PROCUREMENT PLAN (Textual Part) Project information: [countrySri Lanka ]- [Project nameFramework Development and Infrastructure Financing to Support Public Private partnerships] [ -P-number163864 ] Project Implementation agency: [insert legal name]National Agency for Public Private Partnerships Date of the Procurement Plan: [insert date]August 30, 2018 Period covered by this Procurement Plan: [insert from08/30/ –2018 – to period]02/28/2020 Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in [insert appropriate references to the national procurement legislation],Sri Lanka National Procurement Guidelines 2006 such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations and the following conditions. 1. Only bidding documents acceptable to the Bank shall be used for all national open competitive procurement. 2. The request for bids/request for proposals document shall require that bidders/proposers submitting bids/proposals present a signed acceptance at the time of bidding, to be incorporated in any resulting contracts, confirming application of, and compliance with, the Bank’s Anti-Corruption Guidelines, including without limitation the Bank’s right to sanction and the Bank’s inspection and audit rights. 3. The eligibility of bidders shall be as defined under Section III of the World Bank Procurement Regulations for IPF Borrowers (Procurement Regulations): accordingly, no bidder or potential bidder shall be declared ineligible for contracts financed by the Bank for reasons other than those provided in Section III of the Procurement Regulations. List only the applicable conditions required to ensure consistency with paragraph 5.4 of the Procurement Regulations. If no conditions apply, delete the phrase “and the following conditions”. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Otherwise state “Not Applicable”Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables - Otherwise state “Not Applicable” Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Specify for eachNot Applicable Goods: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables]; Works: [is not applicable/is applicable for those contracts identified in the Procurement Plan tables] Hands-on Expanded Implementation Support (HEIS) as specified under paragraphs 3.10 and 3.11 of the Procurement Regulations is Applicable. [Include this sentence only if the Bank has formally agreed to provide the Borrower with HEIS. Otherwise delete] Other Relevant Procurement Information. Provide any other relevant procurement information such as procedures for CDD components, Procurement in Situations of Urgent Need of Assistance or Capacity Constraints etc. PROCUREMENT Sri Lanka : Framework Development and Infrastructure Financing to Support Public-Private Partnerships Project PLAN General Information Country: Sri Lanka Bank’s Approval Date of the Original Procurement Plan: 2019-03-19 2019-06-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P163864 GPN Date: 2019-01-02 Project Name: Framework Development and Infrastructure Financing to Support Public-Private Partnerships Project Loan / Credit No: IBRD / 89070 Executing Agency(ies): National Agency for Public Private Partnerships WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-NAPPP-81963-GO-RFB / Pending Request for Single Stage - One Laptop, IT & Software cost IBRD / 89070 Post Limited 0.00 Implementati 2019-10-22 2020-01-05 2023-01-04 Quotations Envelope (15 units) on LK-NAPPP-82045-GO-RFQ / Pending Request for Single Stage - One Laptop, IT & Software cost IBRD / 89070 Post Limited 0.00 Implementati 2020-05-22 2020-08-05 2023-08-05 Quotations Envelope (10 laptops) on LK-NAPPP-108494-GO-DIR / Microsoft enterprise solution Pending - license cost, set up, IBRD / 89070 Post Direct Selection Direct 0.00 Implementati 2019-10-01 2019-10-13 2019-11-18 2020-11-17 support and main. cost (15 on users) LK-NAPPP-108497-GO-DIR / Microsoft enterprise solution- Pending license cost, set up support IBRD / 89070 Post Direct Selection Direct 0.00 Implementati 2020-05-01 2020-05-13 2020-06-18 2021-06-18 and maintenance cost (10 on users) LK-NAPPP-108778-GO-DIR / Pending Quick Book Accounting IBRD / 89070 Post Direct Selection Direct 0.00 Implementati 2019-06-20 2019-06-25 2019-08-03 2020-08-02 Package on LK-NAPPP-114410-GO-DIR / Pending Office equipment - IBRD / 89070 Post Direct Selection Direct 0.00 Implementati 2019-06-20 2019-07-02 2019-08-07 2020-02-03 Telephone PABX (40 units) on LK-NAPPP-105134-GO-RFQ Pending Request for Single Stage - One / Office Equipment - IBRD / 89070 Post Limited 0.00 Implementati 2019-07-31 2019-10-14 2019-11-13 Quotations Envelope Shredders (3 units) on LK-NAPPP-118507-GO-RFQ Pending Request for Single Stage - One / Office equipment - Video IBRD / 89070 Post Open - National 0.00 Implementati 2019-08-12 2019-10-21 2019-11-20 Quotations Envelope conferencing facility (3 units) on Page 1 LK-NAPPP-104199-GO-RFQ / Office equipment - Video Request for Single Stage - One conferencing facility (2 units) IBRD / 89070 Post Limited 0.00 Canceled 2019-05-22 2019-08-05 2022-08-04 Quotations Envelope and Telephone PABX (40 units) LK-NAPPP-105131-GO-RFQ Pending Request for Single Stage - One / Office equipment - Single IBRD / 89070 Post Limited 0.00 Implementati 2019-08-12 2019-10-26 2019-11-25 Quotations Envelope user printers (6 units) on LK-NAPPP-81960-GO-RFB / Pending Request for Single Stage - One Laptops,IT & Software cost IBRD / 89070 Post Limited 0.00 Implementati 2019-08-01 2019-10-15 2019-11-14 Quotations Envelope (15 units) on LK-NAPPP-108779-GO-DIR / Microsoft enterprise solution- Pending license cost, set up support IBRD / 89070 Post Direct Selection Direct 0.00 Implementati 2019-06-27 2019-07-09 2019-08-14 2020-08-13 and maintenance cost (20 on users). NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-NAPPP-103877-NC-RFQ Pending / Pooneryn Renewable Request for Single Stage - One IBRD / 89070 Post Limited 0.00 Implementati 2019-10-27 2019-12-09 2022-12-08 Energy Park - Geotechnical Quotations Envelope on survey of the project site LK-NAPPP-104013-NC-RFQ Pending Request for Single Stage - One / Web Design, implement IBRD / 89070 Post Limited 0.00 Implementati 2020-01-05 2020-03-13 2023-03-13 Quotations Envelope and maintenance on LK-NAPPP-103879-NC-RFQ / Kandy Mahaiyawe Urban Pending Request for Single Stage - One Housing Project - IBRD / 89070 Post Limited 0.00 Implementati 2020-02-22 2020-04-05 2023-04-05 Quotations Envelope Geotechnical survey of the on project site CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Actual Amount Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual LK-NAPPP-104054-CS-CQS Consultant Open - / Gampaha waste water IBRD / 89070 Post Qualification 0.00 Canceled 2020-06-18 2020-06-18 2020-08-16 2020-09-20 2020-09-27 2020-10-27 International project- Social survey Selection LK-NAPPP-104062-CS-CQS Consultant / Sri Jayawardena Pura Open - IBRD / 89070 Post Qualification 0.00 Canceled 2019-05-19 2019-05-19 2019-07-08 