PROCUREMENT PLAN (Textual Part) Project information: [Mali] [Reinsertion of Ex-Combatants Project] [P157233] Project Implementation agency: [Project Implementation Unit (PIU) of the National Disarmament, Demobilization, and Reinsertion Commission (NDDRC)] Date of the Procurement Plan: [01/28/2018] Period covered by this Procurement Plan: [02/15/2018 to 07/28/2019] Preamble In accordance with paragraph 5.9 of the “World Bank Procurement Regulations for IPF Borrowers” (July 2016) (“Procurement Regulations”) the Bank’s Systematic Tracking and Exchanges in Procurement (STEP) system will be used to prepare, clear and update Procurement Plans and conduct all procurement transactions for the Project. This textual part along with the Procurement Plan tables in STEP constitute the Procurement Plan for the Project. The following conditions apply to all procurement activities in the Procurement Plan. The other elements of the Procurement Plan as required under paragraph 4.4 of the Procurement Regulations are set forth in STEP. The Bank’s Standard Procurement Documents: shall be used for all contracts subject to international competitive procurement and those contracts as specified in the Procurement Plan tables in STEP. National Procurement Arrangements: In accordance with paragraph 5.3 of the Procurement Regulations, when approaching the national market (as specified in the Procurement Plan tables in STEP), the country’s own procurement procedures may be used. When the Borrower uses its own national open competitive procurement arrangements as set forth in the [Decree No. 2015-3721 /MEF-SG dated October 22, 2015], such arrangements shall be subject to paragraph 5.4 of the Procurement Regulations. When other national procurement arrangements other than national open competitive procurement arrangements are applied by the Borrower, such arrangements shall be subject to paragraph 5.5 of the Procurement Regulations. Leased Assets as specified under paragraph 5.10 of the Procurement Regulations: Leasing may be used for those contracts identified in the Procurement Plan tables. Not Applicable Procurement of Second Hand Goods as specified under paragraph 5.11 of the Procurement Regulations – is allowed for those contracts identified in the Procurement Plan tables Not Applicable Domestic preference as specified under paragraph 5.51 of the Procurement Regulations (Goods and Works). Goods: [is not applicable]; Works: [is not applicable] Other Relevant Procurement Information. PROCUREMENT Mali : Mali Reinsertion of Ex-combatants Project PLAN General Information Country: Mali Bank’s Approval Date of the Original Procurement Plan: 2018-01-30 2020-02-24 Revised Plan Date(s): (comma delineated, leave blank if none) Project ID: P157233 GPN Date: Project Name: Mali Reinsertion of Ex-combatants Project Loan / Credit No: IDA / D1680 Executing Agency(ies): ML Reinsertion of Ex-combatants Project WORKS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CW-KID-03 / Tv. réalisation et équip. de 2 forages avec Single Stage - One En attente système solaire à Tintiska et IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 68,970.00 0.00 2019-11-27 2020-01-16 2020-03-01 Envelope d'exécution à Tinta ghène région de Kidal CW-KID-14 / Travaux de surcreusement de puits Single Stage - One En attente pastoral à IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 43,103.00 0.00 2020-07-18 2020-09-06 2020-12-05 Envelope d'exécution Anoumalène/aguelhoc dans la région de Kidal CW-TOM-07 / Tv réhabilitation du château du CSREF de Tombouctou ; Tv Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 71,154.00 0.00 2019-12-04 2020-01-23 2020-03-08 de réalisation d’une ADS à Envelope d'exécution Alkama bangou à Nboura région de Tombouctou CW-KID-07 / Tv. réalisation et équip 1 puit à Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 20,688.00 0.00 2020-02-22 2020-03-26 2020-05-10 Anhar/Tinzawatène commune Envelope d'exécution de Abeibara région de Kidal CW-KID-06 / Tv. réhab. du Single Stage - One En attente radier de amassine dans la IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 31,923.00 0.00 2019-10-23 2019-11-25 2019-12-25 Envelope d'exécution région de Kidal CW-MEN-05 / Travaux de réhabilitation trois adductions d'eau sommaire (AES) à Inzougaz, Assew et Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 85,801.00 0.00 2020-07-29 2020-09-17 2020-12-16 Tinazabène et de réalisation Envelope d'exécution d’une adduction d’eau à Wortakna dans la région de Ménaka CW-TOM-12 / Travaux de construction d'un forage équipé d'un château et Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 41,500.00 0.00 2020-08-08 2020-09-27 2020-12-26 pompe solaire à Faytawane Envelope d'exécution dans la région de Tombouctou CW-TOM-13 / Travaux de réhabilitation du canal principale et équipement Single Stage - One En attente d'un périmètre pour la IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 13,534.00 0.00 2020-08-08 2020-09-27 2020-11-26 Envelope d'exécution culture du riz à Mamadoukoyra dans la région de Tombouctou Page 1 CW-GAO-14 / Travaux de surcreusement de 2 marres à Moudett et Intillit Nord à Moudett et Intillit, de construction d'une digue avec Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 37,931.00 0.00 2020-08-26 2020-10-15 2020-12-29 ouvrage à submersion Envelope d'exécution controlée à Abba Koyra et de construction d'un parc de vaccination à Haoussa dans la région de Gao CW-MEN-03 / Travaux de réalisation et équipement Single Stage - One En attente d’un forage à Adalwag IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 35,512.00 0.00 2019-10-26 2019-11-28 2020-01-12 Envelope d'exécution commune de Tidermène dans la région de Ménaka CW-KID-01 / Tv. Const. 