Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: April 3, 2015]: Revision 9 of Updated Procurement Plan, Mar 2, 2017] 2. Date of General Procurement Notice: October 2015 3. Period covered by this procurement plan: The procurement period of project covered from October 2015 to December 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of Procurement Prior Review Threshold Comments US$ 1. Works Above USD 10M All 2. Goods Above USD 2M All 2. Prequalification. Bidders for _more than US$ 10 million_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Reference to (if any) Project Operational/Procurement Manual: Project Operations Manual and SOPs for Procurement prepared by Planning and Development Department AJK, Provincial Disaster Management Authority Punjab and Punjab Irrigation Department. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 3. Consulting firms Above USD 1M All 4. Individual Consultants Above USD 0.3 M All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_500,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: None March 30, 2017 PROCUREMENT Pakistan : Disaster and Climate Resilience Improvement Project PLAN General Information Country: Pakistan Bank’s Approval Date of the Original Procurement Plan: 2016-10-20 2019-10-10 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P154036 GPN Date: Project Name: Disaster and Climate Resilience Improvement Project Loan / Credit No: IDA / 56860 Executing Agency(ies): Provincial Disaster Management Authority Punjab WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PDMA PUNJAB-2497- Component 2: Managing Request for Single Stage - One GO-RFQ / IT related Office IDA / 56860 Disasters and Climate Post Open - National 26,653.16 Signed 2016-10-15 2016-12-10 2017-06-08 Quotations Envelope Equipment for DDMAs Variability PK-PDMA PUNJAB-2499- Component 2: Managing Request for Single Stage - One GO-RFQ / Office Furniture IDA / 56860 Disasters and Climate Post Open - National 23,736.21 Signed 2016-10-15 2016-12-10 2017-06-08 Quotations Envelope for PIU Variability PK-PDMA PUNJAB-2495- GO-RFQ / 1. Fixtures and Furnishers for Component 2: Managing Under Request for Single Stage - One establishment of PIU Head IDA / 56860 Disasters and Climate Post Open - National 34,059.20 Implementati 2016-10-14 2016-12-09 2017-06-07 Quotations Envelope Quarter Variability on 2. Necessary equipment for PIU HQ PK-PDMA PUNJAB-2503- Component 2: Managing Pending Single Stage - Two GO-RFQ / Establishment of IDA / 56860 Disasters and Climate Post Request for Bids Open - National 0.00 Implementati 2016-11-10 2016-11-15 2016-12-27 2017-03-11 2017-04-15 2017-10-12 Envelope EOC at District Level Variability on PK-PDMA PUNJAB-2769- GO-CD / "Equipment for Component 2: Managing Single Stage - One Establishment of Central IDA / 56860 Disasters and Climate Post Request for Bids Open - National 0.00 Canceled 2016-11-14 2016-11-19 2016-12-31 2017-01-30 2017-03-06 2017-09-02 Envelope Command and Control Variability Center (CCC)" PK-PDMA PUNJAB-2770- Component 2: Managing GO-CD / Relief and Rescue Single Stage - One IDA / 56860 Disasters and Climate Post Request for Bids Open - National 0.00 Canceled 2016-11-17 2016-11-22 2016-12-22 2017-01-21 2017-02-25 2017-08-24 Equipment for Priority Envelope Variability Districts PK-PDMA PUNJAB-2493- Component 2: Managing Request for Single Stage - One GO-RFQ / Operational IDA / 56860 Disasters and Climate Prior Open - National 0.00 Canceled 2016-10-14 2016-12-09 2017-06-07 Quotations Envelope Vehicles (4 x 4) = 04 Variability PK-PDMA PUNJAB-2765- Component 2: Managing Open - Single Stage - One GO-CD / Mobile IDA / 56860 Disasters and Climate Prior Request for Bids 0.00 Canceled 2016-11-17 2016-11-22 2017-01-03 2017-02-02 2017-03-09 2017-09-05 International Envelope Communication Office Variability Page 1 PK-PDMA PUNJAB-3799- Component 2: Managing Request for Single Stage - One GO-RFQ / Operational IDA / 56860 Disasters and Climate Post Open - National 154,252.44 Signed 2016-12-01 2016-12-05 2017-06-03 Quotations Envelope Vehicles (4 x 4) = 04 Variability PK-PDMA PUNJAB-14309- Component 2: Managing GO-RFQ / Critical Request for Single Stage - One IDA / 56860 Disasters and Climate Post Open - National 36,069.72 Signed 2017-05-08 2017-07-03 2017-12-30 Equipment (Furniture) for Quotations Envelope Variability Districts Phase ii PK-PDMA PUNJAB-16391- GO-RFB / Critical Equipment (IT Component 2: Managing Pending Single Stage - One Equipment(Android Mobile IDA / 56860 Disasters and Climate Post Request for Bids Open - National 0.00 Implementati 2017-05-29 2017-06-03 2017-07-15 2017-08-14 2017-09-18 2018-03-17 Envelope Devices,Laptops,Workstations, Variability on Printers,Scanners & UPS) For Phase ii PK-PDMA PUNJAB-16394- Component 2: Managing Pending GO-RFQ / Video Request for Single Stage - One IDA / 56860 Disasters and Climate Post Open - National 0.00 Implementati 2017-06-03 2017-07-29 2018-01-25 Conferencing Equipment Quotations Envelope Variability on Installation at PIU Office PK-PDMA PUNJAB-16671- GO-RFQ / Critical Component 2: Managing Equipment For Districts Request for Single Stage - One IDA / 56860 Disasters and Climate Post Open - National 32,234.15 Signed 2017-06-06 2017-08-01 2018-01-28 (20*UPS(3KVA)/Power Quotations Envelope Variability Backup) Proposed by Capacity Building Firm PK-PDMA PUNJAB-16673- GO-RFQ / Critical Component 2: Managing Equipment for HO (6*UPS Request for Single Stage - One IDA / 56860 Disasters and Climate Post Open - National 133,925.01 Signed 2017-06-06 2017-08-01 2018-01-28 (10KVA) & 220 KVA Gen- Quotations Envelope Variability set )proposed by Capacity Building Firm PK-PDMA PUNJAB-25535- Component 2: Managing GO-RFQ / Additional Request for Single Stage - One IDA / 56860 Disasters and Climate Post Open - National 140,345.76 Signed 2017-08-22 2017-10-03 2018-04-01 Operational Vehicles (4 x 4) Quotations Envelope Variability = 02 PK-PDMA PUNJAB-39964- GO-RFB / IT Equipment (Integration of Early Warning System with DEOCs at District Level - Turnkey Solution, Component 2: Managing Under Single Stage - One Workstation with UPS, IDA / 56860 Disasters and Climate Post Request for Bids Open - National 0.00 Implementati 2017-12-19 2017-12-24 2018-02-04 2018-03-06 2018-04-10 2018-10-07 Envelope Printers, Scanners, Variability on Photocopiers, Fax Machine, Telephone Sets, 02 Ton Cabinet ACs, bandwidth, Biometric Dashboard, Digital Cameras) PK-PDMA PUNJAB-3855- Component 2: Managing Open - Single Stage - One GO-RFB / Mobile IDA / 56860 Disasters and Climate Post Request for Bids 0.00 Canceled 2016-11-30 2016-12-05 2017-01-16 2017-02-15 2017-03-22 2017-09-18 International Envelope Communication Office Variability PK-PDMA PUNJAB-127999- Component 2: Managing Pending Single Stage - One GO-RFB / Procurement of IDA / 56860 Disasters and Climate Post Request for Bids Open - National 0.00 Implementati 2019-09-18 2019-09-23 2019-11-04 2019-12-04 2020-01-08 2020-07-06 Envelope Power Backup Variability on PK-PDMA PUNJAB-128000- Component 2: Managing Pending Single Stage - One GO-RFB / Prourement of IT IDA / 56860 Disasters and Climate Post Request for Bids Open - National 0.00 Implementati 2019-09-20 2019-09-25 2019-11-06 2019-12-06 2020-01-10 2020-07-08 