2019-08-12 2019-08-19 2020-02-15 University- Environmental International Selection and Social Assessment LK-NAPPP-103562-CS-CQS Consultant Open - Pending / Marine Drive Extension- IBRD / 89070 Post Qualification 0.00 2020-12-08 2020-12-08 2021-02-05 2021-03-12 2021-03-19 2023-03-19 International Implementation Legal Consultancy Selection LK-NAPPP-104093-CS-CQS Consultant Open - Pending / Convention Centre Port IBRD / 89070 Post Qualification 0.00 2020-10-12 2020-10-12 2020-12-01 2021-01-05 2021-01-12 2023-01-12 International Implementation City - legal consultancy Selection Page 2 LK-NAPPP-104102-CS-CQS Consultant Open - Pending / Medical Complex Port City IBRD / 89070 Post Qualification 0.00 2020-10-12 2020-10-12 2020-12-01 2021-01-05 2021-01-12 2023-01-12 International Implementation - legal consultancy Selection LK-NAPPP-104107-CS-CQS Consultant Open - Pending / School at Port City - legal IBRD / 89070 Post Qualification 0.00 2020-10-12 2020-10-12 2020-12-01 2021-01-05 2021-01-12 2023-01-12 International Implementation consultancy Selection LK-NAPPP-114009-CS-CQS Consultant / Beira Lake and Kandy Open - Pending IBRD / 89070 Post Qualification 0.00 2019-12-11 2019-12-11 2020-01-30 2020-03-05 2020-03-12 2020-04-17 Mahaiyawe Housing Projects International Implementation Selection - Feasibility Studies LK-NAPPP-114015-CS-CQS Consultant / NHDA Bambalapitiya Flats Open - Pending IBRD / 89070 Post Qualification 0.00 2019-12-11 2019-12-11 2020-01-30 2020-03-05 2020-03-12 2021-03-12 and Mindupura Housing International Implementation Selection Projects- Feasibility Studies LK-NAPPP-114018-CS-CQS Consultant / PPP for GOSL Buildings Open - Pending IBRD / 89070 Post Qualification 0.00 2020-05-11 2020-05-11 2020-06-30 2020-08-04 2020-08-11 2021-04-08 (University of Moratuwa) - International Implementation Selection Feasbility Studies LK-NAPPP-114021-CS-QBS / Kahatagaha Graphite Quality Based Open - Pending IBRD / 89070 Post 0.00 2019-11-11 2019-11-11 2019-12-31 2020-02-11 2020-03-03 2020-03-17 2020-04-02 2020-11-28 (Value Addition) - Feasbility Selection International Implementation Stuides LK-NAPPP-114028-CS-CQS Consultant Open - Pending / Kahatagaha Graphite IBRD / 89070 Post Qualification 0.00 2021-03-10 2021-03-10 2021-04-29 2021-06-03 2021-06-10 2022-06-10 International Implementation (Value Addition)- Legal Selection Consultancy LK-NAPPP-114033-CS-CQS / Kahatagaha Graphite Consultant Open - Pending (Value Addition)- IBRD / 89070 Post Qualification 0.00 2020-02-19 2020-02-19 2020-04-09 2020-05-14 2020-05-21 2020-11-17 International Implementation Environmental and Social Selection Impact Assessment LK-NAPPP-114036-CS-QBS / Valachchanei Paper Mill ( Quality Based Open - Pending IBRD / 89070 Post 0.00 2019-11-11 2019-11-11 2019-12-31 2020-02-11 2020-03-03 2020-03-17 2020-04-02 2020-09-29 Eastern Province) - Selection International Implementation Feasibilty Studies LK-NAPPP-114038-CS-CQS Consultant / Valachchanei Paper Mill ( Open - Pending IBRD / 89070 Post Qualification 0.00 2021-03-10 2021-03-10 2021-04-29 2021-06-03 2021-06-10 2022-06-10 Eastern Province)- Legal International Implementation Selection Consultancy LK-NAPPP-114039-CS-CQS / Valachchanei Paper Mill ( Consultant Open - Pending Eastern Province)- IBRD / 89070 Post Qualification 0.00 2020-02-19 2020-02-19 2020-04-09 2020-05-14 2020-05-21 2020-11-17 International Implementation Environmental and Social Selection Impact Assessment LK-NAPPP-104092-CS-CQS / Biyagama University Consultant Open - (Berkerley/MIT)- IBRD / 89070 Post Qualification 0.00 Canceled 2020-01-01 2020-01-01 2020-03-09 2020-04-13 2020-04-20 2020-10-17 International Environmental and social Selection assessment LK-NAPPP-103735-CS-QBS / Elevated Expressway NKB to Athurugiriya (Phase 1 Quality Based Open - Pending IBRD / 89070 Post 0.00 2019-09-19 2019-09-19 2019-11-08 2019-12-20 2020-01-10 2020-01-24 2020-02-09 2020-10-06 and Phase 2) - Selection International Implementation Environmental and Social Impact Assessment Page 3 LK-NAPPP-104146-CS-QBS / Pooneryn Renewable Quality Based Open - Pending Energy Park (Wind 350MW IBRD / 89070 Post 0.00 2019-09-19 2019-09-19 2019-11-08 2019-12-20 2020-01-10 2020-01-24 2020-02-09 2020-08-07 Selection International Implementation and 250 MW Solar)- Environmental and social assessment LK-NAPPP-109003-CS-CQS Consultant / 2 x 500 MW LNG Power Open - IBRD / 89070 Post Qualification 0.00 Canceled 2019-08-29 2019-08-29 2019-10-18 2019-11-22 2019-11-29 2020-05-27 Plants- Environmental and International Selection social assessment LK-NAPPP-108994-CS-CQS Consultant / Deployment of FSRU in Open - IBRD / 89070 Post Qualification 0.00 Canceled 2019-09-30 2019-09-30 2019-11-19 2019-12-24 2019-12-31 2020-06-28 Sri Lanka- Environmental International Selection and social assessment LK-NAPPP-108981-CS-CQS / 400 MW LNG Power Plant Consultant and LNG Receiving Terminal Open - IBRD / 89070 Post Qualification 0.00 Canceled 2019-08-19 2019-08-19 2019-10-08 2019-11-12 2019-11-19 2020-05-17 in Hambantota- International Selection Environmental and social assessment LK-NAPPP-108977-CS-QBS / Due Diligence of LNG Power Plants 1.400 MW Quality Based Open - Pending LNG Power Plant and LNG IBRD / 89070 Post 0.00 2019-11-11 2019-11-11 2019-12-31 2020-02-11 2020-03-03 2020-03-17 2020-04-02 2022-04-02 Selection International Implementation Receiving Terminal in Hambantota, 2. 2 x 500 MW LNG Power Plants LK-NAPPP-108899-CS-QBS / Sri Lanka Biotechnology Quality Based Open - Pending IBRD / 89070 Post 0.00 2019-08-22 2019-08-22 2019-10-11 2019-11-22 2019-12-13 2019-12-27 2020-01-12 2021-01-11 Innovation Park - Pitipana Selection International Implementation Homagama - feasibility LK-NAPPP-108896-CS-QBS / Installation of New Crude Oil Refinery at Quality Based Open - Pending IBRD / 89070 Post 0.00 2019-08-22 2019-08-22 2019-10-11 2019-11-22 2019-12-13 2019-12-27 2020-01-12 2020-05-11 Sapugaskanda - review and Selection International Implementation due diligence of the feasibility studies LK-NAPPP-104162-CS-CQS Consultant / Laksala York Street Open - IBRD / 89070 Post Qualification 0.00 Canceled 2020-01-01 2020-01-01 2020-03-09 2020-04-13 2020-04-20 2021-10-12 Building - environmental International Selection and social assessment LK-NAPPP-108772-CS-CQS Consultant / Elevated Expressway NKB Open - Pending IBRD / 89070 Post Qualification 0.00 2019-10-10 2019-10-10 2019-11-29 2020-01-03 2020-01-10 2020-07-08 to Athurugiriya ( P1) - International Implementation Selection Legal Consultancy LK-NAPPP-108775-CS-CQS / Elevated Expressway New Consultant Open - Pending Kelani Bridge to IBRD / 89070 Post Qualification 0.00 2019-10-10 2019-10-10 2019-11-29 2020-01-03 2020-01-10 2021-01-09 International Implementation Athurugiriya (P 2) - Selection Feasibility Studies LK-NAPPP-104021-CS-CQS Consultant / Marine Drive Extension Open - Pending IBRD / 89070 Post Qualification 0.00 2020-05-21 2020-05-21 2020-07-28 2020-09-01 2020-09-08 2021-03-07 Project-Environmental and International