The World Bank Implementation Status & Results Report Solomon Islands Community Benefit Sharing Pilot Project (P153986) Solomon Islands Community Benefit Sharing Pilot Project (P153986) EAST ASIA AND PACIFIC | Solomon Islands | Social Global Practice | Recipient Executed Activities | Investment Project Financing | FY 2018 | Seq No: 1 | ARCHIVED on 05-Oct-2019 | ISR38741 | Implementing Agencies: Solomon Islands, Ministry of Mines, Energy & Rural Electrification, Solomon Islands Electricity Authority Key Dates Key Project Dates Bank Approval Date: 18-Sep-2017 Effectiveness Date: 10-Apr-2018 Original Closing Date: 30-Jun-2021 Revised Closing Date: 30-Jun-2021 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective is to establish the institutional arrangements and capacity for Benefit Sharing Communities to manage a share of the revenues from the operation of a large-scale infrastructure investment project and to improve their basic services and skills for income generation during the construction period. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO -- ►Moderately Satisfactory Overall Implementation Progress (IP) -- ►Moderately Satisfactory Implementation Status and Key Decisions Since the agreement for this project was signed, implementation has been delayed by two years due to delays in the signing of agreements for the associated Tina River Hydropower Development Project (TRHDP) and an incomplete process of compensation for land acquisition related to the TRHDP. With the TRHDP Project agreements signed, and with the recent establishment of the last tribal cooperative society to receive compensation for land acquisition, an environment conducive to launching this project is now in place. The project has begun to disburse funds and the core personnel to implement the project will be in place shortly. While an extension of the closing date will be needed due to the delays, the next six months will be a critical period for determining whether the project can be put on track for accomplishing the project objective. Risks Overall Risk Rating 10/5/2019 Page 1 of 6 The World Bank Implementation Status & Results Report Solomon Islands Community Benefit Sharing Pilot Project (P153986) Risk Category Rating at Approval Previous Rating Current Rating Overall -- -- ►Substantial 5. Results Project Development Objective Indicators IN00749397 ►Benefit sharing fund legally registered (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- -- Yes Date 01-Sep-2017 -- -- 29-Mar-2019 IN00749398 ►Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 4,200.00 Date 01-Sep-2017 -- -- 30-Jun-2021 IN00749410 ►Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 50.00 IN00749399 ►Percentage of individuals trained who are earning increased income (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 50.00 Date 01-Sep-2017 -- -- 30-Jun-2021 IN00749411 ►Percentage of women who are earning increased income (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 50.00 Date 01-Sep-2017 -- -- 30-Jun-2021 10/5/2019 Page 2 of 6 The World Bank Implementation Status & Results Report Solomon Islands Community Benefit Sharing Pilot Project (P153986) IN00749401 ►Percentage of target beneficiaries that participated in consultation meetings regarding benefit sharing institutional arrangements (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 60.00 Date 01-Sep-2017 -- -- 30-Jun-2021 IN00749412 ►Percentage of target beneficiaries that participated in consultation meetings regarding benefit sharing institutional arrangements of which are women (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 50.00 Date 01-Sep-2017 -- -- 30-Jun-2021 Intermediate Results Indicators IN00749404 ►Operations Manual for the benefit sharing fund developed (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No -- -- Yes Date 01-Sep-2017 -- -- 31-Mar-2020 IN00749409 ►Percentage of benefit sharing fund board members trained (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 100.00 Date 01-Sep-2017 -- -- 30-Jun-2021 IN00749408 ►Percentage of people consulted during the project that feel their views are reflected in the design of the Community Benefit Sharing Fund (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 75.00 Date 01-Sep-2017 -- -- 30-Jun-2021 IN00749402 ►Number of people in rural areas provided with access to Improved Water Sources under the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target 10/5/2019 Page 3 of 6 The World Bank Implementation Status & Results Report Solomon Islands Community Benefit Sharing Pilot Project (P153986) Value 0.00 -- -- 4,000.00 Date 01-Sep-2017 -- -- 30-Jun-2021 IN00749403 ►People provided with access to improved sanitation services (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 1,300.00 Date 01-Sep-2017 -- -- 30-Jun-2021 IN00749407 ►Beneficiaries of job-focused interventions (Number, Corporate) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 300.00 Date 01-Sep-2017 -- -- 30-Jun-2021 IN00749414 ►Beneficiaries of job-focused interventions - Female (Number, Corporate Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 150.00 IN00749405 ►Transmission lines constructed or rehabilitated under the project (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 10.00 Date 01-Sep-2017 -- -- 30-Jun-2021 IN00749413 ►Transmission lines constructed under the project (Kilometers, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 10.00 Date 01-Sep-2017 -- -- 31-Mar-2020 IN00749406 ►Number of mid-term and final impact assessment reports prepared (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 2.00 Date 01-Sep-2017 -- -- 30-Jun-2021 10/5/2019 Page 4 of 6 The World Bank Implementation Status & Results Report Solomon Islands Community Benefit Sharing Pilot Project (P153986) IN00749400 ►Number of Knowledge dissemination events on the lessons of the benefit sharing pilot organized (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 -- -- 2.00 Date 01-Sep-2017 -- -- 30-Jun-2021 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P153986 TF-A6839 Effective USD 2.80 2.80 0.00 0.31 2.49 11% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P153986 TF-A6839 Effective 18-Sep-2017 10-Apr-2018 10-Apr-2018 30-Jun-2021 30-Jun-2021 Cumulative Disbursements 10/5/2019 Page 5 of 6 The World Bank Implementation Status & Results Report Solomon Islands Community Benefit Sharing Pilot Project (P153986) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 10/5/2019 Page 6 of 6