Envelope equipment & accessories Variability on PK-PDMA PUNJAB-127977- Component 2: Managing Pending Single Stage - One GO-RFQ / Procurement of IDA / 56860 Disasters and Climate Post Request for Bids Open - National 0.00 Implementati 2019-09-19 2019-09-24 2019-11-05 2019-12-05 2020-01-09 2020-07-07 Envelope office equipment Variability on Page 2 PK-PDMA PUNJAB-128484- Component 2: Managing Pending Single Stage - One GO-RFB / Procurement of IDA / 56860 Disasters and Climate Post Request for Bids Open - National 0.00 Implementati 2019-09-16 2019-09-21 2019-11-02 2019-12-02 2020-01-06 2020-07-04 Envelope Industrial Chiller Variability on PK-PDMA PUNJAB-128499- Component 2: Managing Pending GO-RFB / Procurement of Single Stage - One IDA / 56860 Disasters and Climate Post Request for Bids Open - National 0.00 Implementati 2019-09-30 2019-10-05 2019-11-16 2019-12-16 2020-01-20 2020-07-18 Drone Mapping Device with Envelope Variability on integrated HD camera PK-PDMA PUNJAB-128491- Component 2: Managing Pending Single Stage - One GO-RFB / Procurement of IDA / 56860 Disasters and Climate Post Request for Bids Open - National 0.00 Implementati 2019-09-20 2019-09-25 2019-11-06 2019-12-06 2020-01-10 2020-07-08 Envelope Vehicles 4x4 Variability on PK-PDMA PUNJAB-128493- Component 2: Managing Pending Single Stage - One GO-RFB / Procurement of IDA / 56860 Disasters and Climate Post Request for Bids Open - National 0.00 Implementati 2019-09-30 2019-10-05 2019-11-16 2019-12-16 2020-01-20 2020-07-18 Envelope water bowsers Variability on PK-PDMA PUNJAB-128517- Component 2: Managing Pending Single Stage - One GO-RFB / Procurement of IDA / 56860 Disasters and Climate Post Request for Bids Open - National 0.00 Implementati 2019-09-20 2019-09-25 2019-11-06 2019-12-06 2020-01-10 2020-07-08 Envelope search and rescue equipment Variability on NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PDMA PUNJAB-16392- NC-RFQ / Early Warning Component 2: Managing Notifications through mobile Request for Single Stage - One IDA / 56860 Disasters and Climate Post Open - National 1,479.12 Signed 2017-06-03 2017-07-29 2018-01-25 Short Messaging Service Quotations Envelope Variability (Number of people at risk receive alerts) CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PDMA PUNJAB-2515- CS-QCBS / Hiring of Firm Component 2: Managing Consultant for Development and IDA / 56860 Disasters and Climate Post Qualification Open - National 183,997.48 Signed 2016-10-24 2016-11-14 2016-12-28 2017-01-27 2017-03-03 2017-08-30 Implementation of CBDRM Variability Selection Program PK-PDMA PUNJAB-2767- CS-CQS / Hiring of Firm for Component 2: Managing Consultant Organizational Capacity IDA / 56860 Disasters and Climate Post Qualification Open - National 0.00 Canceled 2016-10-31 2016-11-21 2017-01-04 2017-02-03 2017-03-10 2017-09-06 Assessment and Capacity Variability Selection Enhancement Plan at Provincial and District Level PK-PDMA PUNJAB-3509- CS-CQS / Hiring of Firm for Component 2: Managing Consultant Organizational Capacity IDA / 56860 Disasters and Climate Prior Qualification Open - National 0.00 Canceled 2016-11-17 2016-12-02 2016-12-24 2016-12-27 2017-01-06 2017-07-05 Assessment and Capacity Variability Selection Enhancement Plan at Provincial and District Level PK-PDMA PUNJAB-2511- Component 2: Managing Consultant CS-QCBS / Hiring of Firm IDA / 56860 Disasters and Climate Prior Qualification Open - National 0.00 Canceled 2016-10-23 2016-11-13 2016-12-27 2017-01-26 2017-03-02 2017-08-29 for Provincial Disaster Variability Selection Management Plan and SOPs Page 3 PK-PDMA PUNJAB-3807- CS-CQS / Hiring