PROCUREMENT PLAN (Textual Part) Project information: FYR of Macedonia Project Implementation agency: Ministry of Labor and Social Policy Date of the Procurement Plan: October 2018 Period covered by this Procurement Plan: Duration of the Project Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. PROCUREMENT North Macedonia : Social Services Improvement Project PLAN General Information Country: North Macedonia Bank’s Approval Date of the Original Procurement Plan: 2018-10-22 2019-09-26 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P162246 GPN Date: 2018-09-18 Project Name: Social Services Improvement Project Loan / Credit No: / , IBRD / 89020 Executing Agency(ies): Ministry of Labor and Social Policy WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MK-MLSP-72220-CW-RFB- 1. Promoting social 134 / Renovation of MLSP, Pending inclusion through improved Single Stage - One SWCs, Municipalities, NEA / Prior Request for Bids Open - National 0.00 Implementati 2019-08-01 2019-08-31 2019-10-05 2019-10-22 2019-10-30 2020-04-27 access to social benefits and Envelope and other institutions on services included in the SP system MK-MLSP-96745-CW-RFB- 1. Promoting social Pending Request for Single Stage - One 1313 / Renovation of local IBRD / 89020 inclusion through improved Prior Open - National 0.00 Implementati 2019-02-06 2019-04-03 2019-09-30 Quotations Envelope offices access to social benefits and on services MK-MLSP-122572-CW-RFB- 2. Expanding the access Under TRANSFERS-2.1.1 / Civil Single Stage - One IBRD / 89020 to and improving of the Prior Request for Bids Open - National 0.00 Implementati 2019-07-14 2019-08-13 2019-09-17 2019-10-07 2019-10-29 2021-02-20 works-Kindergarten in Envelope quality of preschool services on Kavadarci MK-MLSP-123252-CW-RFB- 2. Expanding the access Pending TRANSFERS-2.1.1.2 / Civil Single Stage - One IBRD / 89020 to and improving of the Post Request for Bids Open - National 0.00 Implementati 2019-07-19 2019-08-18 2019-09-22 2019-10-12 2019-11-06 2021-02-28 works-Kindergarten in Envelope quality of preschool services on Negotino MK-MLSP-123255-CW-RFB- 2. Expanding the access Pending TRANSFERS-2.1.1.3 / Civil Single Stage - One IBRD / 89020 to and improving of the Post Request for Bids Open - National 0.00 Implementati 2019-07-21 2019-08-20 2019-09-24 2019-10-14 2019-11-08 2021-03-02 works-Kindergarten in Envelope quality of preschool services on Kocani MK-MLSP-123257-CW-RFB- 2. Expanding the access Pending TRANSFERS-2.1.1.4 / Civil Single Stage - One IBRD / 89020 to and improving of the Post Request for Bids Open - National 0.00 Implementati 2019-07-25 2019-08-24 2019-09-28 2019-10-18 2019-11-12 2019-11-15 works-Kindergarten in Kisela Envelope quality of preschool services on Voda MK-MLSP-129124-CW-RFQ- 1315 / Renovation of part of 1. Promoting social the Special Institution Demir Pending inclusion through improved Request for Single Stage - One Kapija and part of the IBRD / 89020 Post Open - National 0.00 Implementati 2019-09-15 2019-10-11 2019-12-20 access to social benefits and Quotations Envelope Public Institution for on services rehabilitation of children and youth GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 1 MK-MLSP-72180-GO-RFB- 131 / Development of an 1. Promoting social Pending integrated social welfare IS inclusion through improved Open - Single Stage - One / Prior Request for Bids 0.00 Implementati 2019-01-15 2019-02-14 2019-03-21 2019-04-07 2019-04-15 2020-04-14 covering both social access to social benefits and International Envelope on assistance benefits and services services MK-MLSP-72182-GO-RFB- 1. Promoting social Pending 132 / Hardware equipment inclusion through improved Single Stage - One / Post Request for Bids Open - National 0.00 Implementati 2019-03-01 2019-03-21 