3 salles de classe équipées 3 Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 46,552.00 0.00 2019-10-23 2019-11-25 2019-12-25 latrines et bureau mag. à Envelope d'exécution Efereur région de Kidal CW-GAO-10 / Travaux de réalisation et équipement de 3 forages en pompe solaire à Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 171,914.00 0.00 2019-11-05 2019-12-08 2020-01-07 Tabankorte à Almoustarat Envelope d'exécution et Nbeykoul lajoulla région de Gao CW-KID-10 / Travaux de construction d'une digue de Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 75,862.00 0.00 2020-07-21 2020-09-09 2020-12-08 protection à Kidal aviation, Envelope d'exécution région de Kidal CW-TOM-14 / Travaux de construction de 2 salles de Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 39,326.00 0.00 2020-08-08 2020-09-27 2020-12-11 classe à Milala dans la Envelope d'exécution région de Tombouctou CW-GAO-13 / Travaux de réalisation d’un périmètre maraicher pour la coopérative des femmes à Single Stage - One En attente Taboye et d’un périmètre 3 IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 19,224.00 0.00 2020-08-22 2020-10-11 2021-01-09 Envelope d'exécution hectares pour l’association des groupements ruraux villageois à Gounga dans la région de Gao CW-GAO-03 / Tv const. 2 magasins dans le marché Taboye Commune Taboye cercle Bourem , Tv Const. 6 Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 31,035.00 0.00 2019-11-02 2019-12-05 2020-01-04 hangars dans le marché Envelope d'exécution TEMERA Commune de Temera cercle Bourem dans la région de Gao CW-GAO-04 / Travaux d’aménagement de la plaine Single Stage - One En attente de Moudakhane Commune IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 77,204.00 0.00 2019-11-02 2019-12-05 2020-01-04 Envelope d'exécution de Taboye cercle Bourem dans la région de Gao CW-MOP-02 / Travaux d'Aménag. de la marre de Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 78,144.00 0.00 2019-10-20 2019-11-22 2019-12-22 Bergue Kounari à Manaco Envelope d'exécution région de Mopti Page 2 CW-GAO-01 / Construction de 3 salles de classes, Bureau magasin et de 2 Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 73,686.00 0.00 2019-11-03 2019-12-06 2019-12-12 blocs de 3 latrines à Envelope d'exécution Tindjirindjitane Tessit dans la région de Gao CW-GAO-11 / Travaux de réalisation et équipement d’un forage en PMH à Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 43,103.00 0.00 2020-03-29 2020-05-18 2020-07-17 Tinassamede cercle de Envelope d'exécution Bourem dans la région de Gao CW-TOM-11 / Travaux de réhabilitation d'une dune Single Stage - One En attente ecole Oguenatt Ag IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 25,862.00 0.00 2019-11-02 2019-12-05 2020-01-04 Envelope d'exécution ALWEYNA Ebanguimalane à GOSSI Gourma rharous CW-TOM-15 / Travaux d’équipement d'un forage en mini adduction d'eau à Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 39,326.00 0.00 2020-08-08 2020-09-27 2020-12-26 Amachachare à Imbodiki Envelope d'exécution dans la région de Tombouctou CW-KID-02 / Tv. réalisation et équip. 2 forage avec Single Stage - One En attente système solaire à Djanchassé IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 85,960.00 0.00 2019-11-27 2020-01-16 2020-03-01 Envelope d'exécution et à Takalout région de Kidal CW-TOM-04 / Travaux de fonçage d’un puit pastoral à Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 27,557.00 0.00 2019-11-27 2020-01-16 2020-03-01 Sakarouratan à BER dans Envelope d'exécution la région de Tombouctou CW-TAO-03 / Travaux de Single Stage - One En attente construction d'un poste de IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 60,259.00 0.00 2019-10-30 2019-12-02 2020-01-31 Envelope d'exécution santé avancé Taoudénit CW-MOP-06 / Travaux de réalisation de trois périmètres maraichers à simérou, à Mopti pour les Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 158,814.00 0.00 2020-07-06 2020-08-25 2020-11-23 femmes et à Dia pour Envelope d'exécution l’association des femmes de Dia BENKOLA dans la région de Mopti CW-TAO-02 / Tv const. 3 salles classes bureau magasin et un bloc 3 latrines Foum Elba cercle de Foum Elba et Tv const. 3 Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 139,102.00 0.00 2019-10-30 2019-12-02 2020-01-16 salles classes bureau Envelope d'exécution magasin et un bloc 3 latrines Al ourch cercle de Al ourch région de Taoudénit CW-MOP-04 / Tv 1 radier 50m kanibonzo: Const. clôture école diandiori Single Stage - One En attente Sokoura; Const. 