of Firm for Component 2: Managing Consultant Organizational Capacity IDA / 56860 Disasters and Climate Post Qualification Open - National 95,065.65 Signed 2016-11-30 2016-12-15 2017-01-12 2017-01-19 2017-02-16 2017-08-15 Assessment and Capacity Variability Selection Enhancement Plan at Provincial and District Level PK-PDMA PUNJAB-3856- Component 2: Managing Consultant CS-CQS / Hiring of Firm for IDA / 56860 Disasters and Climate Post Qualification Open - National 106,989.23 Signed 2016-11-30 2016-12-21 2017-02-03 2017-03-05 2017-04-09 2017-10-06 Provincial Disaster Variability Selection Management Plan and SOPs PK-PDMA PUNJAB-116551- Consultant Component 3: Project Pending CS-CDS / GIS Manager - IDA / 56860 Post Qualification Open - National 0.00 2019-06-03 2019-06-24 2019-08-07 2019-09-06 2019-10-11 2020-04-08 Management Implementation Jhang Selection INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Actual Amount Draft Negotiated Description Component Review Type Method Contract Type Process Status Teams of Reference Identified/Selected Signed Contract Contract Completion No. Approach (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PK-PDMA PUNJAB-2478- Component 2: Managing Individual CS-INDV / Financial IDA / 56860 Disasters and Climate Prior Consultant Open 27,479.61 Terminated 2016-10-10 2016-11-28 2016-12-19 2017-01-23 2017-07-22 Management Specialist Variability Selection Component 2: Managing Individual PK-PDMA PUNJAB-2481- IDA / 56860 Disasters and Climate Post Consultant Open 45,823.39 Signed 2016-10-10 2016-11-28 2016-12-19 2017-01-23 2017-07-22 CS-INDV / DRM Specialist Variability Selection PK-PDMA PUNJAB-2491- Component 2: Managing Individual CS-INDV / Communications IDA / 56860 Disasters and Climate Post Consultant Open 21,760.91 Terminated 2016-10-10 2016-11-28 2016-12-19 2017-01-23 2017-07-22 Expert Variability Selection PK-PDMA PUNJAB-2496- Component 2: Managing Individual CS-INDV / Mainstreaming IDA / 56860 Disasters and Climate Post Consultant Open 1,912.66 Signed 2016-10-10 2016-11-28 2016-12-19 2017-01-23 2017-07-22 DRR Expert Variability Selection PK-PDMA PUNJAB-2506- Component 2: Managing Individual CS-INDV / IT Experts for IDA / 56860 Disasters and Climate Post Consultant Open 189.42 Signed 2016-10-10 2016-11-28 2016-12-19 2017-01-23 2017-07-22 Districts (5 priority districts) Variability Selection and PIU x 12 PK-PDMA PUNJAB-2508- Component 2: Managing Individual CS-INDV / Emergency IDA / 56860 Disasters and Climate Post Consultant Open 21,668.47 Signed 2016-10-10 2016-11-28 2016-12-19 2017-01-23 2017-07-22 Operations Coordinator Variability Selection PK-PDMA PUNJAB-2475- Component 2: Managing Individual CS-INDV / Project Director IDA / 56860 Disasters and Climate Post Consultant Open 162,513.54 Signed 2016-10-09 2016-11-27 2016-12-18 2017-01-22 2017-07-21 for 3 years Variability Selection PK-PDMA PUNJAB-2494- CS-INDV / 1. District Component 2: Managing Individual Disaster Risk Management IDA / 56860 Disasters and Climate Post Consultant Open 51,551.32 Signed 2016-10-08 2016-11-26 2016-12-17 2017-01-21 2017-07-20 Coordinator (DDMC) , Variability Selection Sialkot PK-PDMA PUNJAB-3132- Component 2: Managing Individual CS-INDV / District Disaster IDA / 56860 Disasters and Climate Post Consultant Open 51,551.32 Signed 2016-11-14 2017-01-02 2017-01-23 2017-02-27 2017-08-26 Risk Management Variability Selection Coordinator Hafizabad PK-PDMA PUNJAB-3133- Component 2: Managing Individual CS-INDV / District Disaster IDA / 56860 Disasters and Climate Post Consultant Open 51,551.32 Signed 2016-11-14 2017-01-02 2017-01-23 2017-02-27 2017-08-26 