: Summary Procurement Plan I. General Bank’s approval Date of the procurement Plan [Original: April 5, 2013] Date of General Procurement Notice: April 15, 2013 II. Goods and Works and non-consulting services. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Initial Prior Review Comments Threshold US$ 1. ICB (Goods) Above US$300,000 All 2. NCB (Goods) packages Equal or below US$300,000 First 2 contracts 3. ICB (Works) packages Above US$4,000,000 All 4. NCB (Works) packages Equal or below US$4,000,000 First 2 contracts Prequalification. Not applicable. Proposed Procedures for CDD Components (as per paragraph. 3.19 of the Guidelines: Not applicable Project Operational Manual: The PIU will revise the POM that was originally developed for the IDP and updated for the IREP. Any Other Special Procurement Arrangements: 2 (two) ICB packages (“Construction of Meghri Gravity Scheme” and “Procurement of Water Measurement Equipment Compatible with SCADA system”) will be procured under advance procurement. Summary of the Procurement Packages planned during the first 18 months after project effectiveness (including those that are subject to retroactive financing and advanced procurement) 1 2 3 4 Ref. Description Estimated Packages (Lots) No. Cost US$ million 1 Summary of the ICB (Works) packages 21.88 3 (8 lots) 2 Summary of the ICB (Goods) packages 0.800 1 3 Summary of the NCB (Works) packages 9.30 5 4 Summary of the Shopping (Goods) 0.030 1 packages III. Selection of Consultants Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: # Selection Method Initial Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$100,000 2. Single Source (Firms and Individuals) All 3. Individual Above US$50,000 Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $100,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. Any Other Special Selection Arrangements: 1 (one) QCBS package (“Technical Supervision over Construction of Meghri Gravity Scheme”) and 1 (one) SSS package (“Design Author’s Supervision over Construction of Meghri Gravity Scheme”) will be procured under advance procurement. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. Description of Assignment Estimated Packages Review Comments No. by Bank Cost (Prior / Post) US$ million Summary of number of contracts 1. 2.63 11 Prior that will be let under QCBS Summary of number of contracts 2. 0.43 9 Post that will be let under CQS 2 of SSS contracts for Summary of number of contracts Prior Review/ 3. 0.13 4 Prior/Post that will be let under other methods 2 of Individual contracts for Post Review PROCUREMENT Armenia : IRRIGATION SYSTEM ENHANCEMENT PROJECT PLAN General Information Country: Armenia Bank’s Approval Date of the Original Procurement Plan: 2016-09-15 2018-12-10 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P127759 GPN Date: 2017-11-23 Project Name: IRRIGATION SYSTEM ENHANCEMENT PROJECT Loan / Credit No: IBRD / 82670, IBRD / 87860 Executing Agency(ies): Water Sector Projects Implementation Unit WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ISEP/NCB/CW-14/001 / Rehabilitation of Diversion Canals of Achajur, Single Stage - One IBRD / 82670 Prior Request for Bids Open - National 1,315,223.58 Signed Noyemberyan 4-stage and Envelope Zeytun-Haghtanak Pumps Stations ISEP/ICB/CW-14/002-1 / Construction of Geghardalich Under Open - Single Stage - One Irrigation Scheme - IBRD / 82670 Prior Request for Bids 2,666,506.39 Implementati International Envelope Reconstruction of on Geghardalich Dam Lot 1 ISEP/ICB/CW-14/002-2 / Construction of Geghardalich Open - Single Stage - One Irrigation Scheme - Lot 2 IBRD / 82670 Prior Request for Bids 2,549,710.99 Terminated International Envelope Construction of Main Pipeline DM0 00 DM133 00 ISEP/ICB/CW-14/002-3 / Construction of Geghardalich Irrigation Scheme - Lot 3 Open - Single Stage - One Construction of Main IBRD / 82670 Prior Request for Bids 2,299,509.45 Signed International Envelope Pipeline DM133 00 DM258 64 and Geghadir-Hatsavan pipeline ISEP/ICB/CW-14/001-1 / Construction of Kaghtsrashen Under Irrigation Scheme Lot 1 Open - Single Stage - One IBRD / 82670 Prior Request for Bids 2,148,528.90 Implementati Construction of Main International Envelope on Pipeline DM0 00-DM90 16.32 ISEP/ICB/CW-14/001-3 / Construction of Kaghtsrashen Irrigation Scheme Lot 3 Open - Single Stage - One IBRD / 82670 Prior Request for Bids 2,222,721.29 Signed Construction of Main International Envelope pipeline DM196 60-DM275 79.89 ISEP/ICB/CW-14/001-2 / Construction of Kaghtsrashen Irrigation Scheme Lot 2: Open - Single Stage - One IBRD / 82670 Prior Request for Bids 3,933,328.34 Signed Construction of Main International Envelope pipeline DM90 16.32-DM196 60 Page 1 ISEP/NCB/CW-14/002 / Rehabilitation of Diversion Single Stage - One Canals of Metsamor IBRD / 82670 Prior Request for Bids Open - National 2,191,391.96 Signed Envelope (Tandzut Ghamshlu) and Ghara-Ghala Pumps Stations ISEP/AF/NCB/CW-17/001 / Construction of Baghramyan- Single Stage - One IBRD / 87860 Post Request for Bids Open - National 1,632,609.97 Signed 2017-12-10 2017-12-15 2018-01-22 2018-02-21 2018-03-28 2019-04-28 Norakert On-Farm Irrigation Envelope Network ISEP/NCB/CW-15/003 / Under Single Stage - One Construction of Baghramyan- IBRD / 82670 Post Request for Bids Open - National 0.00 Implementati 2018-04-18 2018-04-18 2018-04-18 2018-04-18 2018-04-18 2018-06-27 Envelope Norakert Gravity Scheme on GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ISEP/ICB/PG-13/001 / Supply and Installation of Open - Single Stage - One Water Measurement IBRD / 82670 Prior Request for Bids 653,690.00 Signed International Envelope Equipment Compatible with Data Acquisition System NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ISEP/QCBS/SW-14/002 / Technical Supervision over Rehabilitation of Diversion Canals of Achajur, Quality And Cost- Open - IBRD / 82670 Prior 99,168.69 Signed Noyemberyan 4-stage, Zeytun- Based Selection International Haghtanak, Metsamor (Tandzut Ghamlu) and Ghara-Ghala Pumps Stations ISEP/QCBS/SW-14/004 / Technical Supervision over Rehabilitation of Diversion Canals of Kaghtsrashen, Quality And Cost- Open - IBRD / 82670 Prior 109,614.16 Terminated Avshar-Aygevan, Armash, Based Selection International Arazap, Jrashen-Azat, Zovk, Argina & Saralanj Pumps Stations ISEP/QCBS/SW-14/003 / Technical Supervision over Quality And Cost- Open - Under IBRD / 82670 Prior 200,714.82 Construction of Geghardalich Based Selection International Implementation Gravity Irrigation Scheme Page 2 ISEP/QCBS/SW-14/001 / Technical Supervision over Quality And Cost- Open - IBRD / 82670 Prior 296,039.40 Signed Construction of Kaghtsrashen Based Selection International Gravity Irrigation Scheme ISEP/QCBS/SW-14/005 / Investigation of Technical Quality And Cost- Open - State of Irrigation System IBRD / 82670 Post 627,163.69 Signed 2017-06-23 2017-06-23 2017-07-31 2017-08-30 2017-09-29 2017-10-09 2017-10-25 2018-06-24 Based Selection International and Assessment of Required Investments ISEP/CQS/SW-13/002 / Enhancement of existing Consultant Pending software by adding features IBRD / 82670 Post Qualification Open - National 0.00 2017-10-02 2017-10-16 2017-11-20 2017-12-20 2017-12-25 2018-06-25 Implementation for management of O&M Selection (including training in WUAs) ISEP/CQS/SW-14/001 / Development of an Consultant Pending informative web site to IBRD / 82670 Post Qualification Open - National 0.00 2017-10-02 2017-10-16 2017-11-20 2017-12-20 2017-12-25 2018-05-25 Implementation improve awareness among Selection water users ISEP/AF/CQS/CS-17/001 / Technical Supervision over Consultant Under Construction of IBRD / 87860 Post Qualification Open - National 0.00 2017-12-01 2017-12-15 2018-01-29 2018-02-28 2018-03-28 2019-04-28 Implementation Baghramyan-Norakert On- Selection Farm Irrigation Network ISEP/CQS/SW-15/001 / Consultant Technical supervision over Pending IBRD / 82670 Post Qualification Open - National 0.00 2018-04-18 2018-04-18 2018-04-18 2018-04-18 2018-04-18 2018-06-27 Construction of Baghramyan- Implementation Selection Norakert Gravity Scheme ISEP/CQS/SW-16/002-D / Consultant Design of Baghramyan- Pending IBRD / 82670 Post Qualification Open - National 0.00 2018-04-18 2018-04-18 2018-04-18 2018-04-18 2018-04-18 2018-04-18 Norakert On-Farm Irrigation Implementation Selection Network ISEP/CQS/SW-16/002-AS / Consultant Author's Supervision of Under IBRD / 82670 Post Qualification Open - National 0.00 2018-04-18 2018-04-18 2018-04-18 2018-04-18 2018-04-18 2018-04-18 Baghramyan-Norakert On- Implementation Selection Farm Irrigation Network INDIVIDUAL CONSULTANTS Page 3