1mag stoc. IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 103,917.00 0.00 2019-10-19 2019-11-21 2019-12-21 Envelope d'exécution Ass. karanga Guiné;Const. salle d’obs. mag. au CSR de Bankass Page 3 CW-KID-08 / Travaux de réalisation de deux (02) Single Stage - One En attente forages équipés à Djalguit et IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 81,896.00 0.00 2020-07-20 2020-08-25 2020-11-23 Envelope d'exécution Tagorast dans la région de Kidal CW-KID-09 / Travaux de réalisation de trois (3) forages équipés de Système Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 129,300.00 0.00 2020-07-21 2020-09-09 2020-09-18 Solaire àTidjazal, Intilit et Envelope d'exécution Abatolnmanit dans la région de Kidal CW-KID-11 / Travaux de réalisation et d’équipement de trois (3) puits citernes, Single Stage - One En attente de château et système IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 85,344.00 0.00 2020-07-21 2020-09-09 2020-12-08 Envelope d'exécution solaire à Abuyou, Agazer et Ibadid dans la région de Kidal CW-KID-12 / Travaux de réalisation de deux forages équipés de Système Solaire Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 86,206.00 0.00 2020-07-21 2020-09-09 2020-09-18 à Tacharaght et Envelope d'exécution Imasrakaden dans la région de Kidal CW-KID-15 / Travaux de construction de la digue de Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 86,207.00 0.00 2020-07-18 2020-09-06 2020-12-05 protection d'Aguelhock dans Envelope d'exécution la région de Kidal CW-MEN-06 / Travaux d’équipement en systéme d'adduction d'eau sommaire à Afaisawa, de forage à Single Stage - One En attente Inafere et Tabakort, de IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 79,870.00 0.00 2020-07-29 2020-09-17 2020-12-16 Envelope d'exécution réhabilitation d’une adduction d'eau sommaire (AES) à Elangue dans la région de Ménaka CW-MEN-07 / Construction d'un parc de vaccination à Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 29,310.00 0.00 2020-07-29 2020-09-17 2020-12-16 Andéraboukane dans la Envelope d'exécution région de Ménaka CW-MOP-07 / Travaux de réalisation d'un puits Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 45,534.00 0.00 2020-07-11 2020-08-30 2020-11-28 moderne dans la région de Envelope d'exécution Mopti CW-TAO-04 / Travaux de Réalisation de deux (2) forges équipés de pompe solaire avec mini d'adduction Single Stage - One En attente d’eau sommaire de 3 bornes IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 121,264.00 0.00 2019-10-30 2019-12-02 2021-09-07 Envelope d'exécution fontaines à Tinaghalhaj et à M’Back Semna dans le Cercle d’Araoune reion Taoudenit CW-MOP-05 / Tv. réalisat. d’un jardin d’arbres fruitiers Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 35,873.00 0.00 2019-10-20 2019-11-22 2019-11-25 à Kanibonzo dans la région Envelope d'exécution de Mopti Page 4 CW-GAO-12 / Travaux de réalisation d'un forage équipé de PMH à Tinassamede, d’un puits d'un Single Stage - One En attente à grand diamètre à IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 55,173.00 0.00 2020-08-22 2020-10-11 2021-01-09 Envelope d'exécution Inamakka et d'un mini forage californien équipé motopompe dans la région de Gao CW-TOM-06 / Tv construction d’un mur de Single Stage - One En attente clôture du second cycle « IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 35,432.00 0.00 2019-12-04 2020-01-23 2020-03-08 Envelope d'exécution yehia alkaya de Tombouctou » région de Tombouctou CW-MEN-02 / Travaux de construction et équipement de 3 salles de classes Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 50,695.00 0.00 2019-11-20 2020-01-09 2020-01-13 équipées à Echaghane Envelope d'exécution commune de Tidèrmène dans la région de Ménaka CW-TOM-08 / Tv réalisation et équipement 1 forage en pompe solaire à Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 60,734.00 0.00 2019-11-19 2020-01-08 2020-02-22 Tabaye-barite commune de Envelope d'exécution Tilemsi cercle Goundam région de Tombouctou CW-TOM-03 / Tv. de réhabilitation d'une AES par soufflage Tindaydaye GOSSI Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 45,348.00 0.00 2019-11-02 2019-12-05 2020-01-19 et Tv. réalisation AES à Envelope d'exécution Tintahaten Gossi dans la région de Tombouctou CW-MOP-01 / Tv. d'Aménag. périmètre maraîcher avec mini Single Stage - One En attente adduction d’eau pour IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 51,080.00 0.00 2019-10-20 2019-11-22 2019-12-22 Envelope d'exécution l'association djiguiya de Saoula à Djenne région de Mopti CW-TOM-10 / Travaux de réalisation et équipement d’un forage moderne en château d’eau et panneaux Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 42,362.00 0.00 2020-03-11 2020-04-30 2020-07-29 solaires à Djiri berra Envelope d'exécution goungou cercle de Gourma- Rharous dans la région de Tombouctou CW-GAO-09 / Travaux de réalisation d'éclairage public Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 67,839.00 0.00 2019-11-05 2019-12-25 2020-01-24 à Borno dans le cercle de Envelope d'exécution Bourem region de gao CW-MEN-01 / Tv. Const.salle de formation et de bureaux pour les femmes d'Anderaboukane Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 51,724.00 0.00 2019-11-20 2020-01-09 2020-02-08 Tv const.maison et centre de Envelope d'exécution formation les jeunes d'Anderaboukane dans la région de Ménaka Page 5 CW-GAO-15 / Travaux de réalisation deux forages Single Stage - One En attente