PROCUREMENT PLAN (Textual Part) Project information: Niger, Niger, Solar Electricity Access Project (NESAP), P-160170 Project Implementation agency: ANPER and NIGELEC Date of the Procurement Plan: September 14, 2017 Period covered by this Procurement Plan: From July 2017 to December 2019 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the national procurement legislation, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is not applicable Works: is not applicable Other Relevant Procurement Information. NA PROCUREMENT Niger : Niger Solar Electricity Access Project (NESAP) PLAN General Information Country: Niger Bank’s Approval Date of the Original Procurement Plan: 2017-09-14 2019-09-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P160170 GPN Date: 2018-10-04 Project Name: Niger Solar Electricity Access Project (NESAP) Loan / Credit No: IDA / 60820 Executing Agency(ies): AGENCE NIGERIENNE DE PROMOTION DE L’ELECTRIFICATION EN MILIEU RURAL - ANPER WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C-20/UEP/NESAP/2018 / Component 4: Single Stage - One Réfection des bureaux au IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 9,000.00 6,756.52 Achevé 2018-05-02 2018-05-30 2018-06-06 Envelope CNES Technical Assistance 001/AP/NESAP/2019 / CONCESSIONS PORTANT SUR LA REALISATION ET Component 2: Rural L'EXPLOITATION DE Electrification through Demande de Single Stage - Two En cours IDA / 60820 A posteriori Open - National 3,777,889.00 0.00 2019-07-29 2019-09-16 2019-09-30 2019-08-19 2019-11-14 2019-12-19 2020-01-23 2021-07-16 PROJETS Service-based Solar Hybrid propositions Envelope d'exécution D'ELECTRIFICATION Mini-grids RURALE AUTONOME HORS RESEAUX GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual AON-01/UEP/NESAP/2017 / Acquisition de 04 vehicles Component 4: au profit de l'ANPER, CNES Single Stage - One IDA / 60820 Implementation Support and A posteriori Appel d'offres Open - National 240,000.00 194,053.65 Achevé 2017-10-20 2017-10-25 2017-12-06 2018-01-05 2018-02-09 2018-08-08 et Ministère de l'Energie Envelope Technical Assistance pour la supervision et le suivi du projet CF-12/UEP/NESAP/2017 / Component 4: Acquisition logiciel de Single Stage - One IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 45,000.00 39,182.72 Signé 2017-10-15 2017-12-10 2018-06-08 gestion financière (multi - Envelope Technical Assistance sites) pour l'UEP ANPER AOIR-01/NIGELEC/2017 / Component 3: Solar PV Hybridation solaire, Hybridization of Isolated Single Stage - One Extension, réhabilitation et IDA / 60820 A priori Appel d'offres Limited 10,000,000.00 0.00 Annulé 2017-11-27 2017-12-02 2018-01-13 2018-02-12 2018-03-19 2018-09-15 Thermal Mini-grids and Envelope renforcement des postes 1ere Expansion of Access phase CF-10/UEP/NESAP/2017 / Component 4: Single Stage - One Entretien et gardiennage du IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2017-10-25 2017-12-20 2018-06-18 Envelope local de UEP ANPER Technical Assistance CF-03/UEP/NESAP/2017 / Component 4: Single Stage - One Matériel informatique et IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 15,000.00 15,170.72 Signé 2018-02-28 2018-04-04 2018-04-18 Envelope consommables Technical Assistance Page 1 AON-02/UEP/NESAP/2017 / Component 4: Fourniture d'équipements de Single Stage - One IDA / 60820 Implementation Support and A posteriori Appel d'offres Open - National 60,000.00 0.00 Annulé 2017-11-30 2017-12-05 2018-01-16 2018-02-15 2018-03-22 2018-09-18 control et demonstration Envelope