Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan [Original: April 2012]: Revision 6 of Updated Procurement Plan, December 2016] 2. Date of General Procurement Notice: April 13, 2012 3. Period covered by this procurement plan: The procurement period of project covered from year January to December 2018 II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Type of procurement Substantial risk Mandatory Prior Methods review thresholds thresholds (US$ (US$ millions) millions) Works (including turnkey, supply & ICB ≥ 5 10 installation of plant and equipment, NCB < 5 and PPP) RfQ < 0.2 Goods, information technology and ICB ≥ 1 2 non-consulting services NCB < 1 RfQ<0.1 2. Prequalification. Bidders for _Not applicable_ shall be prequalified in accordance with the provisions of paragraphs 2.9 and 2.10 of the Guidelines. 3. Reference to (if any) Project Operational/Procurement Manual: Project Implementation Manual for World Bank Loan Project IDA-H7270 November 2015 issued by Bagre Growth 4. Any Other Special Procurement Arrangements: not applicable 5. Summary of the Procurement Packages 1 2 3 4 5 6 7 Ref. Description Estimate Packages Dome Review Commen No. d stic by Bank ts Cost Prefer (Prior / US$ ence Post) million February 21st, 2018 (yes/n o) Summary of the NCB 3.4 6 No Post (Works) Summary of the NCB 1.7 6 No Post (Goods) III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Type of procurement Substantial risk Mandatory Prior Methods review thresholds thresholds (US$ (US$ millions) millions) Consultants: firms CQ< 0.3 1 Consultants: individuals No threshold 0.3 2. Short list comprising entirely of national consultants: Short list of consulting services, estimated to cost less than $ 200,000 or for Engineering & Construction supervision ≦ $400.000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: not applicable 4. Consultancy Assignments with Selection Methods 1 2 3 4 5 6 Ref. No. Description of Estimate Packages Review Comments Assignment d by Bank Cost (Prior / US$ Post) million Summary of number of 3 12 All post contracts that will be let review under QCBS - FBS - LCS Summary of number of 0.6 6 Post CQS contracts that will be let under other methods February 21st, 2018 PROCUREMENT Burkina Faso : Burkina Faso - Bagre Growth Pole Project PLAN General Information Country: Burkina Faso Bank’s Approval Date of the Original Procurement Plan: 2017-10-16 2020-02-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P119662 GPN Date: Project Name: Burkina Faso - Bagre Growth Pole Project Loan / Credit No: IDA / H7270, IDA / 61840 Executing Agency(ies): Bagre Growth Pole WORKS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PPCB-26257-CW-RFB / Construction de parcs de Development of Critical Single Stage - One En attente IDA / H7270 A posteriori Appel d'offres Open - National 1,414,000.00 0.00 2017-12-10 2017-12-15 2018-01-14 2018-01-24 2018-02-07 2018-07-07 vaccination, magasins, Infrastructure Envelope d'exécution d'aires de séchages (lots 1,2,3 et 4) BF-PPCB-26309-CW-DIR / Passation de Development of Critical En attente Extension du réseau IDA / H7270 A posteriori marché de gré à Direct 100,000.00 0.00 2017-09-30 2017-10-05 2017-11-09 2018-05-08 Infrastructure d'exécution électrique à Bagré gré BF-PPCB-26313-CW-RFB / Réalisation des travaux de Development of Critical Single Stage - One En attente mise en place d'un système IDA / H7270 A posteriori Appel d'offres Open - National 370,000.00 0.00 2017-11-15 2017-11-20 2017-12-20 2017-12-30 2018-01-20 2018-06-19 Infrastructure Envelope d'exécution de protection du canal primaire contre les noyades BF-PPCB-26185-CW-RFB / Entretien des infrastructures Development of Critical Single Stage - One En cours IDA / H7270 A posteriori Appel d'offres Open - National 360,000.00 0.00 2017-06-01 2017-06-06 2017-07-06 2017-07-20 2017-08-10 2018-08-05 hydrauliques et de Infrastructure Envelope d'exécution désenclavement BF-PPCB-26295-CW-RFB / travaux d'aménagement des Development of Critical Single Stage - One En attente IDA / H7270 A posteriori Appel d'offres Open - National 500,000.00 0.00 2017-10-15 2017-10-20 2017-11-19 2017-11-29 2017-12-20 2018-04-19 zones pastorales de Infrastructure Envelope d'exécution Doubégué et de Tcherbo Improvement of BF-PPCB-50696-CW-RFQ / institutional capacity for Travaux de reboisement et Single Stage - One En attente IDA / H7270 better zone management A posteriori Demande de prix Limited 160,000.00 0.00 2018-05-06 2018-07-01 2018-09-29 de protection des berges du Envelope d'exécution and investment climate in Nakanbé the Project Area BF-PPCB-26294-CW-RFB / Travaux d’assainissement collectif de la Cité de Bagrépôle et de construction Development of Critical Single Stage - One IDA / H7270 A posteriori Appel d'offres Open - National 200,000.00 0.00 Annulé 2018-02-15 2018-02-20 2018-03-22 2018-04-01 2018-04-22 2018-08-20 de deux dalots entre la cité Infrastructure Envelope ouvrière et le Centre écotouristique (CET) de Bagré BF-PPCB-26266-CW-RFB / construction d’infrastructures socio-économique Development of Critical Single Stage - One IDA / H7270 A posteriori Appel d'offres Open - National 520,000.00 0.00 Annulé 2017-09-25 2017-09-30 2017-10-30 2017-11-09 2017-11-30 2018-03-30 économiques au profit de Infrastructure Envelope toutes les PAP (lots 1  et 2) Improvement of BF-PPCB-50694-CW-RFB / institutional capacity for Construction de latrines au Single Stage - One IDA / H7270 better zone management A posteriori Appel d'offres Open - National 240,000.00 0.00 Annulé 2018-03-15 2018-03-20 2018-04-19 2018-05-03 2018-05-24 2018-09-21 profit des Personnes affectés Envelope and investment climate in par le projet the Project Area BF-PPCB-86969-CW-RFB / Development of Critical Open - Single Stage - One En cours Travaux de construction de IDA / 61840 A priori Appel d'offres 21,000,000.00 0.00 2019-03-25 2019-03-30 2019-05-14 2019-06-13 2019-07-04 2020-09-26 Infrastructure International Envelope d'exécution routes bitumées BF-PPCB-86976-CW-RFB / Development of Critical Open - Single Stage - One En cours Travaux de construction de IDA / 61840 A posteriori Appel d'offres 9,400,000.00 0.00 2019-03-25 2019-03-30 2019-05-14 2019-05-29 2019-06-19 2020-12-10 Infrastructure International Envelope d'exécution routes en terres et pistes BF-PPCB-105136-CW-RFB / entretien des ouvrages Development of Critical Single Stage - One En attente IDA / 61840 A posteriori Appel d'offres Open - National 300,000.00 0.00 2019-03-25 2019-03-30 2019-04-29 2019-05-06 2019-05-20 2020-05-19 hydraulique et de Infrastructure Envelope d'exécution désenclavement Page 1 BF-PPCB-105148-CW-RFQ / Improvement of construction de clôture institutional capacity for grillagée pour la réalisation Single Stage - One En attente IDA / 61840 better zone management A posteriori Demande de prix Limited 40,000.00 0.00 2019-04-06 2019-05-03 2019-07-02 pour les travaux de Envelope d'exécution and investment climate in reboisement et de protection the Project Area des berge du Nakanbé BF-PPCB-126467-CW-RFB / Strengthening Travaux de construction des Single Stage - One En attente IDA / 61840 Entrepreneurship in A posteriori Appel d'offres Open - National 200,000.00 0.00 2019-08-30 2019-09-04 2019-10-04 2019-10-11 2019-11-01 2020-03-30 infrastructures socio- Envelope d'exécution Agribusiness économiques BF-PPCB-132926-CW-RFB / travaux de construction Strengthening d'abris sur les périmètres Single Stage - One En attente IDA / 61840 Entrepreneurship in A posteriori Appel d'offres Open - National 240,000.00 0.00 2019-09-20 2019-09-25 2019-10-25 2019-11-01 2019-11-18 2020-01-17 aménagés au profit des Envelope d'exécution Agribusiness personnes affectées par le Projet BF-PPCB-133537-CW-DIR / Réalisation de ralentisseurs au niveau des pistes secondaires, de garde-corps, de garde-fous, de balises au Passation de Development of Critical En attente niveau des zones IDA / H7270 A posteriori marché de gré à Direct 282,000.00 0.00 2019-09-10 2019-09-15 2019-09-28 2019-11-27 Infrastructure d'exécution dangereuse du canal et de gré bouées de sauvetage (biefs F et G) pour le renforcement du dispositif contre les noyades BF-PPCB-133489-CW-DIR / Réalisation de ralentisseurs au niveau des pistes secondaires, de garde-corps, de garde-fous, de balises au Passation de Development of Critical En attente niveau des