équipés de pompe solaire à IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 79,151.00 0.00 2020-08-26 2020-10-15 2021-01-13 Envelope d'exécution Taffassilite et à Injaguel dans la région de Gao CW-MEN-04 / Travaux de réalisation de deux forages dont un de 180mn à Single Stage - One En attente Agadèye et à Inaghade et IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 87,063.00 0.00 2020-07-29 2020-09-17 2020-12-16 Envelope d'exécution d’un château d’eau sur puits existant à Tamtak dans la région de Ménaka CW-MOP-03 / TTravaux de Réalisation d’un forage avec Single Stage - One En attente adduction d’eau sommaire de IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 67,845.00 0.00 2019-10-20 2019-11-22 2020-01-06 Envelope d'exécution Kende à Bondy région de Mopti CW-TOM-09 / Travaux de réhabilitation d’un CSCOM, d’une école et d’un puit à Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 86,170.00 0.00 2019-12-04 2020-01-23 2020-03-08 Teberent, Cercle de Gourma- Envelope d'exécution Rharous dans la région de Tombouctou CW-TOM-05 / Tv de réalisation et équipement d’un forage en pompe solaire Single Stage - One En attente à Tin Afferene à Gargando IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 103,443.00 0.00 2019-11-02 2019-12-05 2020-01-19 Envelope d'exécution et Tv de réalisation d’une AES à Gargando dans la région de Tombouctou CW-TAO-01 / Tv. F/P Single Stage - One En attente Poteaux élect. Compt. Bouge IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 69,551.00 0.00 2019-10-30 2019-12-02 2020-01-01 Envelope d'exécution Beha Taoudénit CW-GAO-06 / Travaux de réalisation et équipement d'un forage équipé d’une Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 39,655.00 0.00 2019-11-05 2019-12-08 2020-01-22 pompe solaire à Intilit Envelope d'exécution commune de Tilemsi dans la région de Gao CW-KID-04 / Tv. réalisation et équip. 2 forages avec système solaire à Guljiat Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 90,258.00 0.00 2019-11-27 2020-01-16 2020-03-01 Tinessako et Tagoraste Envelope d'exécution Achibogho dans la région de Kidal CW-GAO-02 / Tv const. 03 magasins de stockage de 4 m X 4 m chacun à Bara, Tabangaw et Tanal dans la Commune de BARA cercle Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 41,379.00 0.00 2019-11-02 2019-12-05 2020-01-04 Ansongo , Tv const. d'un Envelope d'exécution magasin de stockage de 4 m X 4 m à Talataye dans la Commune de Talataye cercle Ansongo région de Gao CW-KID-13 / Travaux de réalisation d'un puit avec Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 26,002.00 0.00 2020-07-18 2020-09-06 2020-12-05 équipement solaire à Tassick Envelope d'exécution dans la région de Kidal Page 6 GOODS Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GO-REF-7 / Achat de matériels informatiques Project Management Support Single Stage - One En attente pour l’UEP et de matériels IDA / D1680 to Project Implementation A posteriori Demande de prix Limited 47,681.00 0.00 2018-03-09 2018-05-04 2018-05-19 Envelope d'exécution de communication et de Unit sensibilisation GO-REF-4 / Acquisition de Project Management Support Single Stage - One En attente 2 Véhicules station wagon IDA / D1680 to Project Implementation A posteriori Demande de prix Limited 144,928.00 0.00 2018-04-09 2018-06-04 2018-07-04 Envelope d'exécution pour les missions de l'UEP Unit GO-REF-5 / Acquisition de Project Management Support Single Stage - One En attente groupe électrogène de 50 IDA / D1680 to Project Implementation A posteriori Demande de prix Limited 24,155.00 0.00 2018-03-25 2018-05-20 2018-06-04 Envelope d'exécution KVA pour l’UEP Unit GO-REF-6 / Aquisition de 3 Project Management Support Single Stage - One En attente motos pour chauffeurs et IDA / D1680 to Project Implementation A posteriori Demande de prix Limited 2,899.00 0.00 2018-05-29 2018-07-24 2018-08-08 Envelope d'exécution coursier Unit GO-REF-8 / Equipement de Project Management Support Single Stage - One En attente la salle de conférence de IDA / D1680 to Project Implementation A posteriori Demande de prix Limited 8,293.00 0.00 2018-03-25 2018-05-20 2018-06-09 Envelope d'exécution l’UEP et petits equipements Unit ML-PREC-51762-GO-RFB / Acquisition, transport, Stockage, distribution de Reinsertion Support to Open - Single Stage - One En attente Kits de demarrage pour la IDA / D1680 A posteriori Appel d'offres 1,920,000.00 0.00 2018-06-15 2018-06-20 2018-08-01 2018-08-11 2018-09-08 2018-12-07 Demobilized Ex-combatants International Envelope d'exécution réinsertion des Ex combattants dans les 6 régions GO-REF-11 / Confection Project Management Support Agenda, Calendrier, cartes Single Stage - One En attente IDA / D1680 to Project Implementation A posteriori Demande de prix Limited 10,000.00 0.00 2018-12-14 2019-01-02 2019-01-17 de visites et gadgets de Envelope d'exécution Unit communication GO-TAO-01 / Acq 20 Single Stage - One En attente décortiqueuses Almatla IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 44,414.00 0.00 2019-10-30 2019-12-02 2020-05-30 Envelope d'exécution région de Taoudénit GO-TOM-01 / Acq Grpes Moto pompes à Gourzouguèye et Tourchawane; à 10 groupement maraichers féminins Banikane Niafunké; Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 129,656.00 0.00 2019-12-18 2020-02-06 2020-03-07 pour les ass.