Sample Procurement Plan I. General 1. Bank’s approval Date of the procurement Plan: January 10, 2017 (Original procurement plan). 2. Date of General Procurement Notice: NA 3. Period covered by this procurement plan: 18 months II. Goods and Works and non-consulting services. 1. Prior Review Threshold: Procurement Decisions subject to Prior Review by the Bank as stated in Appendix 1 to the Guidelines for Procurement: Procurement Method Prior Review Threshold Comments US$ 1. Goods Above US$ 4 million All 2. Works Above US$ 15 million All 3. Non-Consultant Services Above US$ 4 million All 2. Prequalification. NA. 3. Proposed Procedures for CDD Components (as per paragraph. 3.17 of the Guidelines: The Project Implementation Manual (PIM) makes reference to all applicable procurement guidelines and manuals including the Commune/Sangkat Fund PIM for small-scale infrastructure activities carried out by the sub-national levels (Commune/Sangkat), has been developed for this project. 4. Any Other Special Procurement Arrangements: 5 packages (goods) would be financed under retroactive financing 5. Summary of the Procurement Packages planned during the first 18 months after project effectiveness. 1 2 3 4 5 6 7 Ref. Description Estimated Packages Domest Review Comments No. Cost ic by Bank US$ Prefere (Prior / Post) million nce (yes/no) Community 5.48 60 No Post procured by infrastructur Communes/Sa es ngkats individually for the whole life of the project June 12, 2017 Procureme 0.92 8 No Post will be nt of procured vehicles, centrally at the office beginning of project equipment, implementation office (shopping furniture, method) motorcycle s, etc. III. Selection of Consultants 1. Prior Review Threshold: Selection decisions subject to Prior Review by Bank as stated in Appendix 1 to the Guidelines Selection and Employment of Consultants: Selection Method Prior Review Threshold Comments 1. Selection of Consulting firms Above US$ 2 million All 2. Selection of Individual Consultant Above US$ 400,000 All 2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $_300,000_equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines. 3. Any Other Special Selection Arrangements: 11 individual consultants would be financed through retroactive financing. 4. Consultancy Assignments with Selection Methods and Time Schedule 1 2 3 4 6 7 Ref. Description Estimated Pack Review Comments No. Cost ages by Bank US$ million (Prior / Post) Producer Group 0.34 1 Post QCBS method Mobilization for Siem Reap (NGO package) Self-help Group 0.27 1 Post QCBS method Mobilization for SRP (NGO) Human Resources 0.92 2 Post QBS method Development Services Provider (HRDSP) for Siem Reap (NGO/Firm) Consulting firms for 0.175 1 Post CQS method baseline survey, impact survey, and final impact June 12, 2017 survey, and External financial auditing Individual consultants 2.93 126 Post Selection of for supporting the individual national level and sub- consultant. national level project entities (finance, procurement, infrastructure, community development, micro- finance experts, livelihood specialists, etc.) June 12, 2017 PROCUREMENT Cambodia : KH - Livelihood Enhancement and Association of the Poor Project (LEAP) PLAN General Information Country: Cambodia Bank’s Approval Date of the Original Procurement Plan: 2017-06-12 2019-10-16 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P153591 GPN Date: Project Name: KH - Livelihood Enhancement and Association of the Poor Project (LEAP) Loan / Credit No: IDA / 59600 Executing Agency(ies): Ministry of Interior WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-99874-CW-RFQ / Pending Component 3: Project Request for Single Stage - One Office Renovation at PCO- IDA / 59600 Post Open - National 30,000.00 0.00 Implementati 2019-03-06 2019-04-17 2019-05-17 Management Quotations Envelope MOI on KH-MOI-99875-CW-CDD / The rehabilitation laterite road (Length 2400m, Width Component 1: Improving Community Pending 4.00m, 0.15m thick) and IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 28,341.00 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 Single Pipe Culvert Ø 1.0m and Vulnerable Households Development on (2 units) for Anlong Samnar, Chi