The World Bank Implementation Status & Results Report CN-Hubei Xiaogan Logistics Infrastructure (P132562) CN-Hubei Xiaogan Logistics Infrastructure (P132562) EAST ASIA AND PACIFIC | China | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2016 | Seq No: 6 | ARCHIVED on 14-Jun-2019 | ISR37530 | Implementing Agencies: People's Republic of China, Xiaogan Airport Economic Zone Management Committee Key Dates Key Project Dates Bank Approval Date: 29-Apr-2016 Effectiveness Date: 24-Aug-2016 Planned Mid Term Review Date: 31-Mar-2019 Actual Mid-Term Review Date: 25-Apr-2019 Original Closing Date: 30-Jun-2021 Revised Closing Date: 30-Jun-2021 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To enhance the connectivity and efficiency of the logistics operations of the Xiaogan Logistics Park in Hubei Province. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Component 1: Connected Logistics:(Cost $84.91 M) Component 2: Efficient Logistics:(Cost $58.15 M) Component 3: Institutional Strengthening:(Cost $2.82 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Moderately Satisfactory Moderately Satisfactory Overall Risk Rating Substantial Substantial Implementation Status and Key Decisions Current project design for the Logistics Park situated within the Xiaogan-AEZ and the monitoring and evaluation arrangements remain on track. The implementation and management arrangements were found to be adequate and necessary, and the safeguards compliance is satisfactory. The fiduciary performance is slow but adequate. Overall project implementation has progressed in a satisfactory manner since last mission in October 2018. There was some delay in civil works mainly due the extended rainy season and minor issues on land acquisition and resettlement. The project remains on track for timely completion. 6/14/2019 Page 1 of 5 The World Bank Implementation Status & Results Report CN-Hubei Xiaogan Logistics Infrastructure (P132562) Risks Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Low Low Low Macroeconomic Low Moderate Moderate Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Moderate Moderate Institutional Capacity for Implementation and Sustainability Substantial Substantial Moderate Fiduciary Substantial Substantial Moderate Environment and Social Moderate Substantial Moderate Stakeholders Moderate Moderate Moderate Other -- -- -- Overall Substantial Substantial Substantial Results PDO Indicators by Objectives / Outcomes To measure improvement in connectivity IN00713986 ►Average travel time (minutes) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 34.00 34.00 34.00 26.00 Date 31-Dec-2015 31-Oct-2018 30-Apr-2019 30-Jun-2021 To measure improvement in efficiency IN00713987 ►Empty-running (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 45.00 45.00 45.00 25.00 Date 31-Dec-2015 31-Oct-2018 30-Apr-2019 30-Jun-2021 Intermediate Results Indicators by Components 6/14/2019 Page 2 of 5 The World Bank Implementation Status & Results Report CN-Hubei Xiaogan Logistics Infrastructure (P132562) Component 1: Connected Logistics IN00713988 ►Standard deviation of travel times (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 4.70 4.70 4.70 2.50 Date 31-Dec-2015 31-Oct-2018 30-Apr-2019 30-Jun-2021 IN00713991 ►Roads constructed, non-rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 9.70 Date 31-Dec-2015 31-Oct-2018 30-Apr-2019 30-Jun-2021 IN00713994 ►Grievances pertaining to the construction and implementation of the project registered and addressed (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No Yes Yes Yes Date 31-Dec-2015 31-Oct-2018 30-Apr-2019 30-Jun-2021 Component 2: Efficient Logistics IN00713989 ►Number of companies operating in the logistics park (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 6.00 6.00 12.00 Date 31-Dec-2015 31-Oct-2018 30-Apr-2019 30-Jun-2021 IN00713992 ►Number of trucks entering the logistics park (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 48,739.00 48,739.00 100,000.00 Date 31-Dec-2015 31-Oct-2018 30-Apr-2019 30-Jun-2021 IN00713995 ►Completion of the logistics information management building (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value Not completed Not completed. Not completed. Completed Date 31-Dec-2015 31-Oct-2018 30-Apr-2019 30-Jun-2021 IN00713996 ►Number of the sub-platforms of the public information platform in operation (Number, Custom) 6/14/2019 Page 3 of 5 The World Bank Implementation Status & Results Report CN-Hubei Xiaogan Logistics Infrastructure (P132562) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 6.00 Date 31-Dec-2015 31-Oct-2018 30-Apr-2019 30-Jun-2021 IN00713997 ►Number of junctions covered by the ITS (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 60.00 Date 31-Dec-2015 31-Oct-2018 30-Apr-2019 30-Jun-2021 Component 3: Institutional Strengthening IN00713990 ►Road Safety Audit of road designs and interactive design support given (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target After preliminary Designs audited for Value Not completed After preliminary design design RS and actions taken Date 31-Dec-2015 31-Oct-2018 30-Apr-2019 30-Jun-2021 IN00713993 ►Completion of the Technical Assistance on green logistics (Text, Custom) Baseline Actual (Previous) Actual (Current) End Target Value Not completed Not completed. Not completed. Completed Date 31-Dec-2015 31-Oct-2018 30-Apr-2019 30-Jun-2021 Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P132562 IBRD-86130 Effective USD 100.00 100.00 0.00 9.94 90.06 9.9% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P132562 IBRD-86130 Effective 29-Apr-2016 26-May-2016 24-Aug-2016 30-Jun-2021 30-Jun-2021 Cumulative Disbursements 6/14/2019 Page 4 of 5 The World Bank Implementation Status & Results Report CN-Hubei Xiaogan Logistics Infrastructure (P132562) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 6/14/2019 Page 5 of 5