Risk Management Variability Selection Coordinator Jhang Page 4 PK-PDMA PUNJAB-3134- Component 2: Managing Individual CS-INDV / District Disaster IDA / 56860 Disasters and Climate Post Consultant Open 51,551.32 Signed 2016-11-14 2017-01-02 2017-01-23 2017-02-27 2017-08-26 Risk Management Variability Selection Coordinator Layyah PK-PDMA PUNJAB-3135- Component 2: Managing Individual CS-INDV / District Disaster IDA / 56860 Disasters and Climate Post Consultant Open 51,551.32 Signed 2016-11-14 2017-01-02 2017-01-23 2017-02-27 2017-08-26 Risk Management Variability Selection Coordinator Muzaffargarh PK-PDMA PUNJAB-3278- Component 2: Managing Individual CS-INDV / Financial IDA / 56860 Disasters and Climate Post Consultant Open 3,454.98 Signed 2016-11-14 2017-01-02 2017-01-23 2017-02-27 2017-08-26 Consultant for Disaster Risk Variability Selection Financing initiative Component 2: Managing Individual PK-PDMA PUNJAB-2504- IDA / 56860 Disasters and Climate Prior Consultant Open 0.00 Canceled 2016-10-10 2016-11-28 2016-12-19 2017-01-23 2017-07-22 CS-INDV / Logistics Expert Variability Selection PK-PDMA PUNJAB-2480- Component 2: Managing Individual CS-INDV / Procurement IDA / 56860 Disasters and Climate Prior Consultant Open 0.00 Canceled 2016-10-10 2016-11-28 2016-12-19 2017-01-23 2017-07-22 Specialist Variability Selection Component 2: Managing Individual PK-PDMA PUNJAB-3858- IDA / 56860 Disasters and Climate Post Consultant Open 857.75 Signed 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2017-09-11 CS-INDV / Logistics Expert Variability Selection PK-PDMA PUNJAB-3861- Component 2: Managing Individual CS-INDV / Procurement IDA / 56860 Disasters and Climate Post Consultant Open 27,473.05 Terminated 2016-11-30 2017-01-18 2017-02-08 2017-03-15 2017-09-11 Specialist Variability Selection PK-PDMA PUNJAB-5988- Component 2: Managing Individual CS-INDV / Financial IDA / 56860 Disasters and Climate Prior Consultant Open 27,363.43 Signed 2017-01-30 2017-02-02 2017-02-03 2017-02-05 2017-08-04 Management Specialist Variability Selection PK-PDMA PUNJAB-6384- Component 2: Managing Individual CS-INDV / Communications IDA / 56860 Disasters and Climate Post Consultant Open 36,000.00 Signed 2017-02-07 2017-02-18 2017-02-20 2017-02-22 2017-08-21 Expert Variability Selection PK-PDMA PUNJAB-12871- CS-INDV / District Disaster Component 2: Managing Individual Management Coordinator IDA / 56860 Disasters and Climate Post Consultant Open 16,251.35 Signed 2017-04-14 2017-06-02 2017-06-23 2017-07-28 2018-01-24 Multan Variability Selection (Detail TORs in comments) PK-PDMA PUNJAB-12858- CS-INDV / District Disaster Component 2: Managing Individual Management Coordinator IDA / 56860 Disasters and Climate Post Consultant Open 16,251.35 Signed 2017-04-14 2017-06-02 2017-06-23 2017-07-28 2018-01-24 Rajanpur Variability Selection (Detail TORs in comments) PK-PDMA PUNJAB-12861- CS-INDV / District Disaster Component 2: Managing Individual Management Coordinator IDA / 56860 Disasters and Climate Post Consultant Open 16,251.35 Signed 2017-04-14 2017-06-02 2017-06-23 2017-07-28 2018-01-24 Rahim Yar Khan Variability Selection (Detail TORs in comments) PK-PDMA PUNJAB-12864- CS-INDV / District Disaster Component 2: Managing Individual Management Coordinator IDA / 56860 Disasters and Climate Post Consultant Open 16,251.35 Signed 2017-04-14 2017-06-02 2017-06-23 2017-07-28 2018-01-24 Dera Ghazi Khan Variability Selection (Detail TORs in comments) PK-PDMA PUNJAB-12868- CS-INDV / District Disaster Component 2: Managing Individual Management Coordinator IDA / 56860 Disasters and Climate Post Consultant Open 16,251.35 