Kraeng. KH-MOI-99886-CW-CDD / The rehabilitation laterite road ( Length 1500m, Width Component 1: Improving Community Pending 4.00m, 0.15m Thick) and IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 29,208.00 0.00 Implementati 2019-03-01 2019-03-08 2019-04-30 2019-05-07 2019-05-21 2019-08-19 Construction of Box Culver and Vulnerable Households Development on heigth 2m with Stop Log (1 unit) for Doun Kaev, Puok. KH-MOI-99878-CW-CDD / The rehabilitation laterite Component 1: Improving Community Pending road (Length 2419m, Width IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 25,921.00 0.00 Implementati 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 2019-07-11 3.50m, 0.15m thick) for Chi and Vulnerable Households Development on Kraeng, Chi Kraeng. KH-MOI-99880-CW-CDD / The rehabilitation laterite road (Length 2090m, Width 4.00m, 0.15m thick) and Component 1: Improving Community Pending Construction of Single Pipe IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 30,721.00 0.00 Implementati 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 2019-07-11 Culvert Ø 0.6m (1 unit), and Vulnerable Households Development on Single Pipe Culvert Ø 0.8m (1 unit) and Single Pipe Culvert Ø 1.0m (1unit) for Dan Run, Soutr Nikom. KH-MOI-99881-CW-CDD / The rehabilitation laterite road (Length 1550m, Width 4.00m, 0.15m thick), Single Component 1: Improving Community Pending Pipe Culvert Ø 1.0m (1unit) IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 29,965.00 0.00 Implementati 2019-03-01 2019-03-06 2019-04-17 2019-05-17 2019-06-21 2019-09-19 and Construction of Double and Vulnerable Households Development on Pipe Culvert Ø 0.8m (5units), for Ballangk, Prasat Bakong. Page 1 KH-MOI-99887-CW-CDD / Construction of Box Culvert heigth 2m with stop Log (1unit), Box Culvert heigth Component 1: Improving Community Pending 1.5m with stop Log (1unit) IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 29,896.00 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 Pipe Culver Ø 0.8m with and Vulnerable Households Development on Stop Log (1unit) and Single Pipe Culvert Ø 0.8m (4 unit) for Sasar Sdam, Puok. KH-MOI-99888-CW-CDD / Construction of Reinforced Component 1: Improving Community Pending Concrete Road (Lengh 260m, IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 30,417.00 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 width 5.00m, 0.15m thick) and Vulnerable Households Development on for Kampong Thkov, Kralanh. Total: 0.260 km KH-MOI-99890-CW-CDD / The rehabilitation ponds size (60mx30mx5m), Component 1: Improving Community Pending (30mx25mx5m), IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 29,949.00 0.00 Implementati 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-04-12 2019-07-11 (40mx20mx5m), and Vulnerable Households Development on (50mx50mx5m) for Slaeng Spean, Srei Snam. Total:4 Places KH-MOI-99891-CW-CDD / The rehabilitation laterite Component 1: Improving Community Pending road (1.450km) and Single IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 32,660.00 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 Pipe Culvert Ø 1.0m (3 and Vulnerable Households Development on units) for Svay Chek, Angkor Thum. KH-MOI-99892-CW-CDD / The rehabilitation laterite road ( Length 2520m, Width Component 1: Improving Community Pending 4.00m, 0.15 Thick) and IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 34,064.00 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 Construction of Single Pipe and Vulnerable Households Development on Culvert Ø 1.0m (2 unit) for Leang Dai, Angkor Thum. KH-MOI-99893-CW-CDD / The rehabilitation laterite road (Length 1080m, Width 4.00m, 0.15m thick) and Component 1: Improving Community Pending Construction of Single Pipe IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 27,869.20 0.00 Implementati 2019-03-01 2019-03-08 2019-03-22 2019-03-29 2019-05-07 2019-08-05 Culvert Ø 0.8m (1 unit) and and Vulnerable Households Development on Triple Pipe Culvert, Ø 1.0m (3 unit) for Ta Siem, Svay Leu. KH-MOI-99894-CW-CDD / Construction of Reinforced Component 1: Improving Community Pending Concrete Road (Length IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 48,510.00 