zones IDA / H7270 A posteriori marché de gré à Direct 394,503.00 0.00 2019-09-09 2019-09-10 2019-09-19 2019-11-18 Infrastructure d'exécution dangereuse du canal et de gré bouées de sauvetage (bief H et I) pour le renforcement du dispositif contre les noyades BF-PPCB-137122-CW-DIR / construction d’une travée Passation de transformateur 132/33 kV Development of Critical IDA / 61840 A priori marché de gré à Direct 3,000,000.00 0.00 Annulé 2019-10-31 2019-11-21 2019-12-02 2021-01-25 de 16/25 MVA pour Infrastructure gré l'extension du réseau électrique BF-PPCB-155573-CW-RFQ / réalisation et pose de Development of Critical Single Stage - One En attente balises pour la IDA / 61840 A posteriori Demande de prix Limited 40,000.00 0.00 2020-02-25 2020-03-27 2020-06-25 Infrastructure Envelope d'exécution délimitation des périmètres aménagés BF-PPCB-87287-CW-RFB / Development of Critical Single Stage - One Extension du réseau IDA / 61840 A posteriori Appel d'offres Open - National 3,520,000.00 0.00 Annulé 2019-09-30 2019-10-05 2019-11-04 2019-11-11 2019-11-28 2020-11-22 Infrastructure Envelope électrique GOODS Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PPCB-26119-GO-RFB / Acquisition d'engrais pour Development of Critical Single Stage - One En cours l'appui des PAP à la mise IDA / H7270 Services and direct support A posteriori Appel d'offres Open - National 540,000.00 0.00 2017-10-15 2017-10-20 2017-11-19 2017-11-29 2017-12-27 2018-02-25 Envelope d'exécution en exploitation des terres to smallholders and SMEs aménagées Improvement of BF-PPCB-26437-GO-RFQ / institutional capacity for Acquisition de mobiliers Single Stage - One En attente IDA / H7270 better zone management A posteriori Demande de prix Limited 62,000.00 0.00 2017-03-06 2017-04-17 2017-06-16 de bureau et d’armoires de Envelope d'exécution and investment climate in rangements the Project Area Improvement of BF-PPCB-26421-GO-RFQ / institutional capacity for Single Stage - One Fourniture de service d’accès IDA / H7270 better zone management A posteriori Demande de prix Limited 70,000.00 57,062.41 Signé 2017-03-20 2017-05-15 2017-06-14 Envelope internet and investment climate in the Project Area Page 2 BF-PPCB-26436-GO-RFB / Improvement of Acquisition de matières institutional capacity for Single Stage - One En cours premières pour la IDA / H7270 better zone management A posteriori Appel d'offres Open - National 98,790.00 0.00 2017-03-10 2017-03-15 2017-04-14 2017-04-28 2017-06-02 2017-11-29 Envelope d'exécution production piscicole au profit and investment climate in du CEP de Bagrépôle the Project Area BF-PPCB-26435-GO-RFB / Improvement of Production et diffusion institutional capacity for Single Stage - One En attente d'outils de communication IDA / H7270 better zone management A posteriori Appel d'offres Open - National 164,000.00 0.00 2017-09-01 2017-09-06 2017-10-06 2017-10-13 2017-11-03 2018-01-02 Envelope d'exécution et d’édition de documents and investment climate in au profit du CNPPC the Project Area BF-PPCB-26270-GO-RFQ / Improvement of fourniture de services institutional capacity for Single Stage - One d'assurance santé au profit IDA / H7270 better zone management A posteriori Demande de prix Limited 98,000.00 84,780.64 Signé 2017-06-06 2017-07-18 2018-07-13 Envelope du personnel et de véhicules and investment climate in automobiles de Bagrépôle the Project Area Improvement of BF-PPCB-26307-GO-RFB / institutional capacity for Acquisition 04 véhicules 4X4 Single Stage - One En cours IDA / H7270 better zone management A posteriori Appel d'offres Open - National 264,000.00 0.00 2017-03-01 2017-03-06 2017-04-05 2017-04-19 2017-05-10 2017-07-09 Pick up double cabine et Envelope d'exécution and investment climate in une station WAGON the Project Area Improvement of BF-PPCB-26296-GO-DIR / institutional capacity for Passation de En cours Mise à jour du logiciel IDA / H7270 better zone management A posteriori marché de gré à Direct 80,000.00 0.00 2017-08-15 2017-08-20 2017-09-24 2017-11-23 d'exécution TOM2PRO and investment climate in gré the Project Area BF-PPCB-26284-GO-RFQ / Acquisition de produits Improvement of vétérinaires ,de sous- institutional capacity for Single Stage - One En attente produits agro industriels IDA / H7270 better zone management A posteriori Demande de prix Limited 54,000.00 0.00 2017-09-25 2017-10-31 2017-12-30 Envelope d'exécution (SPAI) et de Semences and investment climate in fourragères pour l’appui the Project Area aux PAP éleveurs Improvement of BF-PPCB-26297-GO-RFB / institutional capacity for Single Stage - One En cours Acquisition de copieurs et IDA / H7270 better zone management A posteriori Appel d'offres Open - National 80,000.00 0.00 2016-10-01 2016-10-06 2016-11-05 2016-11-15 2016-12-06 2017-02-04 Envelope d'exécution d’équipements informatiques and investment climate in the Project Area BF-PPCB-26353-GO-RFQ / Improvement of Acquisition de fournitures institutional capacity for Single Stage - One En cours de bureau, produits IDA / H7270 better zone management A posteriori Demande de prix Limited 80,000.00 0.00 2017-03-06 2017-04-10 2017-10-07 Envelope d'exécution d’entretien, d’encres et de and investment climate in petits matériels et outillages the Project Area Improvement of BF-PPCB-26405-GO-RFQ / institutional capacity for Single Stage - One En attente Mise en place d’un système IDA / H7270 better zone management A posteriori Demande de prix Limited 10,000.00 0.00 2017-09-05 2017-10-08 2017-11-07 Envelope d'exécution audio conférence and investment climate in the Project Area Improvement of BF-PPCB-26415-GO-RFQ / institutional capacity for Single Stage - One En cours Acquisition et l’installation IDA / H7270 better zone management A posteriori Demande de prix Limited 50,000.00 0.00 2017-09-05 2017-10-10 2017-12-09 Envelope d'exécution d’un groupe électrogène and investment climate in the Project Area BF-PPCB-26434-GO-RFQ / Improvement of Acquisition de petits institutional capacity for Single Stage - One En attente matériels pour la production IDA / H7270 better zone management A posteriori Demande de prix Limited 40,000.00 0.00 2017-08-20 2017-10-01 2017-10-31 Envelope d'exécution piscicole au profit du CEP and investment climate in de Bagrépôle the Project Area BF-PPCB-26443-GO-RFQ / Improvement of Mise en place d'un système institutional capacity for Single Stage - One d'optimisation de la bande IDA / H7270 better zone management A posteriori Demande de prix Limited 16,000.00 0.00 Annulé 2017-09-15 2017-10-20 2017-11-19 Envelope passante et de cryptage de and investment climate in données the Project Area Improvement of BF-PPCB-50704-GO-RFQ / institutional capacity for Interconnections des sites Single Stage - One En attente IDA / H7270 better zone management A posteriori Demande de prix Limited 17,000.00 0.00 2018-06-20 2018-07-25 2018-09-23 du PEP et de l’IFODER au Envelope d'exécution and investment climate in siège de Bagrépôle the Project Area Page 3 BF-PPCB-50701-GO-RFQ / Improvement of Acquisition de matériel institutional capacity for Single Stage - One En attente informatique et mise en IDA / H7270 better zone management A posteriori Demande de prix Limited 64,000.00 0.00 2018-05-06 2018-06-10 2018-09-08 Envelope d'exécution place d'un système Visio- and investment climate in conférence the Project Area Improvement of BF-PPCB-50693-GO-RFQ / institutional capacity for Acquisition d’équipements Single Stage - One En attente IDA / H7270 better zone management A posteriori Demande de prix Limited 30,000.00 0.00 2018-03-20 2018-04-24 2018-07-23 techniques au profit de la Envelope d'exécution and investment climate in radio Bagrépôle FM the Project Area Improvement of BF-PPCB-50702-GO-RFQ / institutional capacity for Single Stage - One En attente Entretien et réparation de IDA / H7270 better zone management A posteriori Demande de prix Limited 30,000.00 0.00 2018-03-20 2018-04-24 2019-04-24 Envelope d'exécution matériel roulant and investment climate in the Project Area BF-PPCB-66888-GO-DIR / Improvement of acquisition, paramétrage du institutional capacity for Passation de En attente module TOM Monitoring du IDA / H7270 better zone management A posteriori marché de gré à Direct 50,000.00 0.00 2018-06-30 2018-07-05 2018-07-26 2018-09-24 d'exécution logiciel TOM2PRO et and investment climate