Signed 2017-04-14 2017-06-02 2017-06-23 2017-07-28 2018-01-24 Mianwali Variability Selection (Detail TORs in comments) Page 5 PK-PDMA PUNJAB-12870- CS-INDV / District Disaster Component 2: Managing Individual Management Coordinator IDA / 56860 Disasters and Climate Post Consultant Open 16,251.35 Signed 2017-04-14 2017-06-02 2017-06-23 2017-07-28 2018-01-24 Khushab Variability Selection (Detail TORs in comments) PK-PDMA PUNJAB-12866- CS-INDV / District Disaster Component 2: Managing Individual Management Coordinator IDA / 56860 Disasters and Climate Post Consultant Open 16,251.35 Signed 2017-04-14 2017-06-02 2017-06-23 2017-07-28 2018-01-24 Bhakkar Variability Selection (Detail TORs in comments) PK-PDMA PUNJAB-26387- CS-INDV / International Component 2: Managing Individual Consultant on Disaster Risk IDA / 56860 Disasters and Climate Post Consultant Open 40,500.00 Signed 2017-08-28 2017-09-04 2017-09-05 2017-09-07 2017-11-06 Financing Strategy Variability Selection Development PK-PDMA PUNJAB-27894- Component 2: Managing Individual CS-INDV / Climate Change IDA / 56860 Disasters and Climate Post Consultant Open 18,935.29 Signed 2017-09-08 2017-09-14 2017-09-16 2017-09-20 2018-03-19 Expert Variability Selection PK-PDMA PUNJAB-36023- Component 2: Managing Individual CS-INDV / Procurement IDA / 56860 Disasters and Climate Post Consultant Open 31,962.45 Signed 2017-11-08 2017-11-13 2017-11-15 2017-12-07 2018-12-02 Specialist Variability Selection PK-PDMA PUNJAB-47701- CS-INDV / District Disaster Management Coordinator Individual Component 3: Project Mandi Bahauddin, Individual IDA / 56860 Post Consultant Open 956.33 Signed 2018-02-06 2018-02-24 2018-03-17 2018-04-21 2019-12-31 Management consultant for supporting Selection DDMA and PDMA's activities at District level PK-PDMA PUNJAB-47710- CS-INDV / District Disaster Management Coordinator Individual Component 3: Project Chiniot, Individual IDA / 56860 Post Consultant Open 17.22 Signed 2018-02-07 2018-03-28 2018-04-18 2018-05-23 2019-12-31 Management consultant for supporting Selection DDMA and PDMA's activities at District level PK-PDMA PUNJAB-47740- CS-INDV / District Disaster Management Coordinator Individual Component 3: Project Jhelum, Individual IDA / 56860 Post Consultant Open 956.33 Signed 2018-02-07 2018-03-28 2018-04-18 2018-05-23 2019-12-31 Management consultant for supporting Selection DDMA and PDMA's activities at District level PK-PDMA PUNJAB-47844- CS-INDV / District Disaster Management Coordinator Individual Component 3: Project Pending Sargodha, assist DDMA and IDA / 56860 Post Consultant Open 0.00 2018-02-07 2018-03-28 2018-04-18 2018-05-23 2019-12-31 Management Implementation PDMA in accomplishment Selection Disaster Management related activities PK-PDMA PUNJAB-47845- CS-INDV / District Disaster Management Coordinator Individual Component 3: Project Pending Gujrat, assist DDMA and IDA / 56860 Post Consultant Open 0.00 2018-02-07 2018-03-28 2018-04-18 2018-05-23 2019-12-31 Management Implementation PDMA in accomplishment Selection Disaster Management related activities Page 6 PK-PDMA PUNJAB-47846- CS-INDV / District Disaster Management Coordinator Individual Component 3: Project Pending Narowal, assist DDMA and IDA / 56860 Post Consultant Open 0.00 2018-02-07 2018-03-28 2018-04-18 2018-05-23 2019-12-31 Management Implementation PDMA in accomplishment Selection Disaster Management related activities PK-PDMA PUNJAB-47847- CS-INDV / District Disaster Management Coordinator Individual Component 3: Project Pending Narowal, assist DDMA and IDA / 56860 Post Consultant Open 0.00 2018-02-07 2018-03-28 2018-04-18 