« Aniya de Envelope d'exécution thiaye et diékabara de sandy » de Koumayra ; à 10 groupements féminins de Ngorkou région de Tombouctou GO-TOM-02 / Acquisition de 3 moulins et de 7 décortiqueuses aux Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 25,483.00 0.00 2019-11-02 2019-12-05 2020-01-04 associations de femmes de Envelope d'exécution Diré dans la région de Tombouctou Page 7 GO-TOM-06 / Acquisition d'animaux pour la reconstitution de cheptel au profit des jeunes à risques de 4 fractions d’éleveurs à Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 42,414.00 0.00 2019-11-02 2019-12-05 2019-12-08 Lafia et au profit des Envelope d'exécution communautés d’éleveurs de Gossi cercle de Gourma- Rharous dans la région de Tombouctou GO-MEN-04 / Acquisition d’animaux pour la reconstitution de cheptel à Single Stage - One En attente Tiderméne au profit de 107 IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 34,229.00 0.00 2020-07-25 2020-09-13 2020-10-13 Envelope d'exécution familles et des communautés de Tinabaw dans la région de Ménaka GO-REF-2 / Acquisition équipement du Système Reinsertion Support to Single Stage - One En attente IDA / D1680 A posteriori Demande de prix Limited 64,412.00 0.00 2018-04-07 2018-05-17 2018-07-01 d’Information et de Gestion Demobilized Ex-combatants Envelope d'exécution (SIG) GO-MOP-04 / Acq. Mob. Scolaires des écoles Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 12,036.00 0.00 2019-10-20 2019-11-22 2019-12-22 Commune Soubala cercle de Envelope d'exécution bankass région de Mopti GO-MEN-03 / Acq Equip CSCOM de Emiss-Emiss Single Stage - One En attente IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 34,479.00 0.00 2019-10-27 2019-11-29 2019-12-29 commune de Inékar région Envelope d'exécution de Ménaka Project Management Support GO-REF-10 / Fourniture de Single Stage - One En attente IDA / D1680 to Project Implementation A posteriori Demande de prix Limited 11,667.00 0.00 2018-12-12 2018-12-29 2019-01-13 Comsommables de Bureau Envelope d'exécution Unit GO-GAO-01 / Acquisition d’animaux au bénéfice de Single Stage - One En attente trois groupements d’éleveurs IDA / D1680 Community Rehabilitation A posteriori Demande de prix Limited 11,379.00 0.00 2020-08-26 2020-10-15 2020-11-14 Envelope d'exécution de Tinahamma dans la région de Gao NON CONSULTING SERVICES Bid Evaluation Activity Reference No. / Draft Bidding Loan / Credit Market Procurement Prequalification Estimated Actual Amount Process Draft Pre-qualification Prequalification Specific Procurement Bidding Documents Proposal Submission / Report and Description Component Review Type Method Document / Signed Contract Contract Completion No. Approach Process (Y/N) Amount (US$) (US$) Status Documents Evaluation Report Notice / Invitation as Issued Opening / Minutes Recommendation for Justification Award Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual GO-REF-9 / Acquisition et Project Management Support installation d'un logiciel de Single Stage - One En attente IDA / D1680 to Project Implementation A posteriori Demande de prix Open - National 59,581.00 0.00 2018-04-14 2018-05-26 2021-05-25 comptabilité pour le projet Envelope d'exécution Unit et formation des utilisateurs CONSULTING FIRMS Activity Reference No. / Combined Evaluation Loan / Credit Market Contract Type Estimated Actual Expression of Interest Short List and Draft Request for Proposals Opening of Technical Evaluation of Description Component Review Type Method Process Status Terms of Reference Report and Draft Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Notice Request for Proposals as Issued Proposals / Minutes Technical Proposal Negotiated Contract Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual Page 8 CS-REF-2 / P.E pour l'Encadrement, l'Appui conseil, l'Orientation et Sélection fondée Reinsertion Support to Open - dispense de Kit de formation IDA / D1680 A priori sur la qualité et 1,000,000.00 0.00 Annulé 2018-02-06 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Demobilized Ex-combatants International aux ex- combattants le coût démobilisés dans la région de Mopti. CS-REF-3 / P.E pour l'Encadrement, l'Appui conseil, l'Orientation et Sélection fondée Reinsertion Support to Open - dispense de Kit de formation IDA / D1680 A priori sur la qualité et 1,000,000.00 0.00 Annulé 2018-02-06 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Demobilized Ex-combatants International aux ex- combattants le coût démobilisés dans la région de Gao CS-REF-5 / P.E pour l'Encadrement, l'Appui conseil, l'Orientation et Sélection fondée Reinsertion Support to Open - dispense de Kit de formation IDA / D1680 A priori sur la qualité et 1,000,000.00 0.00 Annulé 2018-02-06 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Demobilized Ex-combatants International aux ex- combattants le coût démobilisés dans la région de Kidal. CS-REF-7 / P.E pour l'Encadrement, l'Appui conseil, l'Orientation et Sélection fondée Reinsertion Support to Open - dispense de Kit de formation IDA / D1680 A priori sur la qualité et 1,000,000.00 0.00 Annulé 2018-02-06 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Demobilized Ex-combatants