The World Bank Implementation Status & Results Report Alat and Karakul Water Supply Project (P118197) Alat and Karakul Water Supply Project (P118197) EUROPE AND CENTRAL ASIA | Uzbekistan | Water Global Practice | IBRD/IDA | Investment Project Financing | FY 2013 | Seq No: 14 | ARCHIVED on 25-Jun-2019 | ISR37599 | Implementing Agencies: Republic of Uzbekistan, BUKHARA REGIONAL PRODUCTION ENTERPRISE SUVOKOVA Key Dates Key Project Dates Bank Approval Date: 13-Dec-2012 Effectiveness Date: 13-Feb-2014 Planned Mid Term Review Date: 15-Jun-2015 Actual Mid-Term Review Date: 04-Dec-2014 Original Closing Date: 31-Dec-2017 Revised Closing Date: 30-Jun-2020 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) The project development objective (PDO) is to improve the coverage, quality and efficiency of public water supply service in the two districts of Alat and Karakul in the Bukhara region. The objective will be achieved through the rehabilitation and expansion of water production, transmission and distribution infrastructure in urban and rural areas. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component A: Improvement of Water Supply Infrastructure (estimated at US$101.47 million of which IDA finances 64.70%)::(Cost $101.47 M) Component B: Institutional Strengthening and Capacity Building (estimated cost US$2.07 million, of which IDA finances 100%).:(Cost $2.07 M) Component C: Studies for Future Investments (estimated cost US$0.35 million of which IDA finances 100%).:(Cost $0.35 M) Component D: Project Management (estimated cost US$2.18 million of which IDA finances 100%):(Cost $2.18 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Satisfactory Moderately Satisfactory Overall Implementation Progress (IP) Moderately Unsatisfactory Moderately Unsatisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions 6/26/2019 Page 1 of 8 The World Bank Implementation Status & Results Report Alat and Karakul Water Supply Project (P118197) Progress towards achievement of the Project Development Objectives (PDO) remains Moderately Satisfactory. Since the last ISR, the final civil works contract was awarded and is now in progress. The IDA financing is now fully committed with total disbursements reaching almost US$ 40 million (or 54 percent of total IDA credits), including around US$6 million over the last six months. The current progress of civil works is estimated at around 55 percent. Out of nine signed works contracts, three are completed, and four contracts are substantially progressed. However, two packages are facing serious challenges due largely to the poor performance of the contractors: (i) AK/W/01 for rehabilitation of water treatment plant Dvoinik, and (ii) AK/W/05 for construction of primary and secondary trunk mains, distribution network in western part of Alat district. Institutional strengthening activities under Component B, have progressed modestly over the reporting period, but are largely expected to be completed prior to closure. The Bank’s recent mission noted some progress in addressing several issues, including non-compliance with safeguards and financial management; but again, emphasized the need to strengthen implementation capacity, including the form, function and resources of the Project Coordination Unit. Recommendations were provided to help facilitate a more active and structured engagement covering the full range of activities and accelerate implementation progress and results. Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance -- Moderate Moderate Macroeconomic -- Low Low Sector Strategies and Policies -- Moderate Moderate Technical Design of Project or Program -- Moderate Moderate Institutional Capacity for Implementation and Sustainability -- Substantial Substantial Fiduciary -- Substantial Substantial Environment and Social -- Moderate Moderate Stakeholders -- Low Low Other -- -- -- Overall -- Moderate Moderate Results PDO Indicators by Objectives / Outcomes Improved coverage of public water supply service in the districts of Alat and Karakul IN00715812 ►Direct project beneficiaries (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 40,456.00 59,469.00 59,469.00 232,000.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 6/26/2019 Page 2 of 8 The World Bank Implementation Status & Results Report Alat and Karakul Water Supply Project (P118197) No access to improved water supply until commissioning of AKWSP project. The actual figure is the Comments: updated baseline as of 2014 after effectiveness IN00715815 Female beneficiaries (Percentage, Custom Supplement) Baseline Actual (Previous) Actual (Current) End Target Value 50.68 52.00 52.00 50.70 Improved quality of public water supply service in the districts of Alat and Karakul IN00715813 ►Percentage of regulatory water samples meeting potable quality standards (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 53.00 55.00 55.00 98.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 Indicator will improve after completion and commissioning of Dvoinik WTP Comments: IN00715816 Percentage of regulatory water samples meeting potable quality standards in Alat District (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 53.00 53.00 53.00 98.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 IN00715818 Percentage of regulatory water samples meeting potable quality standards for Karakul District (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 57.00 57.00 57.00 98.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 Improved efficiency of public water supply service in the districts of Alat and Karakul IN00715814 ►Bill collection ratio (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 46.00 100.00 100.00 80.