2019-04-25 2019-05-05 2019-05-13 2019-11-09 for the MLSP and the social access to social benefits and Envelope on institutions services MK-MLSP-72678-GO-RFB- 2. Expanding the access Pending Single Stage - One 223 / Training for pre- / to and improving of the Post Request for Bids Open - National 0.00 Implementati 2019-01-15 2019-02-04 2019-03-11 2019-03-21 2019-03-29 2020-03-28 Envelope primary school program quality of preschool services on MK-MLSP-72679-GO-RFB- 2. Expanding the access Pending Single Stage - One 224 / In service teacher / to and improving of the Post Request for Bids Open - National 0.00 Implementati 2019-02-15 2019-03-07 2019-04-11 2019-04-21 2019-04-29 2020-04-28 Envelope training quality of preschool services on Pending MK-MLSP-77087-GO-RFQ- 3. Project Management, Request for Single Stage - One / Post Open - National 0.00 Implementati 2019-01-09 2019-02-04 2019-04-05 3118 / Equipment (4 years ) Monitoring and Evaluation Quotations Envelope on MK-MLSP-93096-GO-DIR- 1. Promoting social Pending 1310 / Maintenance and IBRD / 89020 inclusion through improved Prior Direct Selection Direct 0.00 Implementati 2019-01-03 2019-01-08 2019-02-12 2021-01-02 Upgrade of CBMIS access to social benefits and on services MK-MLSP-94588-GO-RFQ- 3. Project Management, Request for Single Stage - One 3121 / Camera and IBRD / 89020 Post Open - National 15,750.48 Signed 2019-02-09 2019-03-07 2019-04-06 Monitoring and Evaluation Quotations Envelope Recording devices MK-MLSP-94585-GO-DIR- 1. Promoting social 1310 / Maintenance and IBRD / 89020 inclusion through improved Prior Direct Selection Direct 186,501.75 Signed 2019-01-21 2019-01-26 2019-03-02 2021-03-01 Upgrade of CBMIS access to social benefits and services MK-MLSP-96729-GO-RFB- 1. Promoting social Under 1311 / Hardware equipment inclusion through improved Single Stage - One IBRD / 89020 Prior Request for Bids Open - National 0.00 Implementati 2019-02-01 2019-03-03 2019-04-07 2019-04-24 2019-05-02 2019-10-29 for the local offices and the access to social benefits and Envelope on MLSP services MK-MLSP-96739-GO-RFQ- 1. Promoting social Pending Request for Single Stage - One 1312 / Furniture for the IBRD / 89020 inclusion through improved Post Open - National 0.00 Implementati 2019-02-10 2019-03-08 2019-09-04 Quotations Envelope local offices access to social benefits and on services MK-MLSP-77092-GO-RFQ- 3. Project Management, Request for Single Stage - One / Prior Open - National 0.00 Canceled 2019-02-15 2019-03-18 2019-05-17 326 / Vehicles (2) Monitoring and Evaluation Quotations Envelope MK-MLSP-122570-GO-RFQ- Under 3. Project Management, Request for Single Stage - One 328 / Procurement of IBRD / 89020 Prior Open - National 0.00 Implementati 2019-07-27 2019-09-02 2019-12-01 Monitoring and Evaluation Quotations Envelope Vehicles (2) on MK-MLSP-129121-GO-RFQ- 1. Promoting social Pending Request for Single Stage - One 1314 / Furniture for the IBRD / 89020 inclusion through improved Post Open - National 0.00 Implementati 2019-09-10 2019-10-24 2019-12-23 Quotations Envelope Center for Cerebral palsy access to social benefits and on services MK-MLSP-129129-GO-DIR- 1. Promoting social Pending 1316 / Upgrade of CBMIS- IBRD / 89020 inclusion through improved Post Direct Selection Direct 0.00 Implementati 2019-09-10 2019-09-15 2019-09-25 2020-03-23 SSIP Financial module access to social benefits and on services NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MK-MLSP-72163-CS-CQS- 1. Promoting social Consultant 112 / Technical assistance inclusion through improved / Post Qualification Open - National 0.00 Canceled 2019-02-15 2019-02-23 2019-03-20 2019-03-27 2019-04-04 2020-04-03 for activation of GMI access to social benefits and Selection beneficiaries services MK-MLSP-72166-CS-CQS- 