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 445m, Width 3.50m, 0.15m and Vulnerable Households Development on thick) for khnang Phnum, Svay Leu. KH-MOI-99889-CW-CDD / The rehabilitation laterite Component 1: Improving Community Pending road (Length 2600m, Width IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 29,932.00 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 5.00m, 0.15m thick) for and Vulnerable Households Development on Klang Hay, Srei Snam. Total: 2.600 km Page 2 KH-MOI-110153-CW-CDD / Construction:1- Reinforcement concrete road:(L353m, W 4m, T0.15m) and drainage Component 1: Improving Community Pending system (L353m, 0.6m ) and IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 89,712.00 0.00 Implementati 2019-04-30 2019-05-07 2019-05-21 2019-05-28 2019-06-11 2019-09-09 2-Reinforcement concrete and Vulnerable Households Development on road (L357m, W 4m, T 0.15m) in Sangkat Dangkao, Khan Dangkao KH-MOI-110154-CW-CDD / Construction of Reinforcement concrete road and Drainage System: 1- Component 1: Improving Community Pending Road (100m) , 2-Road IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 98,080.00 0.00 Implementati 2019-05-15 2019-05-22 2019-06-05 2019-06-12 2019-06-26 2019-09-24 (171m ), 3-Road (52m), 4- and Vulnerable Households Development on Road(88m) ,5- Road (90m), 6- Road (93m) and 7-Road (L128m) in Sangkat Prey Veaeng, Khan Dangkao KH-MOI-110159-CW-CDD / Construction of reinforcement concrete road:(466m, width 5m, thickness 0.15m ), 2- Component 1: Improving Community Pending Road:(312m, width 4m, IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 105,204.00 0.00 Implementati 2019-05-15 2019-05-22 2019-06-05 2019-06-12 2019-06-26 2019-09-24 thickness 0.15m ) and and Vulnerable Households Development on drainage system:(312m,cross section 0.6m) in Sangkat Kork Roka, Khan Preak Pnov KH-MOI-110165-CW-CDD / Construction of reinforcement concrete road and and drainage system in Prey Component 1: Improving Community Pending Spueu & Prey Sandaek, IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 84,579.00 0.00 Implementati 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 2019-10-09 Sangkat Chaom Chau 2, and Vulnerable Households Development on Khan Por Sen Chey (663m) and drainage system (523m) in Sangkat Chaom Chau 2, Khan Por Sen Chey KH-MOI-110174-CW-CDD / Construction of reinforcement concrete: 1- Road(124m), 2- Road (137m). 3- Road (117m Component 1: Improving Community Pending ). 4-Installation of Sola IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 30,250.00 0.00 Implementati 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 2019-10-09 street lighting and poles and Vulnerable Households Development on (117m), and (139m ) in Sangkat Chbar Ampov Ti Pir, Khan Chbar Ampov KH-MOI-110155-CW-CDD / Construction of reinforcement concrete: 1- Road (99m) ,1- Road(101m), 2-Road(60m), 3- Drainage system:(9m), 4- Component 1: Improving Community Pending Installation of Sola street IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 28,703.49 0.00 Implementati 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 2019-12-25 lighting and poles and Vulnerable Households Development on (120m),(439m),(439m) and (98m) in Sangkat Chrang Chamreas Ti Muoy,Khan Russey Keo Page 3 KH-MOI-110151-CW-CDD / Construction: 1-Reinforcement concrete road (340m) and drainage system:(448m), 2- Road (L130m) and drainage Component 1: Improving Community Pending system (130m), 3-Road IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 171,670.08 0.00 Implementati 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 2019-12-25 (120m) and drainage and Vulnerable Households Development on system:(250m), 4- Road (238m) and drainage system (238m) in Sangkat Trapeang Krasang, Khan Por Sen Chey KH-MOI-110147-CW-CDD / Construction:1-Reinforcement concrete road, Drainage (L171m),Installation of Sola street lighting and Component 1: Improving Community Pending poles(171m), 2-Reinforcement IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 43,476.23 0.00 Implementati 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 2019-12-25 concrete and Vulnerable Households Development on road(147m),drainage(48m), Installation