Technical Assistance CNES CF-19/UEP/NESAP/2017 / Component 4: Single Stage - One Achat de carburant pour les IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 10,000.00 0.00 Annulé 2017-12-05 2018-01-30 2018-07-29 Envelope véhicules de l'UEP ANPER Technical Assistance CF-17-2/UEP/NESAP/2017 / Component 4: Single Stage - One Réfrigérateur et materiel de IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 5,000.00 0.00 Annulé 2017-10-27 2017-12-22 2018-06-20 Envelope café pour l'UEP ANPER Technical Assistance CF-01/UEP/NESAP/2017 / Mobilier pour les bureaux, la Component 4: Single Stage - One salle de réunion et Armoires IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 35,000.00 33,153.76 Achevé 2018-01-31 2018-03-07 2018-03-21 Envelope + Etagère de classement des Technical Assistance dossier ANPER CF-13/UEP/NESAP/2017 / Component 4: Matériel et mobilier de Single Stage - One IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 12,000.00 8,242.59 Achevé 2018-05-04 2018-05-30 2018-06-13 bureau au profit du CNES Envelope Technical Assistance et la DGFOR CF-14/UEP/NESAP/2017 / Component 4: Matériel informatique et Single Stage - One IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 26,000.00 23,034.94 Achevé 2018-05-03 2018-05-31 2018-06-14 logiciel au profit du CNES Envelope Technical Assistance et la DGFOR C-18/UEP/NESAP/2018 / Component 4: Besoin complémentaire en Single Stage - One IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 20,000.00 15,518.19 Achevé 2018-04-30 2018-05-26 2018-06-09 matériel informatique à Envelope Technical Assistance l'UEP ANPER C-19/UEP/NESAP/2018 / Component 4: Single Stage - One En cours Acquisition des armoires au IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 10,000.00 0.00 2018-05-01 2018-05-29 2018-06-12 Envelope d'exécution profit de l'UEP ANPER Technical Assistance C-22/UEP/NESAP/2018 / Component 4: Acquisition d'équipement Single Stage - One En cours IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 5,000.00 0.00 2018-05-04 2018-06-01 2018-06-15 divers au profit du CNES et Envelope d'exécution Technical Assistance la DGFOR CF-09/UEP/NESAP/2017 / Component 4: Single Stage - One Groupe électrogène 55 KVA IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 34,000.00 28,706.76 Achevé 2018-06-01 2018-06-29 2018-07-13 Envelope ANPER Technical Assistance CF-02/UEP/NESAP/2017 / Component 4: Single Stage - One En cours Fournitures de bureau à IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 10,000.00 10,233.41 2018-05-04 2018-05-23 2018-06-06 Envelope d'exécution l'UCP ANPER Technical Assistance AON-02/UEP/NESAP/2017 Component 4: MOD / Fourniture Single Stage - One En attente IDA / 60820 Implementation Support and A posteriori Appel d'offres Open - National 60,000.00 0.00 2018-06-29 2018-07-04 2018-08-15 2018-09-14 2018-10-19 2018-12-18 d'équipements de contrôle et Envelope d'exécution Technical Assistance de démonstration au CNES CF-05/UEP/NESAP/2017 / Matériel de communication Component 4: Single Stage - One ANPER ( Internet, IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 20,000.00 18,523.04 Achevé 2018-05-02 2018-05-30 2018-06-13 Envelope téléphones câblage réseau Technical Assistance etc...) C-03/UEP/NESAP/2018 / Component 4: Acquisition d'un véhicule Single Stage - One IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 54,000.00 51,201.72 Signé 2018-09-07 2018-10-22 2018-11-21 4X4 double cabine pour la Envelope Technical Assistance DGOFR Page 2 C-21/UEP/NESAP/2018 / Component 4: Matériel informatique pour Single Stage - One IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 12,500.00 12,944.67 Signé 2018-09-07 2018-10-19 2018-11-09 le compte du Ministère de Envelope Technical Assistance l'Energie C-22/UEP/NESAP/2018 / Component 4: Single Stage - One Mobilier de bureau pour le IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 7,000.00 6,593.96 Signé 2018-09-07 2018-10-19 2018-11-09 Envelope Ministère de l'Energie Technical Assistance 03ED/NESAP/2018 / Component 4: Passation de Acquisition de logiciel En attente IDA / 60820 Implementation Support and A posteriori marché de gré à Direct 12,000.00 0.00 2018-11-16 2018-11-21 2019-01-09 2020-01-04 HOMER au profit de l'Unité d'exécution Technical Assistance gré de coordination du projet COT-001-NESAP-2019 / Component 4: Single Stage - One Acquisition de matériel de IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 20,000.00 21,583.19 Achevé 2019-05-05 2019-06-09 2019-06-30 Envelope terrain Technical Assistance COT-004-NESAP-2019 / Component 4: Single Stage - One Acquisition de matériel IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 8,000.00 7,227.55 Achevé 2019-05-05 2019-06-02 2019-06-16 Envelope informatique complémentaire Technical Assistance NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CBUR-001-NESAP-2019 / Component 4: Single Stage - One En attente Création du site web pour le IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 11,000.00 0.00 2019-06-05 2019-07-31 2019-09-29 Envelope d'exécution projet et pour l'ANERSOL Technical Assistance COT-003-NESAP-2019 / Conception et impression des Component 4: Single Stage - One En attente affiches de sensibilisation IDA / 60820 Implementation Support and A posteriori Demande de prix Limited 16,900.00 0.00 2019-05-28 2019-07-02 2019-07-23 Envelope d'exécution pour la composante 1 du Technical Assistance projet CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual C-24/UEP/NESAP/2017 / Recrutement d'un ingénieur conseil - Supervision de la Component 3: Solar PV construction, mise en œuvre Sélection fondée Hybridization of Isolated Open - de l'hybridation solaire et IDA / 60820 A priori sur la qualité et 2,200,000.00 0.00 Annulé 2017-09-21 2017-10-05 2017-10-19 2017-11-23 2017-12-14 2017-12-28 2018-01-25 2020-01-25 Thermal Mini-grids and International expansion des réseaux de le coût Expansion of Access distribution et réhabilitation et renforcement des sous- stations (Composante 3) C-03/UEP/NESAP/2017 MOD / Recrutement d'un cabinet pour l'élaboration, la mise en œuvre et le suivi Component 4: Sélection fondée Open - de la stratégie de IDA / 60820 Implementation Support and A posteriori sur la qualité et 400,000.00 172,984.97 Signé 2017-12-04 2017-12-18 2018-01-08 2018-02-05 2018-02-19 2018-03-05 2018-03-26 2019-03-26 International communication pour la Technical Assistance le coût vulgarisation de technologies photovoltaïques hors-réseau de qualité pour le CNES Page 3 C-03/UEP/NESAP/2017 / Recrutement d'une firme/ONG pour l'élaboration, la mise en œuvre et le suivi Component 4: Sélection fondée Open - de la stratégie de IDA / 60820 Implementation Support and A priori sur la qualité et 400,000.00 0.00 Annulé 2017-11-25 2017-12-09 2017-12-23 2018-01-20 2018-02-03 2018-02-17 2018-03-03 2019-03-03 International communication pour la Technical Assistance le coût vulgarisation de technologies photovoltaïques hors-réseau de qualité pour le CNES C-01/UEP/NESAP/2017 / Assistance technique (recrutement d'une