in gré formation des utilisateurs the Project Area BF-PPCB-66890-GO-RFQ / Improvement of Mise en place d'un dispositif institutional capacity for Single Stage - One En attente de sécurisation des accès IDA / H7270 better zone management A posteriori Demande de prix Limited 9,000.00 0.00 2018-07-20 2018-08-09 2018-09-08 Envelope d'exécution aux locaux techniques de and investment climate in Bagrépôle the Project Area Improvement of BF-PPCB-66891-GO-RFQ / institutional capacity for Single Stage - One En attente Mise en place d'un système IDA / H7270 better zone management A posteriori Demande de prix Limited 10,000.00 0.00 2018-07-15 2018-08-07 2018-09-06 Envelope d'exécution de sauvegarde des données and investment climate in the Project Area Improvement of BF-PPCB-26419-GO-RFQ / institutional capacity for Fourniture et pose de Single Stage - One IDA / H7270 better zone management A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2017-08-30 2017-10-04 2017-11-03 rideaux au siège de Envelope and investment climate in Bagrépôle à Ouagadougou the Project Area Improvement of BF-PPCB-105150-GO-RFB / institutional capacity for Single Stage - One En cours acquisition de matériels IDA / 61840 better zone management A posteriori Appel d'offres Open - National 180,000.00 0.00 2019-04-10 2019-04-15 2019-05-15 2019-05-22 2019-06-12 2019-09-10 Envelope d'exécution roulants and investment climate in the Project Area Improvement of BF-PPCB-105199-GO-RFQ / institutional capacity for Acquisition de pneumatiques Single Stage - One En attente IDA / 61840 better zone management A posteriori Demande de prix Limited 26,000.00 0.00 2019-06-04 2019-07-05 2020-07-04 pour l'entretien des Envelope d'exécution and investment climate in véhicules automobiles the Project Area Improvement of BF-PPCB-105209-GO-RFQ / institutional capacity for service d'assurance du Single Stage - One En attente IDA / 61840 better zone management A posteriori Demande de prix Limited 30,000.00 0.00 2019-07-06 2019-08-10 2020-08-09 matériel roulant du Projet Envelope d'exécution and investment climate in Pôle de Croissance de Bagré the Project Area BF-PPCB-105218-GO-RFQ / Édition du bulletin Investment Promotion and Single Stage - One En attente d'information de Bagrépôle IDA / 61840 A posteriori Demande de prix Limited 24,000.00 0.00 2019-04-06 2019-05-07 2019-12-03 Investment Climate Envelope d'exécution et brochures sur les réalisation du PPCB BF-PPCB-105213-GO-DIR / Improvement of Acquisition de carburant et institutional capacity for Passation de En attente de lubrifiant pour le IDA / 61840 better zone management A posteriori marché de gré à Direct 120,000.00 0.00 2019-03-31 2019-04-05 2019-04-19 2020-04-18 d'exécution fonctionnement du matériel and investment climate in gré roulant du projet the Project Area Improvement of BF-PPCB-105151-GO-RFB / institutional capacity for Équipements informatiques, Single Stage - One IDA / 61840 better zone management A posteriori Appel d'offres Open - National 105,000.00 0.00 Annulé 2019-04-10 2019-04-15 2019-05-15 2019-05-29 2019-06-12 2019-08-11 licences, antivirus et Envelope and investment climate in mobiliers de bureau the Project Area BF-PPCB-132836-GO-RFQ / Improvement of Acquisition de 09 motos au institutional capacity for Single Stage - One En attente profit des patrouilles IDA / H7270 better zone management A posteriori Demande de prix Limited 25,000.00 0.00 2019-09-16 2019-10-09 2019-10-12 Envelope d'exécution mobiles pour la prévention and investment climate in des noyades the Project Area Page 4 BF-PPCB-133102-GO-RFQ / Investment Promotion and Single Stage - One En attente impression du document sur IDA / 61840 A posteriori Demande de prix Limited 50,000.00 0.00 2019-09-28 2019-10-21 2019-12-20 Investment Climate Envelope d'exécution le cadre foncier BF-PPCB-133105-GO-RFB / Acquisition d'équipements Investment Promotion and Single Stage - One En attente pour la gestion informatisée IDA / 61840 A posteriori Appel d'offres Open - National 100,000.00 0.00 2019-09-30 2019-10-05 2019-11-16 2019-12-16 2020-01-20 2020-07-18 Investment Climate Envelope d'exécution et géo-référencière du système de régime foncier BF-PPCB-133117-GO-RFQ / production et diffusion Investment Promotion and Single Stage - One En attente d'outils de communication IDA / 61840 A posteriori Demande de prix Limited 50,000.00 0.00 2019-09-23 2019-10-18 2019-12-17 Investment Climate Envelope d'exécution au profit de Bagrépôle et de l'A.B.I BF-PPCB-105217-GO-RFB / Production et diffusion Investment Promotion and Single Stage - One d'outils de communication IDA / 61840 A posteriori Appel d'offres Open - National 166,000.00 0.00 Annulé 2019-05-30 2019-06-04 2019-07-04 2019-07-11 2019-08-01 2019-12-29 Investment Climate Envelope au profit de l'ABI et de Bagrépôle BF-PPCB-105219-GO-RFB / acquisition de logiciel de Investment Promotion and Single Stage - One IDA / 61840 A posteriori Appel d'offres Open - National 90,000.00 0.00 Annulé 2019-08-01 2019-08-06 2019-09-05 2019-09-12 2019-10-03 2019-12-02 suivi des investisseurs au Investment Climate Envelope profit de l'ABI Improvement of BF-PPCB-133138-GO-RFQ / institutional capacity for Acquisition d'équipements Single Stage - One En attente IDA / 61840 better zone management A posteriori Demande de prix Limited 70,000.00 0.00 2019-09-13 2019-10-04 2019-12-03 informatiques et mobilier de Envelope d'exécution and investment climate in bureau au profit de l'ABI the Project Area BF-PPCB-133559-GO-RFQ / Acquisition de mobiliers de Strengthening Single Stage - One En attente bureau au profit de la IDA / 61840 Entrepreneurship in A posteriori Demande de prix Limited 33,000.00 0.00 2019-10-03 2019-10-24 2019-12-23 Envelope d'exécution Direction Générale des Agribusiness Impôts BF-PPCB-133562-GO-RFQ / Acquisition de fournitures Strengthening Single Stage - One En attente de bureau au profit de la IDA / 61840 Entrepreneurship in A posteriori Demande de prix Limited 7,000.00 0.00 2019-09-18 2019-10-07 2019-11-06 Envelope d'exécution direction générale des Agribusiness impôts BF-PPCB-133566-GO-RFQ / Acquisition de matériels Strengthening Single Stage - One En attente topographiques au profit de IDA / 61840 Entrepreneurship in A posteriori Demande de prix Limited 86,400.00 0.00 2019-10-03 2019-10-24 2019-12-23 Envelope d'exécution la direction générale des Agribusiness impôts BF-PPCB-133567-GO-RFQ / Acquisition de registres et Strengthening Single Stage - One En attente d'imprimés sur le foncier au IDA / 61840 Entrepreneurship in A posteriori Demande de prix Limited 58,800.00 0.00 2019-10-03 2019-10-26 2019-11-25 Envelope d'exécution profit de la Direction Agribusiness Générale des Impôts BF-PPCB-133576-GO-DIR / Mise en place d’un système Passation de de flotteurs ou de bouées de Development of Critical En attente IDA / 61840 A posteriori marché de gré à Direct 20,000.00 0.00 2019-09-20 2019-09-25 2019-10-07 2019-12-06 sauvetage le long du canal Infrastructure d'exécution gré primaire au niveau des zones accidentogènes BF-PPCB-133109-GO-RFB / Acquisition d'équipements Improvement of informatiques, de mobilier institutional capacity for Single Stage - One En attente de bureau, licences et IDA / 61840 better zone management A posteriori Appel d'offres Open - National 116,000.00 0.00 2020-02-05 2020-02-08 2020-03-09 2020-03-14 2020-03-31 2020-05-30 Envelope d'exécution antivirus au profit de and investment climate in Bagrépôle de l'ABI et de la the Project Area Direction Général des impôt BF-PPCB-155525-GO-RFQ / Improvement of Acquisition de logiciel de institutional capacity for Single Stage - One En attente gestion compte et de IDA / 61840 better zone management A posteriori Demande de prix Limited 50,000.00 0.00 2020-02-02 2020-02-29 2020-04-14 Envelope d'exécution ressources humaines au and investment climate in profit de l'ABI the Project Area BF-PPCB-105215-GO-RFB / acquisition d'un logiciel de Investment Promotion and Single Stage - One gestion comptable et des IDA / 61840 A posteriori Demande de prix Limited 30,000.00 0.00 Annulé 2019-04-30 2019-05-31 2019-07-30 Investment Climate Envelope ressources humaines au profit de l'ABI Page 5 BF-PPCB-155530-GO-RFB / Fourniture et installation d'une travée transformateur Development of Critical Open - Single Stage - One En attente IDA / 61840 A priori Appel