PROCUREMENT PLAN (Textual Part) Project information: Democratic Republic Democratic of Congo - Goma Airport Safety Improvement Project (P153085) Project Implementation agency: UPK Date of the Procurement Plan: February 2018 Period covered by this Procurement Plan: January - December 2018 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016 and revised November 2017) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the Borrower’s Public Procurement Law No 10/010 of April 27, 2010 (PPL) and the Manual of Procedures of the PPL as per Borrower’s Decree No 10/22 of June 2, 2010, such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. (a) Standard Bidding Documents: All standard bidding documents to be used for the Project under NCB shall be found acceptable to the World Bank before their use during the implementation of Project; (b) Eligibility: Eligibility of bidders and acceptability of their goods and services shall not be based on their nationality and/or their origin; and association with a national firm shall not be a condition for participation in a bidding process. Therefore, except for the ineligibility situations referred to in paragraphs 1.10(a) (i) and 1.10(a) (ii) of the Procurement Guidelines, the eligibility of bidders must be based solely on their qualification, experience and capacity to carry out the contract related to the specific bidding process; (c) Advertising and Bid Preparation Time: Bidding opportunities shall be advertised at least in a national newspaper of wide circulation and on the website of the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) and bidders should be given at least 30 days from the date of invitation to bid or the date of availability of the bidding documents, whichever is later; (d) Criteria for Qualification of Bidders: Qualification criteria shall only concern the bidder’s capability and resources to perform the contract taking into account objective and measurable factors. Such criteria for qualification of bidders shall be clearly specified in the bidding documents; (e) Bid Evaluation and Contract Award: A contract shall be awarded to the substantially responsive and lowest evaluated bidder provided that such bidder meets the qualification criteria specified in the bidding documents. No scoring system shall be allowed for the evaluation of bids, and no “blanket” limitation to the number of lots which can be awarded to a bidder shall apply. The criteria for bid evaluation and the contract award conditions shall be clearly specified in the bidding documents; (f) Preferences: No preference shall be given to domestic/regional bidders; to domestically/regionally manufactured goods; and to bidders forming a joint venture with a national firm or proposing national sub-contractors or carrying out economic activities in the territory of the Recipient; (g) Publication of Contract Award: Information on all contract awards shall be published in at least a national newspaper of wide circulation or in the Recipient’s Procurement Regulator (Autorité de Régulation des Marchés Publics) web-site; (h) Fraud and Corruption: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy to sanction firms or individuals found to have engaged in fraud and corruption as set forth in the Procurement Guidelines; (i) Inspection and Audit Rights: In accordance with the Procurement Guidelines, each bidding document and contract shall include provisions stating the World Bank’s policy with respect to inspection and audit of accounts, records and other documents relating to the bid submission and contract performance; (j) Requirement for administrative documents and/or tax clearance certificate: The bidding documents shall not require foreign bidders to produce any administrative or tax related certificates prior to confirmation of awarding a contract; and (k) Modifications of a Signed Contract: Any change in the contract amount which, singly or combined with all previous changes, increases the original contract amount by fifteen (15) percent or more must be done through an amendment to the signed contract instead of signing a new contract. