The World Bank Implementation Status & Results Report CAR Emergency Electricity Supply and Access Project (P164885) CAR Emergency Electricity Supply and Access Project (P164885) AFRICA | Central African Republic | Energy & Extractives Global Practice | IBRD/IDA | Investment Project Financing | FY 2019 | Seq No: 2 | ARCHIVED on 21-Nov-2019 | ISR39390 | Implementing Agencies: Ministry of Development of Energy and Water Resources (MDEWR), Energie Centrafricaine (ENERCA), Ministry of Economy, Planning, and International Corporation Key Dates Key Project Dates Bank Approval Date: 28-Feb-2019 Effectiveness Date: 27-Jun-2019 Planned Mid Term Review Date: -- Actual Mid-Term Review Date: Original Closing Date: 28-Feb-2024 Revised Closing Date: 28-Feb-2024 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The PDO is to increase electricity supply and access in Central African Republic. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1: Construction of a Solar PV Electricity Generation Plant:(Cost $48.00 M) Component 2: Strengthening of the transmission and distribution (T&D) networks:(Cost $10.60 M) Component 3: Institutional strengthening, capacity building, and project implementation support:(Cost $6.40 M) Component 4: Contingent emergency response Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Satisfactory Moderately Satisfactory Overall Risk Rating High High Implementation Status and Key Decisions The Project was approved by the Board in February 28, 2019 and the Financing Agreement was signed in April 9, 2019. The Project is effective as of June 27, 2019. The project is currently under implementation, with the early procurement of key contracts, including the solar plant. The objective is to start construction in May 2020. Project sites will be prepared as soon as all safeguards issues are solved, including compensation of people affected by the project. 11/21/2019 Page 1 of 6 The World Bank Implementation Status & Results Report CAR Emergency Electricity Supply and Access Project (P164885) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance High High High Macroeconomic High High High Sector Strategies and Policies Substantial Substantial Substantial Technical Design of Project or Program Substantial Substantial Substantial Institutional Capacity for Implementation and Sustainability High High High Fiduciary High High High Environment and Social Moderate Moderate Moderate Stakeholders Moderate Moderate Moderate Other High High High Overall High High High Results PDO Indicators by Objectives / Outcomes Increase electricity supply IN00768650 ►Annual electricity generation dispatched from solar energy (Gigawatt-hour (GWh), Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 37.00 Date 01-May-2018 30-Apr-2019 08-Nov-2019 28-Feb-2024 The indicator measures the annual amount of electricity (in gigawatt hour) that is produced by the solar Comments: plant and transmitted to the existing transmission line Boali/Bangui. Increase electricity access IN00768649 ►People provided with new or improved electricity service (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 250,000.00 Date 01-Feb-2018 30-Apr-2019 08-Nov-2019 28-Feb-2024 11/21/2019 Page 2 of 6 The World Bank Implementation Status & Results Report CAR Emergency Electricity Supply and Access Project (P164885) IN00768776 People provided with new or improved electricity service - Female (Number, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 125,000.00 Overall Comments PDO All indicators remain at the baseline as procurement of key contracts is on-going. Intermediate Results Indicators by Components Construction of a Solar PV Electricity Generation Plant IN00768777 ►Generation capacity of energy constructed or rehabilitated (Megawatt, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 25.00 Date 01-May-2018 30-Apr-2019 08-Nov-2019 28-Feb-2024 IN00768785 Renewable energy generation capacity (other than hydropower) constructed under the project (Megawatt, Corporate Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 25.00 Date 01-May-2018 30-Apr-2019 08-Nov-2019 28-Feb-2024 Strengthening of the Transmission and Distribution Networks IN00768778 ►Distribution lines constructed or rehabilitated under the project (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 450.00 Date 01-May-2018 30-Apr-2019 08-Nov-2019 28-Feb-2024 The indicator measures in kilometers (KM) the distribution lines rehabilitated or constructed under the Comments: project IN00768780 ►Transmission and distribution substations rehabilitated or constructed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 42.00 Date 01-May-2018 30-Apr-2019 08-Nov-2019 28-Feb-2024 11/21/2019 Page 3 of 6 The World Bank Implementation Status & Results Report CAR Emergency Electricity Supply and Access Project (P164885) 2 transmission substations (Bangui A and Bangui B) should be rehabilitated (including construction of a 25 Comments: MVA transformed in Bangui A), and 40 new low and medium voltage substations constructed IN00768782 ►SCADA system installed and operated (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 1.00 Date 01-May-2018 30-Apr-2019 08-Nov-2019 28-Feb-2024 Comments: The indicator measures the number of SCADA systems that are installed and operational Institutional Strengthening, Capacity Building, and Project Implementation Support IN00768779 ►Number of ENERCA and MDEWR staff trained (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 30.00 Date 01-Feb-2018 30-Apr-2019 08-Nov-2019 28-Feb-2024 The indicator measures in numbers the staff from ENERCA and MDEWR trained, of which the percentage Comments: of female staff trained IN00768781 percentage of female trained (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 50.00 Date 01-May-2018 30-Apr-2019 08-Nov-2019 28-Feb-2024 IN00768783 ►Number of studies/frameworks completed (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 5.00 Date 01-May-2018 30-Apr-2019 08-Nov-2019 28-Feb-2024 Comments: The indicator measures in number the studies and frameworks completed IN00768784 ►Share of grievances responded to and resolved (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 60.00 100.00 Date 01-May-2018 30-Apr-2019 08-Nov-2019 28-Feb-2024 Comments: Percentage of complaints and grievances recorded by the PIU and resolved. 11/21/2019 Page 4 of 6 The World Bank Implementation Status & Results Report CAR Emergency Electricity Supply and Access Project (P164885) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P164885 IDA-D4300 Effective USD 65.00 65.00 0.00 1.27 63.15 2% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P164885 IDA-D4300 Effective 28-Feb-2019 09-Apr-2019 27-Jun-2019 28-Feb-2024 28-Feb-2024 Cumulative Disbursements Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 11/21/2019 Page 5 of 6 The World Bank Implementation Status & Results Report CAR Emergency Electricity Supply and Access Project (P164885) 11/21/2019 Page 6 of 6