2018-05-23 2018-11-19 Management Implementation PDMA in accomplishment Selection Disaster Management related activities PK-PDMA PUNJAB-116526- Individual Component 3: Project Pending CS-CDS / Database IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 Management Implementation Administrator Selection Individual PK-PDMA PUNJAB-116527- Component 3: Project Pending IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 CS-CDS / Graphic Designer Management Implementation Selection Individual PK-PDMA PUNJAB-116528- Component 3: Project Pending IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 CS-CDS / GIS Developer Management Implementation Selection Individual PK-PDMA PUNJAB-116529- Component 3: Project Pending IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 CS-CDS / Data Analyst-I Management Implementation Selection Individual PK-PDMA PUNJAB-116530- Component 3: Project Pending IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 CS-CDS / Data Analyst-II Management Implementation Selection Individual PK-PDMA PUNJAB-116531- Component 3: Project Pending IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 CS-CDS / IT Manager Management Implementation Selection Individual PK-PDMA PUNJAB-116533- Component 3: Project Pending IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 CS-CDS / Internal Auditor Management Implementation Selection Individual PK-PDMA PUNJAB-116535- Component 3: Project Pending IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 CS-CDS / IT Assistant Management Implementation Selection PK-PDMA PUNJAB-116538- Individual Component 3: Project Pending CS-CDS / GIS Manager - IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 Management Implementation Hafizabad Selection PK-PDMA PUNJAB-116539- Individual Component 3: Project Pending CS-CDS / GIS Manager - IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 Management Implementation Khushab Selection PK-PDMA PUNJAB-116540- Individual Component 3: Project Pending CS-CDS / GIS Manager - IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 Management Implementation Layyah Selection PK-PDMA PUNJAB-116541- Individual Component 3: Project Pending CS-CDS / GIS Manager - IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 Management Implementation Muzaffargarh Selection PK-PDMA PUNJAB-116542- Individual Component 3: Project Pending CS-CDS / GIS Manager - IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 Management Implementation DG Khan Selection Page 7 PK-PDMA PUNJAB-116543- Individual Component 3: Project Pending CS-CDS / GIS Manager - IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 Management Implementation Narowal Selection PK-PDMA PUNJAB-116544- Individual Component 3: Project Pending CS-CDS / GIS Manager - IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 Management Implementation Kasur Selection PK-PDMA PUNJAB-116545- Individual Component 3: Project Pending CS-CDS / GIS Manager - IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 Management Implementation MB Din Selection PK-PDMA PUNJAB-116546- Individual Component 3: Project Pending CS-CDS / GIS Manager - IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 Management Implementation Chiniot Selection PK-PDMA PUNJAB-116547- Individual Component 3: Project Pending CS-CDS / GIS Manager - IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 Management Implementation Gujranwala Selection PK-PDMA PUNJAB-116548- Individual Component 3: Project Pending CS-CDS / GIS Manager - IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 Management Implementation Jhelum Selection PK-PDMA PUNJAB-116549- Individual Component 