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. “Not Applicable” Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables. “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: is applicable for those contracts identified in the Procurement Plan tables; Other Relevant Procurement Information. “Not Applicable” PROCUREMENT Congo, Democratic Republic of : DRC - Goma Airport Safety Improvement Project PLAN General Information Country: Congo, Democratic Republic of Bank’s Approval Date of the Original Procurement Plan: 2018-05-18 2019-10-18 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153085 GPN Date: Project Name: DRC - Goma Airport Safety Improvement Project Loan / Credit No: IDA / D0420, TF / A1623 Executing Agency(ies): Projet de Transport Multimodal WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PTM UPK-59615-CW- RFB / Travaux de Component A: Airport Single Stage - One En attente construction des ouvrages de IDA / D0420 A posteriori Appel d'offres Open - National 2,000,000.00 0.00 2018-10-26 2018-10-31 2018-12-12 2019-01-11 2019-02-15 2019-08-14 Infrastructure Investments Envelope d'exécution drainage à l'aéroport de Goma ZR-PTM UPK-59451-CW- RFB / Travaux de construction de la tour de Component A: Airport Single Stage - One En cours IDA / D0420 A posteriori Appel d'offres Open - National 3,000,000.00 0.00 2018-05-15 2018-05-20 2018-07-01 2018-07-31 2018-09-04 2019-03-03 contrôle avec bloc technique Infrastructure Investments Envelope d'exécution (yc fourniture équipements et installation) ZR-PTM UPK-59610-CW- RFB / Travaux de Component A: Airport Single Stage - One En cours réhabilitation et extension de IDA / D0420 A posteriori Appel d'offres Open - National 3,000,000.00 0.00 2017-06-13 2017-06-18 2017-07-30 2017-08-29 2017-10-03 2018-04-01 Infrastructure Investments Envelope d'exécution l'aire de stationnement (tarmac) ZR-PTM UPK-59773-CW- RFB / Travaux Component A: Airport Single Stage - One En attente IDA / D0420 A posteriori Appel d'offres Open - National 900,000.00 0.00 2019-04-10 2019-04-15 2019-05-27 2019-06-26 2019-07-31 2020-01-27 d'aménagement de la zone Infrastructure Investments Envelope d'exécution fret ZR-PTM UPK-59756-CW- RFB / Travaux de Component A: Airport Single Stage - One En attente modernisation et de mise à IDA / D0420 A posteriori Appel d'offres Open - National 4,000,000.00 0.00 2019-03-20 2019-03-25 2019-05-06 2019-06-05 2019-07-10 2020-01-06 Infrastructure Investments Envelope d'exécution niveau de l'aérogare de l'aéroport de Goma ZR-PTM UPK-59620-CW- RFQ / Travaux d'achevement Component B: Capacity Single Stage - One En attente du batiment devant abriter TF / A1623 Building and Project A posteriori Demande de prix Open - National 72,800.00 0.00 2016-12-04 2017-01-29 2017-07-28 Envelope d'exécution les équipements de Implementation Support laboratoires de l'OVG ZR-PTM UPK-59626-CW- RFB / Travaux Component A: Airport Single Stage - One En attente d'aménagement des sites IDA / D0420 A posteriori Appel d'offres Open - National 1,000,000.00 0.00 2018-12-17 2018-12-22 2019-02-02 2019-03-04 2019-04-08 2019-10-05 Infrastructure Investments Envelope d'exécution pour la réinstallation des PAPs ZR-PTM UPK-59771-CW- RFQ / Travaux de Component A: Airport Single Stage - One En attente IDA / D0420 A posteriori Demande de prix Limited 300,000.00 0.00 2018-09-15 2018-11-10 2019-05-09 construction de l'éxecutoire Infrastructure Investments Envelope d'exécution (Lac Kivu) Page 1 ZR-PTM UPK-59795-CW- RFQ / Travaux de Component A: Airport Single Stage - One En cours réhabilitation de la piste de IDA / D0420 A priori Appel d'offres Limited 18,800,000.00 0.00 2018-06-20 2018-06-25 2018-08-06 2018-09-05 2018-10-10 2019-04-08 Infrastructure Investments Envelope d'exécution l'aéroport de Goma portant sa longueur totale à 3000 m ZR-PTM UPK-77445-CW- DIR / Travaux de Component A: Airport Single Stage - One