Implementation Selection Social Assessment LK-NAPPP-108897-CS-CQS / New Crude Oil refinery at Consultant Open - Sapugaskanda- IBRD / 89070 Post Qualification 0.00 Canceled 2019-09-30 2019-09-30 2019-11-19 2019-12-24 2019-12-31 2020-06-28 International Environmental and social Selection assessment Page 4 LK-NAPPP-108904-CS-CQS / Sri Lanka Biotechnology Consultant Open - Pending Innovation Park - Pitipana IBRD / 89070 Post Qualification 0.00 2020-03-01 2020-03-01 2020-04-20 2020-05-25 2020-06-01 2020-11-28 International Implementation Homagama- Environmental Selection and social assessment LK-NAPPP-104038-CS-CQS Consultant / Kalpitiya desalination Open - Pending IBRD / 89070 Post Qualification 0.00 2020-05-19 2020-05-19 2020-07-26 2020-08-30 2020-09-06 2021-03-05 project- Environmental and International Implementation Selection social Impact assessment LK-NAPPP-104053-CS-CQS Consultant / Gampaha Waste Water Open - Pending IBRD / 89070 Post Qualification 0.00 2020-05-19 2020-05-19 2020-07-26 2020-08-30 2020-09-06 2021-03-05 Project- Environmental and International Implementation Selection social assessment LK-NAPPP-104148-CS-CQS / Social Survey- 1.Pooneryn Renewable Consultant Energy Park for the Pending IBRD / 89070 Post Qualification Open - National 0.00 2020-05-10 2020-05-10 2020-06-29 2020-08-03 2020-08-10 2021-02-06 Transmission line extending Implementation Selection from Pooneryn to Vavuniya 2.Gampaha waste water project LK-NAPPP-104089-CS-CQS / Environmental and social Consultant Open - Pending assessment- IBRD / 89070 Post Qualification 0.00 2020-07-19 2020-07-19 2020-09-07 2020-10-12 2020-10-19 2021-04-17 International Implementation 1. PPP for GOSL Buildings Selection (university of Moratuwa), LK-NAPPP-104058-CS-CQS / Building of Sri Consultant Open - Jayawardena Pura IBRD / 89070 Post Qualification 0.00 Canceled 2019-05-01 2019-05-01 2019-06-29 2019-08-03 2019-08-10 2021-08-09 International University-Legal consultancy Selection for drafting documentation LK-NAPPP-104151-CS-CQS / Assessment and Consultant Open - Pending development of a Roof Top IBRD / 89070 Post Qualification 0.00 2020-05-10 2020-05-10 2020-06-29 2020-08-03 2020-08-10 2022-08-10 International Implementation Solar development framework Selection for Sri Lanka LK-NAPPP-114383-CS-CQS Consultant Open - Pending / Tech City Project IBRD / 89070 Post Qualification 0.00 2020-03-10 2020-03-10 2020-04-29 2020-06-03 2020-06-10 2021-06-10 International Implementation Feasibility Studies Selection LK-NAPPP-104099-CS-CQS / Port City - Environmental Consultant Open - Pending and social assessment for IBRD / 89070 Post Qualification 0.00 2020-01-19 2020-01-19 2020-03-09 2020-05-25 2020-06-10 2020-12-07 International Implementation Convention Centre, Medical Selection Centre, School at Port City LK-NAPPP-104097-CS-CQS Consultant Open - Pending / Convention Centre Port IBRD / 89070 Post Qualification 0.00 2019-09-10 2019-09-10 2019-10-30 2019-12-04 2019-12-11 2020-12-10 International Implementation City - Feasibility Studies Selection LK-NAPPP-104105-CS-CQS Consultant Open - Pending / Medical Complex Port City IBRD / 89070 Post Qualification 0.00 2019-09-10 2019-09-10 2019-10-30 2019-12-04 2019-12-11 2020-12-10 International Implementation - Feasibility Selection LK-NAPPP-104110-CS-CQS Consultant Open - Pending / School at Port City - IBRD / 89070 Post Qualification 0.00 2019-09-10 2019-09-10 2019-10-30 2019-12-04 2019-12-11 2020-12-10 International Implementation Feasibility Study Selection