Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [This is the first procurement plan) 2. Date of General Procurement Notice: April 25, 2017 3. Period covered by this procurement plan: September 2016 to June 2017 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 1,500,000 All 2. NCB (Goods) NA 3. ICB (Works) Above US$ 7 million All 4. NCB (Works) NA 5. ICB and LIB (Non-Consultant Services) Above US$ 1,500,000 All 6 NCB (Non-Consultant Services) NA [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [CDD project implementation Manual to be issued by DRDIP PIU, MoANR for Bank approval) 4. Reference to (if any) Project Operational/Procurement Manual: DRDIP Procurement Manual to be issued by DRDIP PIU. 5. Any Other Special Procurement Arrangements: NA 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] July 9, 2010 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of NA NA NA NA the ICB (Works) Summary of 6.69 4 No Prior the ICB (Goods) Summary of 3.8 9 No Post All the NCB (Works) Summary of 14.70 14 No Post All the NCB (Goods) Summary of NA NA NA NA the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Commentes 1. Competitive Methods (Firms) Above US$ 500,000 2. Single Source (Firms) All 3. Individual Above US$ 200,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: NA 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 0.35 2 Prior number of contracts that July 9, 2010 will be let under QCBS Summary of 1.4 38 Post LCS/ IC number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Africa : Development Response to Displacement Impacts Project in the HoA PLAN General Information Country: Africa Bank’s Approval Date of the Original Procurement Plan: 2018-01-04 2019-12-28 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P152822 GPN Date: Project Name: Development Response to Displacement Impacts Project in the HoA Loan / Credit No: IDA / 58320 Executing Agency(ies): BENISHANGUL - Development Response to Displacement Impacts Project WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-DRDIP-42220-CW-RFQ / construction of three Hand Sustainable Environmental Request for Single Stage - One IDA / 58320 Post Limited 8,695.00 19,308.88 Completed 2018-02-10 2018-04-07 2018-07-06 dug well for SSI at Bambasi Management Quotations Envelope woreda ET-DRDIP-42225-CW-RFQ / Sustainable Environmental Request for Single Stage - One Construction of house hold IDA / 58320 Post Limited 15,018.00 69,735.58 Signed 2018-02-10 2018-04-07 2018-07-06 Management Quotations Envelope pond for Bambasi woreda ET-DRDIP-42251-CW-RFQ / construction of 4 hand dug Sustainable Environmental Request for Single Stage - One well for demonstration for IDA / 58320 Post Limited 11,636.00 23,468.01 Completed 2018-03-10 2018-05-05 2018-05-25 Management Quotations Envelope SSI on FTC for Homosha woreda ET-DRDIP-42260-CW-RFQ / construction of one house Sustainable Environmental Request for Single Stage - One IDA / 58320 Post Limited 15,018.00 34,867.79 Completed 2018-02-27 2018-04-24 2018-05-13 hold pond for demonstration Management Quotations Envelope for Homosha woreda ET-DRDIP-42275-CW-RFQ / construction of one Sustainable Environmental Request for Single Stage - One IDA / 58320 Post Limited 16,948.00 47,921.88 Signed 2018-03-11 2018-05-06 2018-06-05 rehabilitation of diversion Management Quotations Envelope canal for Homosha woreda ET-DRDIP-42304-CW-RFQ / Construction of one spring