122 / Technical assistance 1. Promoting social Consultant for legislative changes inclusion through improved Pending / Post Qualification Open - National 0.00 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2020-04-17 regarding the implementation access to social benefits and Implementation Selection of reformed licensing services system MK-MLSP-72168-CS-CQS- 1. Promoting social Consultant 123 / Social service needs / inclusion through improved Post Qualification Open - National 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2020-04-17 assessment access to social benefits and Selection services MK-MLSP-72170-CS-CQS- 1. Promoting social 124 / Developing system for Consultant inclusion through improved financing of social services / Post Qualification Open - National 0.00 Canceled 2019-05-01 2019-05-09 2019-06-03 2019-06-10 2019-06-18 2020-06-17 access to social benefits and including determination of Selection services cost of services, MK-MLSP-72172-CS-CQS- 127 / Transformation of the large institutional capacities 1. Promoting social into small group homes, Consultant inclusion through improved living with support, / Post Qualification Open - National 0.00 Canceled 2019-01-15 2019-01-23 2019-02-17 2019-02-24 2019-03-04 2020-03-03 access to social benefits and deinstitutionalization through Selection services foster families and other appropriate forms of protection MK-MLSP-72175-CS-CQS- 1. Promoting social 128 / Outreach activities inclusion through improved Quality And Cost- / Prior Open - National 0.00 Canceled 2019-03-01 2019-03-15 2019-04-26 2019-05-01 2019-05-09 2019-05-22 2019-05-30 2020-05-29 includeing Citizen access to social benefits and Based Selection Angegement activities services MK-MLSP-72676-CS-CQS- 2. Expanding the access Consultant 222 / Developing a new / to and improving of the Post Qualification Open - National 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2020-04-17 capitation formula quality of preschool services Selection MK-MLSP-77086-CS-LCS- 3. Project Management, Least Cost Pending / Prior Open - National 0.00 2019-01-01 2019-01-15 2019-02-26 2019-03-03 2019-03-11 2019-03-24 2019-04-01 2024-03-30 3117 / Project Audit Monitoring and Evaluation Selection Implementation MK-MLSP-77089-CS-CQS- 321 / Operational and Consultant Performance Audit of the 3. Project Management, Pending / Post Qualification Open - National 0.00 2019-02-01 2019-02-09 2019-03-06 2019-03-13 2019-03-21 2024-02-17 implementation of the ECDE Monitoring and Evaluation Implementation Selection Grant program for infrastructure projects MK-MLSP-77090-CS-CQS- 322 / Operational and Performance Audit for the Consultant implementation of the grant 3. Project Management, Pending / Post Qualification Open - National 0.00 2019-02-01 2019-02-09 2019-03-06 2019-03-13 2019-03-21 2024-02-17 mechanism that will promote Monitoring and Evaluation Implementation Selection development of (non- institutional) social services at local level Page 3 MK-MLSP-77091-CS-CQS- 323 / Baseline and Follow Consultant 3. Project Management, Pending up Institutional Assessment / Post Qualification Open - National 0.00 2019-02-01 2019-02-09 2019-03-06 2019-03-13 2019-03-21 2024-02-17 Monitoring and Evaluation Implementation of the preschool quality Selection process MK-MLSP-72681-CS-QCBS- 225 / Developing a system 2. Expanding the access Quality And Cost- Open - Pending for evaluation of quality in IBRD / 89020 to and improving of the Post 0.00 2019-01-01 2019-01-09 2019-02-15 2019-02-20 2019-02-25 2019-03-07 2019-03-15 2020-03-14 Based Selection International Implementation the preschool education quality of preschool services system MK-MLSP-72232-CS-QCBS- 2. Expanding the access 221 / Developing of age Quality And Cost- Open - Pending IBRD / 89020 to and