International aux ex- combattants le coût démobilisés dans la région de Taoudenit. CS-REF-9 / Recrutement des Prestataires d'appui au Sélection fondée Reinsertion Support to Open - En attente démarrage des associations IDA / D1680 A posteriori sur la qualité et 300,000.00 0.00 2018-07-18 2018-07-23 2018-08-20 2018-09-17 2018-09-22 2018-10-11 2018-11-15 2018-12-30 Demobilized Ex-combatants International d'exécution économiques et des le coût coopératives CS-REF-10 / Recrutement des Prestataires pour Sélection fondée Reinsertion Support to Open - En attente Dispense des activités IDA / D1680 A posteriori sur la qualité et 600,000.00 0.00 2018-03-30 2018-04-04 2018-05-02 2018-05-30 2018-06-06 2018-06-23 2018-07-28 2019-07-28 Demobilized Ex-combatants International d'exécution d'appui à la réinsertion le coût sociale Sélection fondée CS-REF-11 / Contrat de Reinsertion Support to sur les En attente l'évaluation annuelle IDA / D1680 A posteriori Open - National 60,000.00 0.00 2018-06-19 2018-07-10 2018-08-23 2018-09-22 2018-10-27 2019-04-25 Demobilized Ex-combatants qualifications des d'exécution Indépendante (Audit externe) consultants CS-REF-8 / Recrutement d'un consultant pour l'appui Sélection fondée psycho social en faveur des Reinsertion Support to sur les Open - En attente ex combattants démobilisés IDA / D1680 A posteriori 45,480.00 0.00 2018-04-22 2018-05-06 2018-05-27 2018-06-03 2018-07-04 2019-07-04 Demobilized Ex-combatants qualifications des International d'exécution souffrant de maladies psycho consultants sociales et de troubles mentaux CS-REF-25 / P.E N°02 pour l'Encadrement, l'Appui Sélection fondée conseil, l'Orientation et Reinsertion Support to sur les En attente dispense de Kit de formation IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-15 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Demobilized Ex-combatants qualifications des d'exécution aux ex- combattants consultants démobilisés dans la région de Taoudenit. CS-REF-22 / P.E N°02 pour l'Encadrement, l'Appui Sélection fondée conseil, l'Orientation et Reinsertion Support to sur les En attente dispense de Kit de formation IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-15 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Demobilized Ex-combatants qualifications des d'exécution aux ex- combattants consultants démobilisés dans la région de Tombouctou. Page 9 CS-REF-23 / P.E N°02 pour l'Encadrement, l'Appui Sélection fondée conseil, l'Orientation et Reinsertion Support to sur les En attente dispense de Kit de formation IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-15 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Demobilized Ex-combatants qualifications des d'exécution aux ex- combattants consultants démobilisés dans la région de Kidal. CS-REF-18 / P.E pour l'Encadrement, l'Appui Sélection fondée conseil, l'Orientation et Reinsertion Support to sur les En attente dispense de Kit de formation IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-06 2019-10-21 2019-11-15 2019-11-30 2019-12-21 2020-12-20 Demobilized Ex-combatants qualifications des d'exécution aux ex- combattants consultants démobilisés dans la région de Taoudenit. CS-REF-17 / P.E N°01 pour l'Encadrement, l'Appui Sélection fondée conseil, l'Orientation et Reinsertion Support to sur les En attente dispense de Kit de formation IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-16 2019-10-31 2019-11-25 2019-12-10 2019-12-31 2020-12-30 Demobilized Ex-combatants qualifications des d'exécution aux ex- combattants consultants démobilisés dans la région de Kidal. CS-REF-24 / P.E N°02 pour l'Encadrement, l'Appui Sélection fondée conseil, l'Orientation et Reinsertion Support to sur les En attente dispense de Kit de formation IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-15 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Demobilized Ex-combatants qualifications des d'exécution aux ex- combattants consultants démobilisés dans la région de Menaka. CS-REF-20 / P.E N°02 pour l'Encadrement, l'Appui Sélection fondée conseil, l'Orientation et Reinsertion Support to sur les En attente dispense de Kit de formation IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-15 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Demobilized Ex-combatants qualifications des d'exécution aux ex- combattants consultants démobilisés dans la région de Mopti. CS-REF-21 / P.E N°02 pour l'Encadrement, l'Appui Sélection fondée conseil, l'Orientation et Reinsertion Support to sur les En attente dispense de Kit de formation IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-16 2019-10-31 2019-11-25 2019-12-10 2019-12-31 2020-12-30 Demobilized Ex-combatants qualifications des d'exécution aux ex- combattants consultants démobilisés dans la région de Gao. CS-REF-14 / P.E N°01 pour l'Encadrement, l'Appui Sélection fondée conseil, l'Orientation et Reinsertion Support to sur les En attente dispense de Kit de formation IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-15 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Demobilized Ex-combatants qualifications des d'exécution aux ex- combattants consultants démobilisés dans la région de Mopti. CS-REF-15 / PE N°01 pour l'Encadrement l'Appui conseil Sélection