of Sola street lighting and poles (147m) in Sangkat Khmuonh, Khan Saen Sokh KH-MOI-110144-CW-CDD / Construction: 1-Reinforcement concrete road:(L262m, w 2.6m, T 0.12m) ,Drainage system:(262m,0.6m), 2- Component 1: Improving Community Pending Installation:(18 Sola street IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 71,818.97 0.00 Implementati 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 2019-12-25 lighting and poles for 262m) and Vulnerable Households Development on and 3-Concrete bridge: (L206m, width1.50m, T0.07m) in Sangkat Srah Chak, Khan Daun Penh KH-MOI-110162-CW-CDD / Construction of reinforcement concrete:1- road:(L102m, width 2.5m, thickness 0.12m) Component 1: Improving Community Pending and drainage IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 37,878.83 0.00 Implementati 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 2019-12-25 system:(114m).2- road:(169m, and Vulnerable Households Development on width 3.5m, thickness 0.15m) and drainage system:(169m) in Sangkat Boeng Kak 1, Khan Tuol Kork KH-MOI-110173-CW-CDD / Construction of reinforcement concrete: 1- Road(110m, width 4m, thickness 0.15m), Component 1: Improving Community Pending 2- Road(100m),2-Installation IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 30,281.06 0.00 Implementati 2019-08-15 2019-08-22 2019-09-05 2019-09-12 2019-09-26 2019-12-25 of Sola street lighting and and Vulnerable Households Development on poles (250m) in Khtor,Sangkat Preak Leap, Khan Chroy Changvar KH-MOI-110168-CW-CDD / Construction of reinforcement concrete:1- road(158m) and drainage (138m), 2-Road and drainage system (77m),3- Component 1: Improving Community Pending road(261m) and drainage IDA / 59600 Livelihoods for Rural Poor Post Driven Open - National 73,334.73 0.00 Implementati 2019-05-30 2019-06-06 2019-06-20 2019-06-27 2019-07-11 2019-10-09 (207m),4-Installation of Sola and Vulnerable Households Development on street lighting and poles(158m), (77m)and (261m) in Sangkat Chak Angrae Leu, Khan Mean Chey Page 4 GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-14029-GO-RFQ / Pending Office Furniture for National Component 3: Project Request for Single Stage - One IDA / 59600 Post Open - National 27,380.00 0.00 Implementati 2017-07-14 2017-09-03 2017-10-18 Level and Sub National Management Quotations Envelope on Level KH-MOI-14017-GO-RFQ / Pending Component 3: Project Request for Single Stage - One Softwares ( Accounting) for IDA / 59600 Post Open - National 10,000.00 0.00 Implementati 2017-07-31 2017-09-20 2017-11-19 Management Quotations Envelope PCO-MOI 1 unit on KH-MOI-26199-GO-RFB / Component 1: Improving Pending Motorcycles plus helmets for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Request for Bids Open - National 226,100.00 0.00 Implementati 2017-10-02 2017-10-16 2017-11-15 2017-12-06 2018-01-03 2018-03-04 National level and Sub- Envelope and Vulnerable Households on National (Total 133 Units) KH-MOI-26827-GO-RFB / Lot1: Develop Management Information System (MIS) Pending System Lot2: Component 3: Project Single Stage - One IDA / 59600 Post Request for Bids Open - National 140,000.00 0.00 Implementati 2017-11-01 2017-11-15 2017-12-15 2018-01-05 2018-02-02 2018-04-03 Server, Network, Tablet, Management Envelope on website, etc.) Lot 3:MIS webside maintenance for PCO-MOI KH-MOI-33988-GO-RFQ / 4 Pending Component 3: Project Request for Single Stage - One Laptop Computers for IDA / 59600 Post Open - National 9,200.00 0.00 Implementati 2017-11-05 2017-12-05 2017-12-20 Management Quotations Envelope Management on KH-MOI-34259-GO-RFB / Pending Office Equipment for Component 3: Project Single Stage - One IDA / 59600 Post Request for Bids Open - National 132,200.00 0.00 Implementati 2017-11-08 2017-11-13 2017-12-15 2018-01-14 2018-02-18 2018-04-19 National and Sub National Management Envelope on Leve KH-MOI-36613-GO-UN / Lot1:Vehicles (Station Wagon) 3 units for -PCO- MOI and 1 units for MEF, Component 1: Improving Pending UN Agencies Lot2:Vehicles (Pick up Cars) IDA / 59600 Livelihoods for Rural Poor Post Direct 330,000.00 0.00 Implementati 2017-11-17 2017-11-22 2017-12-25 2018-02-23 (Direct) for 1units for GDA-MAFF, 3 and Vulnerable