Sample Procurement Plan (Text in italic font is meant for instruction to staff and should be deleted in the final version of the PP) (This is only a sample with the minimum content that is required to be included in the PAD. The detailed procurement plan is still mandatory for disclosure on the Bank’s website in accordance with the guidelines. The initial procurement plan will cover the first 18 months of the project and then updated annually or earlier as necessary). I. General 1. Bank’s approval Date of the procurement Plan [Original: December 2007]: Revision 15 of Updated Procurement Plan, June 2010] 2. Date of General Procurement Notice: Dec 24, 2006 3. Period covered by this procurement plan: The procurement period of project covered from year June 2010 to December 2012 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: [Thresholds for applicable procurement methods (not limited to the list below) will be determined by the Procurement Specialist /Procurement Accredited Staff based on the assessment of the implementing agency’s capacity.] Procurement Method Prior Review Threshold Comments US$ 1. ICB and LIB (Goods) Above US$ 500,000 All 2. NCB (Goods) Above US$ 100,000 First contract 3. ICB (Works) Above US$ 15 million All 4. NCB (Works) Above US$ 5 million All 5. (Non-Consultant Services) Below US$ 100,000 First contract [Add other methods if necessary] 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: [Refer to the relevant CDD project implementation document approved by the Bank or delete if not applicable] 4. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project XYZ 04/01/2010 issued by July 9, 2010 5. Any Other Special Procurement Arrangements: [including advance procurement and retroactive financing, if applicable] 5 ICB works packages will be financed under retroactive financing 6. Summary of the Procurement Packages planned during the first 18 months after project effectiveness ( including those that are subject to retroactive financing and advanced procurement) [List the Packages which require Bank’s prior review first and then the other packages] 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Summary of 82 5 No Prior the ICB (Works) Summary of 43.77 15 No Prior the ICB (Goods) Summary of 64.53 18 No Post 1st the NCB contract (Works) for Prior Review Summary of 1.86 4 No Post 1st the NCB contract (Goods) for Prior Review Summary of 0.45 1 No Prior the ICB (Non- Consultant Services) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Competitive Methods (Firms) Above US$ 100,000 2. Single Source (Firms) All 3. Individual Above US$ 50,000 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise July 9, 2010 entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: [including advance procurement and retroactive financing, if applicable or delete if not applicable] 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 5 6 Ref. No. Description of Estimated Packages Review Comments Assignment Cost by Bank US$ (Prior / million Post) Summary of 4.17 7 Prior number of contracts that will be let under QCBS Summary of 0.83 1 Prior CQS number of contracts that will be let under other methods July 9, 2010 PROCUREMENT Bangladesh : BD Private Sector Development PLAN General Information Country: Bangladesh Bank’s Approval Date of the Original Procurement Plan: 2016-08-11 2019-04-25 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P120843 GPN Date: Project Name: BD Private Sector Development Loan / Credit No: IDA / 48660, IDA / 57690 Executing Agency(ies): Bangladesh Hi-Tech Park Authority WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BHTP-WD-1007 / Internal Single Stage - One Road including Land IDA / 57690 Post Request for Bids Open - National 205,020.95 Signed 2016-09-25 2016-09-30 2016-11-11 2016-12-11 2017-01-15 2017-07-14 Envelope Development in Rajshahi BHTP-WD-1002A / Under Single Stage - One Installation of street Light IDA / 57690 Post Request for Bids Open - National 55,282.19 Implementati 2016-09-18 2016-09-20 2016-10-20 2016-10-27 2016-11-06 2017-04-15 Envelope in Rajshahi Hi-Tech Park on BHTP-WD-1010A / Construction