Sustainable Environmental Request for Single Stage - One IDA / 58320 Post Limited 7,636.00 16,784.86 Signed 2018-02-12 2018-04-09 2018-05-07 development for Mao and Management Quotations Envelope Komo special woreda ET-DRDIP-42310-CW-RFQ / construction of 5 hand dug Sustainable Environmental Request for Single Stage - One IDA / 58320 Post Limited 11,636.00 32,181.47 Completed 2018-02-25 2018-04-22 2018-05-22 well for Mao and Komo Management Quotations Envelope special woreda ET-DRDIP-42312-CW-RFQ / construction of one house Sustainable Environmental Request for Single Stage - One IDA / 58320 Post Limited 15,018.00 203,832.20 Signed 2018-02-28 2018-04-25 2018-05-20 hold pond for Mao and Management Quotations Envelope Komo special woreda ET-DRDIP-42672-CW-RFQ / Construction of 3 Biogass ( one for Bambsi,one for Mao Sustainable Environmental Request for Single Stage - One IDA / 58320 Post Limited 14,543.00 0.00 Canceled 2018-02-25 2018-04-22 2018-06-11 & Komo and one for Management Quotations Envelope Homosha woreda ) procured at Regional Level Page 1 ET-DRDIP-81406-CW-RFB / Construction of warehouses for Bambasi, Homosha ans Social and Economic Single Stage - One IDA / 58320 Post Request for Bids Open - National 264,492.00 319,908.67 Completed 2018-12-03 2018-12-08 2019-01-19 2019-02-18 2019-03-25 2019-06-23 Maokomo special weredas Services and Infrastructure Envelope (strategic investment) procured at Regional Level ET-DRDIP-81401-CW-RFB / Construction of three Spring Sustainable Environmental Request for Single Stage - One development for irrigation at IDA / 58320 Post Limited 29,562.00 0.00 Canceled 2018-11-10 2019-01-05 2019-02-19 Management Quotations Envelope two weredas procured at Regional Level ET-DRDIP-81403-CW-RFB / Construction of upgrading Sustainable Environmental Request for Single Stage - One river direction (traditional) IDA / 58320 Post Limited 6,387.00 0.00 Canceled 2018-12-09 2019-02-03 2019-03-05 Management Quotations Envelope for Homosha wereda procured at wereda Levele ET-DRDIP-81400-CW-RFB / construction of three new SSI schems and one canal ( Sustainable Environmental Single Stage - One homosha) at Bambasi , IDA / 58320 Post Request for Bids Open - National 297,699.00 0.00 Canceled 2019-01-01 2019-01-06 2019-02-17 2019-03-19 2019-04-23 2019-07-22 Management Envelope Homosha and Maokomo special weredas procured at regional level ET-DRDIP-81404-CW-RFB / Construction of warehouse Social and Economic Single Stage - One for Bambasi, Homosha ans IDA / 58320 Post Request for Bids Open - National 264,492.00 0.00 Canceled 2018-12-18 2018-12-23 2019-02-03 2019-03-05 2019-04-09 2019-07-08 Services and Infrastructure Envelope Maokomo special wereda procured at Regional Level GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ET-DRDIP-42049-GO-RFQ / Project Management, and Request for Single Stage - One procurement of Stationary IDA / 58320 Post Limited 6,385.00 226.41 Completed 2018-01-10 2018-03-07 2018-03-27 Monitoring and Evaluation Quotations Envelope items for regional unit ET-DRDIP-42062-GO-RFQ / Project Management, and Request for Single Stage - One procurement of stationary IDA / 58320 Post Limited 3,435.00 1,213.57 Completed 2018-01-15 2018-03-12 2018-04-01 Monitoring and Evaluation Quotations Envelope items for Homosha woreda ET-DRDIP-42069-GO-RFQ / procurement of stationary for Project Management, and Request for Single Stage - One IDA / 