improving of the Post 0.00 2019-04-01 2019-04-09 2019-05-16 2019-05-21 2019-05-26 2019-06-05 2019-06-13 2020-06-12 appropriate teaching-learning Based Selection International Implementation quality of preschool services materials MK-MLSP-72229-CS-QCBS- 2. Expanding the access Quality And Cost- Open - Pending 212 / Project designs for IBRD / 89020 to and improving of the Prior 0.00 2019-01-01 2019-01-15 2019-02-26 2019-03-03 2019-03-11 2019-03-24 2019-04-01 2023-12-31 Based Selection International Implementation kindergartens quality of preschool services MK-MLSP-72682-CS-QCBS- 226 / Training of ECED administrators and other 2. Expanding the access Quality And Cost- Open - Pending decision makers to improve IBRD / 89020 to and improving of the Post 0.00 2019-01-15 2019-01-23 2019-03-01 2019-03-06 2019-03-11 2019-03-21 2019-03-29 2020-03-28 Based Selection International Implementation capacity and development of quality of preschool services monitoring programs and tools MK-MLSP-76978-CS-QCBS- 2. Expanding the access 227 / Outreach activities Quality And Cost- Open - IBRD / 89020 to and improving of the Post 0.00 Canceled 2019-01-01 2019-01-09 2019-02-15 2019-02-20 2019-02-25 2019-03-07 2019-03-15 2020-03-14 including Citizen Based Selection International quality of preschool services Engagement activities MK-MLSP-71874-CS-CQS- 1. Promoting social 111 / Technical assistance Consultant inclusion through improved for legislative changes / Prior Qualification Open - National 0.00 Canceled 2019-01-15 2019-01-29 2019-02-28 2019-03-10 2019-03-18 2020-03-17 access to social benefits and regarding the implementation Selection services of GMI MK-MLSP-72164-CS-CQS- 1. Promoting social 121 / Technical assistance Consultant inclusion through improved for legislative changes / Post Qualification Open - National 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2020-04-17 access to social benefits and regarding the implementation Selection services of social services reform MK-MLSP-72171-CS-CQS- 125 / Development of quality 1. Promoting social Consultant standards including licensing inclusion through improved / Post Qualification Open - National 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2020-04-17 and accreditation and system access to social benefits and Selection for monitoring for their services achievement MK-MLSP-95692-CS-CQS- Consultant 327 / Outreach activities 3. Project Management, IBRD / 89020 Post Qualification Open - National 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2021-04-17 including Citizen Monitoring and Evaluation Selection Engagement activities MK-MLSP-98479-CS-CQS- Consultant 327 / Outreach activities 3. Project Management, IBRD / 89020 Post Qualification Open - National 0.00 Canceled 2019-03-01 2019-03-09 2019-04-03 2019-04-10 2019-04-18 2021-04-17 including Citizen Monitoring and Evaluation Selection Engagement activities MK-MLSP-99426-CS-CQS- 1. Promoting social Consultant 114 / Counselling and inclusion through improved IBRD / 89020 Prior Qualification Open - National 0.00 Canceled 2019-02-07 2019-02-28 2019-04-13 2019-05-13 2019-06-17 2020-06-16 Motivation for activation of access to social benefits and Selection GMA beneficiaries services Page 4 MK-MLSP-115906-CS-CQS- 1. Promoting social Consultant 1213 / Social service needs IBRD / 89020 inclusion through improved Post Qualification Open - National 61,155.24 Signed 2019-06-03 2019-06-11 2019-07-06 2019-07-13 2019-07-21 2020-01-17 assessment access to social benefits and Selection services MK-MLSP-115916-CS-CQS- Consultant 324 / Public campaign 3. Project Management, IBRD / 89020 Post Qualification Open - National 0.00 Canceled 2019-06-03 2019-06-11 2019-07-06 2019-07-13 2019-07-21 2023-12-31 including Citizen Monitoring and Evaluation Selection