of Boundary Single Stage - One IDA / 57690 Post Request for Bids Open - National 230,489.53 Signed 2016-10-02 2016-10-07 2016-11-07 2016-12-07 2017-01-11 2018-01-06 wall and gate at Rajshahi Envelope Hi-Tech Park BHTP-WD-1003 / Construction of Incubation Single Stage - One and training center and IDA / 57690 Post Request for Bids Open - National 2,120,294.55 Signed 2016-11-01 2016-11-06 2016-12-18 2017-01-17 2017-02-21 2018-08-25 Envelope others facilities at Rajshahi Hi-Tech Park. BHTP-WD-1013A / Construction of Water Single Stage - One IDA / 57690 Post Request for Bids Open - National 0.00 Canceled 2016-12-04 2016-12-09 2017-01-08 2017-02-07 2017-03-14 2017-06-12 Supply system at Rajshahi Envelope Hi-Tech Park. BHTP-WD-1001A / Solar Single Stage - One Panel at Rajshahi Hi-Tech IDA / 57690 Post Request for Bids Open - National 0.00 Canceled 2016-11-30 2016-12-05 2017-01-16 2017-02-15 2017-03-22 2017-09-18 Envelope Park BHTP-WD-1004 / Construction of Incubation Single Stage - One and Training Centre at IDA / 57690 Post Request for Bids Open - National 2,097,024.92 Signed 2017-05-02 2017-05-07 2017-06-06 2017-07-06 2017-08-10 2019-02-01 Envelope Khulna Hi-Tech Park (KUET) BHTP-WD-1002B / Installation of Street Light Single Stage - One IDA / 57690 Post Request for Bids Open - National 61,216.70 Signed 2017-02-15 2017-02-20 2017-03-24 2017-04-23 2017-05-28 2017-11-24 at Khulna Hi-Tech Park Envelope (KUET) BHTP-WD-1009 / Construction of Internal Single Stage - One Road and Land Development IDA / 57690 Post Request for Bids Open - National 203,627.23 Signed 2017-02-06 2017-02-11 2017-03-15 2017-04-14 2017-05-19 2018-02-13 Envelope at Khulna Hi-Tech Park (KUET) BHTP-WD-1010B / Construction of Boundary Single Stage - One IDA / 57690 Post Request for Bids Open - National 131,681.01 Signed 2017-01-12 2017-01-17 2017-02-07 2017-03-09 2017-04-13 2017-12-09 wall and Gate at Khulna Hi- Envelope Tech Park (KUET) Page 1 BHTP-WD-1008 / Pending Construction of Internal Single Stage - One IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2018-07-26 2018-07-29 2018-08-13 2018-09-12 2018-10-24 2019-02-21 Road at Khulna Software Envelope on Technology Park (KUET) BHTP-WD-1006 / Vertical Extension of Customs Pending Single Stage - One House/Service Building in IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2018-07-15 2018-07-19 2018-08-19 2018-09-19 2018-10-31 2019-08-27 Envelope Bangabondu Hi-Tech City, on Kaliakoir, Gazipur BHTP-WD-1011 / Establishment of Water Pending Request for Single Stage - One Supply line at Khulna IDA / 57690 Post Open - National 0.00 Implementati 2018-09-25 2018-10-16 2018-12-15 Quotations Envelope Software Technology Park in on KUET BHTP-WD-1012 / Establishment of interior Pending Single Stage - One fittings and decoration of IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2019-02-03 2019-02-10 2019-03-10 2019-03-30 2019-05-04 2019-12-05 Envelope Incubation and Training on Center, Rajshahi BHTP-WD-1013 / Establishment of interior Pending Single Stage - One fittings and decoration of IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2019-02-06 2019-02-13 2019-03-14 2019-04-04 2019-05-10 2019-12-11 Envelope Incubation and Training on Center, Khulna BHTP-WD-1014 / Single Stage - One Construction of Internal IDA / 57690 Post Request for Bids Open - National 108,672.17 Signed 2019-02-11 2019-02-18 2019-03-17 2019-04-06 2019-05-13 2019-11-09 Envelope Road & Walkway in RHTP BHTP-WD-1015 / Construction of Internal Under Single Stage - One Road and Walk-way in IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2019-02-13 2019-02-16 2019-03-18 2019-04-07 2019-05-15 2019-11-11 Envelope Khulna Software Technology on Park (KUET) BHTP-WD-1017 / Establishment of Electric Connectivity from High Pending Single Stage - One Tension Line to Incubation IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2019-03-25 2019-03-30 2019-04-26 2019-05-26 2019-06-30 2019-11-27 Envelope & Training Center for on Khulna Software Technology Park (KUET) BHTP-WD-1005 / Vertical Extension of Singapore- Pending Bangkok Market in Single Stage - One IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2018-07-05 2018-07-10 2018-08-08 2018-09-06 2018-10-18 2019-11-22 Chattogram (Establishment Envelope on of Chattogram Software Technology Park) GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 2 BHTPA-P1 / Training on Under 1. ASP.NET core web Single Stage - One IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2018-06-30 application Envelope on 2. Zend Framework BHTPA-P2 / Training on 1. Code Ignator, 2. Laravel, 3. Advanced Data Structures in Under Single Stage - One Java & Web Component IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2018-08-29 Envelope Development, 4. Developing on ASP. NET MVC 5 Web Application BHTPA-P3 / Training on 1. Android, 2. Programming Mobile Applications for Under Single Stage - One Android & device security, 3. IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2018-08-29 Envelope Advanced iOS Bootcamp & on iOS Application Development, 4. IOS BHTPA-P4 / Training on 1. Under Single Stage - One CCNA, 2. CCNP, 3. CCNA IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2019-01-01 Envelope Security on BHTPA-P5 / Training on 1. Under Single Stage - One Linux, 2. Windows Server IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2019-01-01 Envelope 2016 on BHTPA-P6 / Training on 1. Under Professional Digital Content Single Stage - One IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2019-01-01 Management, 2. E-Commerce Envelope on Professional Training BHTPA-P7 / Training on Under Single Stage - One Finance & Accounting IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2019-01-01 Envelope Outsourcing on Under BHTPA-P8 / Training on Single Stage - One IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2019-01-01 Medical Scribing Envelope on BHTPA-P9 / Training on 1. Software Quality Assurance & Testing, 2. Software Under Single Stage - One Quality Assurance- IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2018-06-30 Envelope Implementing Consistent on Quality, 3. Information Security & Auditing BHTPA-P10 / Training on 1. Internet of Things (IoT), Pending 2. Data science modeling, Single Stage - One IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2018-06-30 integration & processing, 3. Envelope on Introduction to Big Data Using HD Insight BHTPA-P11 / Training on 1. Oracle Certified Professional (OCP) Java Pending Single Stage - One SE8, 2. Oracle Business IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2018-07-30 Envelope Intelligence, 3. Oracle on Database Administrator 11g, 4. Oracle Developer 11g BHTPA-P12 / Training on 1. Server & Cloud Operating Pending System and Virtualization, 2. Single Stage - One IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2018-05-01 Data Center Envelope on Management/Design and Implementation Page 3 BHTPA-P13 / Training on 1. Remote IT Infrastructure Operation & Maintenance Pending Management, 2. Optical Single Stage - One IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2018-05-01 Network /Transmission and Envelope on Network Infrastructure Implementation and Management BHTPA-P14 / Training on 1. System Security, 2. UC Pending Single Stage - One (IP Telephone, Video IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2018-05-01 Envelope Conference and IP on Surveillance BHTPA-P15 / Training on Pending 1. Six Sigma Black Belt, 2. Single Stage - One IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2018-06-30 Six Sigma Green Belt, 3. Envelope on Project Management Pending BHTPA-P16 / Training on Single Stage - One IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2018-06-30 SAP User training Envelope on Pending BHTPA-P17 / Training on Single Stage - One IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2018-08-29 Ardunio Envelope on BHTPA-P18 / Training on Pending Single Stage - One 3D Animation & Film IDA / 57690 Post Request for Bids Open - National 0.00 Implementati 2017-09-11 2017-09-16 2017-10-28 2017-11-27 2018-01-01 2019-01-01 Envelope Making on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual PSDSP-BHTPA-34-SBCC-CF- Quality And Cost- Open - BHTP-S1 / Transaction IDA / 48660 Prior 1,876,862.54 Signed Based Selection International Advisory Services S7 / Process Development Quality And Cost- Open - IDA / 48660 Prior 379,242.87 Signed for Firms Based Selection International BHTPA- P1 A / Training course on (Workforce Consultant Pending training) ASP NET core web IDA / 57690 Post Qualification Open - National 0.00 2018-08-16 2018-09-01 2018-09-15 2018-09-22 2018-10-06 2019-04-04 Implementation application (Pack: BHTPA-1 Selection A) BHTPA-P1 B / Training Consultant Pending course on (Workforce IDA / 57690 Post Qualification Open - National 0.00 2018-08-16 2018-09-01 2018-09-15 2018-09-22 2018-10-06 2019-04-04 Implementation training) Zend Framework Selection BHTPA-P2 A / Training Consultant Pending course on (Workforce IDA / 57690 Post Qualification Open - National 0.00 2018-08-16 2018-09-01 2018-09-15 2018-09-22 2018-10-06 2019-04-04 Implementation training) Codelgnator Selection BHTPA-P2 B / Training Consultant Pending course on (Workforce IDA / 57690 Post Qualification Open - National 0.00 2018-08-16 2018-09-01 2018-09-15 2018-09-22 2018-10-06 2019-04-04 Implementation training) Laravel Selection Page 4 BHTPA-P2 C / Training course on (Workforce Consultant Pending training) Development ASP IDA / 57690 Post Qualification Open - National 0.00 2018-08-16 2018-09-01 2018-09-15 2018-09-22 2018-10-06 2019-04-04 Implementation NET MVC 5 Web Selection Application. BHTPA-P3 A / Training Consultant Pending course on (Workforce IDA / 57690 Post Qualification Open - National 0.00 2018-08-16 2018-09-01 2018-09-15 2018-09-22 2018-10-06 2019-04-04 Implementation training) Android Selection BHTPA-P3 C / Training course on (Workforce Consultant Pending training) Advanced iOS IDA / 57690 Post Qualification Open - National 0.00 2018-08-16 2018-09-01 2018-09-15 2018-09-22 2018-10-06 2019-04-04 Implementation Bootcamp & iOS Application Selection Development BHTPA-P3 D / Training Consultant Pending course on (Workforce IDA / 57690 Post Qualification Open - National 0.00 2018-08-16 2018-09-01 2018-09-15 2018-09-22 2018-10-06 2019-04-04 Implementation training) IOS Selection BHTPA-P4 A / Training Consultant Pending course on (Workforce IDA / 57690 Post Qualification Open - National 0.00 2018-08-27 2018-09-03 2018-09-17 2018-09-24 2018-10-08 2019-04-06 Implementation training) CCNA Selection BHTPA-P4 B / Training Consultant Pending course on (Workforce IDA / 57690 Post Qualification Open - National 0.00 2018-08-27 2018-09-03 2018-09-17 2018-09-24 2018-10-08 2019-04-06 Implementation training) CCNP Selection BHTPA-P4 C / Training Consultant Pending course on (Workforce IDA / 57690 Post Qualification Open - National 0.00 2018-08-27 2018-09-03 2018-09-17 2018-09-24 2018-10-08 2019-04-06 Implementation training) CCNA Security Selection BHTPA-P5 A / Training Consultant Pending course on (Workforce IDA / 57690 Post Qualification Open - National 0.00 2018-08-27 2018-09-03 2018-09-17 2018-09-24 2018-10-08 2019-04-06 Implementation training) Linux Selection BHTPA-P5 B / Training Consultant course on (Workforce Pending IDA / 57690 Post Qualification Open - National 0.00 2018-08-27 2018-09-03 2018-09-17 2018-09-24 2018-10-08 2019-04-06 training) Windows Server Implementation Selection 2016 BHTPA-P6 A / Training Consultant course on (Workforce Pending IDA / 57690 Post Qualification Open - National 0.00 2018-08-27 2018-09-03 2018-09-17 2018-09-24 2018-10-08 2019-04-06 training) Professional Digital Implementation Selection Content Management BHTPA-P6 B / Training Consultant course on (Workforce Pending IDA / 57690 Post Qualification Open - National 0.00 2018-08-27 2018-09-03 2018-09-17 2018-09-24 2018-10-08 2019-04-06 training) E-Commerce Implementation Selection Professional Training BHTPA-P7 A / Training Consultant course on (Workforce Pending IDA / 57690 Post Qualification Open - National 0.00 2018-08-27 2018-09-03 2018-09-17 2018-09-24 2018-10-08 2019-04-06 training) Finance & Implementation Selection Accounting Outsourcing BHTPA-P8 A / Training Consultant Pending course on (Workforce IDA / 57690 Post Qualification Open - National 0.00 2018-09-02 2018-09-09 