3: Project Pending CS-CDS / GIS Manager - IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 Management Implementation Mianwali Selection PK-PDMA PUNJAB-116550- Individual Component 3: Project Pending CS-CDS / GIS Manager - IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 Management Implementation Multan Selection PK-PDMA PUNJAB-116552- Individual Component 3: Project Pending CS-CDS / GIS Manager - IDA / 56860 Post Consultant Open 0.00 2019-06-03 2019-07-22 2019-08-12 2019-09-16 2020-03-14 Management Implementation Bhakkar Selection Component 2: Managing Individual PK-PDMA PUNJAB-128524- Pending IDA / 56860 Disasters and Climate Post Consultant Open 0.00 2019-09-12 2019-10-31 2019-11-21 2019-12-26 2020-06-23 CS-INDV / IT assistant Implementation Variability Selection PK-PDMA PUNJAB-128518- Component 2: Managing Individual Pending CS-INDV / District Disaster IDA / 56860 Disasters and Climate Post Consultant Open 0.00 2019-09-11 2019-10-30 2019-11-20 2019-12-25 2020-06-22 Implementation Management Coordinator Variability Selection PK-PDMA PUNJAB-128458- Component 2: Managing Individual Pending CS-INDV / Disaster Risk IDA / 56860 Disasters and Climate Post Consultant Open 0.00 2019-09-11 2019-10-30 2019-11-20 2019-12-25 2020-06-22 Implementation Management Specialist Variability Selection PK-PDMA PUNJAB-128461- Component 2: Managing Individual Pending CS-INDV / Monitoring and IDA / 56860 Disasters and Climate Post Consultant Open 0.00 2019-09-09 2019-10-28 2019-11-18 2019-12-23 2020-06-20 Implementation Evaluation Specialist Variability Selection PK-PDMA PUNJAB-128451- Component 2: Managing Individual Pending CS-INDV / Disaster Risk IDA / 56860 Disasters and Climate Post Consultant Open 0.00 2019-09-09 2019-10-28 2019-11-18 2019-12-23 2020-06-20 Implementation Reduction Specialist Variability Selection PK-PDMA PUNJAB-128520- Component 2: Managing Individual Pending CS-INDV / Communication IDA / 56860 Disasters and Climate Post Consultant Open 0.00 2019-09-12 2019-10-31 2019-11-21 2019-12-26 2020-06-23 Implementation Expert Variability Selection Component 2: Managing Individual PK-PDMA PUNJAB-128434- Pending IDA / 56860 Disasters and Climate Post Consultant Open 0.00 2019-09-02 2019-10-21 2019-11-11 2019-12-16 2020-06-13 CS-INDV / Project Director Implementation Variability Selection Page 8 PK-PDMA PUNJAB-128521- Component 2: Managing Individual Pending CS-INDV / Procurement IDA / 56860 Disasters and Climate Post Consultant Open 0.00 2019-09-11 2019-10-30 2019-11-20 2019-12-25 2020-06-22 Implementation Specialist Variability Selection PK-PDMA PUNJAB-135599- Component 2: Managing Individual CS-INDV / Hiring of DRR Pending IDA / 56860 Disasters and Climate Post Consultant Open 0.00 2019-09-25 2019-11-13 2019-12-04 2020-01-08 2020-07-06 expert for 8 weeks - short Implementation Variability Selection term consultancy PK-PDMA PUNJAB-2488- Component 2: Managing Individual CS-INDV / Monitoring and IDA / 56860 Disasters and Climate Post Consultant Open 0.00 Canceled 2016-10-10 2016-11-28 2016-12-19 2017-01-23 2017-07-22 Evaluation Specialist Variability Selection PK-PDMA PUNJAB-2510- Component 2: Managing Individual CS-INDV / Public Finance IDA / 56860 Disasters and Climate Post Consultant Open 0.00 Canceled 2016-10-10 2016-11-28 2016-12-19 2017-01-23 2017-07-22 Specialist Variability Selection PK-PDMA PUNJAB-3277- Component 2: Managing Individual CS-INDV / Insurance Policy IDA / 56860 Disasters and Climate Post Consultant Open 0.00 Canceled 2016-11-13 2017-01-01 2017-01-22 2017-02-26 2017-08-25 expert for Disaster Risk Variability Selection Financing initiative Page 9