En attente IDA / D0420 A posteriori Appel d'offres Open - National 2,900,000.00 0.00 2018-11-15 2018-11-20 2019-01-01 2019-01-31 2019-03-07 2019-09-03 construction du collecteur Infrastructure Investments Envelope d'exécution de la ville de GOMA ZR-PTM UPK-77548-CW- DIR / Travaux d'achèvement des chantiers ouverts du Passation de collecteur pour l'évacuation Component A: Airport En attente IDA / D0420 A posteriori marché de gré à Direct 155,224.00 0.00 2018-09-14 2018-09-19 2018-10-25 2018-12-24 des eaux des pluies de Infrastructure Investments d'exécution gré l'aéroport vers le lac par l' entreprise Beatitude Building Company BBC ZR-PTM UPK-59600-CW- RFB / Travaux de Component A: Airport Single Stage - One En attente construction du mur de IDA / D0420 A posteriori Appel d'offres Open - National 1,200,000.00 0.00 2018-05-15 2018-05-20 2018-07-01 2018-07-31 2018-09-04 2019-03-03 Infrastructure Investments Envelope d'exécution clôture en trois lots distincts, phase I ZR-PTM UPK-77549-CW- RFB / Travaux de construction des segments de Component A: Airport Single Stage - One En attente IDA / D0420 A posteriori Appel d'offres Open - National 1,600,000.00 0.00 2018-10-15 2018-10-20 2018-12-01 2018-12-31 2019-02-04 2019-08-03 murs de clôture de l'aéroport Infrastructure Investments Envelope d'exécution de Goma, phase II, en quatre (4) lots distincts. ZR-PTM UPK-82149-CW- DIR / Sécurisation des Passation de travaux de construction du Component A: Airport En attente IDA / D0420 A posteriori marché de gré à Direct 30,000.00 0.00 2018-10-17 2018-10-22 2018-11-26 2019-05-25 collecteur de la ville de Infrastructure Investments d'exécution gré Goma avec l'entreprise CCGL ZR-PTM UPK-111488-CW- RFB / Travaux Component A: Airport Single Stage - One En attente d'aménagement et de IDA / D0420 A posteriori Appel d'offres Limited 53,300.00 0.00 2019-04-23 2019-04-28 2019-06-09 2019-07-09 2019-08-13 2020-02-09 Infrastructure Investments Envelope d'exécution construction de 8 puisards dans le quartier Murara GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PTM UPK-59793-GO- RFB / Fourniture d'un Component A: Airport Single Stage - One En attente véhicule flyco et petits IDA / D0420 A posteriori Appel d'offres Open - National 200,000.00 0.00 2016-12-02 2016-12-07 2017-01-18 2017-02-17 2017-03-24 2017-09-20 Infrastructure Investments Envelope d'exécution outillages de secours pour le service anti incendie ZR-PTM UPK-59618-GO- RFQ / Acquisition de Component A: Airport Single Stage - One En attente IDA / D0420 A posteriori Demande de prix Limited 77,300.00 0.00 2016-12-08 2017-02-02 2017-08-01 materiels roulants pour Infrastructure Investments Envelope d'exécution l'OVG ZR-PTM UPK-59613-GO- RFQ / Acquisition des Component A: Airport Single Stage - One En attente équipements des seismologie, IDA / D0420 A posteriori Demande de prix Limited 495,000.00 0.00 2018-11-20 2019-01-15 2019-07-14 Infrastructure Investments Envelope d'exécution géochimie, géodesie pour l'OVG Page 2 ZR-PTM UPK-59614-GO- RFB / Equipements pour la Component A: Airport Open - Single Stage - One En attente réhabilitation de la centrale IDA / D0420 A priori Appel d'offres 2,780,000.00 0.00 2018-09-17 2018-09-22 2018-11-03 2018-12-03 2019-01-07 2019-07-06 Infrastructure Investments International Envelope d'exécution électrique de l'aéroport de Goma ZR-PTM UPK-82132-GO- RFQ / Acquisition de deux Component A: Airport Single Stage - One En attente IDA / D0420 A posteriori Demande de prix Limited 75,000.00 0.00 2018-10-21 2018-12-16 2019-06-14 véhicules TT pour le projet Infrastructure Investments Envelope d'exécution PASAG/GOMA ZR-PTM UPK-82139-GO- RFQ / Acquisition des Component A: Airport Single Stage - One En attente IDA / D0420 A posteriori Demande de prix Limited 25,000.00 0.00 2018-10-21 2018-12-16 2019-06-14 mobiliers de bureaux pour le Infrastructure Investments Envelope d'exécution projet PASAG/Goma ZR-PTM UPK-82141-GO- RFQ / Acquisition d'un Component A: Airport Single Stage - One En attente IDA / D0420 A posteriori Demande de prix Limited 10,000.00 0.00 2018-11-03 2018-12-29 2019-06-27 groupe électrogène de 15Kva Infrastructure Investments Envelope d'exécution pour le projet PASAG/Goma ZR-PTM UPK-99914-GO- RFQ / Fourniture des Component A: Airport Single Stage - One En cours IDA / D0420 A posteriori Demande de prix Limited 20,550.00 0.00 2019-02-14 2019-04-11 2019-10-08 matériels informatiques du Infrastructure Investments Envelope d'exécution PASAG ZR-PTM UPK-99916-GO- RFQ / Fourniture des Component A: Airport Single Stage - One En attente IDA / D0420 A posteriori Demande de prix Limited 11,500.00 0.00 2019-02-25 2019-04-22 2019-10-19 consommables informatiques Infrastructure Investments Envelope d'exécution et bureautiques ZR-PTM UPK-99917-GO- Component A: Airport Single Stage - One En attente RFQ / Acquisition des IDA / D0420 A posteriori Demande de prix Limited 3,200.00 0.00 2019-02-25 2019-04-22 2019-10-19 Infrastructure Investments Envelope d'exécution logiciels et ouvrages ZR-PTM UPK-130479-GO- RFQ / Acquisition du logiciel de gestion financière et Single Stage - One En attente TF / A1623 Contingencies A posteriori Demande de prix Limited 20,000.00 0.00 2019-09-14 2019-11-09 2020-05-07 comptable pour la gestion de Envelope d'exécution l'Observatoire Volcanique de Goma NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PTM UPK-59751-CS- Sélection fondée CQS / Etude de Component A: Airport sur les En attente réhabilitation et extension de IDA / D0420 A posteriori Open - National 100,000.00 0.00 2016-11-10 2016-12-01 2017-01-14 2017-02-13 2017-03-20 2017-09-16 Infrastructure Investments qualifications des d'exécution l'aire de stationnement consultants (tarmac) de l'aéroport de Goma Page 3 ZR-PTM UPK-59619-CS- CQS / Contrôle et Sélection fondée surevillance des travaux de Component A: Airport sur les En attente IDA / D0420 A posteriori Open - National 200,000.00 0.00 2018-07-25 2018-08-15 2018-09-28 2018-10-28 2018-12-02 2019-05-31 construction des ouvrages de Infrastructure Investments qualifications des d'exécution drainage de l'aéroport de consultants Goma ZR-PTM UPK-59607-CS- Sélection fondée QCBS / Conception et Component A: Airport Open - En attente IDA / D0420 A priori sur la qualité et 500,000.00 0.00 2019-01-15 2019-02-05 2019-03-21 2019-04-18 2019-05-18 2019-06-22 2019-07-27 2020-07-26 développement de la zone Infrastructure Investments International d'exécution le coût fret ZR-PTM UPK-59755-CS- QCBS / Préparation des Sélection fondée documents techniques Component A: Airport Open - En attente IDA / D0420 A priori sur la qualité et 1,500,000.00 0.00 2019-01-15 2019-02-05 2019-03-21 2019-04-18 2019-05-18 2019-06-22 2019-07-27 2020-07-26 détaillés pour 2/3 des Infrastructure Investments International d'exécution le coût aéroports nationaux startégiques ZR-PTM UPK-59605-CS- QCBS / Etude architecturale, Sélection fondée conception et surveillance Component A: Airport Open - En attente IDA / D0420 A priori sur la qualité et 1,000,000.00 0.00 2018-11-21 2018-12-12 2019-01-25 2019-02-22 2019-03-24 2019-04-28 2019-06-02 2020-06-01 des travaux de Infrastructure Investments International d'exécution le coût modernisation de l'aérogare de l'aéroport de Goma ZR-PTM UPK-59611-CS- Sélection fondée CQS / Services de consultant Component A: Airport sur les En attente chargé du suivi des aspects IDA / D0420 A posteriori Open - National 56,800.00 0.00 2016-11-22 2016-12-13 2017-01-26 2017-02-25 2017-04-01 2017-09-28 Infrastructure Investments qualifications des d'exécution environnementaux et sociaux consultants du ZR-PTM UPK-59758-CS- Sélection fondée CQS / Etude d'aménagement Component A: Airport sur les En attente des sites pour la IDA / D0420 A posteriori Open - National 100,000.00 0.00 2017-07-20 2017-08-10 2017-09-23 2017-10-23 2017-11-27 2018-05-26 Infrastructure Investments qualifications des d'exécution réinstallation des personnes consultants affectées par le projet (PAPs) ZR-PTM UPK-59453-CS- QCBS / Service de Sélection fondée