58320 Post Limited 3,185.00 293.28 Completed 2018-01-15 2018-03-12 2018-04-06 Mao and Komo special Monitoring and Evaluation Quotations Envelope woreda ET-DRDIP-42072-GO-RFQ / Project Management, and Request for Single Stage - One cleaning materials for IDA / 58320 Post Limited 786.00 54.99 Completed 2018-01-15 2018-03-12 2018-04-01 Monitoring and Evaluation Quotations Envelope Regional Units ET-DRDIP-42083-GO-RFQ / procurement of printing Project Management, and Request for Single Stage - One IDA / 58320 Post Limited 1,756.00 433.42 Completed 2018-01-25 2018-03-22 2018-04-11 materials and brochers for Monitoring and Evaluation Quotations Envelope Regional Units ET-DRDIP-42110-GO-RFQ / procurement of Sustainable Environmental Request for Single Stage - One Demonstration of improved IDA / 58320 Post Limited 15,516.00 3,002.60 Completed 2018-01-15 2018-03-12 2018-04-01 Management Quotations Envelope technologies for Bambasi worda Page 2 ET-DRDIP-42124-GO-RFQ / procurement of Sustainable Environmental Request for Single Stage - One demonistrationimproved IDA / 58320 Post Limited 16,186.00 3,014.87 Signed 2018-01-30 2018-03-27 2018-04-26 Management Quotations Envelope technologies for Homosh woredas ET-DRDIP-42126-GO-RFQ / procurement of Sustainable Environmental Request for Single Stage - One demonstration technologies IDA / 58320 Post Limited 14,216.00 3,002.60 Completed 2018-01-20 2018-03-17 2018-04-11 Management Quotations Envelope for Mao and komo special woredas ET-DRDIP-42128-GO-RFQ / Project Management, and Request for Single Stage - One procurement of vehicle spar IDA / 58320 Post Limited 7,654.00 603.39 Completed 2018-01-15 2018-03-12 2018-04-11 Monitoring and Evaluation Quotations Envelope parts for Regional Unit ET-DRDIP-42132-GO-RFQ / Project Management, and Request for Single Stage - One procurement of vehicle spar IDA / 58320 Post Limited 6,278.00 911.04 Signed 2018-01-15 2018-03-12 2018-04-01 Monitoring and Evaluation Quotations Envelope parts for bambasi woreda ET-DRDIP-42134-GO-RFQ / procurement of vehicle Project Management, and Request for Single Stage - One IDA / 58320 Post Limited 4,567.00 612.72 Completed 2018-01-29 2018-03-26 2018-04-25 sparpart for Homosha Monitoring and Evaluation Quotations Envelope woreda ET-DRDIP-42136-GO-DIR / procurement of uniform for Project Management, and Request for Single Stage - One drivers and safety shoes for IDA / 58320 Post Limited 4,365.00 745.84 Completed 2018-02-20 2018-04-17 2018-05-22 Monitoring and Evaluation Quotations Envelope CIF employees for Regional staffs only ET-DRDIP-42277-GO-RFQ / procurement of 89 motor pump for ( 13 for Homosha Sustainable Environmental Request for Single Stage - One IDA / 58320 Post Limited 97,090.00 2,829.84 Signed 2018-02-11 2018-04-08 2018-05-28 woreda ,60 for Bambasi Management Quotations Envelope woreda and 16 for Homosha ) procured at Regional level ET-DRDIP-42098-GO-RFQ / procurement of 1040 wood saving stoves ( 320 for Sustainable Environmental Request for Single Stage - One Bambasi , 330 for Homosha IDA / 58320 Post Limited 17,698.00 5,111.50 Completed 2018-01-30 2018-03-27 2018-05-01 Management Quotations Envelope and 390 for Mao and Komo special woreda procured at Regional Level ET-DRDIP-42106-GO-RFQ / procurement of 10 solar energy panel ( 3 for Sustainable Environmental Request for Single Stage - One IDA / 58320 Post Limited 25,820.00 3,995.57 Completed 2018-01-27 