d'offres 3,300,000.00 0.00 2020-02-05 2020-02-19 2020-04-04 2020-04-18 2020-05-23 2021-09-15 132/33 kV de 16/25 MVA Infrastructure International Envelope d'exécution pour l'extension du réseau électrique BF-PPCB-66885-GO-RFQ / Réalisation d'un film Improvement of documentaire (succes story) institutional capacity for sur les leçons à tirer de la Single Stage - One IDA / H7270 better zone management A posteriori Demande de prix Limited 24,000.00 0.00 Annulé 2018-07-05 2018-07-28 2018-08-27 cohabitation des Envelope and investment climate in communautés installées et the Project Area des communautés d'accueil de Biré et de Guirmogo Improvement of BF-PPCB-26282-GO-RFQ / institutional capacity for Acquisition de Botteleuses Single Stage - One IDA / H7270 better zone management A posteriori Demande de prix Limited 48,000.00 0.00 Annulé 2017-09-10 2017-10-16 2017-12-15 pour l’appui aux PAP Envelope and investment climate in éleveurs the Project Area Improvement of BF-PPCB-132842-GO-RFQ / institutional capacity for Acquisition de drone équipée Single Stage - One En attente IDA / H7270 better zone management A posteriori Appel d'offres Open - National 120,000.00 0.00 2020-02-14 2020-02-19 2020-03-20 2020-03-27 2020-04-17 2020-06-16 pour la surveillance du Envelope d'exécution and investment climate in canal primaire the Project Area Improvement of BF-PPCB-132869-GO-RFQ / institutional capacity for Outils de sensibilisation et Single Stage - One En attente IDA / 61840 better zone management A posteriori Demande de prix Limited 10,000.00 0.00 2020-02-03 2020-03-01 2020-03-31 de communication sur la Envelope d'exécution and investment climate in prévention des noyades the Project Area BF-PPCB-105190-GO-RFB / Matériels pour l'équipement Development of Critical Single Stage - One En attente des unités de transformation IDA / 61840 Services and direct support A posteriori Appel d'offres Open - National 200,000.00 0.00 2020-02-10 2020-02-15 2020-03-16 2020-03-23 2020-04-13 2020-06-12 Envelope d'exécution au profit des personnes to smallholders and SMEs affectées par le projet BF-PPCB-26265-GO-RFB / Improvement of Acquisition d'équipements de institutional capacity for Single Stage - One production et de IDA / H7270 better zone management A posteriori Appel d'offres Open - National 600,000.00 0.00 Annulé 2017-09-15 2017-09-20 2017-10-20 2017-10-30 2017-11-20 2018-01-19 Envelope transformation au profit des and investment climate in PAP the Project Area Improvement of BF-PPCB-105205-GO-RFB / institutional capacity for Acquisition d'outils mobiles Single Stage - One En attente IDA / 61840 better zone management A posteriori Demande de prix Limited 100,000.00 0.00 2020-03-15 2020-04-26 2020-07-25 pour la collecte et le suivi Envelope d'exécution and investment climate in des activités the Project Area BF-PPCB-155755-GO-RFB / Acquisition d'équipements Investment Promotion and Single Stage - One En attente pour la gestion informatisée IDA / 61840 A posteriori Demande de prix Limited 100,000.00 0.00 2020-03-21 2020-05-16 2020-07-15 Investment Climate Envelope d'exécution et géo référencée du système de régime foncier NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Pre- Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Prequalification Specific Procurement Bidding Documents Proposal Submission Report and Description Component Review Type Method qualification Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Evaluation Report Notice / Invitation as Issued / Opening / Minutes Recommendation for Documents Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PPCB-26432-NC-RFQ / Improvement of Recrutement d’un prestataire institutional capacity for pour l’appui à l’organsinions Single Stage - One En attente IDA / H7270 better zone management A posteriori Demande de prix Limited 30,000.00 0.00 2017-04-06 2017-05-18 2018-05-13 des sessions du Comité Envelope d'exécution and investment climate in National de Pilotage des the Project Area Pôles de Croissance BF-PPCB-105192-NC-DIR / Development of Critical Passation de En attente mise en place d'un numéro IDA / 61840 Services and direct support A posteriori marché de gré à Direct 50,000.00 0.00 2019-03-31 2019-04-05 2019-04-26 2019-05-26 d'exécution vert d'alerte et de secours to smallholders and SMEs gré BF-PPCB-105194-NC-RFQ / Improvement of service d'appui à institutional capacity for l'organisation des ateliers de Single Stage - One En attente IDA / H7270 better zone management A posteriori Demande de prix Limited 50,000.00 0.00 2019-04-10 2019-05-11 2020-05-10 Bagrépôle et des sessions Envelope d'exécution and investment climate in du Comité National Pilotage the Project Area des Pôles de Croissance Page 6 BF-PPCB-105196-NC-RFQ / services de maintenance et Investment Promotion and Single Stage - One En attente IDA / 61840 A posteriori Demande de prix Limited 24,000.00 0.00 2019-03-30 2019-04-30 2020-04-29 de réparation des Investment Climate Envelope d'exécution climatiseurs BF-PPCB-105197-NC-RFQ / Improvement of services de maintenance et institutional capacity for Single Stage - One En attente de réparation des IDA / 61840 better zone management A posteriori Demande de prix Limited 20,000.00 0.00 2019-06-04 2019-07-05 2020-07-04 Envelope d'exécution équipements informatiques and investment climate in et copieurs the Project Area Improvement of BF-PPCB-105195-NC-RFQ / institutional capacity for service de maintenance et Single Stage - One En attente IDA / 61840 better zone management A posteriori Demande de prix Limited 24,000.00 0.00 2019-05-20 2019-06-20 2020-06-19 de réparation des Envelope d'exécution and investment climate in climatiseurs the Project Area Improvement of BF-PPCB-105201-NC-RFQ / institutional capacity for Services de pause café et de Single Stage - One En attente IDA / 61840 better zone management A posteriori Demande de prix Limited 20,000.00 0.00 2019-04-04 2019-05-05 2020-05-04 restauration au profit de Envelope d'exécution and investment climate in Bagrépôle the Project Area Improvement of BF-PPCB-105203-NC-RFQ / institutional capacity for Services d'entretien et de Single Stage - One En attente IDA / 61840 better zone management A posteriori Demande de prix Limited 30,000.00 0.00 2019-05-10 2019-06-10 2020-06-09 réparation de matériel Envelope d'exécution and investment climate in roulant the Project Area Improvement of BF-PPCB-105212-NC-RFQ / institutional capacity for Single Stage - One En attente Assurance santé du IDA / 61840 better zone management A posteriori Demande de prix Limited 95,000.00 0.00 2019-07-06 2019-08-10 2020-08-09 Envelope d'exécution personnel and investment climate in the Project Area BF-PPCB-133136-NC-RFQ / service d'appui à Improvement of l'organisation de la institutional capacity for cérémonie d'inauguration des Single Stage - One En attente IDA / 61840 better zone management A posteriori Demande de prix Limited 80,000.00 0.00 2019-10-03 2019-10-26 2019-11-25 terres aménagées des 2582 Envelope d'exécution and investment climate in ha et au lancement des the Project Area travaux de construction de routes et pistes Improvement of BF-PPCB-155752-NC-RFQ / institutional capacity for Single Stage - One En attente Service d’entretien et IDA / 61840 better zone management A posteriori Demande de prix Limited 16,000.00 0.00 2020-02-08 2020-03-14 2020-10-10 Envelope d'exécution réparation des climatiseurs and investment climate in the Project Area BF-PPCB-155767-NC-RFQ / Improvement of Services de gardiennage des institutional capacity for Single Stage - One En attente locaux et des équipements IDA / 61840 better zone management A posteriori Demande de prix Limited 60,000.00 0.00 2020-02-03 2020-03-01 2020-11-26 Envelope d'exécution de bagrépôle à Ouagadougou and investment climate in et à Bagré the Project Area CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Interest Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PPCB-14255-CS-QCBS / Improvement of mise en place outils de institutional capacity for Sélection fondée gestion du courrier et d'un En attente IDA / H7270 better zone management A posteriori sur la qualité et Open - National 140,000.00 0.00 2017-09-15 2017-09-29 2017-10-13 2017-11-12 2017-11-26 2017-12-13 2017-12-30 2018-05-29 système d'information de d'exécution and investment climate in le coût suivi