fondée l'Orientation et dispense de Reinsertion Support to sur les En attente IDA / D1680 A posteriori Open - National 120,000.00 0.00 2019-10-15 2019-10-30 2019-11-24 2019-12-09 2019-12-30 2020-12-29 Kit de formation aux ex- Demobilized Ex-combatants qualifications des d'exécution combattants démobilisés dans consultants la région de Gao CS-REF-31 / Recrutement d'un Consultant dans la Sélection fondée région de Mopti pour sur les En cours Etudes/Suivi et Contrôle IDA / D1680 Community Rehabilitation A posteriori Open - National 45,208.00 0.00 2019-10-14 2019-10-29 2019-11-20 2019-12-05 2019-12-26 2020-06-23 qualifications des d'exécution dans le cadre de l'execution consultants des sous projets de la composante 3 Page 10 CS-REF-32 / Recrutement d'un Consultant dans la Sélection fondée région de Gao pour sur les En cours Etudes/Suivi et Contrôle IDA / D1680 Community Rehabilitation A posteriori Open - National 30,731.00 0.00 2019-10-04 2019-10-19 2019-11-13 2019-11-28 2019-12-19 2020-06-16 qualifications des d'exécution dans le cadre de l'execution consultants des sous projets de la composante 3 CS-REF-33 / Recrutement d'un Consultant dans la Sélection fondée région de Kidal pour sur les En cours Etudes/Suivi et Contrôle IDA / D1680 Community Rehabilitation A posteriori Open - National 27,166.00 0.00 2019-10-04 2019-10-19 2019-11-13 2019-11-28 2019-12-19 2020-06-16 qualifications des d'exécution dans le cadre de l'execution consultants des sous projets de la composante 3 CS-REF-34 / Recrutement d'un Consultant dans la Sélection fondée région de Tombouctou pour sur les En cours Etudes/Suivi et Contrôle IDA / D1680 Community Rehabilitation A posteriori Open - National 45,283.00 0.00 2019-10-04 2019-10-19 2019-11-13 2019-11-28 2019-12-19 2020-06-16 qualifications des d'exécution dans le cadre de l'execution consultants des sous projets de la composante 3 CS-REF-35 / Recrutement d'un Consultant dans la Sélection fondée région de Menaka pour sur les En cours Etudes/Suivi et Contrôle IDA / D1680 Community Rehabilitation A posteriori Open - National 18,089.00 0.00 2019-10-04 2019-10-19 2019-11-13 2019-11-28 2019-12-19 2020-06-16 qualifications des d'exécution dans le cadre de l'execution consultants des sous projets de la composante 3 CS-REF-36 / Recrutement d'un Consultant dans la Sélection fondée région de Toudenit pour sur les En cours Etudes/Suivi et Contrôle IDA / D1680 Community Rehabilitation A posteriori Open - National 18,119.00 0.00 2019-10-04 2019-10-19 2019-11-13 2019-11-28 2019-12-19 2020-06-16 qualifications des d'exécution dans le cadre de l'execution consultants des sous projets de la composante 3 CS-REF-4 / P.E pour l'Encadrement, l'Appui conseil, l'Orientation et Sélection fondée Reinsertion Support to Open - dispense de Kit de formation IDA / D1680 A priori sur la qualité et 1,000,000.00 0.00 Annulé 2018-02-06 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Demobilized Ex-combatants International aux ex- combattants le coût démobilisés dans la région de Tombouctou CS-REF-6 / P.E pour l'Encadrement, l'Appui conseil, l'Orientation et Sélection fondée Reinsertion Support to Open - dispense de Kit de formation IDA / D1680 A priori sur la qualité et 1,000,000.00 0.00 Annulé 2018-02-06 2018-02-11 2018-03-12 2018-04-21 2018-04-28 2018-05-15 2018-06-19 2019-06-19 Demobilized Ex-combatants International aux ex- combattants le coût démobilisés dans la région de Menaka CS-REF-50 / P.E N°01 pour l'Encadrement, l'Appui Sélection fondée conseil, l'Orientation et Reinsertion Support to sur les Open - En attente dispense de Kit de formation IDA / D1680 A posteriori 120,000.00 0.00 2019-10-25 2019-10-26 2019-12-02 2019-12-17 2020-01-21 2021-01-20 Demobilized Ex-combatants qualifications des International d'exécution aux ex- combattants consultants démobilisés dans la région de Tombouctou CS-REF-51 / P.E N°01 pour l'Encadrement, l'Appui Sélection fondée conseil, l'Orientation et Reinsertion Support to sur les Open - En attente dispense de Kit de formation IDA / D1680 A posteriori 120,000.00 0.00 2019-10-25 2019-11-09 2019-12-09 2019-12-24 2020-01-28 2021-01-27 Demobilized Ex-combatants qualifications des International d'exécution aux ex- combattants consultants démobilisés dans la région de Menaka Page 11 CS-REF-56 / Recrutement Sélection fondée d’un Consultant pour l’étude Project Management Support sur les En attente situation de référence pour IDA / D1680 to Project Implementation A posteriori Open - National 17,241.00 0.00 2020-03-16 2020-03-31 2020-05-10 2020-05-25 2020-06-14 2020-08-13 qualifications des d'exécution l’évaluation des effets/impacts Unit consultants du PREC INDIVIDUAL CONSULTANTS Activity Reference No. / Invitation to Loan / Credit Market Contract Type Estimated Actual Draft Negotiated Description Component Review Type Method Process Status Terms of Reference Identified/Selected Signed Contract Contract Completion No. Approach Amount (US$) Amount (US$) Contract Consultant Planned Actual Planned Actual Planned Actual Planned Actual Planned Actual CS-REF-1 / Recrutement d'un consultant pour l'étude récapitulative socio- économique sur les filières Project Management Support En attente porteuses et les Kits de IDA / D1680 to Project Implementation A