2018-03-24 2018-04-14 Bambasi woreda,3 for Management Quotations Envelope Homosha woreda and 4 Mao and komo special woreda ET-DRDIP-38273-GO-RFQ / Procurement of 64 file Request for Single Stage - One cabinet for Bambasi IDA / 58320 Livelihoods Program Post Limited 9,727.00 9,654.85 Completed 2018-01-25 2018-03-22 2018-04-21 Quotations Envelope ,Homosha and Maokomo wereda at Regional level ET-DRDIP-42239-GO-RFQ / procurement of 115 treadle pump(43 for Homoshaworeda Sustainable Environmental Request for Single Stage - One IDA / 58320 Post Limited 33,454.00 0.00 Canceled 2018-02-25 2018-04-22 2018-06-01 ,30 for Bambasi woreda and Management Quotations Envelope 42 for Mao Komo special woreda )at Regional Level Page 3 ET-DRDIP-42282-GO-RFQ / procurement of 3 rope and washer pump for Irrigation for demonstration, 1for Sustainable Environmental Request for Single Stage - One IDA / 58320 Post Limited 2,120.00 0.00 Canceled 2018-01-13 2018-03-10 2018-04-24 Homosha woreda ,1 for Management Quotations Envelope Bambasi woreda and 1 for Mao Komo Special woreda ) procured at Regional Level ET-DRDIP-42103-GO-RFQ / procurement of 156 solar light ( 40 for Bambasi ,51 Sustainable Environmental Request for Single Stage - One IDA / 58320 Post Limited 39,709.00 0.00 Canceled 2018-01-30 2018-03-27 2018-04-22 for Mao & komo and 65 Management Quotations Envelope for Homosha woreda ) procured at Regional Level ET-DRDIP-42290-GO-RFQ / procurement of one rope and Sustainable Environmental Request for Single Stage - One washer pump for IDA / 58320 Post Limited 545.00 0.00 Canceled 2018-02-18 2018-04-15 2018-05-15 Management Quotations Envelope demonstration for Mao and Komo special woreda ET-DRDIP-42288-GO-RFQ / procurement of 42 treadle Sustainable Environmental Request for Single Stage - One pump for demonstration for IDA / 58320 Post Limited 7,172.00 0.00 Canceled 2018-01-22 2018-03-19 2018-04-15 Management Quotations Envelope Mao and Komo special woreda ET-DRDIP-42248-GO-RFQ / procurement of one rope and Sustainable Environmental Request for Single Stage - One IDA / 58320 Post Limited 654.00 0.00 Canceled 2018-01-30 2018-03-27 2018-04-28 washer for demonstration for Management Quotations Envelope Bambasi woreda ET-DRDIP-42135-GO-RFQ / procurement of vehicle Project Management, and Request for Single Stage - One IDA / 58320 Post Limited 5,654.00 0.00 Canceled 2018-01-29 2018-03-26 2018-04-30 sparpart for Mao and komo Monitoring and Evaluation Quotations Envelope special woreda ET-DRDIP-42079-GO-RFQ / procurement of cleaning Project Management, and Request for Single Stage - One IDA / 58320 Post Limited 537.00 0.00 Canceled 2018-01-15 2018-03-12 2018-04-01 materials for Homosha Monitoring and Evaluation Quotations Envelope woreda ET-DRDIP-42022-GO-RFQ / procurement of office Regional Support for Request for Single Stage - One equipment and other office IDA / 58320 Coordination, Capacity and Post Limited 848.00 0.00 Canceled 2018-01-18 2018-03-15 2018-04-14 Quotations Envelope supplies for Homosha Knowledge woreda ET-DRDIP-42076-GO-RFQ / procurement of cleaning Project Management, and Request for Single Stage - One IDA / 58320 Post Limited 428.00 0.00 Canceled 2018-01-15 2018-03-12 2018-04-01 materials for Mao komo Monitoring and Evaluation Quotations Envelope special woreda ET-DRDIP-81458-GO-RFQ / Procurement of farm tools Request for Single Stage - One IDA / 58320 Livelihoods Program Post Limited 43,478.00 28,812.35 Completed 2018-11-20 2019-01-15 2019-03-06 for wereda FTC procured at Quotations Envelope Regional Level ET-DRDIP-81467-GO-RFQ / procurement of FTC Request for Single Stage - One IDA / 58320 Livelihoods Program Post Limited 80,036.00 17,379.75 Completed 2018-11-25 2019-01-20 2019-04-20 equipment for wereda Quotations Envelope procured at Regional Level ET-DRDIP-81469-GO-RFB / Procurement of Motor pumps Sustainable Environmental Single Stage - One IDA / 58320 Post Request for Bids Open - National 109,601.00 99,006.28 Completed 2018-12-28 2019-01-02 2019-02-13 2019-03-15 2019-04-19 2019-07-18 for irrigation for wereda Management Envelope procured at Regional Level Page 4 ET-DRDIP-81471-GO-RFQ / procurement of vehicle parts Project Management, and Request for Single Stage - One IDA / 58320 Post Limited 20,797.00 13,794.49 Completed 2018-10-15 2018-12-10 2019-01-24 for all project units at Monitoring and Evaluation Quotations Envelope regional level ET-DRDIP-81473-GO-RFQ / Procurement of safety wear Project Management, and Request for Single Stage - One and uniforms for driver and IDA / 58320 Post Limited 2,996.00 186.17 Completed 2019-02-13 2019-04-10 2019-05-25 Monitoring and Evaluation Quotations Envelope Messenger procured at regional Level ET-DRDIP-81530-GO-RFQ / Procurement of Pending demonstration equipment for Request for Single Stage - One IDA / 58320 Livelihoods Program Post Limited 13,405.00 0.00 Implementati 2019-01-19 2019-03-16 2019-04-15 farmers for Maokkomo Quotations Envelope on special were and procured at Maokomo wereda level ET-DRDIP-42019-GO-RFQ / office equipment and other Project Management, and Request for Single Stage - One IDA / 58320 Post Limited 923.00 0.00 Canceled 2018-01-15 2018-03-12 2018-04-16 office supplies Bambasi Monitoring and Evaluation Quotations Envelope woreda ET-DRDIP-42025-GO-RFQ / procurement of office Project Management, and Request for Single Stage - One equipment and other office IDA / 58320 Post Limited 912.00 0.00 Canceled 2018-01-15 2018-03-12 2018-04-16 Monitoring and Evaluation Quotations Envelope supplies for Maokomo woreda ET-DRDIP-42065-GO-RFQ / Project Management, and Request for Single Stage - One procurement of stationary for IDA / 58320 Post Limited 3,219.00 0.00 Canceled 2018-01-15 2018-03-12 2018-04-16 Monitoring and Evaluation Quotations Envelope Bambasi woreda ET-DRDIP-42074-GO-RFQ / procurement of cleaning Project Management, and Request for Single Stage - One IDA / 58320 Post Limited 526.00 0.00 Canceled 2018-01-15 2018-03-12 2018-04-01 materials for Bambaso Monitoring and Evaluation Quotations Envelope woreda ET-DRDIP-81525-GO-DIR / Procurement of improved agricultural technologies for IDA / 58320 Livelihoods Program Post Direct Selection Direct 26,688.00 919.20 Completed 2018-11-06 2018-11-11 2018-12-16 2018-12-26 Bambasi wereda procured ar wereda Level ET-DRDIP-81529-GO-DIR / Procurement of Request for Single Stage - One demonstration equipments at IDA / 58320 Livelihoods Program Post Limited 13,206.00 2,701.18 Completed 2019-01-20 2019-03-17 2019-04-16 Quotations Envelope farmers plot Bambasi wereda procured at wereda Level ET-DRDIP-81526-GO-DIR / procurement of improved seeds and fertilizers for Pending agricultural technologies IDA / 58320 Livelihoods Program Post Direct Selection Direct 26,695.00 0.00 Implementati 2018-11-06 2018-11-11 2018-12-16 2019-01-05 demonstration