évaluation et de the Project Area pilotage BF-PPCB-26288-CS-QCBS / Réalisation des évaluations Improvement of environnementales et Sélection fondée institutional capacity for sociales du mini-marché et sur les En attente IDA / H7270 better zone management A posteriori Open - National 100,000.00 0.00 2017-09-30 2017-10-14 2017-11-07 2017-11-17 2017-12-01 2018-01-30 du centre de formation qualifications des d'exécution and investment climate in professionnelle, des travaux consultants the Project Area de réhabilitation du barrage de Lega ... Improvement of BF-PPCB-26308-CS-QCBS / institutional capacity for Sélection fondée Réalisation de bornage et IDA / H7270 better zone management A posteriori sur la qualité et Open - National 400,000.00 0.00 Annulé 2017-07-01 2017-07-22 2017-09-04 2017-10-04 2017-10-11 2017-11-04 2017-11-18 2018-05-17 l’immatriculation des sites and investment climate in le coût aménagés the Project Area Page 7 BF-PPCB-26246-CS-QCBS / Etude d’actualisation de Sélection fondée Development of Critical En cours l’APD et du DAO des IDA / H7270 A posteriori sur la qualité et Open - National 400,000.00 0.00 2017-09-05 2017-09-26 2017-10-13 2017-11-12 2017-11-19 2017-12-13 2017-12-27 2017-12-31 Infrastructure d'exécution travaux de construction de le coût routes et pistes BF-PPCB-26269-CS-QCBS / Etude d'adaptation et suivi contrôle des travaux de Sélection fondée Development of Critical En attente construction de  parcs de IDA / H7270 A posteriori sur la qualité et Open - National 140,000.00 0.00 2017-09-20 2017-10-04 2017-10-21 2017-11-20 2017-11-27 2017-12-21 2018-01-04 2018-08-02 Infrastructure d'exécution vaccination et le coût d'infrastructures au profit des PAP BF-PPCB-26293-CS-CQS / études techniques, Sélection fondée élaboration de DAO et suivi- Development of Critical sur les En cours contrôle des travaux IDA / H7270 A posteriori Open - National 100,000.00 0.00 2017-09-15 2017-09-29 2017-10-23 2017-11-06 2017-11-20 2018-06-18 Infrastructure qualifications des d'exécution d’assainissement collectif de consultants la Cité de Bagrépôle et de construction de dalots Improvement of Sélection fondée BF-PPCB-26355-CS-CQS / institutional capacity for sur les En cours Mise en place d’un service IDA / H7270 better zone management A posteriori Open - National 20,000.00 0.00 2017-06-01 2017-06-22 2017-07-07 2017-08-06 2017-08-20 2017-10-19 qualifications des d'exécution de messagerie électronique and investment climate in consultants the Project Area BF-PPCB-26424-CS-QCBS / Mise en place d’outils de Improvement of gestion automatisée du institutional capacity for Sélection fondée En attente courrier et d’un système IDA / H7270 better zone management A posteriori sur la qualité et Open - National 140,000.00 0.00 2017-07-20 2017-08-10 2017-09-19 2017-10-19 2017-11-02 2017-11-30 2017-12-28 2018-04-27 d'exécution d’information de suivi and investment climate in le coût évaluation et de pilotage de the Project Area Bagrépôle Improvement of Sélection fondée BF-PPCB-26292-CS-CQS / institutional capacity for sur les En attente Réalisation du bilan IDA / H7270 better zone management A posteriori Open - National 100,000.00 0.00 2017-12-15 2017-12-29 2018-02-11 2018-02-25 2018-03-25 2018-05-24 qualifications des d'exécution technique du PPCB and investment climate in consultants the Project Area BF-PPCB-26433-CS-QCBS / Etude technique, d’APD et élaboration de DAO pour la Sélection fondée Development of Critical En attente réalisation des travaux IDA / H7270 A posteriori sur la qualité et Open - National 120,000.00 0.00 2017-09-15 2017-10-06 2017-10-30 2017-11-29 2017-12-13 2018-01-10 2018-02-07 2018-07-07 Infrastructure d'exécution d’aménagement de la Zone le coût industrielle et commerciale de Bagrépôle BF-PPCB-26354-CS-CQS / Sélection fondée Etude technique et suivi Development of Critical sur les En cours contrôle des travaux IDA / H7270 A posteriori Open - National 190,000.00 0.00 2016-11-01 2016-11-22 2017-01-05 2017-02-04 2017-03-11 2017-11-06 Infrastructure qualifications des d'exécution d’aménagement de la zone consultants pastorale BF-PPCB-26271-CS-QCBS / Elaboration d’un dossier technique pour le Sélection fondée recrutement d’un opérateur Development of Critical En cours IDA / H7270 A posteriori sur la qualité et Open - National 416,000.00 0.00 2016-06-01 2016-06-22 2016-08-05 2016-09-04 2016-10-04 2016-11-08 2016-12-13 2017-12-08 privé chargé de la gestion Infrastructure d'exécution le coût de l’eau, de l’entretien des ouvrages hydrauliques et la collecte des redevances BF-PPCB-26302-CS-CQS / Improvement of Réalisation de la situation Sélection fondée institutional capacity for de référence sur les En attente IDA / H7270 better zone management A posteriori Open - National 120,000.00 0.00 2017-08-25 2017-09-08 2017-10-02 2017-10-16 2017-11-02 2018-01-01 environnementale sur l’eau qualifications des d'exécution and investment climate in et l’air en rive gauche du consultants the Project Area Nakambé BF-PPCB-26287-CS-QCBS / Improvement of Actualisation des EIES et institutional capacity for Sélection fondée PAR des travaux de En attente IDA / H7270 better zone management A posteriori sur la qualité et Open - National 400,000.00 0.00 2017-09-30 2017-10-14 2017-10-31 2017-11-30 2017-12-07 2017-12-31 2018-01-14 2018-04-14 construction de routes/pistes d'exécution and investment climate in le coût et d’extension du réseau the Project Area électrique BF-PPCB-32280-CS-QCBS / Etude diagnostique technique de l'ensemble des Sélection fondée dégradations des Development of Critical En attente IDA / H7270 A posteriori sur la qualité et Open - National 400,000.00 0.00 2017-10-16 2017-10-30 2017-11-13 2017-12-13 2017-12-20 2018-01-10 2018-01-24 2018-06-23 aménagements existants à Infrastructure d'exécution le coût Bagré (3380 HA) et évaluation des coûts de réhabilitation Page 8 BF-PPCB-26125-CS-QCBS / Recrutement d'un consultant chargé de l'élaboration d'un Improvement of dossier technique pour le institutional capacity for Sélection fondée recrutement d'un opérateur IDA / H7270 better zone management A posteriori sur la qualité et Open - National 416,000.00 0.00 Annulé 2017-08-24 2017-09-07 2017-09-24 2017-10-24 2017-11-03 2017-12-01 2017-12-15 2018-06-13 privé chargé de la gestion and investment climate in le coût de l'eau, de l'entretien des the Project Area ouvrages hydrauliques et la collecte des redevances BF-PPCB-50667-CS-QCBS / Sélection fondée Actualisation APD et DAO Development of Critical IDA / H7270 A posteriori sur la qualité et Open - National 200,000.00 0.00 Annulé 2018-04-01 2018-04-22 2018-05-13 2018-05-14 2018-05-21 2018-06-18 2018-07-02 2018-10-30 des travaux d'extension du Infrastructure le coût reseau électrique BF-PPCB-50676-CS-QCBS / Bornage, morcellement et Development of Critical Sélection fondée immatriculation des En cours IDA / H7270 Services and direct support A posteriori sur la qualité et Open - National 440,000.00 0.00 2017-09-01 2017-09-22 2017-11-05 2017-12-03 2018-01-02 2018-02-06 2018-03-13 2018-12-23 parcelles des périmètres d'exécution to smallholders and SMEs le coût aménagés des 2200 ha à l'aval du barrage en rive gauche BF-PPCB-50677-CS-QCBS / Bornage, morcellement et Sélection fondée immatriculation des Development of Critical En cours IDA / H7270 A posteriori sur la qualité et Open - National 455,000.00 0.00 2017-09-01 2017-09-22 2017-11-05 2017-12-03 2018-01-02 2018-01-30 2018-02-27 2018-12-09 parcelles des périmètres Infrastructure d'exécution le coût aménagés des 2194 ha en rive droite à l'aval du barrage BF-PPCB-50680-CS-QCBS / Bornage, morcellement et immatriculation des Sélection fondée Development of Critical En cours parcelles des périmètres IDA / H7270 A posteriori sur la qualité et Open - National 210,000.00 0.00 2017-09-01 2017-09-22 2017-11-05 2017-12-03 2018-01-02 2018-02-06 2018-03-13 2018-09-14 Infrastructure d'exécution aménagés existant des 1200 le coût ha en rive droite à l'aval du barrage BF-PPCB-50691-CS-QCBS / Bornage, morcellement et Sélection fondée immatriculation des Development of Critical En cours IDA / H7270 A posteriori sur la qualité et Open - National 166,500.00 0.00 2017-09-01 2017-09-22 2017-10-20 2017-11-19 2017-12-03 2017-12-31 2018-01-21 2018-07-25 parcelles des périmètres Infrastructure d'exécution le coût aménagés des 680 ha existants