2018-09-23 2018-09-30 2018-10-14 2019-04-12 Implementation training) Medical Scribing Selection BHTPA-P 9 A / Training Consultant course on (Workforce Pending IDA / 57690 Post Qualification Open - National 0.00 2018-09-02 2018-09-09 2018-09-23 2018-09-30 2018-10-14 2019-04-12 training) Software Quality Implementation Selection Assurance & Testing Page 5 BHTPA-P9 B / Training course on (Workforce Consultant Pending training) Software Quality IDA / 57690 Post Qualification Open - National 0.00 2018-09-02 2018-09-09 2018-09-23 2018-09-30 2018-10-14 2019-04-12 Implementation Assurance-Implementing Selection Consistent Quality BHTPA-P9 C / Training Consultant course on (Workforce Pending IDA / 57690 Post Qualification Open - National 0.00 2018-09-02 2018-09-09 2018-09-23 2018-09-30 2018-10-14 2019-04-12 training) Information Implementation Selection Security & Auditing BHTPA-P11 A / Training Consultant course on (Workforce Pending IDA / 57690 Post Qualification Open - National 0.00 2018-09-02 2018-09-09 2018-09-23 2018-09-30 2018-10-14 2019-04-12 training) Oracle Certified Implementation Selection Professional (OCP) Java SE8 BHTPA-P11 B / Training Consultant course on (Workforce Pending IDA / 57690 Post Qualification Open - National 0.00 2018-09-02 2018-09-09 2018-09-23 2018-09-30 2018-10-14 2019-04-12 training) Oracle Database Implementation Selection Administrator 11g BHTPA-P11 C / Training Consultant course on (Workforce Pending IDA / 57690 Post Qualification Open - National 0.00 2018-09-02 2018-09-09 2018-09-23 2018-09-30 2018-10-14 2019-04-12 training) Oracle Developer Implementation Selection 11g BHTPA-P13 A / Training course on (Workforce Consultant Pending training) Remote IT IDA / 57690 Post Qualification Open - National 0.00 2018-09-02 2018-09-09 2018-09-23 2018-09-30 2018-10-14 2019-04-12 Implementation Infrastructure Operation & Selection Maintenance Management BHTPA-P14 A / Training Consultant Pending course on (Workforce IDA / 57690 Post Qualification Open - National 0.00 2018-09-05 2018-09-12 2018-09-26 2018-10-03 2018-10-17 2019-04-15 Implementation training) System Security Selection BHTPA-P14 B / Training course on (Workforce Consultant Pending training) UC (IP Telephone, IDA / 57690 Post Qualification Open - National 0.00 2018-09-05 2018-09-12 2018-09-26 2018-10-03 2018-10-17 2019-04-15 Implementation Video Conference and IP Selection Surveillance BHTPA-P15 A / Training Consultant course on (Workforce Pending IDA / 57690 Post Qualification Open - National 0.00 2018-09-05 2018-09-12 2018-09-26 2018-10-03 2018-10-17 2019-04-15 training) Six Sigma Black Implementation Selection Belt BHTPA-P15 B / Training Consultant course on (Workforce Pending IDA / 57690 Post Qualification Open - National 0.00 2018-09-05 2018-09-12 2018-09-26 2018-10-03 2018-10-17 2019-04-15 training) Six Sigma Green Implementation Selection Belt BHTPA-P15 C / Training Consultant course on (Workforce Pending IDA / 57690 Post Qualification Open - National 0.00 2018-09-05 2018-09-12 2018-09-26 2018-10-03 2018-10-17 2019-04-15 training) Project Implementation Selection Management BHTPA-P16 A / Training Consultant Pending course on (Workforce IDA / 57690 Post Qualification Open - National 0.00 2018-09-05 2018-09-12 2018-09-26 2018-10-03 2018-10-17 2019-04-15 Implementation training) SAP User Training Selection BHTPA-P17 A / Training Consultant Pending course on (Workforce IDA / 57690 Post Qualification Open - National 0.00 2018-09-05 2018-09-12 2018-09-26 2018-10-03 2018-10-17 2019-04-15 Implementation training) Ardunio Selection Page 6 BHTPA-P18 A / Training Consultant course on (Workforce Pending IDA / 57690 Post Qualification Open - National 0.00 2018-09-05 2018-09-12 2018-09-26 2018-10-03 2018-10-17 2019-04-15 training) 3D Animation & Implementation Selection Film Making BHTPA-P3 B / Training course on (Workforce Consultant Pending training) Programming IDA / 57690 Post Qualification Open - National 0.00 2018-08-16 2018-09-01 2018-09-15 2018-09-22 2018-10-06 2019-04-04 Implementation Mobile Applications for Selection Android & device security INDIVIDUAL CONSULTANTS Page 7