Component A: Airport En attente consultant chargé de l'audit IDA / D0420 A posteriori sur la qualité et Open - National 100,000.00 0.00 2018-04-30 2018-05-21 2018-07-04 2018-08-01 2018-08-31 2018-10-05 2018-11-09 2019-11-09 Infrastructure Investments d'exécution de la RVA(Exercices le coût 2016,2017 et 2018) ZR-PTM UPK-59630-CS- Sélection fondée CQS / Service de consultant Component A: Airport sur les En attente chargé de la détermination IDA / D0420 A posteriori Open - National 170,000.00 0.00 2017-12-13 2018-01-03 2018-02-16 2018-03-18 2018-04-22 2018-10-19 Infrastructure Investments qualifications des d'exécution du PCN de chaussées de consultants l'aéroport de Goma ZR-PTM UPK-59632-CS- QCBS / Contrôle et Sélection fondée Component A: Airport Open - En attente surveillance des travaux IDA / D0420 A posteriori sur la qualité et 250,000.00 0.00 2018-11-20 2018-12-11 2019-01-24 2019-02-21 2019-03-23 2019-04-27 2019-06-01 2020-05-31 Infrastructure Investments International d'exécution d'aménagement des sites de le coût réinstallation des PAPs ZR-PTM UPK-59791-CS- QCBS / Service de Sélection fondée Component A: Airport En attente consultant chargé de l'audit IDA / D0420 A posteriori sur la qualité et Open - National 100,000.00 0.00 2016-12-08 2016-12-29 2017-02-11 2017-03-11 2017-04-10 2017-05-15 2017-06-19 2018-06-19 Infrastructure Investments d'exécution du projet PASAG(Exercices le coût 2016,2017 et 2018) ZR-PTM UPK-82126-CS- CQS / Services de consultant Sélection fondée (Bureau) chargé de Component A: Airport sur les En attente l'élaboration des PGES pour IDA / D0420 A posteriori Open - National 150,000.00 0.00 2018-12-18 2019-01-08 2019-02-21 2019-03-23 2019-04-27 2019-10-24 Infrastructure Investments qualifications des d'exécution la piste, la tour de contrôle, consultants la centrale électrique et les ouvrages de drainage. Page 4 ZR-PTM UPK-118150-CS- CQS / Service ce consultant Sélection fondée chargé de la surveillance et Component A: Airport sur les En attente du contrôle des travaux IDA / D0420 A posteriori Open - National 200,000.00 0.00 2019-06-05 2019-06-26 2019-08-09 2019-09-08 2019-10-13 2020-04-10 Infrastructure Investments qualifications des d'exécution d'achèvement de la consultants construction du collecteur de la ville de Goma ZR-PTM UPK-130481-CS- QCBS / Service de Consultants (firme) chargé Sélection fondée Component A: Airport Open - En attente de l'audit financier et IDA / D0420 A posteriori sur la qualité et 100,000.00 0.00 2019-09-04 2019-09-25 2019-11-08 2019-12-06 2020-01-05 2020-02-09 2020-03-15 2021-03-15 Infrastructure Investments International d'exécution comptable du PASAG le coût (Exercices 2019, 2020 et audit de clôture) ZR-PTM UPK-130486-CS- QCBS / Service de Sélection fondée Component A: Airport En attente Consultants (firme) pour IDA / D0420 A posteriori sur la qualité et Open - National 60,000.00 0.00 2019-09-04 2019-09-25 2019-11-08 2019-12-06 2020-01-05 2020-02-09 2020-03-15 2021-03-15 Infrastructure Investments d'exécution l'audit technique des travaux le coût de génie civil du PASAG INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual ZR-PTM UPK-59764-CS- CDS / Protocole de Sélection de Component A: Airport En attente collaboration pour la mise IDA / D0420 A priori consultants par Direct 1,000,000.00 0.00 2019-03-28 2019-04-07 2019-06-11 2019-12-08 Infrastructure Investments d'exécution en valeur de la roche de entente directe laves avec le FSRDC ZR-PTM UPK-59599-CS- CDS / Services de consultant chargé de l'étude de Sélection de Component A: Airport En attente construction du mur de IDA / D0420 A posteriori consultants par Direct 25,000.00 0.00 2016-11-20 2016-11-30 2017-02-03 2017-08-02 Infrastructure Investments d'exécution cloture de l'aéroport de entente directe Goma avec la firme INTAIRPLAN ZR-PTM UPK-59794-CS- Sélection de CDS / Etude pour Component A: Airport En attente IDA / D0420 A posteriori consultants par Direct 45,000.00 0.00 2018-06-20 2018-06-30 2018-09-03 2019-03-02 l'élaboration d'un