à l'aval du barrage en rive gauche BF-PPCB-50678-CS-QCBS / Bornage morcellement et Sélection fondée immatriculation des Development of Critical En cours IDA / H7270 A posteriori sur la qualité et Open - National 355,000.00 0.00 2017-09-01 2017-09-22 2017-10-07 2017-11-06 2017-11-20 2017-12-25 2018-01-22 2018-08-05 parcelles des périmètres Infrastructure d'exécution le coût aménagés des 1500 ha en rive gauche ancien Improvement of institutional capacity for Sélection fondée BF-PPCB-50706-CS-QCBS / En attente IDA / H7270 better zone management A posteriori sur la qualité et Open - National 60,000.00 0.00 2018-04-15 2018-05-06 2018-06-03 2018-07-03 2018-07-17 2018-08-21 2018-09-11 2018-11-10 Mise en place d’un intranet d'exécution and investment climate in le coût the Project Area BF-PPCB-50700-CS-CQS / Improvement of Sélection fondée Elaboration d’un manuel de institutional capacity for sur les management sur l’hygiène, IDA / H7270 better zone management A posteriori Open - National 40,000.00 0.00 Annulé 2018-04-01 2018-04-22 2018-05-13 2018-05-27 2018-06-24 2018-08-23 qualifications des santé et sécurité et and investment climate in consultants environnement de Bagrépôle the Project Area BF-PPCB-66881-CS-QCBS / Suivi contrôle et Sélection fondée Development of Critical Open - En cours coordination des travaux de IDA / 61840 A posteriori sur la qualité et 575,000.00 0.00 2018-07-15 2018-07-29 2018-08-12 2018-09-26 2018-10-03 2018-10-17 2018-10-31 2019-10-31 Infrastructure International d'examen construction de pistes et le coût routes en terres BF-PPCB-66882-CS-QCBS / Suivi contrôle et Sélection fondée Development of Critical Open - En cours coordination des travaux de IDA / 61840 A posteriori sur la qualité et 675,000.00 0.00 2018-06-30 2018-07-14 2018-07-28 2018-09-11 2018-09-18 2018-10-02 2018-10-12 2019-12-06 Infrastructure International d'examen construction de routes le coût bitumées BF-PPCB-66892-CS-CQS / Sélection fondée mission de suivi contrôle Development of Critical sur les En cours des travaux de construction IDA / H7270 A posteriori Open - National 140,000.00 0.00 2018-06-25 2018-07-05 2018-07-17 2018-07-24 2018-08-03 2019-01-30 Infrastructure qualifications des d'exécution de magasins et aires de consultants séchages BF-PPCB-66893-CS-CQS / Sélection fondée Actualisation des études Development of Critical sur les En cours APD et DAO des travaux IDA / H7270 A posteriori Open - National 180,000.00 0.00 2018-06-30 2018-07-14 2018-08-02 2018-08-09 2018-08-23 2018-11-21 Infrastructure qualifications des d'examen d'extension du réseau consultants électrique Page 9 Improvement of BF-PPCB-74282-CS-LCS / institutional capacity for Audit comptable et financier Sélection au En cours IDA / 61840 better zone management A priori Open - National 60,000.00 0.00 2018-08-31 2018-09-14 2018-09-22 2018-10-22 2018-10-27 2018-11-13 2018-12-04 2021-12-03 des trois exercices (2018, moindre coût d'examen and investment climate in 2019 et 2020) du Projet the Project Area Improvement of BF-PPCB-50698-CS-QCBS / institutional capacity for Sélection fondée Etude de capitalisation et IDA / H7270 better zone management A posteriori sur la qualité et Open - National 80,000.00 0.00 Annulé 2018-07-15 2018-08-05 2018-08-26 2018-09-23 2018-10-07 2018-10-15 2018-10-30 2018-12-29 de valorisation des and investment climate in le coût expériences du PPCB the Project Area Improvement of BF-PPCB-26303-CS-QCBS / institutional capacity for Sélection fondée Evaluation finale du IDA / H7270 better zone management A posteriori sur la qualité et Open - National 170,000.00 0.00 Annulé 2017-10-31 2017-11-14 2017-12-08 2018-01-07 2018-01-14 2018-02-11 2018-03-04 2018-06-02 PPCB and investment climate in le coût the Project Area BF-PPCB-26286-CS-QCBS / Etudes diagnostique et Improvement of techniques pour la institutional capacity for Sélection fondée réalisation des travaux de IDA / H7270 better zone management A posteriori sur la qualité et Open - National 160,000.00 0.00 Annulé 2017-09-15 2017-10-06 2017-11-19 2017-12-19 2017-12-26 2018-01-19 2018-02-02 2018-04-03 reboisement de 60 ha det and investment climate in le coût d’aménagement de 40 ha de the Project Area périmètres maraichers BF-PPCB-105153-CS-QCBS Improvement of / Mise en place système institutional capacity for Sélection fondée En attente d'information de suivi- IDA / 61840 better zone management A posteriori sur la qualité et Open - National 140,000.00 0.00 2019-05-05 2019-05-19 2019-06-09 2019-07-09 2019-07-16 2019-08-06 2019-08-27 2020-02-23 d'exécution évaluation et de pilotage de and investment climate in le coût Bagrépôle the Project Area BF-PPCB-105155-CS-QCBS Sélection fondée Investment Promotion and En attente / Elaboration du plan IDA / 61840 A posteriori sur la qualité et Open - National 90,000.00 0.00 2019-04-10 2019-04-24 2019-05-15 2019-06-14 2019-06-21 2019-07-19 2019-08-02 2019-10-31 Investment Climate d'exécution stratégique de l'ABI le coût BF-PPCB-105161-CS-CQS / Sélection fondée Elaboration d'un manuel de Investment Promotion and sur les En attente IDA / 61840 A posteriori Open - National 40,000.00 0.00 2019-04-25 2019-05-09 2019-05-30 2019-06-13 2019-06-27 2019-08-26 gestion de la banque de Investment Climate qualifications des d'exécution projets au profit de l'ABI consultants BF-PPCB-105159-CS-CQS / Sélection fondée Elaboration manuel de Investment Promotion and sur les En attente IDA / 61840 A posteriori Open - National 40,000.00 0.00 2019-03-30 2019-04-13 2019-05-04 2019-05-11 2019-05-25 2019-07-09 gestion de la banque de Investment Climate qualifications des d'exécution projet de l'ABI consultants Improvement of BF-PPCB-105169-CS-CQS / Sélection fondée institutional capacity for Etudes environnementale et sur les En attente IDA / 61840 better zone management A posteriori Open - National 20,000.00 0.00 2019-03-30 2019-04-20 2019-05-11 2019-05-18 2019-06-08 2019-09-06 sociale des basfonds de qualifications des d'exécution and investment climate in Beka consultants the Project Area Improvement of Sélection fondée BF-PPCB-105172-CS-CQS / institutional capacity for sur les En attente service de recrutement du IDA / 61840 better zone management A posteriori Open - National 50,000.00 0.00 2019-04-01 2019-04-15 2019-05-06 2019-05-13 2019-06-03 2019-08-02 qualifications des d'exécution personnel and investment climate in consultants the Project Area Improvement of BF-PPCB-105179-CS-QBS / institutional capacity for Révision des plans d'action Sélection fondée En attente IDA / H7270 better zone management A posteriori Open - National 120,000.00 0.00 2019-04-25 2019-05-09 2019-05-23 2019-06-22 2019-06-29 2019-07-13 2019-07-27 2019-09-25 de réinstallation des zones sur la qualité d'exécution and investment climate in pastorales et industrielles the Project Area Improvement of BF-PPCB-105182-CS-QCBS institutional capacity for Sélection fondée En cours / Revue du plan stratégique IDA / H7270 better zone management A posteriori sur la qualité et Open - National 150,000.00 0.00 2019-03-31 2019-04-14 2019-05-05 2019-06-04 2019-06-11 2019-07-02 2019-07-23 2019-10-21 d'examen de Bagrépôle and investment climate in le coût the Project Area BF-PPCB-105184-CS-CQS / Improvement of Sélection fondée situation de référence institutional capacity for sur les En cours environnementale de l'eau IDA / 61840 better zone management A posteriori Open - National 60,000.00 0.00 2019-04-10 2019-04-24 2019-05-15 2019-05-29 2019-06-12 2019-09-10 qualifications des d'examen est des organismes végétaux and investment climate in consultants de la zone de Bagré the Project Area BF-PPCB-105173-CS-CQS / Étude d'impact Sélection fondée environnemental et Development of Critical sur les IDA / 61840 A posteriori Open - National 160,000.00 0.00 Annulé 2019-04-15 2019-04-29 2019-05-20 2019-06-03 2019-06-17 2019-08-16 élaboration de PAR des Infrastructure qualifications des travaux d'extension du consultants réseau électrique Page 10 BF-PPCB-133127-GO-RFQ / Sélection fondée conception d'un logiciel de Investment Promotion and sur les En cours IDA / 61840 A posteriori Open - National 40,000.00 0.00 2019-09-30 2019-10-14 2019-10-26 2019-10-27 2019-11-10 2020-02-08 suivi des investisseurs au Investment Climate qualifications des d'exécution profit l'A.B.I consultants BF-PPCB-105163-CS-QCBS / Étude