Households on units for Siem Reap and 2 units for PPM. The total Vehicles: 10 Units KH-MOI-34266-GO-UN / Vehicles (Station Wagon) 3 Component 1: Improving UN Agencies units for -PCO-MOI and 1 IDA / 59600 Livelihoods for Rural Poor Post Direct 132,000.00 0.00 Canceled 2017-11-08 2017-11-13 2017-12-25 2018-02-23 (Direct) units for MEF, Total and Vulnerable Households Vehicles: 4 Units KH-MOI-11051-GO-RFB / Vehicles (Pick up Cars) for Component 1: Improving 1units for GDA-MAFF, 3 Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Request for Bids Open - National 198,000.00 0.00 Canceled 2017-10-02 2017-10-16 2017-11-15 2017-12-15 2018-01-07 2018-05-07 units for Siem Reap and 2 Envelope and Vulnerable Households units for PPM. Total Vehicles: 6 Units KH-MOI-99858-GO-RFQ / Pending Component 3: Project Request for Single Stage - One Total 7 Air Conditioners for IDA / 59600 Post Open - National 4,900.00 0.00 Implementati 2019-03-06 2019-04-03 2019-04-17 Management Quotations Envelope PCO and MAFF on KH-MOI-99860-GO-RFQ / Pending Component 3: Project Request for Single Stage - One Office Furniture for MOI- IDA / 59600 Post Open - National 20,000.00 0.00 Implementati 2019-03-06 2019-04-03 2019-05-03 Management Quotations Envelope PCO on Page 5 KH-MOI-99861-GO-RFQ / Printing Material and Component 1: Improving Pending Thumbprint pad for Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 22,644.00 0.00 Implementati 2019-03-06 2019-04-03 2019-05-03 SHG/producer Quotations Envelope and Vulnerable Households on group/commune federation for 2019 KH-MOI-99863-GO-RFQ / Material for SHG/producer Component 1: Improving Pending Request for Single Stage - One group/commune federation IDA / 59600 Livelihoods for Rural Poor Post Open - National 31,250.00 0.00 Implementati 2019-03-06 2019-04-24 2019-05-24 Quotations Envelope (Boxes for keeping and Vulnerable Households on documents and cash) KH-MOI-99865-GO-RFQ / Equipment for Component 1: Improving Pending Request for Single Stage - One Commune/Sangkat IDA / 59600 Livelihoods for Rural Poor Post Open - National 10,000.00 0.00 Implementati 2019-03-06 2019-04-03 2019-04-18 Quotations Envelope Investment Projects (SRP and Vulnerable Households on and PPCH) KH-MOI-99868-GO-RFQ / 72 Tablets for MIS (3 MoI, Component 1: Improving Pending Request for Single Stage - One 3 GDA, 3 PPCH, 3 Pro. IDA / 59600 Livelihoods for Rural Poor Post Open - National 24,840.00 0.00 Implementati 2019-04-06 2019-05-04 2019-06-03 Quotations Envelope S_Reap, 47 commune, 13 and Vulnerable Households on Sangkat) KH-MOI-99869-GO-RFQ / Printing Materials (Logos, Component 1: Improving Pending Request for Single Stage - One Printed Folder, Factsheets, IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,250.00 0.00 Implementati 2019-05-06 2019-06-03 2019-06-24 Quotations Envelope Newsletters, Brochures, and Vulnerable Households on Posters and Standing Poster) KH-MOI-99871-GO-RFQ / Printing Materials for Component 1: Improving Pending Request for Single Stage - One SHG/producer IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,145.00 0.00 Implementati 2019-12-06 2020-01-04 2020-02-03 Quotations Envelope group/commune federation for and Vulnerable Households on 2020 KH-MOI-26829-GO-RFB / Material for SHG/Poducer group/commune Component 1: Improving federation(books keeping, Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Request for Bids Open - National 126,250.70 0.00 Canceled 2017-11-01 2017-11-15 2017-12-15 2018-01-05 2018-02-02 2018-04-03 cash book, pay and loan Envelope and Vulnerable Households record book, SHG box for keeping docs. And Thumprint pad) for SRP KH-MOI-121052-GO-RFQ / Pending Procurement of supply Component 3: Project Request for Single Stage - One IDA / 59600 Post Open - National 20,000.00 0.00 Implementati 2019-07-10 2019-08-04 2019-09-03 Server and network for Management Quotations Envelope on LEAP Project KH-MOI-136652-GO-RFQ / Component 1: Improving Pending Request for Single Stage - One Office Furniture for Skill IDA / 59600 Livelihoods for Rural Poor Post Open - National 4,400.00 0.00 Implementati 2019-10-16 2019-11-11 2019-11-25 Quotations Envelope Development Activities and Vulnerable Households on KH-MOI-136666-GO-RFQ / Component 1: Improving Pending Motorcycles for Skill Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 17,500.00 0.00 Implementati 2019-10-16 2019-11-11 2019-11-25 Development Activities (10 Quotations Envelope and Vulnerable Households on Units) NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 6 KH-MOI-99864-NC-RFQ / Pending Component 3: Project Request for Single Stage - One Develop Website for LEAP IDA / 59600 Post Open - National 5,600.00 0.00 Implementati 2019-03-06 2019-04-03 2019-05-03 Management Quotations Envelope Projec on Component 1: Improving Pending KH-MOI-99870-NC-RFQ / Request for Single Stage - One IDA / 59600 Livelihoods for Rural Poor Post Open - National 20,000.00 0.00 Implementati 2019-07-06 2019-08-17 2019-10-16 Four (4) Video Spots Quotations Envelope and Vulnerable Households on CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-39863-CS-CQS / Consultant Impact Survey (3nd year of Component 3: Project Pending IDA / 59600 Post Qualification Open - National 30,000.00 0.00 2020-01-02 2020-01-23 2020-03-07 2020-04-06 2020-05-11 2020-11-07 the project/Mid-term review) Management Implementation Selection (Local Firm) at PCO-MOI KH-MOI-39867-CS-CQS / Final Impact Survey ( (5th Consultant Component 3: Project Pending year of Project evaluation IDA / 59600 Post Qualification Open - National 40,000.00 0.00 2022-01-03 2022-01-24 2022-03-09 2022-04-08 2022-05-13 2022-11-09 Management Implementation and completion report) (Local Selection Firm) at PCO-MOI KH-MOI-82848-CS-CQS / Development of Community Component 1: Improving Consultant Institutions of the Poor for Pending IDA / 59600 Livelihoods for Rural Poor Post Qualification Open - National 280,000.00 0.00 2018-10-22 2018-11-12 2019-01-11 2019-02-10 2019-03-17 2022-11-30 4 Districts​​  (Angkor Thum, Implementation and Vulnerable Households Selection Kralanh, Pouk and Srei Snam District) KH-MOI-82083-CS-CQS / Development of Community Institutions of the Poor for Component 1: Improving Consultant Pending 5 Districts ( Chi Kraeng, IDA / 59600 Livelihoods for Rural Poor Post Qualification Open - National 290,000.00 0.00 2018-10-22 2018-11-12 2019-01-11 2019-02-10 2019-03-17 2022-12-05 Implementation Prasat Bakong, Siem Reap, and Vulnerable Households Selection Soutr Nikom and Svay Leu District) KH-MOI-70310-CS-QCBS / Human Resource Component 1: Improving Quality And Cost- Open - Development Service IDA / 59600 Livelihoods for Rural Poor Prior 784,000.00 0.00 Canceled 2018-12-14 2019-01-13 2019-02-26 2019-04-12 2019-05-12 2019-06-16 2019-07-21 2023-06-30 Based Selection International Provider (HRDSP) for SRP and Vulnerable Households and PPCH KH-MOI-39858-CS-QCBS / Human Resources Component 2: Improving Quality And Cost- Open - Development Services IDA / 59600 Livelihoods for Urban Poor Post 367,932.00 0.00 Canceled 2017-12-29 2018-01-19 2018-03-04 2018-04-01 2018-05-01 2018-06-05 2018-07-10 2020-12-26 Based Selection International Provider(HRDSP) for PPM and Vulnerable Households (NGO/Firm) KH-MOI-39860-CS-CQS / Consultant Baseline Survey (1st Component 3: Project IDA / 59600 Post Qualification Open - National 30,000.00 0.00 Canceled 2018-01-15 2018-02-05 2018-03-21 2018-04-20 2018-05-25 2018-11-21 year)(Local Firm) at PCO- Management Selection MOI KH-MOI-39857-CS-QCBS / Human Resources Component 1: Improving Quality And Cost- Open - Development Services IDA / 59600 Livelihoods for Rural Poor Post 545,936.00 0.00 Canceled 2017-12-29 2018-01-19 2018-03-04 2018-04-01 2018-05-01 2018-06-05 2018-07-10 2020-12-26 Based Selection International Provider(HRDSP) for SRP and Vulnerable Households (NGO/Firm) INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Page 7 Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual KH-MOI-13893-CS-INDV / Component 1: Improving Individual Provincial Operation and Under IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 120,000.00 0.00 2017-06-26 2017-08-23 2017-09-06 2017-10-11 2022-10-10 M&E Specialist for SRP (60 Implementation and Vulnerable Households Selection Months) KH-MOI-13901-CS-INDV / Individual Component 3: Project Pending Project Assistant for PCO- IDA / 59600 Post Consultant Open 18,000.00 0.00 2017-07-17 