posteriori Individuel Open 24,155.00 0.00 2018-02-15 2018-03-23 2018-03-30 2018-04-27 2018-05-27 d'exécution Réinsertion dans toutes les Unit régions sur la base d’anciennes études réalisées au Mali CS-REF-13 / Consultant Project Management Support En attente pour l'élaboration de la IDA / D1680 to Project Implementation A posteriori Individuel Open 22,544.00 0.00 2018-02-26 2018-04-03 2018-04-10 2018-05-08 2018-06-07 d'exécution stratégie de communication Unit CS-REF-19 / Contrat Project Management Support recrutement de Secrétaire En attente IDA / D1680 to Project Implementation A posteriori Individuel Open 16,000.00 0.00 2019-01-06 2019-02-11 2019-02-16 2019-02-24 2021-03-15 Administratif Financier d'exécution Unit (SAF) CS-REF-26 / Recrutement Project Management Support Sélection de En attente d'un Consultant pour IDA / D1680 to Project Implementation A posteriori consultants par Direct 20,000.00 0.00 2019-01-08 2019-01-18 2019-02-03 2019-03-05 d'exécution l'Etude du CGES du PREC Unit entente directe CS-REF-27 / Recrutement Project Management Support Sélection de En attente d'un Consultant pour IDA / D1680 to Project Implementation A posteriori consultants par Direct 20,000.00 0.00 2019-01-08 2019-01-18 2019-02-03 2019-03-05 d'exécution l'Etude du CPRP du PREC Unit entente directe CS-REF-28 / Consultant pour l'élaboration du manuel Project Management Support Sélection de En attente technique de la composante IDA / D1680 to Project Implementation A posteriori consultants par Direct 10,000.00 0.00 2019-04-30 2019-05-05 2019-05-20 2019-06-09 d'exécution 2 des projets à la demande Unit entente directe du PREC CS-REF-43 / Recrutement Project Management Support Spécialiste en Développement En attente IDA / D1680 to Project Implementation A posteriori Individuel Open 32,148.00 0.00 2019-08-07 2019-09-16 2019-10-07 2019-11-07 2021-10-31 Social (SDS) de l'UEP du d'exécution Unit PREC CS-REF-44 / Recrutement Project Management Support Spécialiste en Sauvegarde En attente IDA / D1680 to Project Implementation A posteriori Individuel Open 32,148.00 0.00 2019-08-07 2019-09-16 2019-10-07 2019-11-07 2021-10-31 Environnemental (SSEv) de d'exécution Unit l'UEP du PREC CS-REF-12 / Contrat du Project Management Support En attente spécialiste en suivi IDA / D1680 to Project Implementation A posteriori Individuel Open 32,148.00 0.00 2018-04-16 2018-05-17 2018-05-24 2018-06-03 2019-06-03 d'exécution évaluation Unit CS-REF-52 / Recrutement Project Management Support d’un consultant national En attente IDA / D1680 to Project Implementation A posteriori Individuel Limited 5,172.00 0.00 2019-11-06 2019-11-11 2019-11-26 2019-12-25 2020-02-23 pour appui à la passation d'exécution Unit des marchés à L’UEP/PREC Page 12 CS-REF-53 / Recrutement Project Management Support Specialiste en Passation de En cours IDA / D1680 to Project Implementation A posteriori Individuel Limited 41,400.00 0.00 2019-12-23 2019-12-28 2020-01-04 2020-01-15 2021-01-14 marches pour le compte de d'exécution Unit l’UEP du PREC CS-REF-54 / Recrutement Project Management Support Specialiste en Gestion En cours IDA / D1680 to Project Implementation A posteriori Individuel Limited 41,400.00 0.00 2019-12-23 2019-12-28 2020-01-04 2020-01-15 2021-01-14 Financiere pour le compte d'exécution Unit de l’UEP du PREC CS-REF-55 / Recrutement Ingénieur en Infrastructures En cours IDA / D1680 Community Rehabilitation A posteriori Individuel Limited 20,700.00 0.00 2019-12-23 2019-12-28 2020-01-04 2020-01-15 2020-07-13 communautaires pour le d'exécution compte de l’UEP du PREC CS-REF-39 / Recrutement assistant en suivi et En attente IDA / D1680 Community Rehabilitation A posteriori Individuel Open 23,077.00 0.00 2020-04-01 2020-04-28 2020-05-13 2020-06-10 2021-06-10 évaluation dans la région d'exécution Tombouctou CS-REF-57 / Recrutement d’un Spécialiste en Violences En attente IDA / D1680 Community Rehabilitation A posteriori Individuel Open 41,400.00 0.00 2020-02-28 2020-04-02 2020-04-09 2020-04-21 2021-04-21 basées sur le Genre (VBG) d'exécution pour le PREC CS-REF-42 / Recrutement assistant en suivi et En attente IDA / D1680 Community Rehabilitation A posteriori Individuel Open 23,077.00 0.00 2019-10-27 2019-11-23 2019-12-08 2020-01-05 2021-01-04 évaluation dans la région d'exécution Taoudenit CS-REF-37 / Recrutement assistant en suivi et En attente IDA / D1680 Community Rehabilitation A posteriori Individuel Open 23,077.00 0.00 2019-10-27 2019-11-23 2019-12-08 2020-01-05 2021-01-04 évaluation dans la région d'exécution Mopti CS-REF-38 / Recrutement assistant en suivi et En attente IDA / D1680 Community Rehabilitation A posteriori Individuel Open 23,077.00 0.00 2019-10-27 2019-11-23 2019-12-08 2020-01-05 2021-01-04 évaluation dans la région de d'exécution Gao CS-REF-40 / Recrutement assistant en suivi et En attente IDA / D1680 Community Rehabilitation A posteriori Individuel Open 23,077.00 0.00 2019-10-27 2019-11-23 2019-12-08 2020-01-05 2021-01-04 évaluation dans la région d'exécution Kidal CS-REF-41 / Recrutement assistant en suivi et En attente IDA / D1680 Community Rehabilitation A posteriori Individuel Open 23,077.00 0.00 2020-04-01 2020-04-28 2020-05-13 2020-05-28 2021-05-28 évaluation dans la région d'exécution Menaka Page 13