The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Central Highlands Connectivity Improvement Project (P159238) EAST ASIA AND PACIFIC | Vietnam | Transport Global Practice | IBRD/IDA | Investment Project Financing | FY 2017 | Seq No: 5 | ARCHIVED on 03-Nov-2019 | ISR39133 | Implementing Agencies: Socialist Republic of Vietnam, Projects Management Unit No. 2 Key Dates Key Project Dates Bank Approval Date: 22-Jun-2017 Effectiveness Date: 22-May-2018 Planned Mid Term Review Date: 30-Nov-2020 Actual Mid-Term Review Date: Original Closing Date: 30-Jun-2023 Revised Closing Date: 30-Jun-2023 pdoTable Project Development Objectives Project Development Objective (from Project Appraisal Document) To improve the connectivity, safety and climate-resilience of the National Highway 19. Has the Project Development Objective been changed since Board Approval of the Project Objective? No Components Table Name Road Improvements:(Cost $145.00 M) Implementation Support:(Cost $8.70 M) Overall Ratings Name Previous Rating Current Rating Progress towards achievement of PDO Moderately Unsatisfactory Moderately Unsatisfactory Overall Implementation Progress (IP) Unsatisfactory Unsatisfactory Overall Risk Rating Moderate Moderate Implementation Status and Key Decisions The Project was approved by the Board on June 22, 2017, and the FA was signed on December 27, 2017, and the effectiveness was declared on May 22, 2018. After initial delays the Detailed Design consultants have been procured and the work started on preparation of the detailed designs. Risks 11/3/2019 Page 1 of 5 The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Systematic Operations Risk-rating Tool Risk Category Rating at Approval Previous Rating Current Rating Political and Governance Low Low Low Macroeconomic Low Low Low Sector Strategies and Policies Moderate Moderate Moderate Technical Design of Project or Program Moderate Substantial Substantial Institutional Capacity for Implementation and Sustainability Moderate Substantial Substantial Fiduciary Substantial Substantial Substantial Environment and Social Moderate Moderate Moderate Stakeholders Moderate Substantial Substantial Other Low Low Low Overall Moderate Moderate Moderate Results PDO Indicators by Objectives / Outcomes To improve the connectivity, safety and climate-resilience of the National Highway 19 IN00761523 ►Annual average daily traffic (AADT) (Number, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 4,950.00 4,950.00 4,950.00 6,600.00 Date 31-Mar-2017 16-Apr-2019 16-Apr-2019 30-Jun-2023 IN00761524 ►Average travel time on the NH19 Corridor (Hours, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 6.00 6.00 6.00 5.00 Date 31-Mar-2017 16-Apr-2019 16-Apr-2019 30-Jun-2023 IN00761525 ►Number of kilometers of International Road Assessment Program (iRAP) 3-star rating or above for both cars and motorcycles on the NH19 Corridor (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 75.00 75.00 75.00 228.00 Date 31-Mar-2017 16-Apr-2019 16-Apr-2019 30-Jun-2023 IN00761541 ►Kilometers of roads that are upgraded in compliance with climate/disaster resilient design standards (Number, Custom) 11/3/2019 Page 2 of 5 The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 31-Mar-2017 16-Apr-2019 16-Apr-2019 30-Jun-2023 Intermediate Results Indicators by Components Road Improvements IN00761542 ►Roads rehabilitated, Non-rural (Kilometers, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 153.00 Date 31-Mar-2017 16-Apr-2019 16-Apr-2019 30-Jun-2023 IN00761545 ►Share of citizens from affected communes who participated in consultations (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 70.00 Date 31-Mar-2017 16-Apr-2019 16-Apr-2019 30-Jun-2023 IN00761546 ►Share of women from affected communes who participated in consultations (Percentage, Custom) Baseline Actual (Previous) Actual (Current) End Target Value 0.00 0.00 0.00 20.00 Date 31-Mar-2017 16-Apr-2019 16-Apr-2019 30-Jun-2023 Implementation Support IN00761543 ►Manual for motorcycle lane design and specifications (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No Yes Yes Date 31-Mar-2017 16-Apr-2019 29-Oct-2019 30-Jun-2023 Draft Manual has been prepared Comments: IN00761544 ►Guidelines for resilient road design and standards (Yes/No, Custom) Baseline Actual (Previous) Actual (Current) End Target Value No No No Yes 11/3/2019 Page 3 of 5 The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Date 31-Mar-2017 16-Apr-2019 29-Oct-2019 30-Jun-2023 Guidelines preparation is ongoing Comments: Data on Financial Performance Disbursements (by loan) Project Loan/Credit/TF Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P159238 IDA-61080 Effective USD 140.50 140.50 0.00 0.00 142.48 0% P159238 IDA-61090 Effective USD 9.50 9.50 0.00 0.00 9.59 0% Key Dates (by loan) Project Loan/Credit/TF Status Approval Date Signing Date Effectiveness Date Orig. Closing Date Rev. Closing Date P159238 IDA-61080 Effective 22-Jun-2017 27-Dec-2017 22-May-2018 30-Jun-2023 30-Jun-2023 P159238 IDA-61090 Effective 22-Jun-2017 27-Dec-2017 22-May-2018 30-Jun-2023 30-Jun-2023 Cumulative Disbursements 11/3/2019 Page 4 of 5 The World Bank Implementation Status & Results Report Central Highlands Connectivity Improvement Project (P159238) Restructuring History There has been no restructuring to date. Related Project(s) There are no related projects. 11/3/2019 Page 5 of 5