2017-09-06 2017-09-20 2017-10-25 2020-10-24 Management Implementation MOI (60 Months) Selection KH-MOI-13903-CS-INDV / Component 2: Improving Individual National Operation and Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 150,000.00 0.00 2017-06-26 2017-08-23 2017-09-06 2017-10-11 2022-10-10 M&E Specialist for PPM (60 Implementation and Vulnerable Households Selection Months) KH-MOI-13905-CS-INDV / Component 1: Improving Individual Provincial Finance Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-06-26 2017-08-23 2017-09-06 2017-10-11 2020-10-10 Management Specialist for Implementation and Vulnerable Households Selection SRP (36 Months) KH-MOI-13907-CS-INDV / Component 1: Improving Individual Pending Project Assistant for SRP IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 15,000.00 0.00 2017-07-17 2017-09-06 2017-09-20 2017-10-25 2022-10-24 Implementation (60 Months) and Vulnerable Households Selection KH-MOI-13910-CS-INDV / Component 2: Improving Individual Pending Project Assistant for PPM IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 15,000.00 0.00 2017-07-17 2017-09-06 2017-09-20 2017-10-25 2022-10-24 Implementation (60 Months) and Vulnerable Households Selection KH-MOI-13913-CS-INDV / Component 2: Improving Individual 01 PPM Infrastructure Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 72,000.00 0.00 2017-07-17 2017-09-13 2017-09-27 2017-11-01 2020-10-31 Specialist at PPM (36 Implementation and Vulnerable Households Selection Months) KH-MOI-11055-CS-INDV / Individual National Project Management Component 3: Project Pending IDA / 59600 Post Consultant Open 180,000.00 0.00 2017-08-16 2017-10-13 2017-10-27 2017-12-01 2022-11-30 and M&E consultant at PCO- Management Implementation Selection MOI KH-MOI-11263-CS-INDV / Component 1: Improving Individual National Finance Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 90,000.00 0.00 2017-08-16 2017-10-13 2017-10-27 2017-12-01 2020-11-30 Management Specialist for Implementation and Vulnerable Households Selection MOI/PPM(36 Months) KH-MOI-13886-CS-INDV / Component 2: Improving Individual Pending National procurement IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 90,000.00 0.00 2017-08-16 2017-10-13 2017-10-27 2017-12-01 2020-11-30 Implementation Specialist based at PCO and Vulnerable Households Selection KH-MOI-30826-CS-INDV / Provincial Infrastructure Component 1: Improving Individual Pending Specialist (P M & E IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-10-16 2017-12-04 2017-12-25 2018-01-29 2021-01-13 Implementation Engineer) at SRP (36 and Vulnerable Households Selection Months) KH-MOI-30834-CS-INDV / Provincial Infrastructure Component 1: Improving Individual Pending Specialist (Building IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-10-16 2017-12-04 2017-12-25 2018-01-29 2021-01-13 Implementation Construction Engineer) at and Vulnerable Households Selection SRP (36 Months) KH-MOI-30840-CS-INDV / Provincial Infrastructure Component 1: Improving Individual Pending Specialist (Rural Road IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2017-10-16 2017-12-04 2017-12-25 2018-01-29 2021-01-13 Implementation Construction Engineer) at and Vulnerable Households Selection SRP (36 Months) KH-MOI-39794-CS-INDV / Individual Component 3: Project Pending International Micro-Finance IDA / 59600 Post Consultant Open 60,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2018-07-16 Management Implementation Expert at PCO-MOI(60 days) Selection Page 8 KH-MOI-39797-CS-INDV / Individual National Communication Component 3: Project Pending IDA / 59600 Post Consultant Open 90,000.