at Homosha on wereda and procured by wereda Level ET-DRDIP-81527-GO-DIR / procurement of improved seeds and fertilizers for agricultural technologies IDA / 58320 Livelihoods Program Post Direct Selection Direct 26,897.00 5,552.29 Completed 2018-11-06 2018-11-11 2018-12-16 2018-12-26 demonstration at Mao &komo special wereda and procured by wereda Level ET-DRDIP-83278-GO-RFQ / Procurement of local wood Sustainable Environmental Request for Single Stage - One IDA / 58320 Post Limited 4,432.00 2,742.00 Completed 2018-12-09 2019-02-03 2019-03-05 saving stoves for Bambasi Management Quotations Envelope wereda procured at Bambasi Page 5 ET-DRDIP-83279-GO-RFQ / Procurement of local wood Sustainable Environmental Request for Single Stage - One IDA / 58320 Post Limited 4,321.00 791.46 Completed 2018-12-15 2019-02-09 2019-03-11 saving toves for Homosha Management Quotations Envelope wereda procured at Homosha ET-DRDIP-83283-GO-RFQ / Procurement of local wood Under Sustainable Environmental Request for Single Stage - One saving stoves for maokomo IDA / 58320 Post Limited 3,891.00 0.00 Implementati 2018-12-24 2019-02-18 2019-03-20 Management Quotations Envelope special wereda procured at on Maokomo wereda ET-DRDIP-81453-GO-RFQ / procurement of stationary Project Management, and Request for Single Stage - One IDA / 58320 Post Limited 6,340.00 3,202.45 Completed 2018-12-05 2019-01-30 2019-03-31 and office utilities procured Monitoring and Evaluation Quotations Envelope at Regional units ET-DRDIP-81470-GO-RFB / - Procurement of 18 institutional solar panels installed with refrigerator (Hom-5 , bamb- 7 and Mao Single Stage - One & Komo 6) for animal HP. IDA / 58320 Livelihoods Program Post Request for Bids Open - National 263,265.00 202,593.17 Completed 2019-01-21 2019-01-26 2019-03-09 2019-04-08 2019-05-13 2019-09-10 Envelope - Procurment of 156 house hold level solar light (Hom- 65 , Bamb- 40 and Mao & Komo 51) for demonstration procured at region ET-DRDIP-81528-GO-DIR / procurement of Under demonstration equipment for Request for Single Stage - One IDA / 58320 Livelihoods Program Post Limited 24,887.00 0.00 Implementati 2019-01-20 2019-03-17 2019-09-13 farmers for Homosha wereda Quotations Envelope on and procured at Homosha wereda ET-DRDIP-88849-GO-RFQ / procurement of It Equipment for lower level implementing Request for Single Stage - One agencies( desktops 1, IDA / 58320 Livelihoods Program Post Limited 44,109.00 0.00 Canceled 2019-01-13 2019-03-10 2019-04-24 Quotations Envelope printers 12, Lap top 31 and GPS 8) procured at Regional Level ET-DRDIP-81451-GO-RFQ / Request for Single Stage - One procurement of one water IDA / 58320 Livelihoods Program Post Limited 438.00 0.00 Canceled 2018-10-30 2018-12-25 2019-02-23 Quotations Envelope filter for office use ET-DRDIP-88860-GO-RFQ / Procurement of furniture ( shelf's 47, bench chairs 33 Request for Single Stage - One IDA / 58320 Livelihoods Program Post Limited 20,620.00 0.00 Canceled 2019-01-13 2019-03-10 2019-04-24 and Tables 33) for FTC and Quotations Envelope kebeles) procured at Regional level ET-DRDIP-130204-GO-RFQ Regional Support for Pending Request for Single Stage - One / Procurement of It IDA / 58320 Coordination, Capacity and Post Limited 27,790.00 0.00 Implementati 2019-10-05 2019-10-25 2019-11-24 Quotations Envelope Equipments Knowledge on ET-DRDIP-130213-GO-RFQ Pending / Procurement of Laboratory Request