WUAs benefiting from capacity building from the project (Number, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 6 43 20 Date 1-Jan-14 29-Dec- 23-May-19 29-Nov- 17 19 14 ►Number of female members of producer groups, cooperatives, and WUAs benefiting from capacity building from the project (Number, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 141 207 2,000.00 Date 30-Jun- 29-Dec- 23-May-19 29-Nov- 14 17 19 ►Number of Productive Partnerships created (Number, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 2 21 5 Date 1-Jan-14 29-Dec- 23-May-19 29-Nov- 17 19 ►Number of entrepreneurs trained in management skills - biz planning, financial management, marketing, disaggregated by value chain (Number, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 176 400 200 Date 30-Jun- 29-Dec- 23-May-19 29-Nov- 14 17 19 ►Share of production sold to agribusinesses involved in the project (Percentage, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 0 61 20 Date 1-Jan-14 29-Dec- 23-May-19 29-Nov- 2017 19 ►Value of incremental sales (collected at farm level) by project beneficiaries (Amount(USD), Custom) BaselineActual Actual End (Previous) (Current) Target Value 0 312,000.0 156,776.75 200,000.0 0 0 Date 1-Jan-14 29-Dec- 23-May-19 29-Nov- 17 19 ►Number of public-private investment policy dialogue organized through the project (Number, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 4 6 4 Date 1-Jan-14 29-Dec- 23-May-19 29-Nov- 17 19 ►Volume of mango fruits processed (Metric ton, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 2,100.00 1,800.00 3,500.00 Date 31-Oct- 31-Jan-18 23-May-19 29-Nov- 16 19 Component 3: Project Administration and Institution Building ►Periodic progress reports and IFRs produced and submitted timely (Percentage, Custom) 15 Baseline Actual Actual End (Previous) (Current) Target Value 0 100 80 100 Date 30-Jun- 29-Dec- 23-May-19 29-Nov- 14 17 19 ►Level of implementation of annual workplan and budget (Percentage, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 75 98 100 Date 30-Jun- 29-Dec- 23-May-19 29-Nov- 14 2017 19 ►Disbursement of IDA funds (Percentage, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 91 100 100 Date 1-Oct-13 29-Dec- 23-May-19 29-Nov- 17 19 ►Monitoring and evaluation system with database functional (Yes/No, Custom) Baseline Actual Actual End (Previous) (Current) Target Value No Yes Yes Yes Date 30-Jun- 29-Dec- 23-May-19 29-Nov- 14 17 2019 ►Percent of subprojects implemented in conformity with project safeguards frameworks (Percentage, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 70 75 100 Date 30-Jun- 29-Dec- 23-May-19 29-Nov- 14 2017 19 ►Percentage of procurement activities executed in conformity with the timing of the procurement plan (Percentage, Custom) Baseline Actual Actual End (Previous) (Current) Target Value 0 70 75 80 Date 29-Aug- 25-May- 23-May-19 29-Nov- 2014 18 19 16 Annex 3: Procurement plan for the Project Completion Report (PCR) NO. ACTIVITY TIME 1 Preparation and clearance of the TOR 15th July – 30th July 2019 2 Request for CVs 1st July – 15th July 2019 3 Evaluation/Submission & Bank No Objection 15 July – 25th July 2019 4 Negotiation & Minute of the Negotiations 26th July - 28th July 2019 5 Draft Contract & Contract Signature 28st July – 30th July 2019 6 Draft PCR & Final Report 1st Sept. – 31st Oct. 2019 17