Engagement activities MK-MLSP-119370-CS-QCBS- 325 / Public campaign 3. Project Management, Quality And Cost- Under IBRD / 89020 Prior Open - National 0.00 2019-06-17 2019-07-01 2019-08-12 2019-08-17 2019-08-25 2019-09-09 2019-09-22 2024-06-30 including Citizen Monitoring and Evaluation Based Selection Implementation Engagement activities MK-MLSP-122574-CS-CQS- 2121 / Project designs for 2. Expanding the access Consultant Under new kindergartens in IBRD / 89020 to and improving of the Prior Qualification Open - National 0.00 2019-07-15 2019-07-29 2019-08-23 2019-09-07 2019-09-15 2020-01-13 Implementation Arachinovo, Bitola, Lipkovo quality of preschool services Selection and Valandovo MK-MLSP-122578-CS-CQS- 2123 / Revision of basic Project designs for 2. Expanding the access Consultant Under kindergartens in Arachinovo, IBRD / 89020 to and improving of the Post Qualification Open - National 0.00 2019-08-01 2019-08-15 2019-09-14 2019-09-24 2019-10-05 2020-04-02 Implementation Bitola, Lipkovo, Valandovo quality of preschool services Selection ,Probishtip, Gostivar, Karposh 1 and Karposh 2 MK-MLSP-122576-CS-CQS- 2122 / Project designs for 2. Expanding the access Consultant Under upgrades of kindergartens in IBRD / 89020 to and improving of the Post Qualification Open - National 0.00 2019-07-30 2019-08-13 2019-09-12 2019-09-22 2019-10-06 2020-01-04 Implementation Probishtip, Gostivar, Karposh quality of preschool services Selection 1 and Karposh 2 MK-MLSP-129132-CS-CQS- 213 / Supervision of works 2. Expanding the access Consultant Under for construction of IBRD / 89020 to and improving of the Post Qualification Open - National 0.00 2019-09-09 2019-09-17 2019-10-12 2019-10-19 2019-10-27 2021-03-10 Implementation kindergartens in Negotino quality of preschool services Selection and Kavadarci MK-MLSP-129133-CS-CQS- 214 / Supervision of works 2. Expanding the access Consultant Pending for construction of IBRD / 89020 to and improving of the Post Qualification Open - National 0.00 2019-09-09 2019-09-17 2019-10-12 2019-10-19 2019-10-27 2019-12-16 Implementation kindergartens in Kocani and quality of preschool services Selection Kisela Voda MK-MLSP-129135-CS-CQS- 215 / Project for interior 2. Expanding the access Consultant design for Kindergardens in Pending IBRD / 89020 to and improving of the Post Qualification Open - National 0.00 2019-09-09 2019-09-17 2019-10-12 2019-10-19 2019-10-27 2020-01-25 Kocani, Negotino, Kisela Implementation quality of preschool services Selection Voda, Kavadarci and Bogovinje MK-MLSP-129136-CS-CQS- 216 / Project for interior 2. Expanding the access Consultant Pending design for Kindergartens in IBRD / 89020 to and improving of the Post Qualification Open - National 0.00 2019-09-09 2019-09-17 2019-10-12 2019-10-19 2019-10-27 2020-01-25 Implementation Gjorce Petrov, Resen, Kriva quality of preschool services Selection Palanka and Strumica MK-MLSP-135022-CS-CQS- 1214 / Company for providing support to the 1. Promoting social Consultant municipalities/ potential inclusion through improved Pending IBRD / 89020 Post Qualification Open - National 0.00 2019-09-20 2019-10-04 2019-10-14 2019-10-17 2019-10-23 2023-07-04 service providers in access to social benefits and Implementation Selection preparation of application services documents including the project proposals INDIVIDUAL CONSULTANTS Page 5 Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual MK-MLSP-72221-CS-CDS- 1. Promoting social 135 / Actuary in the Unit inclusion through improved IBRD / 89020 Prior Direct Selection Direct 231,638.55 Signed 2019-01-01 2019-01-21 2019-02-08 2024-02-07 for Analysis, Evaluation and access to social benefits and Monitoring services MK-MLSP-72223-CS-CDS- 1. Promoting social Individual 136 / IT in the Unit for inclusion through