addendum Infrastructure Investments d'exécution entente directe au PAR ZR-PTM UPK-59571-CS- INDV / Service de Component A: Airport En attente IDA / D0420 A posteriori Individuel Limited 70,000.00 0.00 2017-10-24 2017-10-29 2017-11-19 2017-12-24 2018-06-22 consultant chargé d'élaborer Infrastructure Investments d'exécution le PAR pour le collecteur ZR-PTM UPK-59792-CS- CDS / Service de consultant chargé de l'étude de vérification du Sélection de dimensionnement du Component A: Airport En attente IDA / D0420 A posteriori consultants par Direct 150,000.00 0.00 2018-02-14 2018-02-24 2018-04-30 2018-10-27 collecteur de Goma et de la Infrastructure Investments d'exécution entente directe conception détaillée du seuil dissipateur d'énergie à construire à l'éxecutoire (Lac Kivu) avec la firme SGI Page 5 ZR-PTM UPK-59797-CS- CDS / Protocole d'accord avec l'Observatoire Volcanologique de Goma Sélection de (OVG) pour la prévention et En cours TF / A1623 Contingencies A priori consultants par Direct 1,254,000.00 0.00 2018-04-25 2018-05-05 2018-07-09 2019-01-05 la gestion des risques d'examen entente directe naturels et la capacité à répondre de la population congolaise face aux dangers naturels ZR-PTM UPK-59800-CS- CDS / Contrôle et Sélection de surveillance des travaux de Component A: Airport En attente IDA / D0420 A priori consultants par Direct 1,000,000.00 0.00 2018-11-30 2018-12-10 2019-02-13 2019-08-12 réhabilitation de la piste de Infrastructure Investments d'exécution entente directe l'aéroport de Goma avec la firme INTAIRPLAN ZR-PTM UPK-59602-CS- CDS / Etude de conception Sélection de détaillée des ouvrages de Component A: Airport IDA / D0420 A posteriori consultants par Direct 350,000.00 264,974.01 Signé 2017-02-13 2017-02-23 2017-04-29 2017-10-26 drainage de l'aéroport de Infrastructure Investments entente directe Goma avec la Firme AECOM ZR-PTM UPK-59761-CS- CDS / Développement et gestion de l'exécution d'un Sélection de Component A: Airport En attente programme HIMO avec la IDA / D0420 A priori consultants par Direct 1,000,000.00 0.00 2019-02-11 2019-02-21 2019-04-27 2019-10-24 Infrastructure Investments d'exécution collaboration du Fonds entente directe Social de la RD Congo (FSRDC) ZR-PTM UPK-59769-CS- CDS / Contrôle et surveillance de la fourniture Sélection de des équipements de la Component A: Airport En attente IDA / D0420 A posteriori consultants par Direct 280,000.00 0.00 2018-06-12 2018-06-22 2018-08-26 2019-02-22 centrale électrique et Infrastructure Investments d'exécution entente directe travaux de réhabilitation du batiment avec la firme INTAIRPLAN ZR-PTM UPK-59763-CS- CDS / Contrôle et surveillance des travaux de Sélection de Component A: Airport En cours construction de la tour de IDA / D0420 A posteriori consultants par Direct 300,000.00 0.00 2018-07-20 2018-07-30 2018-10-03 2019-04-01 Infrastructure Investments d'exécution contrôle avec bloc technique entente directe de l'aéroport de Goma avec la firme INTAIRPLAN ZR-PTM UPK-59790-CS- CDS / Service de consultant chargé de la formation sur Sélection de Component A: Airport En attente la lutte contre les violences IDA / D0420 A posteriori consultants par Direct 100,000.00 0.00 2018-01-25 2018-02-04 2018-04-10 2018-10-07 Infrastructure Investments d'exécution sexuelles qui sera assurée entente directe par l e Centre appelé "Maison de la femme" ZR-PTM UPK-59798-CS- CDS / Contrôle et Sélection de surveillance des travaux de Component A: Airport En attente IDA / D0420 A posteriori consultants par Direct 350,000.00 0.00 2018-09-20 2018-09-30 2018-12-04 2019-06-02 construction du collecteur de Infrastructure Investments d'exécution entente directe la ville de Goma avec la firme SGI ZR-PTM UPK-59747-CS- CDS / Contrôle et Sélection de surveillance des travaux de Component A: Airport En attente IDA / D0420 A posteriori consultants par Direct 300,000.00 0.00 2018-10-10 2018-10-20 2018-12-24 2019-06-22 réhabilitation et extension Infrastructure Investments d'exécution entente directe du tarmac