Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan Original: March 20, 2014: Updated Procurement Plan, February 2016 2. Date of General Procurement Notice: June 10, 2014 3. Period covered by this procurement plan: The procurement period of project covered from year July 2017 to January 2019 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Threshold (At or above US$) Works (including turnkey, supply & 5 installation of plant and equipment, and PPP) Goods, information technology and 1.5 non-consulting services 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: Not Applicable. 4. Reference to (if any) Project Operational/Procurement Manual: Not Applicable. 5. Any Other Special Procurement Arrangements: Not Applicable. 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank (Prior / Post) July 9, 2010 US$ Prefere million nce (yes/no) 1 Summary of 127 4 No Prior the ICB (Works) 2 Summary of 88 3 No Prior the ICB (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Type of Procurement Prior Review Threshold (At or above US$) Consultants: firms 0.5 Consultants: Individuals 0.2 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: Not Applicable. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) 1 Summary of 4 1 Prior number of contracts that will be let under QCBS July 9, 2010 PROCUREMENT Ethiopia : Ethiopia Geothermal Sector Development Project PLAN General Information Country: Ethiopia Banks Approval Date of the Original Procurement Plan: 2017-07-31 Revised Plan Date(s): (comma delineated, leave blank if none) 2018-01-22 Project ID: P133613 GPN Date: Project Name: Ethiopia Geothermal Sector Development Project Loan / Credit No: IDA / 54680 Executing Agency(ies): Ethiopian Electric Power WORKS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-EEP-24663-CW-RFB / Procurement of Full Service Alalobad Geothermal Site Single Stage - One Pending IDA / 54680 Prior Request for Bids Open - International 0.00 2017-10-30 2017-11-15 2018-01-30 2018-04-30 2018-07-15 2020-03-20 Drilling Contractors (FSDC) at Development Envelope Implementation Alalobad ET-EEP-24665-CW-RFB / Alalobad Geothermal Site Single Stage - One Pending Procurement of Civil Works at IDA / 54680 Prior Request for Bids Open - International 0.00 2017-11-15 2017-11-30 2018-01-15 2018-02-20 2018-03-09 2019-04-21 Development Envelope Implementation Alalobad ET-EEP-24662-CW-RFB / Procurement of Two Rigs, Drilling Aluto Geothermal Site Single Stage - One IDA / 54680 Prior Request for Bids Open - International 0.00 Under Review 2017-10-06 2017-11-21 2018-01-30 2018-04-15 2018-07-15 2020-03-20 Crew Operator and Supply of Development Envelope Maintaince at Aluto ET-EEP-24664-CW-RFB / Design and Build of Civil Works (Access Roads, Camp, Casing Aluto Geothermal Site Single Stage - Two Pending IDA / 54680 Post Request for Bids Open - National 0.00 2018-01-22 2018-01-27 2018-03-10 2018-06-05 2018-07-03 2019-12-30 Storage Area, Drilling Sites) for Development Envelope Implementation Aluto Geothermal Sector Development Project ET-EEP-44397-CW-RFB / Design and Build of Civil Works Aluto Geothermal Site Single Stage - Two Pending (Water Supply System) for Aluto IDA / 54680 Post Request for Bids Open - National 0.00 2018-01-24 2018-01-29 2018-03-12 2018-06-13 2018-07-18 2020-01-14 Development Envelope Implementation Geothermal Sector Development Project GOODS Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-EEP-22172-GO-RFB / Water Drilling Rig, Associated Single Stage - One IDA / 54680 Prior Request for Bids Open - International 4,494,826.66 Signed 2015-08-18 2015-08-28 2015-12-01 2016-01-30 2017-08-31 2016-05-25 2017-12-22 2016-11-21 Supply System Accessories and Spare Parts Envelope ET-EEP-22174-GO-RFB / Drilling Rig, Associated Single Stage - One IDA / 54680 Prior Request for Bids Open - International 0.00 Canceled 2015-08-18 2015-08-28 2015-12-01 2016-01-30 2016-05-25 2016-11-21 Supply of Heavy Machinery Accessories and Spare Parts Envelope ET-EEP-22178-GO-RFB / Drilling Rig, Associated Single Stage - One IDA / 54680 Prior Request for Bids Open - International 0.00 Canceled 2015-08-18 2015-08-28 2015-12-01 2016-01-30 2016-05-25 2016-11-21 Supply of Trucks and Vehicles Accessories and Spare Parts Envelope ET-EEP-22159-GO-RFB / Drilling Rig, Associated Single Stage - One Supply of Drilling Rigs and its IDA / 54680 Prior Request for Bids Open - International 0.00 Canceled 2015-08-18 2015-08-28 2015-12-01 2016-01-30 2016-05-25 2016-11-21 Accessories and Spare Parts Envelope accessories NON CONSULTING SERVICES Activity Reference No. / Bid Evaluation Report Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Draft Bidding Document Specific Procurement Bidding Documents as Proposal Submission / Description Loan / Credit No. Component Review Type Method Market Approach and Recommendation Signed Contract Contract Completion Process (Y/N) (US$) Status Documents Evaluation Report / Justification Notice / Invitation Issued Opening / Minutes for Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Technical Description Loan / Credit No. Component Review Type Method Market Approach Process Status Terms of Reference Report and Draft Signed Contract Contract Completion (US$) Notice Request for Proposals as Issued Proposals / Minutes Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Page 1