improved IBRD / 89020 Prior Consultant Open 36,874.03 Signed 2019-01-01 2019-01-29 2019-02-08 2019-02-16 2024-02-15 Analysis, Evaluation and access to social benefits and Selection Monitoring services MK-MLSP-72225-CS-CDS- 1. Promoting social 137 / Researcher in the Unit inclusion through improved IBRD / 89020 Prior Direct Selection Direct 165,237.07 Signed 2019-01-01 2019-01-21 2019-02-08 2024-02-07 for Analysis, Evaluation and access to social benefits and Monitoring services MK-MLSP-72228-CS-CDS- 1. Promoting social 139 / Legal Advisor in the inclusion through improved IBRD / 89020 Prior Direct Selection Direct 197,332.13 Signed 2019-01-01 2019-01-21 2019-02-08 2024-02-07 Unit for Analysis, Evaluation access to social benefits and and Monitoring services MK-MLSP-76981-CS-INDV- 228 / Capacity building of 2. Expanding the access Individual local architects and IBRD / 89020 to and improving of the Post Consultant Open 84,037.50 Signed 2019-03-01 2019-03-24 2019-03-31 2019-04-08 2019-10-05 engineers for such innovative quality of preschool services Selection and highly energy-efficient infrastructure MK-MLSP-77005-CS-CDS- 3. Project Management, IBRD / 89020 Prior Direct Selection Direct 212,485.11 Signed 2019-01-01 2019-01-21 2019-02-08 2024-02-07 311 / Project Manager Monitoring and Evaluation MK-MLSP-77006-CS-CDS- 3. Project Management, IBRD / 89020 Prior Direct Selection Direct 174,176.55 Signed 2019-01-01 2019-01-21 2019-02-08 2024-02-07 312 / Procurement manager Monitoring and Evaluation Individual MK-MLSP-77007-CS-INDV- 3. Project Management, Pending / Prior Consultant Open 0.00 2019-01-01 2019-01-29 2019-02-08 2019-02-16 2024-02-13 313 / Coordinator for ECDE Monitoring and Evaluation Implementation Selection MK-MLSP-77008-CS-INDV- Individual 3. Project Management, 314 / Coordinator for Social IBRD / 89020 Prior Consultant Open 177,444.70 Signed 2019-01-01 2019-01-29 2019-02-08 2019-02-16 2024-02-15 Monitoring and Evaluation services development Selection MK-MLSP-77009-CS-INDV- 3. Project Management, IBRD / 89020 Prior Direct Selection Direct 175,079.26 Signed 2019-01-01 2019-01-21 2019-02-08 2024-02-07 315 / IT manager Monitoring and Evaluation MK-MLSP-77010-CS-CDS- 3. Project Management, IBRD / 89020 Prior Direct Selection Direct 155,828.83 Signed 2019-01-01 2019-01-21 2019-02-08 2024-02-07 316 / Financial manager Monitoring and Evaluation MK-MLSP-77016-CS-INDV- Individual 3. Project Management, 3111 / Environmental/social IBRD / 89020 Prior Consultant Open 79,853.27 Signed 2019-01-01 2019-01-29 2019-02-08 2019-02-16 2024-02-15 Monitoring and Evaluation safeguards specialist Selection MK-MLSP-72227-CS-CDS- 1. Promoting social 138 / Social Consultant in inclusion through improved IBRD / 89020 Prior Direct Selection Direct 117,990.67 Signed 2018-10-24 2018-11-08 2018-11-23 2024-06-30 the Unit for Analysis, access to social benefits and Evaluation and Monitoring services MK-MLSP-77011-CS-CDS- 3. Project Management, IBRD / 89020 Prior Direct Selection Direct 117,594.63 Signed 2018-10-24 2018-11-08 2018-11-23 2024-06-30 317 / Civil engineer/architect Monitoring and Evaluation MK-MLSP-77012-CS-CDS- 3. Project Management, IBRD / 89020 Prior Direct Selection Direct 155,023.10 Signed 2018-10-24 2018-11-08 2018-11-23 2024-06-30 318 / Civil engineer/architect Monitoring and Evaluation Page 6 MK-MLSP-77013-CS-CDS- 3. Project Management, IBRD / 89020 Prior Direct Selection Direct 155,023.10 Signed 2018-10-24 2018-11-08 2018-11-23 2024-06-30 319 / Civil engineer/architect Monitoring and Evaluation MK-MLSP-77014-CS-CDS- 3. Project Management, 3110 / Civil IBRD / 89020 Prior Direct Selection Direct 155,023.10 Signed 2018-10-24 2018-11-08 2018-11-23 2024-06-30 Monitoring and Evaluation engineer/architect MK-MLSP-77022-CS-CDS- Individual 