LK-NAPPP-104156-CS-CQS / Kandy Mahaiyawa Urban Consultant Open - Pending Housing Project- IBRD / 89070 Post Qualification 0.00 2020-02-19 2020-02-19 2020-04-09 2020-05-14 2020-05-21 2020-11-17 International Implementation Environmental and social Selection assessment Page 5 LK-NAPPP-104155-CS-CQS / Housing Projects- Environmental and social Consultant Open - Pending assessment for NHDA IBRD / 89070 Post Qualification 0.00 2020-02-19 2020-02-19 2020-04-09 2020-05-14 2020-05-21 2020-11-17 International Implementation Bambalapitiya Flats, Selection Mihindupura and Beira Lake Housing projects LK-NAPPP-105610-CS-QBS / NHDA Bambalapitiya Flats Quality Based Open - IBRD / 89070 Post 0.00 Canceled 2019-05-10 2019-05-10 2019-06-29 2019-08-10 2019-08-31 2019-09-14 2019-09-30 2021-09-29 and Mindupura Housing Selection International Projects- transaction advisory LK-NAPPP-108968-CS-CQS / E-Solution for Data Information Management, Spot fine Payment Collection Consultant Open - and Demerit point system IBRD / 89070 Post Qualification 0.00 Canceled 2019-10-21 2019-10-21 2019-12-10 2020-01-14 2020-01-21 2020-07-19 International for Drivers in relation to Selection Traffic Offences (PPP basis) - environmental and social assessment LK-NAPPP-108909-CS-CQS / E-solution for Data and Information Management, Consultant Spot Fine Payment Open - IBRD / 89070 Post Qualification 0.00 Canceled 2019-07-10 2019-07-10 2019-08-29 2019-10-03 2019-10-10 2020-04-07 Collections and Demerit International Selection Points System for Drivers in relation to Traffic Offences (PPP basis) LK-NAPPP-108972-CS-CQS / E-Solution for Data Information Management, Consultant Spot fine Payment Collection Open - IBRD / 89070 Post Qualification 0.00 Canceled 2019-06-10 2019-06-10 2019-07-30 2019-09-03 2019-09-10 2020-05-07 and Demerit point system International Selection for Drivers in relation to Traffic Offences (PPP basis) - Transaction Advisory LK-NAPPP-118961-CS-CQS / Transaction Advisory Consultant Open - Pending Services for seeking a IBRD / 89070 Post Qualification 0.00 2019-08-15 2019-08-15 2019-10-03 2019-11-07 2019-11-14 2020-05-12 International Implementation strategic partner for Sri Selection Lankan Air Lines LK-NAPPP-104935-CS-QBS Quality Based Open - Pending / Desalination Plant in IBRD / 89070 Post 0.00 2020-01-15 2020-01-15 2020-03-26 2020-05-07 2020-05-21 2020-06-25 2020-07-18 2021-07-18 Selection International Implementation Kalpitiya - feasibility LK-NAPPP-105600-CS-QBS / Beira Lake and Mahaiyawe Quality Based Open - Housing Projects - IBRD / 89070 Post 0.00 Canceled 2019-05-10 2019-05-10 2019-06-29 2019-08-10 2019-08-31 2019-09-14 2019-09-30 2021-09-29 Selection International Transaction Advisory Services LK-NAPPP-104048-CS-QBS / Gampaha Waste Water - Quality Based Open - transaction advisory IBRD / 89070 Post 0.00 Canceled 2020-06-18 2020-06-18 2020-08-16 2020-09-27 2020-10-18 2020-11-01 2020-11-17 2022-11-17 Selection International (financial, legal and technical) LK-NAPPP-104930-CS-QBS / Marine Drive Extension Project - Feasibility Study Quality Based Open - Pending IBRD / 89070 Post 0.00 2019-10-12 2019-10-12 2019-12-22 2020-02-02 2020-02-16 2020-03-22 2020-04-14 2020-12-10 (technical, commercial, Selection International Implementation geotechnical survey, E&S and financial due diligence) Page 6 LK-NAPPP-104030-CS-CQS Consultant / Transit Smart Card - Open - IBRD / 89070 Post Qualification 0.00 Canceled 2020-01-16 2020-01-16 2020-03-06 2020-04-10 2020-04-17 2021-04-17 