90740 Procurement Plan September 24, 2013 I. General 1. Project information: Country: The People’s Republic of China Project Name: GEF City Cluster Eco-Transport Project (P121263) GEF Implementing Agency: World Bank Project Executive Agency: Ministry of Transport, P. R. China 2. Bank’s approval Date of the procurement Plan [Original: April 1, 2011;] 3. Date of General Procurement Notice: June 26, 2012 4. Period covered by this procurement plan: April, 2011 to June, 2015 II. Procurement Plan and Budget for GEF City Cluster Eco-transport Project Review Expected Selection by Bank Proposals Ref. No. Description of Assignment Method (Prior / Submission Comments Post) Date Provision Integrated transport ET/CP1 development strategy planning QCBS Prior Mar. 2014 and policy study Developing technical guidelines ET/CP2 for city cluster integrated QCBS Prior Mar. 2014 transport planning and design Monitoring and evaluation of the achievements of energy saving ET/CP3 and emission reduction of pilot QBS Prior Jan. 2014 project-integrated multi-modal passenger transport terminals Optimization of transport integration planning and ET/CP4 implementation plan in CZT QBS Prior Jan. 2014 City Cluster (including Strategic Environmental Assessment) Design review of integrated ET/CP5 multi-modal transport terminals QCBS Prior Jan. 2014 in CZT City Cluster Project management ET/PM1 SSS Prior Done specialist/PMO director ET/PM2 Transport Planning specialist IC Post Done Integrated transport policy ET/PM3 IC Post Done specialist 1 Review Expected Selection by Bank Proposals Ref. No. Description of Assignment Method (Prior / Submission Comments Post) Date ET/PM4 Finance specialist IC Post Done ET/PM5 Procurement specialist IC Post Done External Environmental ET/PM6 IC Post Done Monitoring Consultant Resettlement Monitoring ET/PM7 IC Post Done Consultant ET/PM8 Finance support IC Post Done ET/PM9 Specialist support IC Post Done ET/WEB Project website IC Post Done Training Specialist (Passenger ET/CS1 IC Post Jul. 2014 demand model dissemination) ET/CS2 Technical Support Specialist IC Post Done International Urban Integrated ET/CS3 IC Post Jul. 2013 Transport Planning Specialist ET/CS4 Intelligent Transport Specialist IC Post Jul. 2013 Integrated Passenger Hub ET/CS5 IC Post Jul. 2013 Specialist Project M&E ET/CS6 Project interim report and IC Post Jun. 2014 evaluation Project M&E ET/CS7 IC Post Jan. 2015 Project completion report Project M&E ET/CS8 IC Post Jun. 2015 Post project evaluation report Prior for ET/OE Office Equipment Shopping first Done contract ET/CS1- International Consultant IC Post Done PPG PPG (passenger terminal design) ET/CS2- Domestic Consultant (Strategy IC Prior Done PPG PPG and Planning) Consultant on Integrated ET/CS3- Transport Policy and Project IC Post Done PPG PPG Coordination ET/CS4- Domestic Consultant (Passenger IC Post Done PPG PPG Transport Terminals) 2 ET/CS5- Domestic Consultant IC Post Done PPG PPG (Environmental Assessment ) ET/CS6- Domestic Consultant IC Post Done PPG PPG (Involuntary Resettlement) ET/CSS- Consulting Specialist Support IC Post Done PPG PPG ET/OS- Office Equipment Shopping Post Done PPG PPG 3