Public Disclosure Copy The World Bank Implementation Status & Results Report GN-Rural Roads Emergency Improvement Project (P156557) GN-Rural Roads Emergency Improvement Project (P156557) AFRICA | Guinea | Transport & Digital Development Global Practice | Recipient Executed Activities | Investment Project Financing | FY 2016 | Seq No: 2 | ARCHIVED on 27-Jun-2018 | ISR32889 | Implementing Agencies: Ministry of Finance, National Directorate of Rural Engineering Key Dates Key Project Dates Bank Approval Date:08-Mar-2016 Effectiveness Date:10-Jun-2016 Original Closing Date:31-Dec-2017 Revised Closing Date:30-Jun-2018 Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to improve the accessibility of local communities to health services and Ebola treatment facilities in the targeted area by mitigating key bottlenecks along selected rural roads. Has the Project Development Objective been changed since Board Approval of the Project Objective? No PHRPDODEL Components Name Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO  Moderately Unsatisfactory  Moderately Unsatisfactory Overall Implementation Progress (IP)  Moderately Unsatisfactory  Moderately Unsatisfactory Implementation Status and Key Decisions From December 31, 2018 to now, 2 missions were ( March 6, and March 23-29) conducted and on average 3 video-conferences per months were held with the client. Significant progress has been made the past six months. The disbursement increased from 34% to 71%. The project has 2 civil works contracts. The first contract which is the improvement of about 40 km of rural roads is satisfactorily completed. The second contract involves the construction of 10 prefabricated metallic bridges. The construction of the abutments and the approaches are completed. However the metallic bridges which are manufactured overseas ( China precisely) have not reached the sites ( expected arrival at 6/27/2018 Page 1 of 5 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report GN-Rural Roads Emergency Improvement Project (P156557) Conakry port end of September). To meet the PDO, a second extension of the closing date is needed so that the prefabricated metallic bridges can be transported to project sites in Guinea. Risks Overall Risk Rating Risk Category Rating at Approval Previous Rating Current Rating Overall  --  Substantial  Substantial Comments The risk is still substantial due to the poor performance of both the contractors and the implementing agency. Results Project Development Objective Indicators PHINDPDOTBL Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 66,000.00 Date 01-Jan-2016 -- -- 31-Dec-2017 PHINDPDOTBL Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 33,000.00 PHINDPDOTBL Travel time reduction (Percentage, Custom) 6/27/2018 Page 2 of 5 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report GN-Rural Roads Emergency Improvement Project (P156557) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 01-Jan-2016 -- -- 31-Dec-2017 Overall Comments indicators will be informed after the installation of the metallic bridge Intermediate Results Indicators PHINDIRITBL Roads rehabilitated, Rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 40.00 40.00 Date 01-Jan-2016 -- -- 31-Dec-2017 Comments The rehabilitation of 40 km of rural roads are completed. PHINDIRITBL Length of constructed bridges (Meter(m), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 135.00 Date 01-Jan-2016 -- -- 31-Dec-2017 Comments The metallic bridges are still not available 6/27/2018 Page 3 of 5 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report GN-Rural Roads Emergency Improvement Project (P156557) PHINDIRITBL Number of Ebola Treatment Unit served (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 7.00 Date 01-Jan-2016 -- -- 31-Dec-2017 Comments The metallic bridges need to be installed in order to inform this indicator Overall Comments indicator will be informed after the installation of the metallic bridges. Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed Disbursed P156557 TF-A2432 Effective USD 2.85 2.85 0.00 2.01 0.84 71% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P156557 TF-A2432 Effective 08-Mar-2016 10-Jun-2016 10-Jun-2016 31-Dec-2017 30-Jun-2018 Cumulative Disbursements 6/27/2018 Page 4 of 5 Public Disclosure Copy Public Disclosure Copy The World Bank Implementation Status & Results Report GN-Rural Roads Emergency Improvement Project (P156557) Restructuring History Level 2 Approved on 21-Dec-2017 Related Project(s) There are no related projects. 6/27/2018 Page 5 of 5 Public Disclosure Copy