transaction advisory (legal, International Selection financial, technical) LK-NAPPP-104033-CS-CQS / Kalpitiya Desalination - Quality Based Open - transaction advisory IBRD / 89070 Post 0.00 Canceled 2020-06-18 2020-06-18 2020-08-16 2020-09-27 2020-10-18 2020-11-01 2020-11-17 2022-11-17 Selection International (financial, legal and technical) LK-NAPPP-103741-CS-QBS / Elevated Expressway New Kelani Bridge to Quality Based Open - Athurugiriya (Phase 2) - IBRD / 89070 Post 0.00 Canceled 2020-04-27 2020-04-27 2020-06-25 2020-08-06 2020-08-27 2020-09-10 2020-09-26 2023-03-15 Selection International Transaction Advisory services (technical, commercial, financial and legal) LK-NAPPP-108905-CS-QBS / Sri Lanka Biotechnology Quality Based Open - Innovation Park - Pitipana IBRD / 89070 Post 0.00 Canceled 2020-03-30 2020-03-30 2020-05-19 2020-06-30 2020-07-21 2020-08-04 2020-08-20 2022-08-20 Selection International Homagama - transaction advisory LK-NAPPP-104070-CS-CQS / PPP for GOSL Buildings Consultant (University of Moratuwa) - Open - IBRD / 89070 Post Qualification 0.00 Canceled 2019-05-01 2019-05-01 2019-06-29 2019-08-03 2019-08-10 2021-08-09 Transaction Advisory (legal International Selection consultancy, technical and financial) LK-NAPPP-104157-CS-QBS Quality Based Open - / Tech City Projects - IBRD / 89070 Post 0.00 Canceled 2020-01-01 2020-01-01 2020-02-29 2020-04-11 2020-05-02 2020-05-16 2020-06-01 2022-06-01 Selection International transaction advisory LK-NAPPP-108997-CS-QBS / 2 x 500 MW LNG Power Quality Based Open - IBRD / 89070 Post 0.00 Canceled 2019-05-27 2019-05-27 2019-07-16 2019-08-27 2019-09-17 2019-10-01 2019-10-17 2021-10-16 Plants - due diligence and Selection International transaction negotiation LK-NAPPP-104160-CS-CQS Consultant / Laksala York Street Open - IBRD / 89070 Post Qualification 0.00 Canceled 2020-01-01 2020-01-01 2020-02-29 2020-04-04 2020-04-11 2021-10-03 Building - transaction International Selection advisory LK-NAPPP-108898-CS-QBS / Installation of New Crude Oil Refinery at Quality Based Open - IBRD / 89070 Post 0.00 Canceled 2020-04-20 2020-04-20 2020-06-09 2020-07-21 2020-08-11 2020-08-25 2020-09-10 2023-02-27 Sapugaskanda - transaction Selection International advisory (financial, technical, legal) LK-NAPPP-104158-CS-CQS Consultant / Tech City Projects - Open - IBRD / 89070 Post Qualification 0.00 Canceled 2020-06-19 2020-06-19 2020-08-26 2020-09-30 2020-10-07 2021-04-05 environmental and social International Selection assessment LK-NAPPP-104024-CS-CQS Consultant Open - / Transit Smart Card - IBRD / 89070 Post Qualification 0.00 Canceled 2019-08-12 2019-08-12 2019-10-01 2019-11-05 2019-11-12 2020-05-10 International feasibility Selection LK-NAPPP-104937-CS-QBS / Waste Water Treatment Quality Based Open - Pending IBRD / 89070 Post 0.00 2019-08-10 2019-08-10 2019-10-20 2019-12-01 2019-12-15 2020-01-19 2020-02-11 2021-02-10 Plant in Gampaha - Selection International Implementation feasibility study Page 7 LK-NAPPP-105963-CS-QBS / Assessment of the fiscal Quality Based Open - IBRD / 89070 Post 0.00 Canceled 2019-08-12 2019-08-12 2019-10-01 2019-11-12 2019-12-03 2019-12-17 2020-01-02 2021-01-01 exposure from the LRT Selection International projects LK-NAPPP-120175-CS-CQS Consultant / Assessment of the fiscal Open - Pending IBRD / 89070 Post Qualification 0.00 2019-08-12 2019-08-12 2019-10-01 2019-11-05 2019-11-12 2019-11-15 exposure from the LRT International Implementation Selection projects INDIVIDUAL CONSULTANTS Page 8