3. Project Management, Pending 3114 / Grant application IBRD / 89020 Prior Consultant Open 0.00 2019-01-01 2019-01-29 2019-02-08 2019-02-16 2024-06-30 Monitoring and Evaluation Implementation officer Selection Individual MK-MLSP-77083-CS-INDV- 3. Project Management, Pending IBRD / 89020 Prior Consultant Open 0.00 2019-01-01 2019-01-24 2019-01-31 2019-02-08 2024-06-30 3115 / M&E Officer Monitoring and Evaluation Implementation Selection MK-MLSP-77018-CS-CDS- 3. Project Management, 31112 / Grant IBRD / 89020 Prior Direct Selection Direct 165,237.07 Signed 2018-10-24 2018-11-08 2018-11-23 2024-06-30 Monitoring and Evaluation Administrative Coordinator MK-MLSP-77020-CS-CDS- 3. Project Management, 3113 / Financial and IBRD / 89020 Prior Direct Selection Direct 88,621.61 Signed 2018-10-24 2018-11-08 2018-11-23 2024-06-30 Monitoring and Evaluation administrative officer Individual MK-MLSP-77085-CS-CDS- 3. Project Management, Under IBRD / 89020 Prior Consultant Open 0.00 2019-01-01 2019-01-29 2019-02-08 2019-02-16 2024-06-30 3116 / IT officer Monitoring and Evaluation Implementation Selection MK-MLSP-94587-CS-INDV- Individual 3. Project Management, Pending 3120 / Environmental/social IBRD / 89020 Post Consultant Open 0.00 2019-03-01 2019-03-24 2019-03-31 2019-04-08 2024-04-06 Monitoring and Evaluation Implementation safeguards assistance Selection Individual MK-MLSP-94589-CS-INDV- 3. Project Management, IBRD / 89020 Post Consultant Open 152,884.40 Signed 2019-03-01 2019-03-24 2019-03-31 2019-04-08 2024-04-06 3122 / Interior Designer Monitoring and Evaluation Selection Individual MK-MLSP-94590-CS-INDV- 3. Project Management, IBRD / 89020 Post Consultant Open 29,590.53 Signed 2019-02-01 2019-02-24 2019-03-03 2019-03-11 2024-03-09 3123 / Business Analyst Monitoring and Evaluation Selection MK-MLSP-94593-CS-INDV- 1. Promoting social Individual 113 / Social Safety Net IBRD / 89020 inclusion through improved Post Consultant Open 96,631.92 Signed 2019-02-01 2019-02-24 2019-03-03 2019-03-11 2024-03-09 Specialist access to social benefits and Selection services MK-MLSP-94594-CS-INDV- 129 / Development of norms 1. Promoting social Individual and standards for inclusion through improved IBRD / 89020 Post Consultant Open 13,459.20 Signed 2019-03-01 2019-03-24 2019-03-31 2019-04-08 2020-04-07 establishing of social services access to social benefits and Selection and for ensuring quality in services the service delivery MK-MLSP-94596-CS-INDV- 1210 / Support for 1. Promoting social Development of norms and Individual inclusion through improved standards for establishing of IBRD / 89020 Post Consultant Open 8,335.63 Signed 2019-03-01 2019-03-24 2019-03-31 2019-04-08 2020-04-07 access to social benefits and social services and for Selection services ensuring quality in the service delivery MK-MLSP-94598-CS-INDV- 1. Promoting social 1211 / Developing a system Individual inclusion through improved Pending for evaluation of quality in IBRD / 89020 Post Consultant Open 0.00 2019-03-01 2019-03-24 2019-03-31 2019-04-08 2020-04-07 access to social benefits and Implementation the social services delivery Selection services system Page 7 MK-MLSP-95684-CS-INDV- 1. Promoting social 1212 / Preparation of Cost Individual inclusion through improved Methodology for Establishing IBRD / 89020 Post Consultant Open 22,275.54 Signed 2019-02-01 2019-02-24 2019-03-03 2019-03-11 2019-09-07 access to social benefits and of Social Services including Selection services pricing list MK-MLSP-95686-CS-INDV- 2. Expanding the access Individual Pending 229 / Developing a new IBRD / 89020 to and improving of the Post Consultant Open 0.00 2019-05-01 2019-05-24 2019-05-31 2019-06-08 2019-12-05 Implementation capitation formula quality of preschool services Selection MK-MLSP-96725-CS-INDV- Individual 