The World Bank Report No: ISR12242 Implementation Status & Results El Salvador Education Quality Improvement Project (P126364) Public Disclosure Copy Operation Name: Education Quality Improvement Project (P126364) Project Stage: Implementation Seq.No: 5 Status: ARCHIVED Archive Date: 13-Mar-2014 Country: El Salvador Approval FY: 2012 Product Line: IBRD/IDA Region: LATIN AMERICA AND CARIBBEAN Lending Instrument: Specific Investment Loan Implementing Agency(ies): Ministry of Education Key Dates Board Approval Date 13-Dec-2011 Original Closing Date 31-Dec-2017 Planned Mid Term Review Date 31-Mar-2015 Last Archived ISR Date 27-Aug-2013 Effectiveness Date 15-May-2012 Revised Closing Date 31-Dec-2017 Actual Mid Term Review Date Project Development Objectives Project Development Objective (from Project Appraisal Document) The objective of the Project is to improve access, retention and graduation rates for students in the Lower Secondary Education andthe Upper Secondary Education of the Borrower's public schools adopting the Inclusive Full Time School Model (IFTS Model). Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Adoption of the IFTS Model 54.85 Improvement of MINED's Institutional Capacity and the Schooling System's Governance 4.00 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Moderately Satisfactory Public Disclosure Copy Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Moderate Moderate Implementation Status Overview Following the Project's restructuring of January 2013 and subsequent supervision missions to assist in further planning efforts, Project implementation has accelerated over the past 6 months. The teacher professional development component made important progress through the selection of organizations to deliver teacher training and the design of learning modules. Capacity Development activities will commence in 2014. The infrastructure component has provided inputs for 60 of the 201 schools planned for the Project to date. For the monitoring and evaluation and impact evaluation of the Project, data collection and instrument development will be realized in the first half of 2014. Locations Page 1 of 5 The World Bank Report No: ISR12242 Country First Administrative Division Location Planned Actual El Salvador Sonsonate Departamento de Sonsonate ✔ Public Disclosure Copy El Salvador Departamento de La Libertad Departamento de La Libertad ✔ Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Improvement in the Access Rate for lower Percentage Value 96.30 96.30 98.80 secondary education Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 Comments Improvement in the Retention Rate for lower Percentage Value 95.10 95.10 98.40 secondary education Date 01-Nov-2011 13-Feb-2014 Comments Improvement in the Graduation Rate for upper Percentage Value 75.00 75.00 91.70 secondary education Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 Comments Number of municipalities with clusters Number Value 0.00 0.00 29.00 effectively implemented Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 Comments Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Direct project beneficiaries Number Value 7162.00 7162.00 43871.00 Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 Comments Public Disclosure Copy Female beneficiaries Percentage Value 49.00 49.00 50.00 Sub Type Supplemental Number of additional qualified primary teachers Number Value 0.00 0.00 1216.00 resulting from project interventions. Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 Comments Page 2 of 5 The World Bank Report No: ISR12242 Number of additional qualified secondary Number Value 0.00 0.00 943.00 school teachers and number of additional Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 qualified school directors resulting from Comments Projectintervention Public Disclosure Copy Number of additional qualified MINED technical Number Value 0.00 0.00 82.00 staff (at the central and departmental level) Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 resulting from Project intervention Comments Number of IFTS that are being renovated and/ Number Value 0.00 0.00 201.00 or equipped with educational material and Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 equipment according to the IFTS standards Comments Number of new classrooms built under the Number Value 0.00 0.00 723.00 Project, including necessary furniture Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 Comments Number of IFTS being renovated under the Number Value 0.00 0.00 201.00 Project Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 Comments Number of students in grades 7 to 9 that have Number Value 0.00 0.00 34017.00 40 weekly hours of pedagogical activities Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 coordinated by the school Comments Number of students transported to school in Number Value 0.00 0.00 11906.00 the cluster Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 Comments Municipalities with a monitoring system at the Number Value 0.00 0.00 29.00 cluster level Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 Comments Municipalities that implemented the Number Value 0.00 0.00 29.00 communication strategy for the IFTS Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 Public Disclosure Copy Comments Municipalities that have undertaken a process Number Value 0.00 0.00 7.00 evaluation of the governance system Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 Comments Municipalities with an Impact Evaluation started Number Value 0.00 0.00 29.00 Date 01-Nov-2011 13-Feb-2014 30-Jun-2017 Comments Page 3 of 5 The World Bank Report No: ISR12242 Data on Financial Performance (as of 26-Feb-2014) Financial Agreement(s) Key Dates Project Ln/Cr/Tf Status Approval Date Signing Date Effectiveness Date Original Closing Date Revised Closing Date Public Disclosure Copy P126364 IBRD-81100 Effective 13-Dec-2011 14-Mar-2012 15-May-2012 31-Dec-2017 31-Dec-2017 P126364 TF-10361 Effective 25-Aug-2011 12-Sep-2011 12-Sep-2011 30-Jun-2014 30-Jun-2014 P126364 TF-14166 Effective 09-Oct-2013 09-Oct-2013 09-Oct-2013 30-Jun-2015 30-Jun-2015 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P126364 IBRD-81100 Effective USD 60.00 60.00 0.00 4.31 55.69 7.00 P126364 TF-10361 Effective USD 0.13 0.13 0.00 0.13 0.00 100.00 P126364 TF-14166 Effective USD 0.10 0.10 0.00 0.00 0.10 0.00 Disbursement Graph Public Disclosure Copy Key Decisions Regarding Implementation None. Restructuring History Level two Approved on 24-Jan-2013 Page 4 of 5 The World Bank Report No: ISR12242 Related Projects There are no related projects. Public Disclosure Copy Public Disclosure Copy Page 5 of 5