économique sur les Sélection fondée filières porteuses et analyse Investment Promotion and IDA / 61840 A posteriori sur la qualité et Open - National 100,000.00 0.00 Annulé 2019-05-05 2019-05-19 2019-06-09 2019-07-09 2019-07-16 2019-08-13 2019-08-27 2019-11-25 sectorielle spatiale et la Investment Climate le coût typologie des produits du PCB BF-PPCB-105158-CS-CQS / Sélection fondée Situation des Investment Promotion and sur les IDA / 61840 A posteriori Open - National 50,000.00 0.00 Annulé 2019-05-05 2019-05-19 2019-06-09 2019-06-23 2019-07-07 2019-10-05 investissements dans le pôle Investment Climate qualifications des de croissance de Bagré consultants Improvement of BF-PPCB-105157-CS-QCBS institutional capacity for Sélection fondée / stratégie de communication IDA / 61840 better zone management A posteriori sur la qualité et Open - National 100,000.00 0.00 Annulé 2019-04-15 2019-04-29 2019-05-20 2019-06-19 2019-07-03 2019-07-24 2019-08-14 2019-10-13 de l'ABI et de Bagrépôle and investment climate in le coût the Project Area BF-PPCB-105166-CS-CQS / Sélection fondée Sratégie de promotion des Investment Promotion and sur les IDA / 61840 A posteriori Open - National 40,000.00 0.00 Annulé 2019-05-30 2019-06-13 2019-07-04 2019-07-18 2019-08-08 2019-11-06 investissements du pôle de Investment Climate qualifications des croissance de Bagré consultants BF-PPCB-133425-CS-CQS / Sélection fondée Etude d'impact Development of Critical sur les En cours environnement et social des IDA / 61840 A posteriori Open - National 80,000.00 0.00 2019-09-20 2019-10-04 2019-10-19 2019-10-24 2019-10-30 2019-12-29 Infrastructure qualifications des d'exécution travaux d'extension du consultants réseau électriques BF-PPCB-133427-CS-CQS / Élaboration de plan d'action Sélection fondée et de réinstallation des Development of Critical sur les En cours IDA / 61840 A posteriori Open - National 80,000.00 0.00 2019-09-20 2019-10-04 2019-10-21 2019-10-26 2019-11-01 2019-12-31 personnes (PAR) affectées Infrastructure qualifications des d'exécution par le projet d'extension du consultants réseau électrique BF-PPCB-133428-CS-CQS / Sélection fondée Suivi contrôle et Development of Critical sur les En cours coordination des travaux IDA / 61840 A posteriori Open - National 180,000.00 0.00 2019-09-25 2019-10-09 2019-10-24 2019-10-31 2019-11-06 2020-10-31 Infrastructure qualifications des d'examen d'extension du réseau consultants électrique BF-PPCB-105180-CS-QCBS Sélection fondée / Étude diagnostique pour Development of Critical IDA / 61840 A posteriori sur la qualité et Open - National 400,000.00 0.00 Annulé 2019-04-15 2019-04-29 2019-05-20 2019-06-19 2019-06-26 2019-07-17 2019-08-07 2020-01-04 l'aménagement d'un parc Infrastructure le coût industriel Improvement of BF-PPCB-105154-CS-CQS / Sélection fondée institutional capacity for Réalisation de la situation sur les IDA / 61840 better zone management A posteriori Open - National 50,000.00 0.00 Annulé 2019-03-30 2019-04-13 2019-04-27 2019-05-11 2019-05-25 2019-08-23 de référence du financement qualifications des and investment climate in additionnel du PPCB consultants the Project Area BF-PPCB-66883-CS-CQS / Improvement of Sélection fondée réalisation du Bilan institutional capacity for sur les technique du Projet, IDA / H7270 better zone management A posteriori Open - National 180,000.00 0.00 Annulé 2018-06-30 2018-07-14 2018-08-04 2018-08-11 2018-08-21 2018-11-19 qualifications des capitalisation des bonnes and investment climate in consultants pratiques... the Project Area BF-PPCB-133469-CS-CQS / Improvement of Sélection fondée Réalisation du bilan institutional capacity for sur les En attente technique du projet et IDA / 61840 better zone management A posteriori Open - National 120,000.00 0.00 2019-09-10 2019-09-24 2019-10-11 2019-10-18 2019-10-24 2020-02-21 qualifications des d'exécution capitalisation des bonnes and investment climate in consultants pratiques the Project Area Sélection fondée BF-PPCB-105152-CS-CQS / Investment Promotion and sur les Mise à jour du site Web de IDA / 61840 A posteriori Open - National 50,000.00 0.00 Annulé 2019-04-30 2019-05-14 2019-06-04 2019-06-18 2019-07-09 2019-10-07 Investment Climate qualifications des Bagrépôle et de l'ABI consultants Improvement of Sélection fondée BF-PPCB-133484-CS-CQS / institutional capacity for sur les En cours Mise à jour des sites WEB IDA / 61840 better zone management A posteriori Open - National 20,000.00 0.00 2019-09-16 2019-09-30 2019-10-13 2019-10-18 2019-10-30 2019-12-29 qualifications des d'exécution de Bagrépôle et de l'A.B.I. and investment climate in consultants the Project Area Page 11 Improvement of Sélection fondée BF-PPCB-133529-CS-CQS / institutional capacity for sur les En cours Revue du plan stratégique IDA / 61840 better zone management A posteriori Open - National 150,000.00 0.00 2019-09-09 2019-09-23 2019-10-14 2019-10-21 2019-10-27 2020-02-24 qualifications des d'exécution de Bagrépôle and investment climate in consultants the Project Area BF-PPCB-133447-CS-QCBS Sélection fondée / Étude diagnostique pour Development of Critical sur les En attente IDA / 61840 A posteriori Open - National 200,000.00 0.00 2019-09-30 2019-10-14 2019-11-04 2019-11-11 2019-11-25 2020-05-23 l'aménagement d'un parc Infrastructure qualifications des d'exécution industriel consultants BF-PPCB-133087-CS-INDV Sélection fondée / Suivi contrôle des travaux Strengthening sur les En attente de construction des IDA / 61840 Entrepreneurship in A posteriori Open - National 20,000.00 0.00 2019-10-10 2019-10-31 2019-11-21 2019-11-28 2019-12-08 2020-06-05 qualifications des d'exécution infrastructures socio- Agribusiness consultants économiques Improvement of BF-PPCB-133251-CS-QCBS Sélection fondée institutional capacity for / Élaboration de la stratégie sur les En cours IDA / 61840 better zone management A posteriori Open - National 50,000.00 0.00 2019-10-01 2019-10-15 2019-11-01 2019-11-08 2019-12-15 2020-04-13 de communication de qualifications des d'exécution and investment climate in Bagrépôle et de l'A.B.I. consultants the Project Area BF-PPCB-133307-CS-QCBS Sélection fondée / Réalisation d'une étude de Investment Promotion and sur les En attente l'écosystème de IDA / 61840 A posteriori Open - National 100,000.00 0.00 2019-09-16 2019-09-26 2019-10-15 2019-10-20 2019-10-26 2019-12-25 Investment Climate qualifications des d'exécution l'entreprenariat au Burkina consultants Faso Improvement of BF-PPCB-26289-CS-QCBS / institutional capacity for Sélection fondée Réalisation de la revue du IDA / H7270 better zone management A posteriori sur la qualité et Open - National 150,000.00 0.00 Annulé 2017-09-30 2017-10-14 2017-10-31 2017-11-30 2017-12-14 2018-01-11 2018-01-25 2018-06-24 plan stratégique de and investment climate in le coût Bagrépôle the Project Area BF-PPCB-133223-CS-QCBS Sélection fondée / Conception d'un Système Investment Promotion and sur les En attente d'Information Foncier (SIF) IDA / 61840 A posteriori Open - National 100,000.00 0.00 2020-03-10 2020-03-24 2020-04-14 2020-04-21 2020-05-05 2020-09-02 Investment Climate qualifications des d'exécution géo-référencé au profit de consultants Bagrépôle BF-PPCB-133238-CS-CQS / Étude quantitative et Sélection fondée qualitative sur les secteurs Investment Promotion and sur les En attente IDA / 61840 A posteriori Open - National 50,000.00 0.00 2020-02-25 2020-03-10 2020-03-31 2020-04-07 2020-04-17 2020-07-16 de l'industrie culturelle et Investment Climate qualifications des d'exécution Bâtiments Travaux Publics consultants (BTP) /Immobilier BF-PPCB-133305-CS-CQS / Élaboration d'une stratégie nationale de promotion des Sélection fondée investissements assortie Investment Promotion and sur les En attente IDA / 61840 A posteriori Open - National 100,000.00 0.00 2020-02-10 2020-02-20 2020-03-11 2020-03-18 2020-03-28 2020-06-26 d'une stratégie spécifique de Investment Climate qualifications des d'exécution promotion des consultants investissements du pôle de croissance de Bagré BF-PPCB-155590-CS-CQS / Sélection fondée Elaboration du plan Investment Promotion and sur les En attente stratégique de l'Agence IDA / 61840 A posteriori Open - National 90,000.00 0.00 2020-01-31 2020-02-14 2020-03-02 2020-03-16 2020-03-30 2020-05-29 Investment Climate qualifications des d'exécution Burkinabè des consultants