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 The transfer of collection responsibilities from the Suvokova to the Enforcement Bureau under the Office of Prosecutor General following Presidential Decree of November 16, 2017 resulted in the increase of the Comments: bill collection ratio up to 100%. IN00715817 Bill Collection Ratio - Alat (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target 6/26/2019 Page 3 of 8 The World Bank Implementation Status & Results Report Alat and Karakul Water Supply Project (P118197) Value 46.00 100.00 100.00 80.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 IN00715819 Bill Collection Ratio - Karakul (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 58.00 100.00 100.00 85.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 IN00715820 ►Reliability of water supply service (Hours, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 4.00 6.00 6.00 20.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 Water continues to be supplied intermittently (6 hours in Alat and 4 hours in Karakul) as major civil works Comments: have not completed yet. Intermediate Results Indicators by Components Component A: Improvement of Water Supply Infrastructure IN00715821 ►New piped household water connections that are resulting from the project intervention (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 7,235.00 12,500.00 35,400.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 Household connections under contracts AK/W/06 and AK/W/07 Comments: IN00715823 ►Piped household water connections that are benefiting from rehabilitation works undertaken by the project (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 7,400.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 Connections will be carried out under contract AK/W/04, which is 49% complete Comments: IN00715825 ►Number of connections with operating water meters (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 7,235.00 12,500.00 42,900.00 6/26/2019 Page 4 of 8 The World Bank Implementation Status & Results Report Alat and Karakul Water Supply Project (P118197) Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 Meters were installed in 7,235 connected households. Comments: IN00715827 ►Number of breakage per km of water transmission mains (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1.00 0.13 0.13 0.20 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 IN00715829 ►Number of breakage per km of water distribution networks (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1.20 0.42 0.42 0.40 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 Number of breakages decreased considerably. Comments: Component B: Institutional Strengthening and Capacity Building IN00715822 ►BVK Cash Working Ratio (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 1.57 0.89 0.47 0.90 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 0.23 for Alat; and 0.47 for Karakul. Data for 6 months of CY2019 Comments: IN00715824 BVK Cash Working Ratio - Alat (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 0.90 0.47 0.23 0.90 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 IN00715826 BVK Cash Working Ratio - Karakul (Number, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 1.18 0.89 0.47 0.90 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 IN00715828 ►Percent of households for whom water is a priority problem (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 85.00 65.00 65.00 20.00 6/26/2019 Page 5 of 8 The World Bank Implementation Status & Results Report Alat and Karakul Water Supply Project (P118197) Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 IN00715830 Percent of households for whom water is a priority problem - Alat (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 75.00 65.00 65.00 20.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 IN00715831 Percent of households for whom water is a priority problem - Karakul (Percentage, Custom Breakdown) Baseline Actual (Previous) Actual (Current) End Target Value 85.00 65.00 65.00 20.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 IN00715832 ►Number of water utilities that the project is supporting (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1.00 1.00 1.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 IN00715833 ►Number of BVK staff recruited, and trained for Alat and Karakul water supply service needs (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 3.00 3.00 1.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 According to draft staffing plans for Alat and Karakul, the number of staff to be recruited for operation of new/reconstructed facilities is 152 (including 118 operations and support staff) in Alat district and 131 (84 Comments: operations and support staff) in Karakul district. IN00715834 ►Non revenue water (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 51.00 32.00 32.00 25.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 Alat district - 30%; Karakul district - 35%. Water losses have decreased due to the reconstruction and Comments: construction of new networks. IN00715835 ►BVK Participation in IBNET for water and sanitation utilities (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 1.00 1.00 1.00 Date 22-Jun-2012 27-Nov-2018 15-Jun-2019 30-Jun-2020 Comments: Data is to be updated in IBNET in 2019. 6/26/2019 Page 6 of 8 The World Bank Implementation Status & Results Report Alat and Karakul Water Supply Project (P118197) Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P118197 IDA-51890 Effective USD 82.00 82.00 0.00 39.69 34.29 54% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P118197 IDA-51890 Effective 13-Dec-2012 18-Jul-2013 13-Feb-2014 31-Dec-2017 30-Jun-2020 Cumulative Disbursements 6/26/2019 Page 7 of 8 The World Bank Implementation Status & Results Report Alat and Karakul Water Supply Project (P118197) Restructuring History Level 2 Approved on 23-Nov-2017 ,Level 2 Approved on 07-Nov-2018 Related Project(s) There are no related projects. 6/26/2019 Page 8 of 8