firme) Component 4: Sélection fondée Open - pour la définition du IDA / 60820 Implementation Support and A priori sur la qualité et 350,000.00 0.00 Annulé 2017-10-31 2017-11-21 2018-01-04 2018-02-01 2018-03-03 2018-04-07 2018-05-12 2019-05-12 International mécanisme financier avec Technical Assistance le coût l'intermédiaire financier de la Composante 1 du NESAP C-23/UEP/NESAP/2017 / Recrutement d'un ingénieur Component 2: Rural Sélection fondée conseil - Supervision de la Electrification through Open - IDA / 60820 A priori sur la qualité et 1,500,000.00 1,429,129.00 Signé 2018-01-30 2018-02-13 2018-03-13 2018-04-10 2018-04-24 2018-05-08 2018-06-05 2021-06-04 construction, mise en œuvre Service-based Solar Hybrid International le coût de mini-réseaux solaires Mini-grids (Composante 2) C-01/UEP/NESAP/2017 MOD / Assistance technique (recrutement d'une firme) Component 4: Sélection fondée Open - pour la définition du IDA / 60820 Implementation Support and A posteriori sur la qualité et 350,000.00 0.00 Annulé 2018-06-29 2018-07-13 2018-08-03 2018-08-31 2018-09-14 2018-09-28 2018-10-19 2019-10-19 International mécanisme financier avec Technical Assistance le coût l'intermédiaire financier de la Composante 1 du NESAP C-01/UEP/NESAP/2018 / Sélection fondée Assistance technique aux Component 4: sur les Open - banques dans le cadre de IDA / 60820 Implementation Support and A posteriori 200,000.00 0.00 Annulé 2018-06-28 2018-07-19 2018-08-16 2018-08-30 2018-09-13 2019-09-08 qualifications des International gestion de la ligne de crédit Technical Assistance consultants de la composante 1 C-02/UEP/NESAP/2018 / Assistance technique aux Sélection fondée Component 4: institutions de micro finance sur les Open - IDA / 60820 Implementation Support and A posteriori 150,000.00 0.00 Annulé 2018-06-28 2018-07-19 2018-08-16 2018-08-23 2018-09-13 2019-09-08 dans le cadre de la gestion qualifications des International Technical Assistance de la ligne de crédit de la consultants composante 1 Component 2: Rural Sélection fondée C-31/UEP/NESAP/2017 / Electrification through sur les Open - Elaboration PAR et EIES IDA / 60820 A posteriori 150,000.00 0.00 Annulé 2018-06-29 2018-07-20 2018-09-02 2018-10-02 2018-11-06 2019-05-05 Service-based Solar Hybrid qualifications des International composante 2 Mini-grids consultants C-08/UEP/NESAP/2017 / Recrutement d'un bureau Sélection fondée d'études pour élaborer et Component 4: sur les Open - mettre en œuvre un système IDA / 60820 Implementation Support and A posteriori 200,000.00 0.00 Annulé 2018-06-29 2018-07-20 2018-09-02 2018-10-02 2018-11-06 2019-11-06 qualifications des International de suivi et évaluation des Technical Assistance consultants Composantes 1 et 2 du Projet sur la base d'un SIG C- Sélection fondée Component 4: 001/NESAP/COMP1/DGOFR2 sur les Open - En attente IDA / 60820 Implementation Support and A posteriori 200,000.00 0.00 2019-10-31 2019-11-21 2019-12-12 2019-12-26 2020-01-30 2020-05-29 019 / Assistance techniques qualifications des International d'exécution Technical Assistance aux banques consultants C- Sélection fondée 002/NESAP/COMP1/DGOFR2 Component 4: sur les Open - En attente 019 / Assistance technique IDA / 60820 Implementation Support and A posteriori 150,000.00 0.00 2019-10-31 2019-11-21 2019-12-12 2020-01-11 2020-02-15 2020-05-15 qualifications des International d'exécution aux Institutions de micro Technical Assistance consultants finance Page 4 INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual RC2-UCP/ANPER / Component 4: Recrutement d'un second IDA / 60820 Implementation Support and A posteriori Individuel Open 24,000.00 17,235.51 Achevé 2017-12-04 2018-01-05 2018-01-12 2018-01-26 2019-01-26 Comptable à l'UCP/ANPER Technical Assistance C-02/UEP/NESAP/2017 / Assistance technique Component 4: (Consultant individuel) pour IDA / 60820 Implementation Support and A posteriori Individuel Open 150,000.00 37,333.22 Achevé 2018-02-27 2018-04-10 2018-04-24 2018-05-15 2019-05-15 l'appui au developpement du Technical Assistance marché solaire au CNES C-18/UEP/NESAP/2017 / Component 4: Recrutement d'un spécialiste IDA / 60820 Implementation Support and A priori Individuel Limited 25,000.00 0.00 Annulé 2017-11-02 2017-11-07 2017-11-28 2018-01-02 2018-07-01 en contrôle technique d'appui Technical Assistance au CNES C-19/UEP/NESAP/2017 / Recrutement d'un consultant Component 4: individuel chargé d'appuyer IDA / 60820 Implementation Support and A priori Individuel Limited 200,000.00 0.00 Annulé 2017-09-18 2017-10-02 2017-10-16 2017-10-30 2019-10-30 l'ANPER dans la mise en Technical Assistance oeuvre de projects d'electrification rurale C-14/UEP/NESAP/2017 / Recrutement d'un consultant Component 4: individuel spécialiste en IDA / 60820 Implementation Support and A priori Individuel Limited 24,000.00 0.00 Annulé 2017-10-30 2017-11-04 2017-11-25 2017-12-30 2018-06-28 sauvegardes d'appui à l'UEP Technical Assistance de l'ANPER C-16/UEP/NESAP/2017 / Component 4: Recrutement d'un spécialiste IDA / 60820 Implementation Support and A priori Individuel Limited 25,000.00 0.00 Annulé 2017-11-06 2017-11-11 2017-12-02 2018-01-06 2018-07-05 en communication d'appui au Technical Assistance CNES C-16/UEP/NESAP/2017 Component 4: MOD / Recrutement d'un IDA / 60820 Implementation Support and A posteriori Individuel Open 25,000.00 25,061.03 Signé 2017-12-04 2018-01-22 2018-02-12 2018-02-26 2019-02-26 spécialiste en communication Technical Assistance d'appui au CNES C-17/UEP/NESAP/2017 / Component 4: Recrutement d'un spécialiste IDA / 60820 Implementation Support and A priori Individuel Limited 25,000.00 0.00 Annulé 2017-11-24 2017-11-29 2017-12-20 2018-01-24 2018-07-23 en suivi et évaluation Technical Assistance d'appui au CNES C-13/UEP/NESAP/2017 / Component 4: Recrutement d'un expert en IDA / 60820 Implementation Support and A priori Individuel Limited 24,000.00 0.00 Annulé 2017-10-15 2017-10-20 2017-11-10 2017-12-15 2018-06-13 developpement d'affaires de Technical Assistance l'ANPER C-13/UEP/NESAP/2017 Component 4: MOD / Recrutement d'un IDA / 60820 Implementation Support and A posteriori Individuel Open 24,000.00 23,948.80 Signé 2017-12-04 2018-01-13 2018-01-27 2018-02-17 2019-02-17 expert en développement Technical Assistance d'affaires de l'ANPER Component 4: Sélection de C-25/UEP/NESAP/2017 / IDA / 60820 Implementation Support and A priori consultants par Direct 124,128.00 0.00 Annulé 2017-10-23 2017-11-04 2017-12-25 2021-04-30 Audit externe Technical Assistance entente directe C-17/UEP/NESAP/2017 Component 4: MOD / Recrutement d'un IDA / 60820 Implementation Support and A posteriori Individuel Open 25,000.00 25,043.34 Signé 2017-12-04 2018-01-06 2018-01-27 2018-02-17 2019-02-17 spécialiste en suivi et Technical Assistance évaluation d'appui au CNES Page 5 C-06/UEP/NESAP/2017 / Assistance Technique pour Component 4: Sélection de l'incubation des compagnies IDA / 60820 Implementation Support and A posteriori consultants par Direct 363,460.00 290,105.40 Signé 2018-05-17 2018-05-29 