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-14 Specialist at PCO-MOI (36 Management Implementation Selection Months) KH-MOI-39798-CS-INDV / Individual Component 3: Project Pending National MIS Specialist at IDA / 59600 Post Consultant Open 60,000.00 0.00 2017-12-29 2018-02-16 2018-03-09 2018-04-13 2020-04-02 Management Implementation PCO-MOI (24 Months) Selection KH-MOI-39800-CS-INDV / Component 1: Improving Individual National Agriculture Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 90,000.00 0.00 2018-01-15 2018-03-05 2018-03-26 2018-04-30 2021-04-14 Likelihood Specialist for Implementation and Vulnerable Households Selection GDA-MAFF (36 Months) KH-MOI-39817-CS-INDV / Component 1: Improving Individual National HR Development Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 48,000.00 0.00 2017-12-29 2018-02-16 2018-03-09 2018-04-13 2020-04-02 Specialist for SRP (24 Implementation and Vulnerable Households Selection Months) KH-MOI-39821-CS-INDV / Component 2: Improving Individual National HR Development Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 48,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2020-05-06 Specialist for PPM ( 24 Implementation and Vulnerable Households Selection Months) KH-MOI-39888-CS-INDV / 7 Component 1: Improving Individual Pending District Facilitators (7 DF x IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 336,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 Implementation 55 Months) at Siem Reap and Vulnerable Households Selection KH-MOI-40438-CS-INDV / Component 1: Improving Individual Provincial Micro-Finance Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 72,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2021-05-01 Specialist for SRP ( 36 Implementation and Vulnerable Households Selection Months) KH-MOI-40440-CS-INDV / Component 1: Improving Individual Senior Livelihood/business Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 90,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2021-05-01 development Specialist for Implementation and Vulnerable Households Selection SRP (36 Months) KH-MOI-40447-CS-INDV / Component 1: Improving Individual Pending 47 Commune Facilitators IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 564,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 Implementation (47CFs x55 Months) for SRP and Vulnerable Households Selection KH-MOI-40449-CS-INDV / 47 Commune Animal Health Component 1: Improving Individual Pending & Extension Workers (47 IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 338,400.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 Implementation CAHEW x 55 Months) for and Vulnerable Households Selection SRP KH-MOI-40453-CS-INDV / 4 Component 2: Improving Individual Local Coordinator for urban Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 96,000.00 0.00 2018-02-01 2018-03-22 2018-04-12 2018-05-17 2022-11-22 poor(4CLUPs x 55 Months) Implementation and Vulnerable Households Selection for PPM Individual KH-MOI-99872-CS-INDV / Component 3: Project Pending IDA / 59600 Post Consultant Open 15,000.00 0.00 2019-03-01 2019-04-21 2019-05-05 2019-06-09 2022-06-08 Project Assistant for MAFF Management Implementation Selection KH-MOI-99873-CS-INDV / Component 1: Improving Individual Pending Tracer Study Consultant (60 IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 18,000.00 0.00 2019-06-03 2019-07-22 2019-07-29 2019-08-12 2019-10-11 Implementation Working Days) and Vulnerable Households Selection KH-MOI-136635-CS-INDV / International Skill Component 1: Improving Individual Development Advisor (120 Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 112,800.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2020-03-27 days x 1 pax) for (20day- Implementation and Vulnerable Households Selection 2019, 80 days-2020 and 20 days-2021) Page 9 KH-MOI-136641-CS-INDV / Component 2: Improving Individual National Skills Development Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 85,000.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2022-09-13 Specialist (34 monthsx1pax) Implementation and Vulnerable Households Selection for PCO-LEAP KH-MOI-136643-CS-INDV / Component 2: Improving Individual Human Resource Pending IDA / 59600 Livelihoods for Urban Poor Post Consultant Open 190,400.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2022-09-13 Development Facilitators for Implementation and Vulnerable Households Selection SRP (34month x 7 paxes) KH-MOI-136648-CS-INDV / Component 1: Improving Individual Human Resource Pending IDA / 59600 Livelihoods for Rural Poor Post Consultant Open 81,600.00 0.00 2019-10-04 2019-11-10 2019-11-15 2019-11-28 2022-09-13 Development Facilitators for Implementation and Vulnerable Households Selection PPCH (34month x 3 paxes) Page 10