for Single Stage - One IDA / 58320 Livelihoods Program Post Limited 34,965.00 0.00 Implementati 2019-12-15 2020-01-09 2020-02-08 equipment for plant clinic Quotations Envelope on procured at Regional Level ET-DRDIP-130224-GO-RFQ Pending / Procurement of Desil Request for Single Stage - One IDA / 58320 Livelihoods Program Post Limited 36,225.00 0.00 Implementati 2019-12-27 2020-01-21 2020-03-06 Generator for Plance clinic, Quotations Envelope on woreda and office use (03) Page 6 ET-DRDIP-130404-GO-RFQ / procurement of equipment Pending of streng=ghning nursery Request for Single Stage - One IDA / 58320 Livelihoods Program Post Limited 4,370.00 0.00 Implementati 2019-12-20 2020-01-14 2020-02-03 site ( seeds, grass , woods Quotations Envelope on ...etc) procured at Bambasi woreda ET-DRDIP-130407-GO-RFQ Pending / Procurement of equipment Request for Single Stage - One IDA / 58320 Livelihoods Program Post Limited 5,420.00 0.00 Implementati 2019-12-20 2020-01-14 2020-02-03 of strengthening nursery site Quotations Envelope on ( seeds, grass, woods ..etc) ET-DRDIP-130409-GO-RFQ / procurement of equipment Pending for strengthening Request for Single Stage - One IDA / 58320 Livelihoods Program Post Limited 4,370.00 0.00 Implementati 2019-12-20 2020-01-14 2020-02-03 horticultural nursery site Quotations Envelope on (seeds, grass, woods ...etc) procured at Homosha woreda ET-DRDIP-130424-GO-RFQ / Procurement of Industrial materials for strengthening Pending Request for Single Stage - One multipurpose cooperatives IDA / 58320 Livelihoods Program Post Limited 7,874.00 0.00 Implementati 2020-01-13 2020-02-07 2020-02-27 Quotations Envelope (cement, nail roofing iron on sheet .....etc )procured at Maokomo special woreda ET-DRDIP-130426-GO-RFQ / Procurement of Industrial materials for strengthening Pending Request for Single Stage - One multipurpose cooperatives ( IDA / 58320 Livelihoods Program Post Limited 5,874.00 0.00 Implementati 2020-01-13 2020-02-07 2020-02-27 Quotations Envelope cement, roofing iron sheet, on nail ...etc procured at Bambasi woreda ET-DRDIP-130430-GO-RFQ / Procurement of Industrial materials for strengthening Pending Request for Single Stage - One multipurpose cooperatives IDA / 58320 Livelihoods Program Post Limited 3,916.00 0.00 Implementati 2020-01-13 2020-02-07 2020-02-27 Quotations Envelope (roofing iron sheet, cement, on nail ....etc ) procured at Homosh woreda ET-DRDIP-130461-GO-RFQ / Procurement of improved Pending agricultural technologies for IDA / 58320 Livelihoods Program Post Direct Selection Direct 19,408.00 0.00 Implementati 2019-12-25 2019-12-30 2020-02-03 2020-02-23 FTC( seeds. fertilizer, animal on hybrids,behaves ....Etc) procured at Bambasi woreda ET-DRDIP-130462-GO-RFQ / Procurement of improved agricultural technologies for Pending FTC( seeds, fertilize.animal IDA / 58320 Livelihoods Program Post Direct Selection Direct 25,527.00 0.00 Implementati 2019-12-10 2019-12-15 2020-01-19 2020-02-08 hybrid, behaves ....etc) on procured at Maokom special woreda ET-DRDIP-130464-GO-RFQ / Procurement of improved agricultural technologies for Pending FTC( seeds, fertilizer, animal IDA / 58320 Livelihoods Program Post Direct Selection Direct 26,778.00 0.00 Implementati 2019-11-12 2019-11-17 2019-12-22 2020-01-06 hybrids, behaves...etc) on procured at Homosha woreda ) NON CONSULTING SERVICES Page 7 Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 8