avec la firme INTAIRPLAN Page 6 ZR-PTM UPK-82124-CS- Sélection de Component A: Airport En attente CDS / Protocole de IDA / D0420 A priori consultants par Direct 1,500,000.00 0.00 2019-01-15 2019-01-25 2019-03-31 2019-09-27 Infrastructure Investments d'exécution collaboration CEPTM/PASAG entente directe avec l'OACI ZR-PTM UPK-82146-CS- CDS / Consultant chargé de Sélection de Component A: Airport En attente l'étude hydrologique des IDA / D0420 A posteriori consultants par Direct 152,500.00 0.00 2018-10-16 2018-10-26 2018-12-30 2019-06-28 Infrastructure Investments d'exécution bassins versants en amonts entente directe du périmètre de l'aéroport ZR-PTM UPK-83777-CS- CDS / Contrôle et surveillance des travaux de réhabilitation de la piste, du Sélection de tarmac, de la centrale Component A: Airport En cours IDA / D0420 A priori consultants par Direct 4,000,000.00 0.00 2018-10-29 2018-11-08 2019-01-12 2019-07-11 électrique, la construction Infrastructure Investments d'exécution entente directe d'une nouvelle tour de contrôle et du mur de clôture avec le bureau INTAIRPLAN ZR-PTM UPK-97586-CS- INDV / Consultant chargé du contrôle et de la Component A: Airport En cours surveillance des travaux IDA / D0420 A posteriori Individuel Limited 12,000.00 0.00 2019-02-06 2019-02-11 2019-03-04 2019-04-08 2019-10-05 Infrastructure Investments d'examen d'aménagement et de construction de 8 puisards dans le quartier Murara ZR-PTM UPK-97578-CS- CDS / Consultant chargé du contrôle et de surveillance Sélection de Component A: Airport En attente des travaux de réhabilitation IDA / D0420 A posteriori consultants par Direct 349,434.00 0.00 2019-02-06 2019-02-16 2019-04-22 2019-10-19 Infrastructure Investments d'exécution et de la construction des entente directe infrastructures de l'aéroport de Goma ZR-PTM UPK-99906-CS- INDV / Recrutement du Component A: Airport En attente IDA / D0420 A posteriori Individuel Limited 15,720.00 0.00 2019-02-09 2019-02-14 2019-03-07 2019-04-11 2019-10-08 troisième Chauffeur du Infrastructure Investments d'exécution PASAG à Goma ZR-PTM UPK-99902-CS- INDV / Recrutement du Component A: Airport En attente Chargé de Suivi et IDA / D0420 A posteriori Individuel Open 52,100.00 0.00 2019-02-09 2019-03-30 2019-04-20 2019-05-25 2019-11-21 Infrastructure Investments d'exécution Evaluation du PASAG à Goma ZR-PTM UPK-99900-CS- INDV / Recrutement du Component A: Airport En attente Responsable Administratif et IDA / D0420 A posteriori Individuel Open 75,200.00 0.00 2019-02-09 2019-03-30 2019-04-20 2019-05-25 2019-11-21 Infrastructure Investments d'exécution Financier du PASAG à Goma ZR-PTM UPK-99901-CS- INDV / Recrutement du Component A: Airport En attente Responsable de Passation IDA / D0420 A posteriori Individuel Open 63,380.00 0.00 2019-02-09 2019-03-30 2019-04-20 2019-05-25 2019-11-21 Infrastructure Investments d'exécution des marchés du PASAG à Goma ZR-PTM UPK-99904-CS- INDV / Recrutement du Component A: Airport En attente IDA / D0420 A posteriori Individuel Open 47,060.00 0.00 2019-02-09 2019-03-30 2019-04-20 2019-05-25 2019-11-21 comptable du PASAG à Infrastructure Investments d'exécution Goma Page 7 ZR-PTM UPK-104090-CS- INDV / Consultant chargé de la mise à jour du manuel des procédures de Component A: Airport En attente IDA / D0420 A posteriori Individuel Open 35,000.00 0.00 2019-03-04 2019-04-22 2019-05-13 2019-06-17 2019-12-14 gestion administrative, Infrastructure Investments d'exécution comptable et finance, de PM et de E &E de la CEPTM/PASAG ZR-PTM UPK-108481-CS- CDS / Atelier de formation des agents du PASAG sur Sélection de Component A: Airport En cours la prévention de IDA / D0420 A posteriori consultants par Direct 2,710.00 0.00 2019-04-01 2019-04-11 2019-06-15 2019-12-12 Infrastructure Investments d'exécution l'exploitation et des abus entente directe sexuels sur les sites du Projet (HEAL AFRICA) ZR-PTM UPK-108482-CS- CDS / Atelier de formation des agents de la Maison de Sélection de la Femme/DP-GFF sur la Component A: Airport En cours IDA / D0420 A posteriori consultants par Direct 6,510.00 0.00 2019-04-01 2019-04-11 2019-06-15 2019-12-12 prévention de l'exploitation Infrastructure Investments d'exécution entente directe et des abus sexuels sur les sites du projet (HEAL AFRICA) ZR-PTM UPK-108484-CS- CDS / Mobilisation du conciliateur pour le litige opposant SAFRICAS et la Sélection de CEPTM/PASAG concernant Component A: Airport En cours IDA / D0420 A posteriori consultants par Direct 12,560.00 0.00 2019-04-01 2019-04-11 2019-06-15 2019-12-12 les contrats de travaux de Infrastructure Investments d'exécution entente directe construction/réhabilitation des infrastructures de l'aéroport de Goma (Bernard FOURNET) ZR-PTM UPK-111490-CS- CDS / Consultant chargé du Sélection de contrôle et de la surveillance Component A: Airport En attente IDA / D0420 A posteriori consultants par Direct 6,800.00 0.00 2019-04-22 2019-05-02 2019-07-06 2020-01-02 des travaux d'aménagement Infrastructure Investments d'exécution entente directe et construction de 8 puisards dans le quartier Murara ZR-PTM UPK-111492-CS- CDS / Accompagnement juridique à la CEPTM/PASAG au Sélection de Component A: Airport En attente contentieux d'exécution des IDA / D0420 A posteriori consultants par Direct 7,700.00 0.00 2019-04-22 2019-05-02 2019-07-06 2020-01-02 Infrastructure Investments d'exécution marchés de construction des entente directe collecteurs d'eaux et de réhabilitation de la piste de l'aéroport de Goma ZR-PTM UPK-111493-CS- CDS / Accompagnement technique de la CEPTM/PASAG au Sélection de contentieux d'exécution du Component A: Airport En attente IDA / D0420 A posteriori consultants par Direct 4,000.00 0.00 2019-04-23 2019-05-03 2019-07-07 2020-01-03 marché de construction du Infrastructure Investments d'exécution entente directe collecteur de la ville de Goma pour évacuation des eaux de pluie de l'aéroport de Goma ZR-PTM UPK-111504-CS- INDV / Deuxième Spécialiste Component A: Airport En attente en sauvegarde IDA / D0420 A posteriori Individuel Limited 28,400.00 0.00 2019-04-23 2019-04-28 2019-05-19 2019-06-23 2019-12-20 Infrastructure Investments d'exécution environnementale et sociale du PASAG Page 8 ZR-PTM UPK-118151-CS- CDS / Consultant pour la mise à disposition et l'accompagnement d'un expert aérodrome de l'OACI Sélection de Component A: Airport En attente en faveur de la IDA / D0420 A posteriori consultants par Direct 110,000.00 0.00 2019-06-05 2019-06-15 2019-08-19 2020-02-15 Infrastructure Investments d'exécution CEPTM/PASAG en vue de entente directe superviser la revue apex et participer à la mission d'appui de la BM à la mise en oeuvre du PASAG ZR-PTM UPK-119012-CS- INDV / Recrutement de Component A: Airport En attente l'auditeur interne du Projet IDA / D0420 A posteriori Individuel Open 64,610.00 0.00 2019-06-13 2019-08-01 2019-08-22 2019-09-26 2020-03-24 Infrastructure Investments d'exécution d'Amélioration de la Sécurité à l'Aéroport de Goma ZR-PTM UPK-119019-CS- INDV / Recrutement du Component A: Airport En attente trésorier du Projet IDA / D0420 A posteriori Individuel Open 51,320.00 0.00 2019-06-13 2019-08-01 2019-08-22 2019-09-26 2020-03-24 Infrastructure Investments d'exécution d'Amélioration de la Sécurité à l'Aéroport de Goma ZR-PTM UPK-130493-CS- INDV / Service de consultants pour l'élaboration d'un audit social indépendant sur la mise en Component A: Airport En attente oeuvre du PAR du sous IDA / D0420 A posteriori Individuel Limited 20,000.00 0.00 2019-09-04 2019-09-09 2019-09-30 2019-11-04 2020-05-02 Infrastructure Investments d'exécution projet des travaux de construction du collecteur de Goma pour l'évacuation des eaux de l'aéroport au lac Kivu ZR-PTM UPK-130496-CS- CDS / Service de Sélection de Consultants (firme) pour Component A: Airport En attente TF / A1623 A posteriori consultants par Direct 12,000.00 0.00 2019-09-04 2019-09-14 2019-11-18 2020-05-16 l'assistance technique sur le Infrastructure Investments d'exécution entente directe logiciel TOM2PRO sur place (à Goma) au PASAG Page 9