3. Project Management, 3124 / Business Analyst IBRD / 89020 Post Consultant Direct 0.00 Canceled 2019-02-01 2019-02-14 2019-02-24 2019-03-04 2024-03-02 Monitoring and Evaluation Assistant Selection MK-MLSP-97638-CS-CDS- 1. Promoting social 114 / Counselling and inclusion through improved IBRD / 89020 Prior Direct Selection Direct 0.00 Canceled 2019-02-01 2019-02-11 2019-04-17 2020-04-16 Motivation for activation of access to social benefits and GMA beneficiaries services MK-MLSP-119013-CS-INDV- Individual 3. Project Management, 3125 / Business Analyst IBRD / 89020 Post Consultant Limited 9,958.84 Signed 2019-06-13 2019-06-23 2019-06-30 2019-07-08 2020-01-04 Monitoring and Evaluation Assistant Selection Individual MK-MLSP-129139-CS-INDV- 3. Project Management, Pending IBRD / 89020 Post Consultant Open 0.00 2019-09-09 2019-10-02 2019-10-09 2019-10-24 2024-07-29 3126 / Civil engineer Monitoring and Evaluation Implementation Selection Individual MK-MLSP-129140-CS-INDV- 3. Project Management, Pending IBRD / 89020 Post Consultant Open 0.00 2019-09-09 2019-10-02 2019-10-09 2019-10-24 2024-07-29 3127 / Civil engineer/arhitect Monitoring and Evaluation Implementation Selection Individual MK-MLSP-129143-CS-INDV- 3. Project Management, Pending IBRD / 89020 Post Consultant Open 0.00 2019-09-09 2019-10-02 2019-10-09 2019-10-24 2024-07-29 3128 / Electrical engineer Monitoring and Evaluation Implementation Selection Individual MK-MLSP-129144-CS-INDV- 3. Project Management, Pending IBRD / 89020 Post Consultant Open 0.00 2019-09-09 2019-10-02 2019-10-09 2019-10-24 2024-07-29 3129 / Mechanical engineer Monitoring and Evaluation Implementation Selection MK-MLSP-129624-CS-INDV- 1. Promoting social Individual 1317 / Economist in the inclusion through improved Under IBRD / 89020 Post Consultant Limited 0.00 2019-08-29 2019-09-06 2019-09-11 2019-10-10 2024-08-14 Unit for Analysis, Evaluation access to social benefits and Implementation Selection and Monitoring services Individual MK-MLSP-129625-CS-INDV- 3. Project Management, Under IBRD / 89020 Post Consultant Open 0.00 2019-09-18 2019-10-11 2019-10-26 2019-11-03 2020-05-01 3130 / Procurement officer Monitoring and Evaluation Implementation Selection MK-MLSP-135381-CS-INDV- 2. Expanding the access Individual Pending 1.2.10 / Principal IBRD / 89020 to and improving of the Post Consultant Open 0.00 2019-10-01 2019-10-24 2019-10-26 2019-11-12 2024-06-18 Implementation Investigator quality of preschool services Selection MK-MLSP-135385-CS-INDV- 2. Expanding the access Individual Pending 2211 / Local Support to the IBRD / 89020 to and improving of the Post Consultant Open 0.00 2019-10-01 2019-10-24 2019-10-31 2019-11-22 2024-06-28 Implementation Principal Investigator quality of preschool services Selection MK-MLSP-135386-CS-INDV- 2.2.12 / National Coordinator 2. Expanding the access Individual Pending for Measuring Early IBRD / 89020 to and improving of the Post Consultant Open 0.00 2019-10-01 2019-10-24 2019-10-31 2019-11-08 2024-06-14 Implementation Learning Environment quality of preschool services Selection (MELE) Page 8 MK-MLSP-135387-CS-INDV- 2.2.13 / National Coordinator 2. Expanding the access Individual Pending for Measurement of IBRD / 89020 to and improving of the Post Consultant Open 0.00 2019-10-01 2019-10-24 2019-10-31 2019-11-08 2024-06-14 Implementation Development and Early quality of preschool services Selection Learning (MODEL) MK-MLSP-135389-CS-INDV- 2.2.14 / Local Consultant for 2. Expanding the access Individual Pending strengthening the preschool IBRD / 89020 to and improving of the Post Consultant Open 0.00 2019-10-01 2019-10-24 2019-10-31 2019-11-08 2024-06-14 Implementation system for pre-service and in- quality of preschool services Selection service teacher training Page 9