investissements BF-PPCB-155696-CS-CQS / Elaboration du Plan d’Action Sélection fondée de Réinstallation des Development of Critical sur les En attente IDA / 61840 A posteriori Open - National 100,000.00 0.00 2020-05-30 2020-06-13 2020-07-04 2020-07-11 2020-07-25 2020-10-23 personnes affectées par le Infrastructure qualifications des d'exécution projet de construction de la consultants zone industrielle à Bagré BF-PPCB-133232-CS-CQS / Sélection fondée Étude sur les problèmes de Investment Promotion and sur les En attente tarification et de spéculation IDA / 61840 A posteriori Open - National 60,000.00 0.00 2020-02-14 2020-02-28 2020-03-20 2020-03-23 2020-04-02 2020-07-31 Investment Climate qualifications des d'exécution foncière et leur impact sur consultants la gestion des terres BF-PPCB-155798-CS-CQS / Etude économique des Sélection fondée travaux de construction de Development of Critical sur les En cours IDA / 61840 A posteriori Open - National 50,000.00 0.00 2020-01-31 2020-02-14 2020-03-02 2020-03-05 2020-03-15 2020-04-14 routes bitumées dans zone Infrastructure qualifications des d'exécution de concentration du pôle de consultants croissance de Bagré Page 12 BF-PPCB-155585-CS-QCBS Sélection fondée / Etude de faisabilité pour Development of Critical Open - En attente IDA / 61840 A posteriori sur la qualité et 600,000.00 0.00 2020-02-17 2020-03-02 2020-03-23 2020-03-27 2020-04-03 2020-04-24 2020-05-08 2020-09-05 la mise en place d’un parc Infrastructure International d'exécution le coût industriel à Bagré BF-PPCB-159913-CS-CQS / Improvement of Sélection fondée Etude de la rentabilité socio- institutional capacity for sur les En attente économique et financière du IDA / 61840 better zone management A posteriori Open - National 120,000.00 0.00 2020-03-31 2020-04-14 2020-05-05 2020-05-19 2020-06-02 2020-08-31 qualifications des d'exécution Projet Pôle de Croissance de and investment climate in consultants Bagré the Project Area INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual BF-PPCB-26312-CS-INDV / Suivi contrôle des travaux de mise en place d’un Development of Critical En attente IDA / H7270 A posteriori Individuel Limited 10,000.00 0.00 2017-10-15 2017-10-20 2017-11-10 2017-12-01 2018-04-30 système de prévention Infrastructure d'exécution contre les noyades dans le canal primaire BF-PPCB-26430-CS-INDV / Etude technique pour la mise en place d'un système Development of Critical En cours IDA / H7270 A posteriori Individuel Limited 20,000.00 0.00 2017-08-25 2017-08-30 2017-09-13 2017-10-04 2017-12-03 de prévention contre les Infrastructure d'exécution noyades dans le canal primaire BF-PPCB-26285-CS-INDV / Suivi contrôle des travaux de mise en place d’un Development of Critical En attente IDA / H7270 A posteriori Individuel Open 10,000.00 0.00 2017-10-15 2017-11-17 2017-12-01 2017-12-15 2018-05-14 système de prévention Infrastructure d'exécution contre les noyades dans le canal primaire BF-PPCB-26438-CS-CDS / Improvement of Réalisation de la situation institutional capacity for Sélection de de référence En attente IDA / H7270 better zone management A posteriori consultants par Direct 80,000.00 0.00 2017-09-30 2017-10-10 2017-12-14 2018-02-12 environnementale sur les d'exécution and investment climate in entente directe sols des extension Nord 2 the Project Area et Est BF-PPCB-32605-CS-INDV / Mission d'analyse des demandes d'indemnisation des entreprises chargées des Improvement of travaux lot 1 suite au institutional capacity for En attente rendu des résultats de IDA / H7270 better zone management A posteriori Individuel Open 80,000.00 0.00 2017-10-18 2017-11-29 2017-12-06 2017-12-20 2018-02-03 d'exécution l'adaptation des études and investment climate in techniques d'exécution des the Project Area travaux d'aménagement de 2582 HA en rive gauche du Nakambé à Bagré Improvement of BF-PPCB-66884-CS-CDS / institutional capacity for Sélection de En cours Actualisation du manuel IDA / H7270 better zone management A posteriori consultants par Direct 10,000.00 0.00 2018-06-25 2018-07-05 2018-07-18 2018-08-17 d'examen d'exécution du PPCB and investment climate in entente directe the Project Area BF-PPCB-66889-CS-INDV / mission d'expertise et réalisation d'étude technique détaillée en vue de la Development of Critical En cours réalisation des travaux de IDA / H7270 A posteriori Individuel Limited 50,000.00 0.00 2018-06-20 2018-06-25 2018-07-02 2018-07-16 2018-08-30 Infrastructure d'exécution confortement du siphon situé sur le périmètre aménagé des 2582 ha à Bagré BF-PPCB-68396-CS-INDV / Improvement of Élaboration manuel de institutional capacity for En cours management sur l'hygiène IDA / H7270 better zone management A posteriori Individuel Open 40,000.00 0.00 2018-06-29 2018-07-25 2018-08-01 2018-08-11 2018-09-10 d'exécution santé sécurité et and investment climate in environnement the Project Area BF-PPCB-26310-CS-INDV / Contrôle à pieds d’œuvre Development of Critical construction d’infrastructures IDA / H7270 A posteriori Individuel Limited 16,000.00 0.00 Annulé 2017-10-01 2017-10-06 2017-10-27 2017-11-10 2018-03-10 Infrastructure socio-économiques au profit des PAP Page 13 BF-PPCB-105167-CS-INDV Improvement of / Formation sur la institutional capacity for En attente négociation et la IDA / 61840 better zone management A posteriori Individuel Open 20,000.00 0.00 2019-06-25 2019-07-21 2019-08-04 2019-08-18 2019-09-17 d'exécution contractualisation en matière and investment climate in commerciale the Project Area BF-PPCB-105175-CS-INDV Improvement of / Audit global des institutional capacity for En attente instruments de sauvegardes IDA / 61840 better zone management A posteriori Individuel Open 40,000.00 0.00 2019-04-01 2019-04-27 2019-05-04 2019-05-18 2019-07-17 d'exécution environnementales et and investment climate in sociales the Project Area Improvement of BF-PPCB-105185-CS-CDS / institutional capacity for Sélection de En attente Réalisation des analyses IDA / 61840 better zone management A posteriori consultants par Direct 12,400.00 0.00 2019-04-05 2019-04-15 2019-06-05 2019-07-05 d'exécution microbiologiques des sols and investment climate in entente directe the Project Area Improvement of BF-PPCB-133140-CS-INDV institutional capacity for / Recrutement d'un expert En attente IDA / 61840 better zone management A posteriori Individuel Limited 60,000.00 0.00 2019-09-15 2019-09-25 2019-09-30 2019-10-06 2020-09-30 en promotion des d'exécution and investment climate in investissements the Project Area BF-PPCB-133143-CS-INDV / recrutement d'un assistant Investment Promotion and En attente IDA / 61840 A posteriori Individuel Limited 15,000.00 0.00 2019-09-16 2019-09-26 2019-10-01 2019-10-09 2020-10-03 chargé de la promotion des Investment Climate d'exécution investissements BF-PPCB-133144-CS-INDV / Recrutement d'un assistant Investment Promotion and En attente IDA / 61840 A posteriori Individuel Limited 15,000.00 0.00 2019-09-16 2019-09-21 2019-10-01 2019-10-16 2020-10-10 chargé de la facilitation des Investment Climate d'exécution affaires Improvement of BF-PPCB-133431-CS-INDV institutional capacity for / Formation des acteurs En attente IDA / 61840 better zone management A posteriori Individuel Limited 50,000.00 0.00 2019-09-20 2019-09-25 2019-10-16 2019-11-20 2020-05-18 pour l'application du cadre d'exécution and investment climate in foncier the Project Area BF-PPCB-133308-CS-CDS / Étude d'évaluation des Sélection de potentialités et des Investment Promotion and En attente IDA / 61840 A posteriori consultants par Direct 200,000.00 0.00 2019-09-15 2019-09-26 2019-10-12 2019-11-11 opportunités d'investissement Investment Climate d'exécution entente directe dans le pôle de croissance de Bagré BF-PPCB-132922-CS-INDV / suivi contrôle des travaux Development of Critical de renforcement du IDA / H7270 A posteriori Individuel Limited 15,000.00 0.00 Annulé 2019-09-12 2019-09-19 2019-09-26 2019-10-02 2019-12-01 Infrastructure dispositif de sécurité autour du canal primaire BF-PPCB-133082-CS-INDV / Elaboration d'un plan de Development of Critical En attente sécurité et d'un plan IDA / 61840 Services and direct support A posteriori Individuel Open 50,000.00 0.00 2019-09-20 2019-10-08 2019-10-15 2019-10-25 2019-12-24 d'exécution d'évacuation d'urgence au to smallholders and SMEs profit de Bagrépôle Page 14