2018-07-26 2020-07-25 (solaires et de pompage Technical Assistance entente directe solaire) Component 4: Sélection de C-25/UEP/NESAP/2017 IDA / 60820 Implementation Support and A posteriori consultants par Direct 124,128.00 37,379.10 Signé 2018-06-29 2018-07-09 2018-09-12 2022-01-16 MOD / Audit externe Technical Assistance entente directe C-18/UEP/NESAP/2017 Component 4: MOD / Recrutement d'un IDA / 60820 Implementation Support and A posteriori Individuel Open 25,000.00 0.00 Annulé 2017-12-22 2018-01-24 2018-02-07 2018-02-21 2019-02-21 spécialiste en contrôle Technical Assistance technique d'appui au CNES C-18-NESAP / Recrutement d'un consultant individuel Component 4: chargé d'appuyer l'ANPER IDA / 60820 Implementation Support and A priori Individuel Limited 200,000.00 0.00 Annulé 2017-10-20 2017-10-25 2017-11-24 2018-01-05 2020-01-05 dans la mise en oeuvre du Technical Assistance projet d'électrification rurale C-14/UEP/NESAP/2017 MOD / Recrutement d'un Component 4: consultant individuel IDA / 60820 Implementation Support and A posteriori Individuel Limited 24,000.00 0.00 Annulé 2017-12-04 2017-12-09 2017-12-30 2018-01-20 2019-01-20 spécialiste en sauvegardes Technical Assistance d'appui à l'UEP de l'ANPER NE- NESAP-27952-CS-INDV Component 4: / Recrutement d'un analyste IDA / 60820 Implementation Support and A posteriori Individuel Limited 25,000.00 0.00 Annulé 2017-09-20 2017-09-25 2017-10-16 2017-11-20 2018-11-20 financier à la DGFOR Technical Assistance C-14-UEP-NESAP-2017 Component 4: MOD / Recrutement d'un IDA / 60820 Implementation Support and A posteriori Individuel Open 24,000.00 1,949.84 Signé 2017-09-28 2017-11-16 2017-12-07 2018-01-11 2019-01-11 Expert en sauvegarde Technical Assistance environnementale et sociale NE-NESAP-27952-CS-INDV Component 4: / Recutement d'un Analyste IDA / 60820 Implementation Support and A posteriori Individuel Open 25,000.00 2,319.87 Signé 2017-09-11 2017-10-30 2017-11-20 2017-12-25 2018-12-25 financier à la DGOFR Technical Assistance C-18-NESAP-2019 / Component 4: En attente Recrutement d'un Expert en IDA / 60820 Implementation Support and A posteriori Individuel Limited 100,000.00 0.00 2017-09-11 2017-09-16 2017-10-07 2017-11-11 2018-11-06 d'exécution électrification rurale Technical Assistance CIND-001-NESAP-2019 / Recrutement d'un consultant Component 4: individuel pour élaborer des IDA / 60820 Implementation Support and A posteriori Individuel Limited 20,000.00 13,593.87 Signé 2019-05-15 2019-05-20 2019-06-03 2019-06-11 2019-08-10 NIES pour les cinq (5) Technical Assistance grappes de la phase pilote. AVENANT AU CONTRAT Component 4: Sélection de 002/NESAP/2017 / Avenant En attente IDA / 60820 Implementation Support and A posteriori consultants par Direct 28,544.00 0.00 2019-05-14 2019-05-20 2019-06-01 2020-05-26 au contrat de l'Auditeur d'exécution Technical Assistance entente directe Interne du projet AVENANT AU CONTRAT Component 4: Sélection de 003/NESAP/2017 / Avenant En attente IDA / 60820 Implementation Support and A posteriori consultants par Direct 28,544.00 0.00 2019-05-14 2019-05-20 2019-06-01 2020-05-26 au contrat de la Comptable d'exécution Technical Assistance entente directe Principale C-IND-001/NESAP/2019 / Component 4: Sélection de Consultant Local d'Appui à En attente IDA / 60820 Implementation Support and A posteriori consultants par Direct 25,000.00 0.00 2019-07-31 2019-08-10 2019-10-14 2020-10-13 la Mise en Oeuvre de la d'exécution Technical Assistance entente directe Composante 1 du projet Page 6